4. Activities :-
To appoint a project steering
committee
Technical Investigation such as Land
and Geological survey
Non-technical Investigation such as
Economic and Social factors
5. Designing Stage
A detailed cost estimate of the project
can be prepared during this stage
Purpose :-
Complete the Project Summary
Determine method of Construction
Preparation of Drawing Specifications
Decide Project Cost
6. Activities :-
Prepare detailed design and drawing
Prepare detailed specifications
Decide cost of project
Develop the project summary
7. Tendering Stage
Purpose :-
The purpose of this stage is to appoint a
contractor who will undertake the
construction work on the most suitable
terms and conditions of quality and
cost
8. Activities :-
To invite tenders from the contractors
for the construction work and award
the contract
To prepare contract document, to be
signed by the client and the contractor
9. Construction Stage
This stage involves the execution of
construction work as per the design,
drawing and within agreed limits of
time, cost and specified quality
10. Activities :-
Preparation of : - Construction schedule
- Manpower schedule
- Plant and Machinery schedule
- Material delivery schedule
Control of : - Supply of materials and equipments
- supervision for quality control
- Supply of necessary drawings
- co-ordination among sub-contractors
11. Commissioning Stage
Purpose :-
It is the stage in which the performance
of the structure is evaluate
Activities :-
To keep various records of actual work
To prepare operating instructions and maintenance
manuals
To inspect the construction work thoroughly and
have any defects rectified