SlideShare a Scribd company logo
1 of 46
Anbarasu B
Erection and commissioning Engineer
2*600MW ITPCL Power project
Cuddalore-India
SWITCHYARD:
Switchyard will exist at a generating station to
coordinate the exchange of power between the
generators and the transmission lines.
PURPOSE & NECESSITY OF SWITCHYARD
Generatedpowertobeevacuatedtoloadcentersforconsumption.
Generatingstationsarefarfromloadcenters.
Theprocessof
Generation Transmission Consumption/Load center
(in22kV) (in400kV) (in230V)
Air insulated switchyard
Limitation of AIS
 Large dimensions due to statutory clearances
and poor dielectric strength of air.
 Wastage of space.
 Life of steel structures degrades.
 Seismic instability.
 Large planning & execution time.
 Regular maintenance of the substation
required.
Gas Insulated Switchgear
Gas Insulated Switchgear (GIS), where the
conductors and equipments are insulated by
pressurized sulphur hexafluoride gas(SF6).
I. Outdoor GIS (without screen house)
II. Indoor GIS (with screen house)
• Outdoor GIS • Indoor GIS
Merits of GIS
 The space occupied by switch gear is greatly
reduced.
 Totally unaffected by atmospheric conditions.
 Provides high operational reliability.
 Easier to install in difficult site conditions.
 Installation time is lesser than air insulated
switchgear.
TECHNICAL PARAMETERS OF GIS
 Make: Xian XD Electric switchgear Co.,Ltd
 System nominal voltage: 400kV
 Maximum working voltage: 550kV
 Rated current: 4000A
 Rated frequency: 50Hz
 Rated short-circuit breaking current: 63kA for 1sec
 Rated peak withstand current: 170kA
 Rated control voltage: 220V DC
 SF6 Gas pressure at 20°C: 0.5Mpa (Breaker chamber)
0.4Mpa (other gas chamber)
Typical Layout Of 1½ Breaker Scheme
One & Half Breaker Description
 In this two buses are provided.
 These two buses are inter-connected by three circuit
breakers.
 They are designated as 1-52 CB, 2-52 CB, and 3-52 CB.
 Line - 1 is connected in between 1-52 CB & 2-52 CB.
 Line - 2 is connected in between 3-52 CB & 2-52 CB.
 Line-1 having two feeding paths i.e.
A. Via bus-1 & 1-52 CB
B. Via bus-2, 3-52CB & 2-52CB
 Line-2 having two feeding paths i.e.
A. Via bus-2 & 3-52 CB
B. Via bus-1, 1-52CB & 2-52CB
 For interrupting line-1 the 1-52CB and 2-52CB is to be
tripped.
 For interrupting line-2 the 3-52CB and 2-52CB is to be
tripped.
 For any problem in line-1 or line-2 along with main breaker, the
tie breaker (2-52 CB) must trip.
 Normally in all types of busbar configurations one breaker is
sufficient for one feeder.
 Here two feeders are controlled by three breakers.
 So these two feeders controlled by three circuit breakers 1-52
CB,2-52CB & 3-52CB.
It is called one & half breaker system.
 The bay between bus-1 & line-1 is called main bay for feeder-1.
 The bay between line-1 & line-2 is called tie bay for feeder-1 &
2.
 The bay between bus-2 & line-2 is called main bay for feeder-2.
 In this system full dia means 2 feeders controlled by 3 CBs.
 Half dia means 1 feeder controlled by 2 CBs.
GIS EQUIPMENT
• Bus bar
• Circuit breaker
• Disconnecting switch
• Earthing switch
• Current transformer
• Voltage transformer
• SF6 to air termination
• Lightning arrestor
• Capacitance voltage transformer
• Wave trap
Outdoor
equipments
Circuit Breaker
Arcing Chamber
Disconnecting Switches Earthing Switches
CURRENT TRANSFORMER
VOLTAGE TRANSFORMER
SF6 to Air Termination
Properties of SF6
• Non-toxic, very stable chemically.
• Insulating properties is 3-times more than air.
• Colorless & heavier than air.
• Density is 5 times more than air.
• Non inflammable.
Compactness of GIS
• Saving of land depending upon voltage level.
• Land required is 10-20% of AIS.
Concept & Design of GIS
Type of insulator in GIS modules
Bellow and Flange
Bellow Flange
Impact of insulating medium on size of the
switchyard
Voltage Level Bay Width AIS Bay Width GIS
132KV 12m 1m
220KV 18m 2m
400KV 27m 3.6m
765KV 51.5m 6.5m
ERECTION AND COMMISSIONING
 Switchgear assemblies are split into optimized
shipping units for easy transport.
 Quick installation is facilitated because of easy to
handle factory assembled modular units.
 Need of special tools for erection is very less.
 Take less time to check all switching devices and
control circuits.
 All flanges are double checked for tightness.
 All tests are performed in accordance with IEC
standards.
Lifting of equipment by using EOT crane
Step:1 Assemble of circuit breaker an its mechanism box by using
EOT crane.
ERECTION OF GIS EQUIPMENT
Step:2 Erection of walk way over circuit breaker
Step3: Install the current transformer
on the circuit-breakers
Step4: Assemble the disconnectors and
earthing switches on to the current
transformer.
OVERVIEW OF CB, CT & DS AFTER ASSEMBLED
Step5: Install the interconnecting straight enclosures with bellows on to Bus CB
to Tie CB section.
Step6: install straight enclosure on tie breaker section to connect feeder
disconnector.
Step7: Install voltage transformer next to the feeder disconnector with
earth switch
Step8: At last erect the main bus-1 & bus-2 straight enclosure.
MAIN BUS-1 & 2
SECTIONAL VIEW OF GIS
Gantry structure from transformer to GIS
building
View of GIS to LILO
SEGRECATION OF GAS COMPARTMENT
PARTITION CONCEPT
SF6 gas pressure gauge
Life Cycle & Cost of GIS
 Life cycle of GIS is about 50 years, where as for AIS life
cycle is 25 years.
 Approximate cost per bay for 400 KV of GIS & AIS is as
follows:
GIS 7-8 crores
AIS 4-5 crores.
Hence initial cost of GIS is approximately
1.5-1.7 times that of AIS.
 When all merits over the life cycle of GIS is considered
then GIS becomes techno-economic feasible than AIS.
Demerits of GIS
 High cost compared to conventional
substation(AIS).
 Excessive damage in case of internal fault.
 Diagnosis of internal fault and rectifying takes
very long time (high outage time).
 Reduction in the pressure of the SF6 gas in
any module results in flash over and faults.
 SF6 causes ozone depletion and global
warming.
CONCLUSION
 Excellent adoptability due to low space
requirement and high dielectric strength of SF6
gas.
 Short erection and commissioning time.
 Safety to operators
 less requirement of maintenance.
 Initial cost of GIS is higher than AIS, but when all
merits and life cycle cost of GIS is considered the
GIS becomes techno-economic feasible than AIS.
GIS  400kv substation

More Related Content

What's hot

Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,Sameer Kumar
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersSARAVANAN A
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)Power System Operation
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSPradeep Avanigadda
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationshivashankar307
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substationIshank Ranjan
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationraiamitesh8
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protectionsrini09
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationankesh kumar
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...jbpatel7290
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationhimanshu kumar
 

What's hot (20)

GIS-NESCL-6
GIS-NESCL-6GIS-NESCL-6
GIS-NESCL-6
 
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,Gis ppt (gas insulated sub station)  deepak kumar kannaujiya,
Gis ppt (gas insulated sub station) deepak kumar kannaujiya,
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)Gas Insulated Switchgear?  Gas-Insulated High-Voltage Switchgear (GIS)
Gas Insulated Switchgear? Gas-Insulated High-Voltage Switchgear (GIS)
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
Busbar configuarations
Busbar configuarationsBusbar configuarations
Busbar configuarations
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 
Gas insulated substation.
Gas insulated substation.Gas insulated substation.
Gas insulated substation.
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
Bus Bar protection
Bus Bar protectionBus Bar protection
Bus Bar protection
 
220 kv G.S.S (report)
220 kv G.S.S (report)220 kv G.S.S (report)
220 kv G.S.S (report)
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substation
 
HVDC
HVDC HVDC
HVDC
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
 
substation internship report
substation internship report substation internship report
substation internship report
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 

Similar to GIS 400kv substation

Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSoumya Raj Poddar
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxborapring
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Power System Operation
 
Gas insulated substation 2
Gas insulated substation 2Gas insulated substation 2
Gas insulated substation 2naga pooja
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationAjay Kuriakose
 
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstationraja sukumar
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentationRamendra Dhiman
 
HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014Kanai Banerjee
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report imkanhaiyalal
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1Ronal Parmar
 
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationModeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationIRJET Journal
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptxssuser1b3e431
 
Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...Engineers Australia
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationRaushanKumar582
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3Ronal Parmar
 
substation 101
substation 101substation 101
substation 101danica11
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...f95346
 

Similar to GIS 400kv substation (20)

Seminar on Gas Insulated Substation
Seminar on Gas Insulated SubstationSeminar on Gas Insulated Substation
Seminar on Gas Insulated Substation
 
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptxChapter 11 Introduction to Gas Insulation Substation (GIS).pptx
Chapter 11 Introduction to Gas Insulation Substation (GIS).pptx
 
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
Medium-Voltage, Gas-Insulated Arc-Resistant Switchgear Types 8DA10 & 8DB10
 
Gas insulated substation 2
Gas insulated substation 2Gas insulated substation 2
Gas insulated substation 2
 
Ppt
PptPpt
Ppt
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Gases insulation powerstation
Gases  insulation powerstationGases  insulation powerstation
Gases insulation powerstation
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014HarmonicFilter_VFDdrives2014
HarmonicFilter_VFDdrives2014
 
132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report 132 KV GSS NPH jodhpur treaning report
132 KV GSS NPH jodhpur treaning report
 
Gas insulated substation 1
Gas insulated substation 1Gas insulated substation 1
Gas insulated substation 1
 
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated SubstationModeling and Analysis of a 3-Phase 132kv GasInsulated Substation
Modeling and Analysis of a 3-Phase 132kv GasInsulated Substation
 
220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx220kv-switch-yard-ppt.pptx
220kv-switch-yard-ppt.pptx
 
Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...Jacobs Recent changes to transmission line design standards and the impact on...
Jacobs Recent changes to transmission line design standards and the impact on...
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
132kv G.S.S. Jalore
132kv G.S.S. Jalore132kv G.S.S. Jalore
132kv G.S.S. Jalore
 
Gas insulated sub station 3
Gas insulated sub station 3Gas insulated sub station 3
Gas insulated sub station 3
 
Gagan
GaganGagan
Gagan
 
substation 101
substation 101substation 101
substation 101
 
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
Analysis of example_capacitor_bank_switching_solution_and_recommendations_for...
 

Recently uploaded

TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 

Recently uploaded (20)

TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 

GIS 400kv substation

  • 1. Anbarasu B Erection and commissioning Engineer 2*600MW ITPCL Power project Cuddalore-India
  • 2. SWITCHYARD: Switchyard will exist at a generating station to coordinate the exchange of power between the generators and the transmission lines. PURPOSE & NECESSITY OF SWITCHYARD Generatedpowertobeevacuatedtoloadcentersforconsumption. Generatingstationsarefarfromloadcenters. Theprocessof Generation Transmission Consumption/Load center (in22kV) (in400kV) (in230V)
  • 4. Limitation of AIS  Large dimensions due to statutory clearances and poor dielectric strength of air.  Wastage of space.  Life of steel structures degrades.  Seismic instability.  Large planning & execution time.  Regular maintenance of the substation required.
  • 5. Gas Insulated Switchgear Gas Insulated Switchgear (GIS), where the conductors and equipments are insulated by pressurized sulphur hexafluoride gas(SF6). I. Outdoor GIS (without screen house) II. Indoor GIS (with screen house)
  • 6. • Outdoor GIS • Indoor GIS
  • 7. Merits of GIS  The space occupied by switch gear is greatly reduced.  Totally unaffected by atmospheric conditions.  Provides high operational reliability.  Easier to install in difficult site conditions.  Installation time is lesser than air insulated switchgear.
  • 8. TECHNICAL PARAMETERS OF GIS  Make: Xian XD Electric switchgear Co.,Ltd  System nominal voltage: 400kV  Maximum working voltage: 550kV  Rated current: 4000A  Rated frequency: 50Hz  Rated short-circuit breaking current: 63kA for 1sec  Rated peak withstand current: 170kA  Rated control voltage: 220V DC  SF6 Gas pressure at 20°C: 0.5Mpa (Breaker chamber) 0.4Mpa (other gas chamber)
  • 9.
  • 10. Typical Layout Of 1½ Breaker Scheme
  • 11. One & Half Breaker Description
  • 12.  In this two buses are provided.  These two buses are inter-connected by three circuit breakers.  They are designated as 1-52 CB, 2-52 CB, and 3-52 CB.  Line - 1 is connected in between 1-52 CB & 2-52 CB.  Line - 2 is connected in between 3-52 CB & 2-52 CB.  Line-1 having two feeding paths i.e. A. Via bus-1 & 1-52 CB B. Via bus-2, 3-52CB & 2-52CB  Line-2 having two feeding paths i.e. A. Via bus-2 & 3-52 CB B. Via bus-1, 1-52CB & 2-52CB  For interrupting line-1 the 1-52CB and 2-52CB is to be tripped.  For interrupting line-2 the 3-52CB and 2-52CB is to be tripped.
  • 13.  For any problem in line-1 or line-2 along with main breaker, the tie breaker (2-52 CB) must trip.  Normally in all types of busbar configurations one breaker is sufficient for one feeder.  Here two feeders are controlled by three breakers.  So these two feeders controlled by three circuit breakers 1-52 CB,2-52CB & 3-52CB. It is called one & half breaker system.  The bay between bus-1 & line-1 is called main bay for feeder-1.  The bay between line-1 & line-2 is called tie bay for feeder-1 & 2.  The bay between bus-2 & line-2 is called main bay for feeder-2.  In this system full dia means 2 feeders controlled by 3 CBs.  Half dia means 1 feeder controlled by 2 CBs.
  • 14. GIS EQUIPMENT • Bus bar • Circuit breaker • Disconnecting switch • Earthing switch • Current transformer • Voltage transformer • SF6 to air termination • Lightning arrestor • Capacitance voltage transformer • Wave trap Outdoor equipments
  • 19. SF6 to Air Termination
  • 20. Properties of SF6 • Non-toxic, very stable chemically. • Insulating properties is 3-times more than air. • Colorless & heavier than air. • Density is 5 times more than air. • Non inflammable.
  • 21. Compactness of GIS • Saving of land depending upon voltage level. • Land required is 10-20% of AIS.
  • 23. Type of insulator in GIS modules
  • 25. Impact of insulating medium on size of the switchyard Voltage Level Bay Width AIS Bay Width GIS 132KV 12m 1m 220KV 18m 2m 400KV 27m 3.6m 765KV 51.5m 6.5m
  • 26. ERECTION AND COMMISSIONING  Switchgear assemblies are split into optimized shipping units for easy transport.  Quick installation is facilitated because of easy to handle factory assembled modular units.  Need of special tools for erection is very less.  Take less time to check all switching devices and control circuits.  All flanges are double checked for tightness.  All tests are performed in accordance with IEC standards.
  • 27. Lifting of equipment by using EOT crane
  • 28. Step:1 Assemble of circuit breaker an its mechanism box by using EOT crane. ERECTION OF GIS EQUIPMENT
  • 29. Step:2 Erection of walk way over circuit breaker
  • 30. Step3: Install the current transformer on the circuit-breakers Step4: Assemble the disconnectors and earthing switches on to the current transformer.
  • 31. OVERVIEW OF CB, CT & DS AFTER ASSEMBLED
  • 32. Step5: Install the interconnecting straight enclosures with bellows on to Bus CB to Tie CB section.
  • 33. Step6: install straight enclosure on tie breaker section to connect feeder disconnector.
  • 34. Step7: Install voltage transformer next to the feeder disconnector with earth switch
  • 35. Step8: At last erect the main bus-1 & bus-2 straight enclosure.
  • 38. Gantry structure from transformer to GIS building
  • 39. View of GIS to LILO
  • 40. SEGRECATION OF GAS COMPARTMENT
  • 43. Life Cycle & Cost of GIS  Life cycle of GIS is about 50 years, where as for AIS life cycle is 25 years.  Approximate cost per bay for 400 KV of GIS & AIS is as follows: GIS 7-8 crores AIS 4-5 crores. Hence initial cost of GIS is approximately 1.5-1.7 times that of AIS.  When all merits over the life cycle of GIS is considered then GIS becomes techno-economic feasible than AIS.
  • 44. Demerits of GIS  High cost compared to conventional substation(AIS).  Excessive damage in case of internal fault.  Diagnosis of internal fault and rectifying takes very long time (high outage time).  Reduction in the pressure of the SF6 gas in any module results in flash over and faults.  SF6 causes ozone depletion and global warming.
  • 45. CONCLUSION  Excellent adoptability due to low space requirement and high dielectric strength of SF6 gas.  Short erection and commissioning time.  Safety to operators  less requirement of maintenance.  Initial cost of GIS is higher than AIS, but when all merits and life cycle cost of GIS is considered the GIS becomes techno-economic feasible than AIS.