SEMINAR PRESENTATION TOPIC:
GAS INSULATED SUBSTATIONS
SESSION:2014-2015
PRESENTED BY:
NAME:MOHAMMAD SAIF
BRANCH:ELECTRICAL AND ELECTRONICS ENGG.
1
Contents
 Introduction of GIS
 Gas Insulated Substation
 Internal equipments of GIS.
 Definitions of equipments.
 Internal equipments of GIS.
 Need of GIS
 Service condition of GIS
 Services offered by GIS to supplier.
 Drawback of GIS.
 Advantages of GIS.
 Application of GIS .
 Conclusion.
 References
Introduction to GIS
 GIS was first developed in various countries between 1968
and 1972.
 After about 5 years of experience, the use rate increased to
about 20% of new substations in countries where space is
limited.
 Conventional substations requires, small installations size,
protection against atmosphere pollution and moisture,
noiseless operation, on explosive and flame resistant,
reduced maintenance, minimal radio interference, but totally
enclosed substations using SF6 gas as insulation that are
also known as GIS which is stand for GAS INSULATED
SUBSTATIONS.
 GIS is now in widespread use in the electrical power industry.
GAS INSULATED SUBSTATIONS
Definition:
 A gas insulated substation(GIS) is a substation that uses a
superior dielectric gas, sulfur hexafluoride (SF6),high voltage.
 The basic principle of GIS equipment:
 Is that the high-voltage current carrying parts are within a
metal enclosure and are held in a concentric configuration by
cast epoxy spacer insulators.
 The space between the conductor and the enclosure is filled
with SF6 gas under moderate pressure.
GAS INSULATED SUBSTATIONS
 Components:
 1- Circuit breaker.
 2-Disconnector(Isolator).
 3-Ground switches.
 4-Bus-bar.
 5-Transformer.
 8-Outgoing bus-bar for electrically
connecting the gas insulated substation
with bus-bar.
 9-Outgoing portion of the transformer
being arranged in accordance with
extending direction of outgoing bus-bar.
INTERNAL EQUIPMENTS OF GIS
Definition's of equipment's
BUS-BAR:
 An electrical conductor that carries a large current,
especially one that is part of a power distribution
system; typically a thick strip, or a tube, of copper or
aluminum.
CIRCUIT BREAKER:
 Under short circuit conditions,however,the current
may reach tens of thousands of amperes at a power
factor as low as 0.1.
 It is duty of a circuit breaker to interrupt such currents
as soon as possible to avoid equipment damage.
CURRENT TRANSFORMER:
In the single phase enclosed core of CT is
located outside the enclosure inside for three
phase.
Gas compartment to reduce access of
moisture and to suppress gas-tight bushing for
secondary connections.
CT current rating is 120% of rated primary
current.
VOLTAGE TRANSFORMER:
Variable location on feeder and busbars.
Integrated disconnecting facility for GIS and
power cable testing without dismantling and
gas handling.
DISCONNECTOR:
Disconnectors or isolators are used for
electrical isolation of circuit parts.
Disconnect switches can be three pole,group-
operated,or single pole operated.
They are slow acting and operating at off load.
EARTHING SWITCH:
Slow operating earthing switch are used for
protection purpose.
 When work is being done in the substation,
but are operated only when it is certain that
the high-voltage system is not energized.
The fast closing earthing switch can close
against full voltage and short circuit power.
The high speed earthing switch is achieved by
means of a spring-closing device.
CABLES COMPARTMENT:
 Optimized solution for plug-in type power cable
connection.
 Adjustable support structure for minimum
requirements for the GIS floor.
 Fixation to the GIS floor by cemented anchor
bolts, no need for special foundation (steel
beams….etc.)
LOCAL CONTROL CUBICLE:
 LCC is the interface cubicles to all secondary system of a substation which
are represent a station control and protection.
 LCC includes control and alarm functions as well as the correct distribution
of auxiliary power supply for the relevant GIS .
 In general, each cabinet should contain the following equipment for
control, indication and protection of switches, circuit breaker, and
associated components:
 1. One control switch for each three phase circuit breaker.
 2. One remote local switch for each three phase circuit breaker.
 3. One open close control switch for each motor operated grounding switch.
 4. One or two red light-emitting diodes and one green for each circuit breaker, each
disconnect and grounding switch, or contact position indication .
 5. Control switches for ac and dc supply to each compartment.
Need for GIS
 Non availability of sufficient space.
 Reduction in length of feeders.
 Improvement of the quality of voltage regulation due to short length feeder.
 Total space required for GIS is 10% of the needed for a conventional substation.
 GIS technology can be used for installations in areas where the cost of real estates
is appreciable.
 Overcome or decrease the magnitude of limitation of AIS site selection.
Service condition of GIS
As per IEEE 122,IEEE123 and IEC 62271
 Indoor or outdoor :As per customer
 Elevation above sea level :As per site location
 Design ambient temperature :40 degree Celsius as per IEC 62271
 Maximum ambient temperature : 105 degree Celsius as per IEC 62271
Maximum Allowable Total Temperature in Celsius
Internal contacts/joints silver plated and 105
conductor in compact with epoxy insulator.
External surface-accessible . 70
External surface-inaccessible. 110
External surface-normally handled by 50
an operator.
Service offered by GIS user and GIS
supplier
Unless otherwise specified or agreed upon,the user should receive,install,and
field test the apparatus specified herein,installation and field testing of the
GIS should be completed under the supervision of the supplier to ensure
correct installation.Unless otherwise specified,the following equipment and
services should also be furnished by the user:
 Concrete foundation.
 Power transformer or reactor including bushings.
 Surge arrester,outsidee the GIS
 The station ground grid,below ground,and vertical connection risers of
adequate length.
 Ac and dc auxilary power to furnished equipment.
Drawbacks of GIS substation
 High cost.
 Waves get reflected and refracted.
 Excessive damage incase of internal faults.
 Diagnosis of internal takes very long time.
 SF6 gas pressure must be monitered in each compartment.
 SF6 cause ozone layer depletion and global warming.
Advantages of GIS
Occupies very less space.
Most reliable.
Number of outages due to the fault is less.
Maintenance free.
Applications of GIS
High voltage installations
The higher the voltage, the more favorable gas insulated technology becomes. The
footprint of 765kV conventional substation is enormous, and GIS technology allows a
significant size reduction.
Urban Installations
GIS technology can be used for installations in areas where the cost of real estate or aesthetic
appeal is a significant consideration.
Indoor Installations
Building an air insulated substation indoors is usually impractical, but a GIS can easily go inside
buildings.
Environmentally Sensitive Installations
GIS technology is popular in desert and arctic areas because it can be enclosed in a building with
environmental control.
Conclusion
GIS generate no noise and have no idea no
radio interference.
GIS is necessary for extra HV and Ultra HV
substations.
More conservative.
Reference
• www.google.com/gasinsulatedsubstation
• www.yahoo.com/gasinsulatedsubstation
• www.slideshare.com/gasinsulatedsubstation
Thanking you

More Related Content

What's hot

Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationRaushanKumar582
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONsujitmandalsk
 
Gis substation
Gis substationGis substation
Gis substationAsif Eqbal
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1Ronal Parmar
 
SF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKERSF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKERsssspp
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationMOHDFAIZAN75
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...Ali Sepehri
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protectionsrini09
 
Classification of unified power quality compensators
Classification of unified power quality compensatorsClassification of unified power quality compensators
Classification of unified power quality compensatorsDuvvuruSravya
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substationsvishalgohel12195
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSoumya Raj Poddar
 
substation automation
substation automationsubstation automation
substation automationMahbub Rashid
 
Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substationsbhanu lucky
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 

What's hot (20)

Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
GAS INSULATED SUB-STATION
GAS INSULATED SUB-STATIONGAS INSULATED SUB-STATION
GAS INSULATED SUB-STATION
 
Ehv substation
Ehv substationEhv substation
Ehv substation
 
Gis substation
Gis substationGis substation
Gis substation
 
Switchyard
SwitchyardSwitchyard
Switchyard
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
 
SF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKERSF6 CIRCUIT BREAKER
SF6 CIRCUIT BREAKER
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
High Voltage Gas Insulted Switchgear (GIS) Field Testing According to IEEE C3...
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
 
Classification of unified power quality compensators
Classification of unified power quality compensatorsClassification of unified power quality compensators
Classification of unified power quality compensators
 
Power Line Carrier Communication PLCC
Power Line Carrier Communication PLCCPower Line Carrier Communication PLCC
Power Line Carrier Communication PLCC
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
 
substation automation
substation automationsubstation automation
substation automation
 
Sub stations-air insulated substations
Sub stations-air insulated substationsSub stations-air insulated substations
Sub stations-air insulated substations
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
Ppt
PptPpt
Ppt
 

Viewers also liked

FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARashwini kumar
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)Prateek Agarwal
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
Moct magneto-optic-current-transformer
Moct magneto-optic-current-transformerMoct magneto-optic-current-transformer
Moct magneto-optic-current-transformerLaxmikant Sain
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthingNitesh Dash
 
132kv Substation
132kv Substation132kv Substation
132kv Substationguestecdd58
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and detailsMahesh Sontyal
 
digital testing of high voltage circuit breaker
digital testing of high voltage circuit breakerdigital testing of high voltage circuit breaker
digital testing of high voltage circuit breakerRenuka Verma
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSPradeep Avanigadda
 
Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...
Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...
Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...Thorne & Derrick International
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3Ronal Parmar
 
Reactivepowercompensation 140401183847-phpapp01 (6)
Reactivepowercompensation 140401183847-phpapp01 (6)Reactivepowercompensation 140401183847-phpapp01 (6)
Reactivepowercompensation 140401183847-phpapp01 (6)REVANTH CHINTU
 
Gas insulated sub station 4
Gas insulated sub station 4Gas insulated sub station 4
Gas insulated sub station 4Ronal Parmar
 

Viewers also liked (20)

FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWARFACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
FACULTY OF ENGINEERING & TECHNOLOGY , GURUKULA KANGARI UNIVERSITY ,HARIDWAR
 
Substation overview
Substation overviewSubstation overview
Substation overview
 
Deepak kumar
Deepak kumarDeepak kumar
Deepak kumar
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Moct magneto-optic-current-transformer
Moct magneto-optic-current-transformerMoct magneto-optic-current-transformer
Moct magneto-optic-current-transformer
 
Electrical grounding and earthing
Electrical grounding and earthingElectrical grounding and earthing
Electrical grounding and earthing
 
132kv Substation
132kv Substation132kv Substation
132kv Substation
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
Transmission Line Towers and details
Transmission Line Towers and detailsTransmission Line Towers and details
Transmission Line Towers and details
 
digital testing of high voltage circuit breaker
digital testing of high voltage circuit breakerdigital testing of high voltage circuit breaker
digital testing of high voltage circuit breaker
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
Dtl nit-1496-140709 (1)
Dtl nit-1496-140709 (1)Dtl nit-1496-140709 (1)
Dtl nit-1496-140709 (1)
 
Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...
Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...
Schneider RM6 - MV Medium Voltage Compact Switchboard (Ring Main Unit) up to ...
 
Multi-Parameter Measurement of ICU Patient Using GSM and Embedded Technology
Multi-Parameter Measurement of ICU Patient Using GSM and Embedded TechnologyMulti-Parameter Measurement of ICU Patient Using GSM and Embedded Technology
Multi-Parameter Measurement of ICU Patient Using GSM and Embedded Technology
 
Blue LED
Blue LEDBlue LED
Blue LED
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3
 
Reactivepowercompensation 140401183847-phpapp01 (6)
Reactivepowercompensation 140401183847-phpapp01 (6)Reactivepowercompensation 140401183847-phpapp01 (6)
Reactivepowercompensation 140401183847-phpapp01 (6)
 
Gas insulated sub station 4
Gas insulated sub station 4Gas insulated sub station 4
Gas insulated sub station 4
 

Similar to Gas insulated substation.

Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptxBasavarajbanakar6
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxborapring
 
substation 101
substation 101substation 101
substation 101danica11
 
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstationraja sukumar
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptxSatish Pydimarla
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURHARISH KUMAR
 
Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...
Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...
Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...IJERA Editor
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Power System Operation
 
Compact DC switch gear
Compact DC switch gearCompact DC switch gear
Compact DC switch gearVeenaVK
 
Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...IRJET Journal
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid SubstationAng Sovann
 
IRJET- A Review: Microstrip Antenna
IRJET-  	  A Review: Microstrip AntennaIRJET-  	  A Review: Microstrip Antenna
IRJET- A Review: Microstrip AntennaIRJET Journal
 
IRJET- Battery Management System by using PWM Charge Controller
IRJET- Battery Management System by using PWM Charge ControllerIRJET- Battery Management System by using PWM Charge Controller
IRJET- Battery Management System by using PWM Charge ControllerIRJET Journal
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesYashwant Chaudhari
 

Similar to Gas insulated substation. (20)

Gagan
GaganGagan
Gagan
 
Internship ppt(santhosh).pptx
Internship ppt(santhosh).pptxInternship ppt(santhosh).pptx
Internship ppt(santhosh).pptx
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
 
substation 101
substation 101substation 101
substation 101
 
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstation
 
Substation_fundamental.pptx
Substation_fundamental.pptxSubstation_fundamental.pptx
Substation_fundamental.pptx
 
GIS(GAS INSULATED SUBSTATION)
GIS(GAS  INSULATED  SUBSTATION) GIS(GAS  INSULATED  SUBSTATION)
GIS(GAS INSULATED SUBSTATION)
 
GSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPURGSS (GIS) OLD POWER HOUSE JODHPUR
GSS (GIS) OLD POWER HOUSE JODHPUR
 
Substation
Substation Substation
Substation
 
Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...
Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...
Massive Energy Saving Systems and Strategies at Equipment Level in the Highes...
 
GIS PRESENTATION.pdf
GIS PRESENTATION.pdfGIS PRESENTATION.pdf
GIS PRESENTATION.pdf
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
 
Compact DC switch gear
Compact DC switch gearCompact DC switch gear
Compact DC switch gear
 
Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...Analysis of Fault Detection and its Location using Microcontroller for Underg...
Analysis of Fault Detection and its Location using Microcontroller for Underg...
 
TYPES OF SUBSTATION.pptx
TYPES OF SUBSTATION.pptxTYPES OF SUBSTATION.pptx
TYPES OF SUBSTATION.pptx
 
Gi e
Gi eGi e
Gi e
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
 
IRJET- A Review: Microstrip Antenna
IRJET-  	  A Review: Microstrip AntennaIRJET-  	  A Review: Microstrip Antenna
IRJET- A Review: Microstrip Antenna
 
IRJET- Battery Management System by using PWM Charge Controller
IRJET- Battery Management System by using PWM Charge ControllerIRJET- Battery Management System by using PWM Charge Controller
IRJET- Battery Management System by using PWM Charge Controller
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniques
 

Recently uploaded

Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 

Recently uploaded (20)

Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 

Gas insulated substation.

  • 1. SEMINAR PRESENTATION TOPIC: GAS INSULATED SUBSTATIONS SESSION:2014-2015 PRESENTED BY: NAME:MOHAMMAD SAIF BRANCH:ELECTRICAL AND ELECTRONICS ENGG. 1
  • 2. Contents  Introduction of GIS  Gas Insulated Substation  Internal equipments of GIS.  Definitions of equipments.  Internal equipments of GIS.  Need of GIS  Service condition of GIS  Services offered by GIS to supplier.  Drawback of GIS.  Advantages of GIS.  Application of GIS .  Conclusion.  References
  • 3. Introduction to GIS  GIS was first developed in various countries between 1968 and 1972.  After about 5 years of experience, the use rate increased to about 20% of new substations in countries where space is limited.  Conventional substations requires, small installations size, protection against atmosphere pollution and moisture, noiseless operation, on explosive and flame resistant, reduced maintenance, minimal radio interference, but totally enclosed substations using SF6 gas as insulation that are also known as GIS which is stand for GAS INSULATED SUBSTATIONS.  GIS is now in widespread use in the electrical power industry.
  • 4.
  • 5. GAS INSULATED SUBSTATIONS Definition:  A gas insulated substation(GIS) is a substation that uses a superior dielectric gas, sulfur hexafluoride (SF6),high voltage.  The basic principle of GIS equipment:  Is that the high-voltage current carrying parts are within a metal enclosure and are held in a concentric configuration by cast epoxy spacer insulators.  The space between the conductor and the enclosure is filled with SF6 gas under moderate pressure.
  • 6. GAS INSULATED SUBSTATIONS  Components:  1- Circuit breaker.  2-Disconnector(Isolator).  3-Ground switches.  4-Bus-bar.  5-Transformer.  8-Outgoing bus-bar for electrically connecting the gas insulated substation with bus-bar.  9-Outgoing portion of the transformer being arranged in accordance with extending direction of outgoing bus-bar.
  • 7.
  • 9.
  • 10. Definition's of equipment's BUS-BAR:  An electrical conductor that carries a large current, especially one that is part of a power distribution system; typically a thick strip, or a tube, of copper or aluminum. CIRCUIT BREAKER:  Under short circuit conditions,however,the current may reach tens of thousands of amperes at a power factor as low as 0.1.  It is duty of a circuit breaker to interrupt such currents as soon as possible to avoid equipment damage.
  • 11. CURRENT TRANSFORMER: In the single phase enclosed core of CT is located outside the enclosure inside for three phase. Gas compartment to reduce access of moisture and to suppress gas-tight bushing for secondary connections. CT current rating is 120% of rated primary current.
  • 12. VOLTAGE TRANSFORMER: Variable location on feeder and busbars. Integrated disconnecting facility for GIS and power cable testing without dismantling and gas handling. DISCONNECTOR: Disconnectors or isolators are used for electrical isolation of circuit parts. Disconnect switches can be three pole,group- operated,or single pole operated. They are slow acting and operating at off load.
  • 13. EARTHING SWITCH: Slow operating earthing switch are used for protection purpose.  When work is being done in the substation, but are operated only when it is certain that the high-voltage system is not energized. The fast closing earthing switch can close against full voltage and short circuit power. The high speed earthing switch is achieved by means of a spring-closing device.
  • 14. CABLES COMPARTMENT:  Optimized solution for plug-in type power cable connection.  Adjustable support structure for minimum requirements for the GIS floor.  Fixation to the GIS floor by cemented anchor bolts, no need for special foundation (steel beams….etc.)
  • 15. LOCAL CONTROL CUBICLE:  LCC is the interface cubicles to all secondary system of a substation which are represent a station control and protection.  LCC includes control and alarm functions as well as the correct distribution of auxiliary power supply for the relevant GIS .  In general, each cabinet should contain the following equipment for control, indication and protection of switches, circuit breaker, and associated components:  1. One control switch for each three phase circuit breaker.  2. One remote local switch for each three phase circuit breaker.  3. One open close control switch for each motor operated grounding switch.  4. One or two red light-emitting diodes and one green for each circuit breaker, each disconnect and grounding switch, or contact position indication .  5. Control switches for ac and dc supply to each compartment.
  • 16. Need for GIS  Non availability of sufficient space.  Reduction in length of feeders.  Improvement of the quality of voltage regulation due to short length feeder.  Total space required for GIS is 10% of the needed for a conventional substation.  GIS technology can be used for installations in areas where the cost of real estates is appreciable.  Overcome or decrease the magnitude of limitation of AIS site selection.
  • 17. Service condition of GIS As per IEEE 122,IEEE123 and IEC 62271  Indoor or outdoor :As per customer  Elevation above sea level :As per site location  Design ambient temperature :40 degree Celsius as per IEC 62271  Maximum ambient temperature : 105 degree Celsius as per IEC 62271 Maximum Allowable Total Temperature in Celsius Internal contacts/joints silver plated and 105 conductor in compact with epoxy insulator. External surface-accessible . 70 External surface-inaccessible. 110 External surface-normally handled by 50 an operator.
  • 18. Service offered by GIS user and GIS supplier Unless otherwise specified or agreed upon,the user should receive,install,and field test the apparatus specified herein,installation and field testing of the GIS should be completed under the supervision of the supplier to ensure correct installation.Unless otherwise specified,the following equipment and services should also be furnished by the user:  Concrete foundation.  Power transformer or reactor including bushings.  Surge arrester,outsidee the GIS  The station ground grid,below ground,and vertical connection risers of adequate length.  Ac and dc auxilary power to furnished equipment.
  • 19. Drawbacks of GIS substation  High cost.  Waves get reflected and refracted.  Excessive damage incase of internal faults.  Diagnosis of internal takes very long time.  SF6 gas pressure must be monitered in each compartment.  SF6 cause ozone layer depletion and global warming.
  • 20. Advantages of GIS Occupies very less space. Most reliable. Number of outages due to the fault is less. Maintenance free.
  • 21. Applications of GIS High voltage installations The higher the voltage, the more favorable gas insulated technology becomes. The footprint of 765kV conventional substation is enormous, and GIS technology allows a significant size reduction. Urban Installations GIS technology can be used for installations in areas where the cost of real estate or aesthetic appeal is a significant consideration. Indoor Installations Building an air insulated substation indoors is usually impractical, but a GIS can easily go inside buildings. Environmentally Sensitive Installations GIS technology is popular in desert and arctic areas because it can be enclosed in a building with environmental control.
  • 22. Conclusion GIS generate no noise and have no idea no radio interference. GIS is necessary for extra HV and Ultra HV substations. More conservative.