Corrugated (Roaring) Rails
In certain places the heads of rails are
found to be corrugated rather than straight ones.
Such type of rails are known as corrugated rails
or roaring rails.
When trains pass over such rails, a
roaring noise is caused, which is unpleasant to
the passengers. The corrugations consists of
minute depression on the surface of rails. They
are usually created at places where brakes are
applied or trains start.
i. Corrugation develop in any part of the whole rail
gets corrugated in a short time.
ii. Corrugation occur at any gradient and on any
track, whether a straight track or a curved track.
iii. When corrugated rails are relaid in other sections,
the corrugation sometimes get smoothened.
iv. When new rails are laid in places where
corrugation are prevalent, the new rails get
corrugated.
v. Rails carrying empty trains are easily corrugated
than rails carrying loaded trains.
Some of the peculiarity of corrugated rails
in nature are :
Causes of corrugations :
i. Where brakes are applied to trains for stopping them.
ii. Where trains start.
iii. Where the ballast consists of broken bricks.
iv. In electrified section of a railway track.
v. High speed of trains.
vi. Rigid railway track.
vii. Use of light wagons and coaches.
viii. Steep gradient
ix. Slipping of wheels of engine.
Remedial Measures
The corrugations of rails can be removed by
grinding a few thousands of a millimetre of the
rail heads. For this purpose, rail grinding trains
are used which move at 3 km.ph when the
grinders are in action.
Hogged Rails
Due to battering action of wheels over the
end of the rails, the rails get bent down and are
deflected at ends. These rails are called ‘hogged
rails’.
The hogging of the rails is mainly due to
loose packing under the joints and loose fish
plates. This defect causes rough riding.
Remedial measures :
1. Cropping :
In this measure, the hogged ends of the rails are cut
off and fresh holes for fixing the fish plates are provided.
The cutting of rails either is done in workshop or at the
site.
2. Welding :
Hogged rails are brought to the level by welding the
wornout or deflected ends.
3. Replacing :
In this method, the hogged rails are completely
removed and replaced by new rails. But, this measure is
very costly.
4. Dehogging :
This method involves straightening the hogged ends
Buckling of rails :
Buckling of rails means the track has gone out
of its original position or alignment due to prevention
of expansion of rails in hot weather. Buckling,
usually take place on tangent lengths or at curves.
Causes :
i. When expansion gap between ends of two rails
is not sufficient.
ii. The fish plates being bolted so tight that the
rails are not allowed to slip or expand.
iii. Due to welded rails on weak tracks.
Remedial measures :
i. Sufficient expansion gap should be provided.
ii. The fish bolts should not be tightened so much
as to prevent the expansion or contraction of
rails.
iii. The contact surface between the fish plates
and rails should be periodically lubricated.
iv. Provision of steel sleepers or anchoring of
welded rails should be done.
v. Number of welded rails should not be large.
Kinks in rails :
When the ends of adjoining rails move
slightly out of position ‘kinks’ or ‘shoulders’ are
formed.
Causes :
i. Loose packing at joints
ii. Defect in cross level at joints
iii. Defect in gauge and alignment
iv. Uneven wear of rail head
Effects :
i. The kinks causes unpleasant jerks in vehicles.
ii. On curves, it causes defect in gauge alignment
and camber.
Remedial Measures :
i. Providing proper packing at joints
ii. Correct alignment of joints and curves
iii. Periodical maintenance of the track in respect
of gauge, welding, cross levels etc.
Corrugated (roaring), Hogging, Buckling, Kinks in rails

More Related Content

What's hot

Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: TurnoutsVijai Krishnan V
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1Arun G
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionBathla Tuition Centre
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossingshiranrathva
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationMani Vel
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenenceGhanashyam Prajapati
 
classification of indian railway
classification of indian railway classification of indian railway
classification of indian railway addavidson
 
Different types of rail failures
Different types of rail failuresDifferent types of rail failures
Different types of rail failuresSunil Kumar Meena
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
Types of failure in rigid pavements
Types of failure in rigid pavementsTypes of failure in rigid pavements
Types of failure in rigid pavementsAglaia Connect
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringLatif Hyder Wadho
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railwayRAMPRASAD KUMAWAT
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackMani Vel
 
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and railsDeven Diran
 
Dynamic Pile Formulae
Dynamic Pile FormulaeDynamic Pile Formulae
Dynamic Pile FormulaeKriti Singh
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway EngineeringLatif Hyder Wadho
 

What's hot (20)

Railway Engineering: Turnouts
Railway Engineering: TurnoutsRailway Engineering: Turnouts
Railway Engineering: Turnouts
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Railway Planning - Unit 1
Railway Planning - Unit 1Railway Planning - Unit 1
Railway Planning - Unit 1
 
Railway Engineering- Basic Introduction
Railway Engineering- Basic IntroductionRailway Engineering- Basic Introduction
Railway Engineering- Basic Introduction
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Railway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevationRailway Engineering-Curves and superelevation
Railway Engineering-Curves and superelevation
 
Railway track construction, drainage & maintenence
Railway track  construction, drainage & maintenenceRailway track  construction, drainage & maintenence
Railway track construction, drainage & maintenence
 
classification of indian railway
classification of indian railway classification of indian railway
classification of indian railway
 
Different types of rail failures
Different types of rail failuresDifferent types of rail failures
Different types of rail failures
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Types of failure in rigid pavements
Types of failure in rigid pavementsTypes of failure in rigid pavements
Types of failure in rigid pavements
 
Earthwork & track formation Railway Engineering
Earthwork & track formation Railway EngineeringEarthwork & track formation Railway Engineering
Earthwork & track formation Railway Engineering
 
Point and crossing of railway
Point and crossing of railwayPoint and crossing of railway
Point and crossing of railway
 
Railway Engineering - Geometric design of track
Railway Engineering - Geometric design of trackRailway Engineering - Geometric design of track
Railway Engineering - Geometric design of track
 
Points and crossings
Points and crossingsPoints and crossings
Points and crossings
 
1.railway intro and rails
1.railway intro and rails1.railway intro and rails
1.railway intro and rails
 
Dynamic Pile Formulae
Dynamic Pile FormulaeDynamic Pile Formulae
Dynamic Pile Formulae
 
Rail gauges & rail sections Railway Engineering
Rail gauges & rail sections  Railway EngineeringRail gauges & rail sections  Railway Engineering
Rail gauges & rail sections Railway Engineering
 

Similar to Corrugated (roaring), Hogging, Buckling, Kinks in rails

Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent waydhara dattani
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...Hossam Shafiq I
 
Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1AJEETH B
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdfTVijayaGowri
 
POINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptxPOINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptxShruthiBS13
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptxMayuriPatel90
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfTVijayaGowri
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfTURUMELLAVIJAYAGOWRI
 
Railway and highways, Airways material.pptx
Railway and highways, Airways material.pptxRailway and highways, Airways material.pptx
Railway and highways, Airways material.pptxRajuyadav437367
 
SLEEPERS - RAILWAY ENGINEERING
SLEEPERS - RAILWAY ENGINEERINGSLEEPERS - RAILWAY ENGINEERING
SLEEPERS - RAILWAY ENGINEERINGKrishnendu Biswas
 
01-Rail span correction compressor house
01-Rail span correction compressor house01-Rail span correction compressor house
01-Rail span correction compressor houseDeepak kumar sahoo
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railwayKHUSHBU SHAH
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineeringDnyaneshwar More
 
Haulage system in Mines
Haulage system in MinesHaulage system in Mines
Haulage system in Minesajeetkm
 

Similar to Corrugated (roaring), Hogging, Buckling, Kinks in rails (20)

Chapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent wayChapter 1 introductution to railway and permanent way
Chapter 1 introductution to railway and permanent way
 
Railway track
Railway trackRailway track
Railway track
 
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
08 Maintenance of Railway Tracks (Railway Engineering Lectures هندسة السكك ال...
 
Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1Railway planning RHTA - VTU Module 1
Railway planning RHTA - VTU Module 1
 
Rail gauge
Rail gaugeRail gauge
Rail gauge
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
 
POINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptxPOINTS AND CROSSINGS (1) FINAL.pptx
POINTS AND CROSSINGS (1) FINAL.pptx
 
1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx1. Introduction to Railway engg..pptx
1. Introduction to Railway engg..pptx
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
 
Cross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdfCross Section of Permanent Way.pdf
Cross Section of Permanent Way.pdf
 
Railway and highways, Airways material.pptx
Railway and highways, Airways material.pptxRailway and highways, Airways material.pptx
Railway and highways, Airways material.pptx
 
railwaypartPPT
railwaypartPPTrailwaypartPPT
railwaypartPPT
 
SLEEPERS - RAILWAY ENGINEERING
SLEEPERS - RAILWAY ENGINEERINGSLEEPERS - RAILWAY ENGINEERING
SLEEPERS - RAILWAY ENGINEERING
 
CULVERTS.pdf
CULVERTS.pdfCULVERTS.pdf
CULVERTS.pdf
 
railway.pdf
railway.pdfrailway.pdf
railway.pdf
 
01-Rail span correction compressor house
01-Rail span correction compressor house01-Rail span correction compressor house
01-Rail span correction compressor house
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
Introduction railway engineering
Introduction railway engineeringIntroduction railway engineering
Introduction railway engineering
 
Haulage system in Mines
Haulage system in MinesHaulage system in Mines
Haulage system in Mines
 

More from Sagar Kaptan

Micropiling & Heaving of Piles
Micropiling & Heaving of PilesMicropiling & Heaving of Piles
Micropiling & Heaving of PilesSagar Kaptan
 
SUBGRADE SOIL STRENGTH AND ITS EVALUTION
SUBGRADE SOIL STRENGTH AND ITS EVALUTION SUBGRADE SOIL STRENGTH AND ITS EVALUTION
SUBGRADE SOIL STRENGTH AND ITS EVALUTION Sagar Kaptan
 
Functions of management
Functions of managementFunctions of management
Functions of managementSagar Kaptan
 
HDFC (Housing development finance corporation)
HDFC (Housing development finance corporation)HDFC (Housing development finance corporation)
HDFC (Housing development finance corporation)Sagar Kaptan
 
SPRINKLER IRRIGATION
SPRINKLER IRRIGATIONSPRINKLER IRRIGATION
SPRINKLER IRRIGATIONSagar Kaptan
 
Mass transit system
Mass transit systemMass transit system
Mass transit systemSagar Kaptan
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONSagar Kaptan
 
ANALYSIS OF FRAMES USING SLOPE DEFLECTION METHOD
ANALYSIS OF FRAMES USING SLOPE DEFLECTION METHODANALYSIS OF FRAMES USING SLOPE DEFLECTION METHOD
ANALYSIS OF FRAMES USING SLOPE DEFLECTION METHODSagar Kaptan
 
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDINGAPPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDINGSagar Kaptan
 
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...Sagar Kaptan
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectSagar Kaptan
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Floating Concrete Research Paper
Floating Concrete Research PaperFloating Concrete Research Paper
Floating Concrete Research PaperSagar Kaptan
 
Floating Concrete Review Paper
Floating Concrete Review PaperFloating Concrete Review Paper
Floating Concrete Review PaperSagar Kaptan
 

More from Sagar Kaptan (19)

CAUSES OF FLOOD
CAUSES OF FLOODCAUSES OF FLOOD
CAUSES OF FLOOD
 
Micropiling & Heaving of Piles
Micropiling & Heaving of PilesMicropiling & Heaving of Piles
Micropiling & Heaving of Piles
 
SUBGRADE SOIL STRENGTH AND ITS EVALUTION
SUBGRADE SOIL STRENGTH AND ITS EVALUTION SUBGRADE SOIL STRENGTH AND ITS EVALUTION
SUBGRADE SOIL STRENGTH AND ITS EVALUTION
 
RETAINING WALLS
RETAINING WALLSRETAINING WALLS
RETAINING WALLS
 
Functions of management
Functions of managementFunctions of management
Functions of management
 
HDFC (Housing development finance corporation)
HDFC (Housing development finance corporation)HDFC (Housing development finance corporation)
HDFC (Housing development finance corporation)
 
SPRINKLER IRRIGATION
SPRINKLER IRRIGATIONSPRINKLER IRRIGATION
SPRINKLER IRRIGATION
 
Mass transit system
Mass transit systemMass transit system
Mass transit system
 
IMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATIONIMPORTANCE & PURPOSES OF SPECIFICATION
IMPORTANCE & PURPOSES OF SPECIFICATION
 
Pyrolysis
PyrolysisPyrolysis
Pyrolysis
 
ANALYSIS OF FRAMES USING SLOPE DEFLECTION METHOD
ANALYSIS OF FRAMES USING SLOPE DEFLECTION METHODANALYSIS OF FRAMES USING SLOPE DEFLECTION METHOD
ANALYSIS OF FRAMES USING SLOPE DEFLECTION METHOD
 
Coagulants
CoagulantsCoagulants
Coagulants
 
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDINGAPPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
APPLICATION OF ABC ANALYSIS FOR MATERIAL MANAGEMENT OF RESIDENTIAL BUILDING
 
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
BARRIERS TO GOOD OCCUPATIONAL HEALTH & SAFETY (OHS) PRACTICES BY SMALL CONSTR...
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft Project
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Floating Concrete Research Paper
Floating Concrete Research PaperFloating Concrete Research Paper
Floating Concrete Research Paper
 
Floating Concrete Review Paper
Floating Concrete Review PaperFloating Concrete Review Paper
Floating Concrete Review Paper
 
MIS poster
MIS posterMIS poster
MIS poster
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 

Corrugated (roaring), Hogging, Buckling, Kinks in rails

  • 1. GOVERMENT ENGINEERING COLLEGE, BHARUCH  Name : Kaptan sagar r  Enrollment No. : 130140106021  Topic : Corrugated (roaring), Hogging, Buckling, Kinks in rails  Sub : Railway, Bridge and Tunnel Engineering
  • 2. Corrugated (Roaring) Rails In certain places the heads of rails are found to be corrugated rather than straight ones. Such type of rails are known as corrugated rails or roaring rails. When trains pass over such rails, a roaring noise is caused, which is unpleasant to the passengers. The corrugations consists of minute depression on the surface of rails. They are usually created at places where brakes are applied or trains start.
  • 3.
  • 4. i. Corrugation develop in any part of the whole rail gets corrugated in a short time. ii. Corrugation occur at any gradient and on any track, whether a straight track or a curved track. iii. When corrugated rails are relaid in other sections, the corrugation sometimes get smoothened. iv. When new rails are laid in places where corrugation are prevalent, the new rails get corrugated. v. Rails carrying empty trains are easily corrugated than rails carrying loaded trains. Some of the peculiarity of corrugated rails in nature are :
  • 5. Causes of corrugations : i. Where brakes are applied to trains for stopping them. ii. Where trains start. iii. Where the ballast consists of broken bricks. iv. In electrified section of a railway track. v. High speed of trains. vi. Rigid railway track. vii. Use of light wagons and coaches. viii. Steep gradient ix. Slipping of wheels of engine.
  • 6. Remedial Measures The corrugations of rails can be removed by grinding a few thousands of a millimetre of the rail heads. For this purpose, rail grinding trains are used which move at 3 km.ph when the grinders are in action.
  • 7. Hogged Rails Due to battering action of wheels over the end of the rails, the rails get bent down and are deflected at ends. These rails are called ‘hogged rails’. The hogging of the rails is mainly due to loose packing under the joints and loose fish plates. This defect causes rough riding.
  • 8. Remedial measures : 1. Cropping : In this measure, the hogged ends of the rails are cut off and fresh holes for fixing the fish plates are provided. The cutting of rails either is done in workshop or at the site. 2. Welding : Hogged rails are brought to the level by welding the wornout or deflected ends. 3. Replacing : In this method, the hogged rails are completely removed and replaced by new rails. But, this measure is very costly. 4. Dehogging : This method involves straightening the hogged ends
  • 9. Buckling of rails : Buckling of rails means the track has gone out of its original position or alignment due to prevention of expansion of rails in hot weather. Buckling, usually take place on tangent lengths or at curves.
  • 10. Causes : i. When expansion gap between ends of two rails is not sufficient. ii. The fish plates being bolted so tight that the rails are not allowed to slip or expand. iii. Due to welded rails on weak tracks.
  • 11. Remedial measures : i. Sufficient expansion gap should be provided. ii. The fish bolts should not be tightened so much as to prevent the expansion or contraction of rails. iii. The contact surface between the fish plates and rails should be periodically lubricated. iv. Provision of steel sleepers or anchoring of welded rails should be done. v. Number of welded rails should not be large.
  • 12. Kinks in rails : When the ends of adjoining rails move slightly out of position ‘kinks’ or ‘shoulders’ are formed. Causes : i. Loose packing at joints ii. Defect in cross level at joints iii. Defect in gauge and alignment iv. Uneven wear of rail head
  • 13. Effects : i. The kinks causes unpleasant jerks in vehicles. ii. On curves, it causes defect in gauge alignment and camber. Remedial Measures : i. Providing proper packing at joints ii. Correct alignment of joints and curves iii. Periodical maintenance of the track in respect of gauge, welding, cross levels etc.