Test Unit TST300
1 Functional Description
The test unit TST-300 is designed to test the purging plugs between in the ladle
preparation area.
This to avoid purging failures in the following heat and to prevent the purging
plug from unnecessary cleaning (burning, torching) with oxygen.
Nitrogen or compressed air is used as test media. It‘s not allowed to use natural
gas or any other inflammable gas.
The actual flow rate is between a predefined upper and lo-
wer limit > the porous plug is in good working condition.
The actual flow rate is above the higher limit > there could
be a leakage in the piping.
The actual flow rate is below the lower limit > the plug is
blocked or partly blocked, oxygen washing could be requi-
red (depending on the plug type)
Test Functions:
Plug Test (Test):
The plug test function generates an indication about the porous plug condition.
At a predefined pressure setting the actual flow rate is measured. The actual
flow rate defines the condition of the plug. Three levels are defined:
FC Technik AG Test Unit TST300 page 1
Green:
Orange:
Red:
Oxygen washing support (Bypass):
During the washing procedure with an oxygen lance, a continuous flow rate
trough the plug is produced. The flow rate is monitored continuously, as soon as
the flow rate exceeds a predefined limitation an indication is generated to stop
further oxygen washing.
	 to preserve the refractory material
	 safety due to less burning procedures
	 time savings
	 reproducibility and reliability
The TST is independent from the volumetric capacity, corresponding the height
of the ladle and the amount of plugs integrated in the ladle bottom.
Especially at big size ladles it is difficult to strike the surface of the plug with
the tip of the O2-lance while burning. This depends in general of the weight
and the length, e.g. more than 5 m is not unusual of the pipe. The handling is
offen very difficult for the worker and it needs time for the cleaning procedure.
The result is, that time of burning expands too long and is then inefficient due
to higher abrasion occurred at the refractory of the well-block and of course
the head of the purging plug. This limits the durability of the bottom purging
system and increase times of assembling and changing.
So it is very important to recognize before cleaning wether the plug is per-
meable or blogged. In case the plug is free no burning is necessary (priori-
ty advantage). The TST immediately detects the flow and pressure (test time
runs up to only 30 sec.) which fits at the plug and gives the just-in-time datas
directly to the operation screen and indicates simultaneously a signal by lamp
or buzzer. The exact measured flow and pressure supports the following pro-
cedure in the ladle refining process.
The documentation of the measured Datas helps to achieve a constant re-
peatable process too.
2 Advatages
●
●
●
●
FC Technik AG Test Unit TST300 page 2
FC Technik AG
St. Gallerstrasse 340
CH-8409 Winterthur
Tel. +41 52 238 01 75
Fax +41 52 238 01 77
fc-technik@bluewin.ch
www.fc-techni.ch
Salzgitter Flachstahl GmbH
ArcelorMittal Eisenhüttenstadt
ArcelorMittal Hamburg
Elbe Edelstahlwerke Feralpi GmbH
DEW Siegen (order is placed)
3 References
●
●
●
●
●
FC Technik AG Test Unit TST300 page 3

More Related Content

Viewers also liked

Alexandra bedoya-Postmodernismo
Alexandra bedoya-PostmodernismoAlexandra bedoya-Postmodernismo
Alexandra bedoya-PostmodernismoNattPr
 
Developing and Pricing Products Ch: 2 for MBA
Developing and Pricing Products Ch: 2 for MBADeveloping and Pricing Products Ch: 2 for MBA
Developing and Pricing Products Ch: 2 for MBAMuhammad Khan
 
Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...
Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...
Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...Rafael Serrano Rodríguez
 
99 idee social vol3 parma 12-13-14 ottobre 2012
99 idee social vol3   parma 12-13-14 ottobre 201299 idee social vol3   parma 12-13-14 ottobre 2012
99 idee social vol3 parma 12-13-14 ottobre 2012Massimo Zilioli
 
Collaborative Studio Design Team Workbook
Collaborative Studio Design Team WorkbookCollaborative Studio Design Team Workbook
Collaborative Studio Design Team WorkbookJames Chun
 
Novedades Ediciones Rialp
Novedades Ediciones RialpNovedades Ediciones Rialp
Novedades Ediciones RialpAlberto Tarifa
 
From Keyword to Topic Research - Von der Keywordrecherche zur Themenrecherche
From Keyword to Topic Research - Von der Keywordrecherche zur ThemenrechercheFrom Keyword to Topic Research - Von der Keywordrecherche zur Themenrecherche
From Keyword to Topic Research - Von der Keywordrecherche zur ThemenrechercheFlorian Stelzner
 
Foro innovacion beeva 28 01-2014 -open business and the business of APIs
Foro innovacion beeva 28 01-2014 -open business and the business of APIsForo innovacion beeva 28 01-2014 -open business and the business of APIs
Foro innovacion beeva 28 01-2014 -open business and the business of APIsBEEVA_es
 
User Management and SSO for Austrian Government
User Management and SSO for Austrian GovernmentUser Management and SSO for Austrian Government
User Management and SSO for Austrian Governmentbkraft
 
Criminología ambiental
Criminología ambientalCriminología ambiental
Criminología ambientalWael Hikal
 

Viewers also liked (13)

Alexandra bedoya-Postmodernismo
Alexandra bedoya-PostmodernismoAlexandra bedoya-Postmodernismo
Alexandra bedoya-Postmodernismo
 
Developing and Pricing Products Ch: 2 for MBA
Developing and Pricing Products Ch: 2 for MBADeveloping and Pricing Products Ch: 2 for MBA
Developing and Pricing Products Ch: 2 for MBA
 
Flyer auja
Flyer aujaFlyer auja
Flyer auja
 
Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...
Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...
Indicadores de Transparencia Municipal 2012. Ayuntamiento de El Puerto de San...
 
99 idee social vol3 parma 12-13-14 ottobre 2012
99 idee social vol3   parma 12-13-14 ottobre 201299 idee social vol3   parma 12-13-14 ottobre 2012
99 idee social vol3 parma 12-13-14 ottobre 2012
 
Collaborative Studio Design Team Workbook
Collaborative Studio Design Team WorkbookCollaborative Studio Design Team Workbook
Collaborative Studio Design Team Workbook
 
Novedades Ediciones Rialp
Novedades Ediciones RialpNovedades Ediciones Rialp
Novedades Ediciones Rialp
 
Horno Smeg SFP140S
Horno Smeg SFP140SHorno Smeg SFP140S
Horno Smeg SFP140S
 
From Keyword to Topic Research - Von der Keywordrecherche zur Themenrecherche
From Keyword to Topic Research - Von der Keywordrecherche zur ThemenrechercheFrom Keyword to Topic Research - Von der Keywordrecherche zur Themenrecherche
From Keyword to Topic Research - Von der Keywordrecherche zur Themenrecherche
 
Foro innovacion beeva 28 01-2014 -open business and the business of APIs
Foro innovacion beeva 28 01-2014 -open business and the business of APIsForo innovacion beeva 28 01-2014 -open business and the business of APIs
Foro innovacion beeva 28 01-2014 -open business and the business of APIs
 
User Management and SSO for Austrian Government
User Management and SSO for Austrian GovernmentUser Management and SSO for Austrian Government
User Management and SSO for Austrian Government
 
Tu cerebro creativo pedro
Tu cerebro creativo pedroTu cerebro creativo pedro
Tu cerebro creativo pedro
 
Criminología ambiental
Criminología ambientalCriminología ambiental
Criminología ambiental
 

Recently uploaded

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentBharaniDharan195623
 

Recently uploaded (20)

Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managament
 

SGTEX Inc. Steel Ladle purging plug test unit by FC Technik AG

  • 1. Test Unit TST300 1 Functional Description The test unit TST-300 is designed to test the purging plugs between in the ladle preparation area. This to avoid purging failures in the following heat and to prevent the purging plug from unnecessary cleaning (burning, torching) with oxygen. Nitrogen or compressed air is used as test media. It‘s not allowed to use natural gas or any other inflammable gas. The actual flow rate is between a predefined upper and lo- wer limit > the porous plug is in good working condition. The actual flow rate is above the higher limit > there could be a leakage in the piping. The actual flow rate is below the lower limit > the plug is blocked or partly blocked, oxygen washing could be requi- red (depending on the plug type) Test Functions: Plug Test (Test): The plug test function generates an indication about the porous plug condition. At a predefined pressure setting the actual flow rate is measured. The actual flow rate defines the condition of the plug. Three levels are defined: FC Technik AG Test Unit TST300 page 1 Green: Orange: Red:
  • 2. Oxygen washing support (Bypass): During the washing procedure with an oxygen lance, a continuous flow rate trough the plug is produced. The flow rate is monitored continuously, as soon as the flow rate exceeds a predefined limitation an indication is generated to stop further oxygen washing. to preserve the refractory material safety due to less burning procedures time savings reproducibility and reliability The TST is independent from the volumetric capacity, corresponding the height of the ladle and the amount of plugs integrated in the ladle bottom. Especially at big size ladles it is difficult to strike the surface of the plug with the tip of the O2-lance while burning. This depends in general of the weight and the length, e.g. more than 5 m is not unusual of the pipe. The handling is offen very difficult for the worker and it needs time for the cleaning procedure. The result is, that time of burning expands too long and is then inefficient due to higher abrasion occurred at the refractory of the well-block and of course the head of the purging plug. This limits the durability of the bottom purging system and increase times of assembling and changing. So it is very important to recognize before cleaning wether the plug is per- meable or blogged. In case the plug is free no burning is necessary (priori- ty advantage). The TST immediately detects the flow and pressure (test time runs up to only 30 sec.) which fits at the plug and gives the just-in-time datas directly to the operation screen and indicates simultaneously a signal by lamp or buzzer. The exact measured flow and pressure supports the following pro- cedure in the ladle refining process. The documentation of the measured Datas helps to achieve a constant re- peatable process too. 2 Advatages ● ● ● ● FC Technik AG Test Unit TST300 page 2
  • 3. FC Technik AG St. Gallerstrasse 340 CH-8409 Winterthur Tel. +41 52 238 01 75 Fax +41 52 238 01 77 fc-technik@bluewin.ch www.fc-techni.ch Salzgitter Flachstahl GmbH ArcelorMittal Eisenhüttenstadt ArcelorMittal Hamburg Elbe Edelstahlwerke Feralpi GmbH DEW Siegen (order is placed) 3 References ● ● ● ● ● FC Technik AG Test Unit TST300 page 3