Tech Vidhya is the premier IT and Telecom training institute of India that is running its quality training courses since last decade and we deliver what we promise. Tech Vidhya is the leading training institute in telecom and IT sector that offers various Telecom, telecommunication, Networking and IT/Software courses in an efficient and friendly manner. We are having the highly qualified and experienced trainers for all the courses. The trainers are updated with the latest technologies and they are working on various live projects on India’s top telecom/IT companies.
2. INTRODUCTION
Kallol Ghosh2
A cell site is a site where antennas and electronic communications equipment are
placed, usually on a tower or other high place, to create a cell (or adjacent cells)
in a cellular network. Cellular (cell) phones first became widely available in the
United States in the 1990s, but since then their use has increased dramatically.
The widespread use of cell phones has led to cell phone towers being placed in
many communities. These towers, also called base stations, have electronic
equipment and antennas that receive and transmit radio frequency (RF) signals.
According to the RF Plan we have to install the antenna at a proper height on
tower. Installation procedure is different for many others company, but there are
no any complexity regarding that installation. In case of Nokia Siemens Network
they don’t use any loop or bend on RF cable. Reliance don’t use any Jumper
cable for a cell site. In this presentation we have discussed about the installation
procedure and quality point of outdoor equipments.
3. INDEX
Kallol Ghosh3
TITTLE
Installation & Quality Point
PAGE NO
RF Plan & Requirement List 4-5
Antenna Line 6
Antenna Installation & Quality Point 7-11
Jumper cable Installation & Quality
Point
12-16
RF Cable & Connector Installation &
Quality Point
17-23
Weather Proofing Kit 24-25
Earthing kits 26-29
Roxtec 30-31
Surge Arrestors 32
Cable ties 34
Labels 35
4. RF PLAN:
Kallol Ghosh4
Name: Kallol Ghosh
RF PLAN
SITE NAME : TECHNO CENTRE
SITE ID : A234M08
ADDRESS : 35, B.C.ROAD, BURDWAN,W.B.
PARTICULARS
SITE 1 SITE 2 SITE 3
AZIMUTH
60° 180° 300°
HEIGHT 40m 44m 48m
MECHANICAL TILT 0° 0° 0°
ElECTRICAL TILT 3° 6° 2°
TYPE OF THE ANTENNA X43210 X01234 X21034
5. Requirement List :
5
particulars Specification Status
1.Antenna GSM900 Panel Antenna,65°beam width ,
cross polarized antenna
3
Jumper Cable 1/2" diameter, 1m, 3m, 7/8"M & 7/8"F
connector
12
RF Cable or Feeder
Cable
7/8", copper RF Cable 300m
RF Connector 7/8”M 12
Earthing Kits Copper strips, Ring type copper lugs 12
RF Clamps, cable ties Six way 35,100
Grounding Cable 35sq.mm. y-green grounding
cable,16sq.mm. green grounding cable
108m
8m
Roxtec and Screw 4 way, Full thread steel screw 1,8
Surge Arrestors ------- 6
Weather Proofing Kits PVC(6cm),Rubber,Butyl 3
Labels 100
6. Antenna Line:
6
Antenna
Jumper cable
Rf to jumper connector
Earthing
kit
Rf clamp
Rf cable
Roxtec
Cable tray
Egb
The line between the Antenna and the
BTS is known as antenna line
In antenna line there are following
things:
• Rf cable
• Rf connector
• Jumper cable
• Earthing kit
• Weather proofing kit
• Roxtec
• Surge Arrester
Kallol Ghosh
7. :
PROCEDURE TO INSTALL AN ANTENNA
Kallol Ghosh7
First we have to make the connection between antenna port and jumper cable
and connection should be weather proofed, and other end of jumper cable
should be covered by polythene. If we give mechanical tilt then it should be
done at bellow, electrical tilt should be avoided at this condition because, it
should be change by touching the tower body.
8. ANTENNA INSTALLATION :
Kallol Ghosh8
We have to take the antenna up on tower with the help of pulley or rope
Keep the antenna away from tower body by pulling the rope carefully.
9. BTS
9 Kallol Ghosh
According to the RF Plan we have to set the
antenna at proper height with the pole mount by
using the antenna clamps with the appropriate
electrical tilt. Antenn
a
Jumper
Connect
or
Jumper
Cable
35sqmm
yellow
green
groundin
g cable
VCT
RF connector &
Jumper connector
Earthing
Kits
EGB
RF Cable
HCT
Earthing
kit
S-
bend
Surge
Arrestor
I/D Jumper
cable
IGB EGB
10. Quality Check Point Of Antenna
Kallol Ghosh10
Height of the antenna as per the RF Plan
Tilt of the antenna as per the RF Plan
Type of the antenna as per the RF Plan
Azimuth of the antenna as per the RF Plan
All the nuts bolts of the antenna should be properly
Lock nuts should be provided
Label should be provided of the back of the antenna
Electrical tilt
Mechanical
tilt
Nuts bolts or lock
nuts
11. Kallol Ghosh11
Label should be provided of the back of the antenna
Type of the antenna as per the RF Plan
GSM 900
Antenna
Single port antenna Dual port antenna
Hex port antennaQuad port Antenna
12. Specification of Jumper Cable:
Kallol Ghosh12
Size - ½ inches
Inner core – Pure copper
cylindrical tube of ½ inches filled
with Aluminum.
Outer core – Pure Copper
cylindrical tube like spring.
Soft Insulation – White soft foam.
Hard outer insulation – Black
insulation material.
Impedance – 50Ω.
Flexibility- High.
Length- 1m ,1.5m, 2m, 2m.5m, 3m,
5m, 7 m,10m, 15m.
Inner core
Soft
insulation
Outer
Core
Outer
insulation
13. JUMPER CABLES INSTALLATION :
Kallol Ghosh13
Jumper cable
RF
connect
or
RF
Cable
Now routing the outdoor jumper cable properly by using the cable ties and
connects it to the RF Cable by using the 7/8”M RF connector. Indoor
Jumper should b connected with BTS port.
14. Combination of connector in Jumper cable:
Kallol Ghosh14
1. 7/8 F – 7/8 M
2. 7/8 M – 7/8 M
3. 7/8 F – 7/8 F
4. 7/8 M – 7/8 L.M
5. 7/8 M -7/8 L.M
Apart from these some more arrangements are
1. 7/8 M – 7/16 M
2. 7/8 M – 7/16 F
3. 7/8 F – 7/16 M
4. 7/8 F – 7/16 F
Outdoor jumper cable – 3m
Indoor jumper cable - 1 or 1.5 m
½” Jumper cable
15. Quality Check Point Of Jumper Cable:
Kallol Ghosh15
In case of U-Loop of both jumper cable should be parallel
There should not be any sharp bend in the jumper cable
In case of close loop there should be two cable ties at the
touching point
Routing of Jumper cable should be done by using cable ties
Distance of the two cable ties should be uniform and approx
200mm.
At the bend in the Jumper cable at least two cable ties should
be provided at touching edge
Parallel U-loop
Close loop
Cable
ties
Cable
ties
16. Kallol Ghosh16
Labeling should be done with both the end of jumper cable
Routing of Jumper cable should be together and along with the
tower body
Termination of Jumper cable should be verified by VSWR
measurement
Last hand of PVC tape should be bottom to top
Labeling on Indoor jumper
cable
Proper taping on
jumper
connector
17. Specification Of RF Cable:
Kallol Ghosh17
• Size of the inner core is equal to the size of normal
co-axial cable.
• As it’s a hollow , so it increase surface, decrease
resistance, increase capacity, increase flexibility,
lesser cost
• Inner Core : Pure Copper.
• Soft Insulation : Fume
• Outer Core : Pure Copper Cylindrical Tube.
• Outer Insulation : Hard Insulation , black in color.
• Size Of The Cable : diameter 5/4” or 7/5”
• Impedance : 50Ω
Feeder Cable
Inner core
Soft Insulation
Hard outer insulation
Outer core
18. RF CABLES INSTALLATION FIXING THE RF CABLES WITH RF
CLAMP:
Kallol Ghosh18
Cable
tray
RF clamp
Weather
proofing tape
After that we have to place the RF Cable sector wise on the
cable tray by using the RF Clamp (6-way), and mark on the RF
Cable according to the sector .
19. RF Clamp:
Kallol Ghosh19
1 way RF
clamp
2 way RF clamp
3 way RF clamp
6 way RF clamp
C-clamp made
of GI
Dummy
clamp
20. Kallol Ghosh20
Now the bending portion of RF cable should be carefully placed by using a dummy
clamp at the junction point between VCT and HCT. Then another earthing kit should
be attached along with RF cable by using the cable ties and then RF cable should be
placed on HCT by using the RF clamp. Earthing kit should be straight to the shelter
and connect the grounding cable with EGB properly
Bending portion
of RF cable
EGB
Roxte
c HCT
RF
Cabl
e
21. RF CABLES Connector
CONNECTION BETWEEN RF AND JUMPER:
Quality Point:
Kallol Ghosh21
Routing of RF cable through the RF clam should be according to the sector, there
should not be any cross routing of RF cable.
Connection should be made properly and attach the weather proofing tape properly
Connection should be made by hand tight.
22. RF Connector :
Kallol Ghosh22
Base Outer
Port
BaseOuter
7/8’’ female connector
7/8’’ male connector
23. Quality Point Of RF Cable:
Kallol Ghosh23
There should be a label on RF Cable near RF to Jumper
cable, and RF and Roxtec
Position of RF Clamp should be uniform from the either
edge of cable tray
Routing of RF cable should be in pair and parallel
Distance of the two RF Clamp should be 0.9 or 0.6 on
HCT.
Labeling of RF cable in side the shelter and outside the
shelter should be visible from bottom
Routing of RF cable through the RF clamp should be
according to the sector, there should not be any cross
routing of RF Cable.
Bending of RF Cable should be greater than 300mm
S-Bend on RF Cable should be properly
Labeling on
RF cable
S-
bend
Parallel
Routing
No cross
routing, Sector
wise place
24. WEATHER PROOFING
Kallol Ghosh24
All ourdoor antenna line connections, grounding kits and wall entries have to be weather
proofed.
Connections where weather proofing is needed:
Feeder to jumper at antenna end.
Feeder to antenna
• Direction of last hand of PVC tape should be bottom to top.
PVC Tape
25. WEATHER PROOFING:
Kallol Ghosh25
FEEDERS WEATHER PROOFING
KIT (BUTYL TAPE,3/4” PVC TAPE
,2” PVC TAPES ),
THESE ARE SET OF ONE KIT
1.Connection should be tape using PVC tape.
2.Connection should be sealed by using Rubber
tape.
3.Connection to be tape by using PVC tape
again.
26. EARTHING KITS & GROUNDING CABLE:
Kallol Ghosh26
Earthing Kit
External Jumper
Feeder Cable
Antenna
Grounding Bar
(Normally 1.5m, - see Appendix 2)
200mm < d < 2000mm
d
Jumper Cable or
Antenna Connector
Ground Cable to Main
Site Ground System
Ground Cable (Tail)
600mm long
RFCable
Note: Grounding bar should be f ixed directly
to the tower where the tower is itself
the main ground down-conductor!
Ground Cable to Main
Site Ground System
Alternative Orientation
for Grounding Bar
Earthing Kit
Jumper Cable or
Antenna Connector
27. EARTHING KITS
Kallol Ghosh27
EARTHING STRIP & CABLE
All earthing kits should be attached bellow 1m from
lowest RF connector, along with the RF Cable in same
position on VCT by using the cable ties, and earthing kits
should be connected to EGB. EGB should be grounded
properly.
28. Kallol Ghosh28
EARTHING KIT ,(IT INCLUDES
EARTHING
STRIP,CABLE,WEATHER-
PROOFING KIT).
1.The earthing kit must always be taken together with RF Cable.
2.All earthing kits should be made in same location.
3.One earthing kits should be terminated to the one hole of EGB.
29. Lugs & Strips :
Kallol Ghosh29
Copper strip
Aluminum strip
There are three types of lugs 1) I-type 2) Pin type 3) Ring type
Strips and lugs should be same
material.
30. Roxtec: Quality point
Kallol Ghosh30
1. Arrangement of RF Cable should be sector wise.
2. Routing of RF Cable should not be crossed with each
others
3. 4 Robber boots are there, each and every boot present
a hole.
4. Corner should be sealed by using silicon gel
5. Full thread steel screw of size 1-1.5” should be used
31. Kallol Ghosh31
RF Cable should be entered into the roxtec and mark the position of RF Cable
then it should be removed from roxtec and cut the mark point on RF cable and
connect the 7/8”M connector. Now finally we insert the RF cable into the roxtec
and connect it with Surge arrestors in same location according to sector wise.
After that we have to make an s-bend on RF Cable near the roxtec.
32. Surge Arrestors:
Kallol Ghosh32
Position of all the surge arrestors are in same.
Now other end of surge arrestors should be connected with indoor jumper cable and
route it on the indoor cable tray by using the cable ties.
33. Quality Point Of Surge Arrestor :
Kallol Ghosh33
All the termination of Surge arrestors and jumper
cable should be hand tight
Position of all Surge arrestors should be in same
size
Grounding cable termination on surge arrestors
should be properly tight.
Routing of Grounding cable should be along with
the same RF Cable.
Position of Grounding cable should be bottom of
the RF Cable.
Each Grounding cable should be terminated to
EGB.
Same position
Grounding
cable bottom of
the RF cable
Along with
RF cable
34. Cable Ties: Quality Point
Kallol Ghosh
34
1. Routing of Jumper cable should be done by using cable ties
2. Distance of two cable ties should be uniform and approx 200mm
to route a jumper cable
3. Position of knot and direction of knot for cable ties should be in
same .
4. Unused portion of cable ties should be cut on
35. Labels: Quality Point:
Kallol Ghosh35
1.Labelling on the RF Cable in both inside and outside the shelter should be
visible from bottom.
2.Labels should be provided at the both end of jumper cable.
3.It should be provided of the back of the antenna.