EXTENSION OF TIME
(E.O.T)
By: Ahmed Ibrahim,PMP,PMI-
RMP,MSc,TOT
1
Professionalengineer
Presentation Objectives
Extension of Time Definition
EOT Triggers
Contractual Completion Date(s)
Primary components
Schedule Integrity
Documentation of Causation
Responsibility Assignment
Concurrency of Delays
Schedule Analysis
Presentation is Everything!
Recap
2
Professionalengineer
Extension of Time Definition
“Is a time which reimbursed by one of the contract
sides to the other as compensation for project events
and conditions, prevented that side from execute
portion of project work .”
3
Professionalengineer
EOT Triggers
 1. An Event Occurred or Will Occur that Causes
Delay
 2. 3 Possible EOT Event Types:
– Owner driven events or risk’s (Time & money)
– Neutral events – risk shared (Time only)
– Concurrent events-risk allocated (Time only)
 3. Causes Delay to the Critical Path.
4
Professionalengineer
Contractual Completion Date(s)
 Types of Contractual Completion Dates:
– „Practical Completion‟ Date
– „Substantial Completion‟ Date
– „Mechanical Completion‟ Date
– „Handover‟ Date
– „Separable Portion‟ Date
 May apply to a Section, or the Entire Project
– Each Section is treated separately
– Multiple EOT Claims May Apply
5
Professionalengineer
Primary components
E.O.T
Claims
Solid Schedule
Critical Path
Delay
Causation
Documentation
Responsibility
assignments
Analysis
technique
Packaging
6
Professionalengineer
Schedule Integrity
 No Open Ends
 Limited Constraints
 All Scope Captured
 Majority of Relationships Types: FS
 No Large Lags: “Float Realistic”
 No Redundant Logic Relationships
 Critical Path Makes Sense
 Critical Path is Continuous
 “Longest Path” Filter Confirmation
7
Professionalengineer
Schedule Integrity
 Obligation of Both the Owner and Contractor
 Contract Must State Schedule Requirements
 Updating Must not Stop after Baseline is Accepted
 Schedule Updates Are Contractual Too!
8
Professionalengineer
Schedule Integrity: How do you
Know?
 Ask for the Electronic Version (Not a PDF)…XER
 Run a Schedule Diagnostic on Baseline & Updates
 Primavera: “Schedule Log” and “Claim Digger”
 Others: Acumen “Fuse”, “Schedule Analyzer Pro” , ”XER
toolkit”
 Also look for..
– Added and/or Deleted Activities
– Increase or Decrease in OD
– Calendar Changes – Schedule Calculation Changes –
9
Professionalengineer
Schedule Integrity: Diagnostic
Tools
10
Professionalengineer
Schedule Integrity: Diagnostic Tools "Claim
Digger”
11
Professionalengineer
Schedule Integrity: Diagnostic Tools “XER
Toolkit”
12
Professionalengineer
Documentation of Causation
 1st: Demonstrate Cause (Documentation)
 2nd: Demonstrate Effect (Schedule Analysis)
 The 3 „R’s – Records, Records, and Records
 Record Type Important but Record Content is A Key!
13
Professionalengineer
Documentation of Causation: Record
Types
 Letters and Emails
 RFI’s
 Hold Registers
 Transmittal Logs
 Progress photographs
 Variation Notices
 Daily Field Reports
 Weekly Progress Reports
 Meeting Minutes
 Drawing Revision Logs
14
Professionalengineer
Documentation of Causation: Record
Content
 Instructions given & received
 Conflicts in plans/specifications
 Weather conditions: Not Just Rain
 Work Stoppage: Time Stopped and Why
 Subcontractors
 Equipment Type Utilized and Number
 Daily Activity of Staff
 Specific Location: Zone Number, Area…etc
 Delays Encountered: Specific Activity
 Material Shortages Create a Standardized Daily
Report Form
15
Professionalengineer
Documentation of Causation: Delay
Examples
 Weather
1-We can not continue in excavation
2-We can not pouring the –
ready mix concrete
16
Professionalengineer
Documentation of Causation: Delay
Examples
 Equipment & Material Problems
1-excavation hydraulic pipe broken again
2-Power generator is down again
17
Professionalengineer
Documentation of Causation: Delay
Examples
 Design issues
 Environmental
 Site accidents
18
Professionalengineer
Responsibility Assignment
 What Does the Contract Say?
– Owner Caused Delays
– Force Majeure Delays
– Neutral Delays-Weather
– Non-Excusable Delays
19
Professionalengineer
Concurrent Delay – Requirements…
 Two or more delays during the “same” time
 Delays unrelated and independent
 Must delay the critical path
 Responsibility of different parties
 Each party bears its own expenses for that delay
 Substantial and not easily curable
20
Professionalengineer
Concurrency: Net Affect Matrix
Delay event Concurrent with Net effect
Owner delay Another delay by owner xxx
Owner delay Another delay by owner xxxx
Contractor delay Force majeure delay xx
Contractor delay
Another contractor
delay
xxxxxx
21
Professionalengineer
Schedule Analysis:
 1.As-Planned vs. As-Built
 2.Windows Analysis
 3.TIA
22
Professionalengineer
As-Planned vs. As-Built
 Comparison of start/finish dates between two schedule
updates
 Purely mathematical-Variance between dates
23
Professionalengineer
As-Planned vs. As-Built
 When should it be used?
-Limited time and money
-No electronic schedules
-Inadequate schedule logic
24
Professionalengineer
As-Planned vs. As-Built
Not Good For:
– Concurrent delays or acceleration
– Critical path changes between updates
– Multiple critical or near-critical paths per update
– Recovering extended overhead costs
– Arbitration or Litigation
25
Professionalengineer
As-Planned vs. As-Built
Pros:
– Easy to understand, explain, and graphically depict
– Technically simple to perform
Data Required:
– Baseline schedule
– As-built schedule
26
Professionalengineer
Windows Analysis
 Quantify loss or gain of time along a float path
 Loss and gains tallied by window
 A “window” is the time period framed between two
revisions:
• The as-planned schedule for the beginning of the
window
• The as-built schedule for the end of the window As-
Planned As- Built
27
Professionalengineer
Windows Analysis
28
Professionalengineer
Windows Analysis
 When Should the Schedule Analysis Method be Used?
– Complex schedules with large critical paths
– Very high delay damages
– Concurrent delays
– Client has the time and budget
– Need graphical depiction of concurrency
 What does the Schedule Analysis Method Best Prove?
– Excusable non-compensable delay
– Excusable compensable delay
– Concurrent delay
29
Professionalengineer
Impacted As-Planned (TIA)
 Insertion of impact activities into a baseline or update schedule
 Integrated into the network logic before, in- between, or after the
activity it affected
 Additive model that simulates the possible effect of actual delay
events to the schedule completion date
 Comparison of IAP schedule and succeeding update to determine
possible acceleration or non-excusable delays
 Comparison of IAP schedule and planned schedule to determine
time extension
30
Professionalengineer
Impacted As-Planned
31
Professionalengineer
Impacted As-Planned
32
Professionalengineer
Presentation
 1. Attach Source Documentation
 2. Graphical Representation
• Schedule Updates: Prior to Impact and After Impact
• Critical Path in Gantt Chart Format with Logic
• Concurrency
 3. Write Up
• Keep it Short and Sweet (Ishikawa , Pareto and time lines)
• Explanation of Impact Event: Timing , Activities , Duration
33
Professionalengineer
Presentation
 4. Cost Impact
• Stand-By Costs of Equipment and Staff Affected
• Don't Claim Costs on Staff That Were Working!
5. Executive Summary at the Beginning
6. Submit Once Impact Event Is Known
7. Submit Again Once Full Impact Understood
34
Professionalengineer
Ishikawa example
Management process and
Procedure
Too much process and unneeded
procedure activities which take
more time
All major and minor decisions by PM
only
Q u a l I t y C o n t r o l P r o c e
PM staff came very late to
project
Material submittals take
unusual review time
Shop drawing submittals
take unusual review time
Open R.F.Is which hold much
works
Delay in issuing (L.O.Is)
Poor Coordination Management
Hold Critical schedule
work areas
Salco work with site
premises
Professionalengineer
Pareto Chart-(20/80)Rule
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
10
20
30
40
50
60
70
80
90
100
Material submittals
review>15days
Shop drawing review
>15days
General Project
Submittals
Issuing LOIs Open RFIs Exceeding project
specifications
Pareto Chart-(20/80)Rule
OCCURRENCES CUMULATIVE PERCENT
Professionalengineer
Summary
• Documentation is Key: Content Must be Consistent
• Schedules Must Be Sound and Accurate
• Don't Ignore Updates
• Choose Your Technique Wisely
• Consider Concurrency
• Present Claim as a Concise Package
• Don't Throw the Kitchen Sink into the Claim
• Resolution time sure will be near to your EOT issue
37
WWW.PROFESSIONALENGINEERS.US
PROFESSIONAL2ENGINEERS@GMAIL.COM
0545821579
Ahmed Ibrahim,MSc,BSc,PMP,PMI-RMP,TOT
Thank
You…
38

More Related Content

What's hot

Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...Gaurav Verma
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 

What's hot (20)

Construction delays
Construction delaysConstruction delays
Construction delays
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Claims
ClaimsClaims
Claims
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 

Similar to Extension of time (E.O.T) By Ahmed Ibarhim

EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptyashchotaliyael21
 
Lecture6
Lecture6Lecture6
Lecture6soloeng
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...Egyptian Engineers Association
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 ) SAJJAD KHUDHUR ABBAS
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.pptUtkarshDwivedi74
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
edSe275 ms project-assignment
edSe275 ms project-assignmentedSe275 ms project-assignment
edSe275 ms project-assignmentharinathinfotech
 
Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02kongara
 

Similar to Extension of time (E.O.T) By Ahmed Ibarhim (20)

08 ch06
08 ch0608 ch06
08 ch06
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
 
Lecture6
Lecture6Lecture6
Lecture6
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Intro to PM.ppt
Intro to PM.pptIntro to PM.ppt
Intro to PM.ppt
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
139 مبادرة #تواصل_تطوير المحاضرة ال 139 من المبادرة مهندس / محمد ماجد استشاري...
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Episode 30 : Project Execution ( Part 1 )
Episode 30 :  Project Execution ( Part 1 ) Episode 30 :  Project Execution ( Part 1 )
Episode 30 : Project Execution ( Part 1 )
 
lec11.ppt
lec11.pptlec11.ppt
lec11.ppt
 
Traditional Management System.ppt
Traditional Management System.pptTraditional Management System.ppt
Traditional Management System.ppt
 
C10 project management
C10 project managementC10 project management
C10 project management
 
C10 project management
C10 project managementC10 project management
C10 project management
 
edSe275 ms project-assignment
edSe275 ms project-assignmentedSe275 ms project-assignment
edSe275 ms project-assignment
 
Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02Pert cpm-120421125920-phpapp02
Pert cpm-120421125920-phpapp02
 

More from Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP

Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)
Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)
Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...25 11-big 5- critical success factors for applying (OPM)governance in MENA re...
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP
 

More from Ahmed Al-Senosy Ph.D(cand),MSc,PMP,RMP (13)

Masar alryadah Arabic profile
Masar alryadah  Arabic profileMasar alryadah  Arabic profile
Masar alryadah Arabic profile
 
Masar alryadah English profile
Masar alryadah  English profileMasar alryadah  English profile
Masar alryadah English profile
 
Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)
Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)
Hybrid Module for Applying Projects Portfolio Management with PMO(8 3-2018)
 
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...
Big5 Saudi (7-3-2018)- Critical Success Factors for Applying (Organizational ...
 
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...25 11-big 5- critical success factors for applying (OPM)governance in MENA re...
25 11-big 5- critical success factors for applying (OPM)governance in MENA re...
 
Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.Curcial Factors that affect Cost Management.
Curcial Factors that affect Cost Management.
 
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
final thisis 2016,Ahmed Alsenosy,BPCPM of applying PMI Module in construction...
 
Pmp taking first attempt public
Pmp taking first attempt  publicPmp taking first attempt  public
Pmp taking first attempt public
 
Hbrc professional engineers-presentation
Hbrc professional engineers-presentationHbrc professional engineers-presentation
Hbrc professional engineers-presentation
 
الموارد البشريه والانتاجيه والتحفيز
الموارد البشريه والانتاجيه والتحفيزالموارد البشريه والانتاجيه والتحفيز
الموارد البشريه والانتاجيه والتحفيز
 
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5PMP,Lecture 1 Projects Frame Work based on PMBOK v5
PMP,Lecture 1 Projects Frame Work based on PMBOK v5
 
Offline pmp course
Offline pmp courseOffline pmp course
Offline pmp course
 
organization charts....rules
organization charts....rulesorganization charts....rules
organization charts....rules
 

Recently uploaded

Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for LearningCIToolkit
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 

Recently uploaded (20)

Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 

Extension of time (E.O.T) By Ahmed Ibarhim