Presentation by
Ashrant Dass
1. Boiler Drum is a pressure vessel it is used to
Separate steam and water mixture
2. Mixing feed water with water separated from
steam-water mixture and re-circulate through the
evaporating tubes.
3. Reduce dissolved solid contents of the steam
( Blow down)
4. Storage of water
2
There is a considerable difference
between the density of water and steam at
low pressure but as the pressure
increases towards critical point the density
difference decreases.
3
1. Primary Separation
2. Secondary Separation
3. Tertiary Separation
4
 Baffle plates are used to reverse flow direction of
the mixture and acts as impact plate.
 Reversing hoods combine the desirable features
of baffles and change of direction principles.
Steam & water from the active generating tubes
are directed behind a baffle into slotted reversing
hoods.
5
 Mixture passes through the Turbo separator.
 The resulting centrifugal force causes the higher
density water from a layer against the cylinder
walls and the steam moves to the core of the
cylinder and then upward. The water flows
downward through the annular can below the
drum level
 Further steam passes through a small corrugated
scrubber attached with the Turbo separator for
additional separation.
6
 To arrest the residual moisture if any steam is
passed through the screen dryer before leaving
the drum.
 Closely spaced corrugated or bent plates, screens
or mats of woven wire mesh can be used as dryer
surface materials. The screen type dryers are
commonly used.
7
8
9
10
1. Wet steam entering the drum from the riser tubes
is collected in a compartment called separating
chamber
2. From this compartment the steam is first led
through two rows of turbo separators.
3. Each turbo-separator consists of a primary stage
and a secondary stage
11
4. Two concentric cans form the primary stage.
Spinner blades impart a centrifugal motion to the
mixture of steam and water flowing upward
through the inner can, thereby throwing the water
to the outside and forcing the steam to inside.
The water is arrested by a skim-off lip and flows
down through the annular between the two cans.
The steam proceeds up to the secondary
separator stage.
12
5. The secondary stage consists of two opposed
banks of closely spaced thin corrugated sheets,
which direct the steam through a tortuous path,
and separate the remaining entrained water.
6. Since the velocity is relatively low, this water
does not get picked up again, but runs down the
plates and flows off the second stage lips at the
outlets
13
7. From the secondary separators the steam flows
uniformly and with relatively low velocity upward
to the series of screen dryers, extending in layers
across the length of the drum. These screens
perform the final stage of separation.
14
CBD Lines
To keep concentration of impurities within
specified limit it is necessary to drain a portion of
water from the drum continuously and
compensate the same with fresh make up water
having lower impurities so that no scaling occurs
in side boiler tubes and to prevent silica carry
over. Normally % of CBD will be maximum 1% of
the Steam generation.
CBD % =
TDS in make up water in PPM
TDS allowed in boiler water in PPM
=% of make up
15
Emergency Blow down Lines
During certain operating condition water level may
raise above the NWL which may lead to carry over
of water by Steam and at times the separators
may be submerged into the water. In such
situation to bring the water level to normal, this
blow down provision is made in the drum. The line
remained open till the level comes back to normal.
16
Chemical Dosing Line Purpose:
1. To reduce chances of scale forming salt by
converting it to sludge and removal through low
point drain. Tri Sodium Phosphate is used to react
with scale forming salts like Calcium Chloride,
Calcium Sulphate etc. and convert them into
sludge.
3CaCl2 + 2NA3PO4 Ca3 (PO4) 2 +6NaCl
17
 Chemical Dosing Line Purpose:
2. Tri sodium Phosphate Dosing improves the pH value of
boiler water and produce Sodium Hydroxide
NA3PO4 + H2O NaOH + NA2HPO4
Higher the pH value also limits the Silica carry Over.
However excess dosing may cause free caustic deposits
in boiler tubes called caustic embrittlement in boiler
18
19
20
 Length : 27998 mm
 ID : 1778 mm
 Wall Thk. : 185 mm / 155mm
 Weight : 247.67 MT
 Material : SA 299
 Turbo separators : 110 Nos.
 Screen Dryers : 148 Nos.
 Riser Connections : 80 nos.
 Super Heater Connection : 26 Nos.
 Down comers : 6 nos.
 Safety valve : 6 nos.
 Feed Nozzle : 3 nos.
 Drum Elevation: : 80.561 m
21
 MAIN CONNECTIONS
1. Feed Lines
2. Down Comers
3. Risers
4. Super heater supply tubes
 AUXILLARY CONNECTIONS
1. Blow Down Lines
2. Chemical Dosing Lines
3. Instrumentation Tappings
4. Air Vents
5. Safety valves
6. Nitrogen Filling Line
7. High & Low level trips
22
 Feed Lines
Feed water from economiser outlet is supplied to drum
through feed lines and connected to the feed nozzles
mounted with the drum. Feed nozzles in turn are
connected to the feed header provided inside the drum.
 Downcomers
The downcomer pipe are connected to the bottom of the
drum. The water from drum is circulated to the
evaporating tubes through the downcomers which are
kept external to the heating zone of the boiler. There are
6 nos of down comers at 600MW boiler drum.
23
 Riser Tubes
The water steam mixtures formed inside the
evaporating tubes is collected in the top headers
from where water steam mixture enters the drum
through risers tubes.
 Super Heater Supply Tubes
The dry saturated steam separated inside the
drum is circulated to Superheaters through these
tubes connected at the top of the drum
24
 The water entry from drum to down comers
connected at the bottom leads to the formation of
vortex at the inlet. This may cause drawl of steam
into down comers and water hammering. To
prevent this vortex formation anti-vortex spider in
the form of cruciform are located at the down
comers inlet.
25
 Air Vents :Vent pipes fitted with valves and open
to atmosphere are mounted on the top of the
drum. The vents are required to evacuate the air
while filling water in drum and to kill the vacuum
during shutdown due to condensing of steam in
drum.
 Nitrogen filling line: To charge nitrogen into drum
when boiler is under shut down for preservation
purpose.
26
Safety Valve
To prevent drum explosion from excessive
pressure, drum is provided with spring loaded
safety valve. The valves open automatically when
the drum pressure increases more than the set
pressure of the valve by the action of steam itself
without any operator interference and relieve
excess pressure.
27
◦ Boiler drum is a heavy wall pressure vessel having
hemispherical ends
◦ Heavy thickness plate are rolled/pressed and welded to
construct the drum
◦ It consists of cylindrical portion with two hemispherical
end
◦ Generally made of carbon steel plate conforming
specification SA 299 or SA 515-70
◦ Located at the Top of the Boiler hanging from Ceiling
Girder by means of U rods, bolts & nuts.
◦ It is the first pressure parts element to be erected after
completion of necessary structural work.
28
 The fitting and alignment of drum internals are
very important for its efficient performance. Any
misalignment with gap will lead to heavy carry-
over of impurities into steam which will get
deposited in the super heater . The alignment
should be checked and drum internals should be
set right at every annual overhaul. In between
also, it is desirable to check the drum internals fit
up during any shut down for a few days.
29
THANK YOU
30

More Related Content

What's hot

Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheaterHOANG VAN DUC
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boilerAshvani Shukla
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculationSHIVAJI CHOUDHURY
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plantsSHIVAJI CHOUDHURY
 
Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsSHIVAJI CHOUDHURY
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedureAshvani Shukla
 
condensate system
condensate systemcondensate system
condensate systemvikrantdesh
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsSHIVAJI CHOUDHURY
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protectionanujkumarsingh79
 
Combustion in a CFBC Boiler
Combustion in a CFBC BoilerCombustion in a CFBC Boiler
Combustion in a CFBC BoilerTapash Nag
 
Condenser and cooling tower
Condenser and cooling towerCondenser and cooling tower
Condenser and cooling towerYashvir Singh
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Manohar Tatwawadi
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and FillShad Edwards
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 

What's hot (20)

boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheater
 
660 mw supercritical boiler
660 mw supercritical boiler660 mw supercritical boiler
660 mw supercritical boiler
 
Turbine cycle heat rate calculation
Turbine  cycle heat rate calculationTurbine  cycle heat rate calculation
Turbine cycle heat rate calculation
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Condensate system
Condensate systemCondensate system
Condensate system
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
 
Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plants
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
condensate system
condensate systemcondensate system
condensate system
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plants
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
Combustion in a CFBC Boiler
Combustion in a CFBC BoilerCombustion in a CFBC Boiler
Combustion in a CFBC Boiler
 
Condenser and cooling tower
Condenser and cooling towerCondenser and cooling tower
Condenser and cooling tower
 
Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1Frequently asked questions on turbines Part 1
Frequently asked questions on turbines Part 1
 
Hydrogen Purge and Fill
Hydrogen Purge and FillHydrogen Purge and Fill
Hydrogen Purge and Fill
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 

Viewers also liked

Principle of operation bowl mill
Principle of operation bowl millPrinciple of operation bowl mill
Principle of operation bowl millDevidutta Panda
 
Ash Handling System of a Thermal Power Plant
Ash Handling System of a Thermal Power PlantAsh Handling System of a Thermal Power Plant
Ash Handling System of a Thermal Power PlantAmay Jain
 
Ash handling system
Ash handling systemAsh handling system
Ash handling systemVvs Pradeep
 
Cooling towers
Cooling towersCooling towers
Cooling towersctlin5
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsHrishikesh Devan
 

Viewers also liked (6)

coal pulveriser
coal pulveriser coal pulveriser
coal pulveriser
 
Principle of operation bowl mill
Principle of operation bowl millPrinciple of operation bowl mill
Principle of operation bowl mill
 
Ash Handling System of a Thermal Power Plant
Ash Handling System of a Thermal Power PlantAsh Handling System of a Thermal Power Plant
Ash Handling System of a Thermal Power Plant
 
Ash handling system
Ash handling systemAsh handling system
Ash handling system
 
Cooling towers
Cooling towersCooling towers
Cooling towers
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam Generators
 

Similar to Boiler Drum And Its Internals

Steam generating unit
Steam generating unitSteam generating unit
Steam generating unitJonalyn Cali
 
Construction of babcock and wilcox boiler
Construction of babcock and wilcox boilerConstruction of babcock and wilcox boiler
Construction of babcock and wilcox boilerAQIB_HAIDER
 
Babcock and Wilcox Boiler
Babcock and Wilcox BoilerBabcock and Wilcox Boiler
Babcock and Wilcox Boilerrishironak
 
High pressure boiler
High pressure boilerHigh pressure boiler
High pressure boilershah amit
 
Study of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringStudy of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringAbdullahKafi18
 
Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Dinesh Panchal
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)sneh patel
 
BOILER MOUNTING AND ACCESSORIES
BOILER MOUNTING AND ACCESSORIES BOILER MOUNTING AND ACCESSORIES
BOILER MOUNTING AND ACCESSORIES AnkitBihola
 
Steam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghSteam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghVarun Pratap Singh
 
BOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIESBOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIESSmit Shah
 
Boilers report
Boilers reportBoilers report
Boilers reportR.K. JAIN
 

Similar to Boiler Drum And Its Internals (20)

Steam generating unit
Steam generating unitSteam generating unit
Steam generating unit
 
Babcock & wilcox boiler
Babcock & wilcox boilerBabcock & wilcox boiler
Babcock & wilcox boiler
 
Construction of babcock and wilcox boiler
Construction of babcock and wilcox boilerConstruction of babcock and wilcox boiler
Construction of babcock and wilcox boiler
 
Babcock and Wilcox Boiler
Babcock and Wilcox BoilerBabcock and Wilcox Boiler
Babcock and Wilcox Boiler
 
MET 214 Module 5
MET 214 Module 5MET 214 Module 5
MET 214 Module 5
 
High pressure boiler
High pressure boilerHigh pressure boiler
High pressure boiler
 
Study of Boilers for Mechanical Engineering
Study of Boilers for Mechanical EngineeringStudy of Boilers for Mechanical Engineering
Study of Boilers for Mechanical Engineering
 
Cv presentation of boiler
Cv presentation of boilerCv presentation of boiler
Cv presentation of boiler
 
Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Boilers ppt (energy conversion)
Boilers ppt (energy conversion)
 
High pressure boilers (1)
High pressure boilers (1)High pressure boilers (1)
High pressure boilers (1)
 
BOILER MOUNTING AND ACCESSORIES
BOILER MOUNTING AND ACCESSORIES BOILER MOUNTING AND ACCESSORIES
BOILER MOUNTING AND ACCESSORIES
 
internship report
internship reportinternship report
internship report
 
Boilers
BoilersBoilers
Boilers
 
Boilers (2)
Boilers (2)Boilers (2)
Boilers (2)
 
Boilers IN EME
Boilers IN EMEBoilers IN EME
Boilers IN EME
 
Turbine vacuum system.ppt
Turbine vacuum system.pptTurbine vacuum system.ppt
Turbine vacuum system.ppt
 
Steam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghSteam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap Singh
 
BOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIESBOILER MOUNTINGS & ACCESSORIES
BOILER MOUNTINGS & ACCESSORIES
 
STEAM CONDENSER
STEAM CONDENSERSTEAM CONDENSER
STEAM CONDENSER
 
Boilers report
Boilers reportBoilers report
Boilers report
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 

Boiler Drum And Its Internals

  • 2. 1. Boiler Drum is a pressure vessel it is used to Separate steam and water mixture 2. Mixing feed water with water separated from steam-water mixture and re-circulate through the evaporating tubes. 3. Reduce dissolved solid contents of the steam ( Blow down) 4. Storage of water 2
  • 3. There is a considerable difference between the density of water and steam at low pressure but as the pressure increases towards critical point the density difference decreases. 3
  • 4. 1. Primary Separation 2. Secondary Separation 3. Tertiary Separation 4
  • 5.  Baffle plates are used to reverse flow direction of the mixture and acts as impact plate.  Reversing hoods combine the desirable features of baffles and change of direction principles. Steam & water from the active generating tubes are directed behind a baffle into slotted reversing hoods. 5
  • 6.  Mixture passes through the Turbo separator.  The resulting centrifugal force causes the higher density water from a layer against the cylinder walls and the steam moves to the core of the cylinder and then upward. The water flows downward through the annular can below the drum level  Further steam passes through a small corrugated scrubber attached with the Turbo separator for additional separation. 6
  • 7.  To arrest the residual moisture if any steam is passed through the screen dryer before leaving the drum.  Closely spaced corrugated or bent plates, screens or mats of woven wire mesh can be used as dryer surface materials. The screen type dryers are commonly used. 7
  • 8. 8
  • 9. 9
  • 10. 10
  • 11. 1. Wet steam entering the drum from the riser tubes is collected in a compartment called separating chamber 2. From this compartment the steam is first led through two rows of turbo separators. 3. Each turbo-separator consists of a primary stage and a secondary stage 11
  • 12. 4. Two concentric cans form the primary stage. Spinner blades impart a centrifugal motion to the mixture of steam and water flowing upward through the inner can, thereby throwing the water to the outside and forcing the steam to inside. The water is arrested by a skim-off lip and flows down through the annular between the two cans. The steam proceeds up to the secondary separator stage. 12
  • 13. 5. The secondary stage consists of two opposed banks of closely spaced thin corrugated sheets, which direct the steam through a tortuous path, and separate the remaining entrained water. 6. Since the velocity is relatively low, this water does not get picked up again, but runs down the plates and flows off the second stage lips at the outlets 13
  • 14. 7. From the secondary separators the steam flows uniformly and with relatively low velocity upward to the series of screen dryers, extending in layers across the length of the drum. These screens perform the final stage of separation. 14
  • 15. CBD Lines To keep concentration of impurities within specified limit it is necessary to drain a portion of water from the drum continuously and compensate the same with fresh make up water having lower impurities so that no scaling occurs in side boiler tubes and to prevent silica carry over. Normally % of CBD will be maximum 1% of the Steam generation. CBD % = TDS in make up water in PPM TDS allowed in boiler water in PPM =% of make up 15
  • 16. Emergency Blow down Lines During certain operating condition water level may raise above the NWL which may lead to carry over of water by Steam and at times the separators may be submerged into the water. In such situation to bring the water level to normal, this blow down provision is made in the drum. The line remained open till the level comes back to normal. 16
  • 17. Chemical Dosing Line Purpose: 1. To reduce chances of scale forming salt by converting it to sludge and removal through low point drain. Tri Sodium Phosphate is used to react with scale forming salts like Calcium Chloride, Calcium Sulphate etc. and convert them into sludge. 3CaCl2 + 2NA3PO4 Ca3 (PO4) 2 +6NaCl 17
  • 18.  Chemical Dosing Line Purpose: 2. Tri sodium Phosphate Dosing improves the pH value of boiler water and produce Sodium Hydroxide NA3PO4 + H2O NaOH + NA2HPO4 Higher the pH value also limits the Silica carry Over. However excess dosing may cause free caustic deposits in boiler tubes called caustic embrittlement in boiler 18
  • 19. 19
  • 20. 20
  • 21.  Length : 27998 mm  ID : 1778 mm  Wall Thk. : 185 mm / 155mm  Weight : 247.67 MT  Material : SA 299  Turbo separators : 110 Nos.  Screen Dryers : 148 Nos.  Riser Connections : 80 nos.  Super Heater Connection : 26 Nos.  Down comers : 6 nos.  Safety valve : 6 nos.  Feed Nozzle : 3 nos.  Drum Elevation: : 80.561 m 21
  • 22.  MAIN CONNECTIONS 1. Feed Lines 2. Down Comers 3. Risers 4. Super heater supply tubes  AUXILLARY CONNECTIONS 1. Blow Down Lines 2. Chemical Dosing Lines 3. Instrumentation Tappings 4. Air Vents 5. Safety valves 6. Nitrogen Filling Line 7. High & Low level trips 22
  • 23.  Feed Lines Feed water from economiser outlet is supplied to drum through feed lines and connected to the feed nozzles mounted with the drum. Feed nozzles in turn are connected to the feed header provided inside the drum.  Downcomers The downcomer pipe are connected to the bottom of the drum. The water from drum is circulated to the evaporating tubes through the downcomers which are kept external to the heating zone of the boiler. There are 6 nos of down comers at 600MW boiler drum. 23
  • 24.  Riser Tubes The water steam mixtures formed inside the evaporating tubes is collected in the top headers from where water steam mixture enters the drum through risers tubes.  Super Heater Supply Tubes The dry saturated steam separated inside the drum is circulated to Superheaters through these tubes connected at the top of the drum 24
  • 25.  The water entry from drum to down comers connected at the bottom leads to the formation of vortex at the inlet. This may cause drawl of steam into down comers and water hammering. To prevent this vortex formation anti-vortex spider in the form of cruciform are located at the down comers inlet. 25
  • 26.  Air Vents :Vent pipes fitted with valves and open to atmosphere are mounted on the top of the drum. The vents are required to evacuate the air while filling water in drum and to kill the vacuum during shutdown due to condensing of steam in drum.  Nitrogen filling line: To charge nitrogen into drum when boiler is under shut down for preservation purpose. 26
  • 27. Safety Valve To prevent drum explosion from excessive pressure, drum is provided with spring loaded safety valve. The valves open automatically when the drum pressure increases more than the set pressure of the valve by the action of steam itself without any operator interference and relieve excess pressure. 27
  • 28. ◦ Boiler drum is a heavy wall pressure vessel having hemispherical ends ◦ Heavy thickness plate are rolled/pressed and welded to construct the drum ◦ It consists of cylindrical portion with two hemispherical end ◦ Generally made of carbon steel plate conforming specification SA 299 or SA 515-70 ◦ Located at the Top of the Boiler hanging from Ceiling Girder by means of U rods, bolts & nuts. ◦ It is the first pressure parts element to be erected after completion of necessary structural work. 28
  • 29.  The fitting and alignment of drum internals are very important for its efficient performance. Any misalignment with gap will lead to heavy carry- over of impurities into steam which will get deposited in the super heater . The alignment should be checked and drum internals should be set right at every annual overhaul. In between also, it is desirable to check the drum internals fit up during any shut down for a few days. 29