Extension of Time (EOT) and Related Costs
in Construction
© www.asia-masters.com
•Time is of Essence
•Delays are inevitable on construction projects
•The only project to have completed on time is a Mosque. Divine
intervention (or God’s help) was understood to be the force behind the
timely completion of this Mosque.
•Time and Money go hand-in-hand. When projects get late, additional
costs are incurred.
•This makes it imperative to take control of project delays; timely and
effectively.
© www.asia-masters.com
•Majority of construction projects worldwide are administered by the
FIDIC forms of contract.
•FIDIC recognises delay and related costs and has provisions related
thereto. For example;
 Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)
 Clauses 44 & 53 (FIDIC 1987 Edition)
FIDIC
FIDIC
FIDIC
FIDIC
FIDIC
© www.asia-masters.com
The FIDIC Provisions define the conditions where delay may be
claimed as the basis for an Extension of Time (EOT). Some examples are;
 Late provision of design or drawings
 Unforeseeable Physical Conditions encountered on Site
 Inclement Weather
 Variations instructed by the Engineer (Additional Works etc.)
© www.asia-masters.com
Meanwhile the principles of how delay and related
costs should be calculated are not defined by FIDIC.
This leads to issues; issues which are usually
contentious due to various 'schools of thoughts' and
varied interpretations existing worldwide.
Disputes are the usual outcome.
© www.asia-masters.com
Contentious Issues in Delay Analysis
resulting in Disputes
– Critical Path
– Who owns the Float?
– Concurrent (or Contractor) Delays and how these effect
Entitlement
– EOT and its relation with Compensation for Delay
– Which is the best Method of Delay Analysis?
» As-Planned Vs. As-Built Comparison
» Impacted As-Planned
» Collapsed As-Built / But-For
» Time Slice / Sub-Networks / Time-Impact
» Etc.
© www.asia-masters.com
In order to eliminate disputes or facilitate settlement of
disputes, there are now certain standards used worldwide.
The leading standards are;
 Society of Construction Law’s
Delay and Disruption Protocol (SCL Protocol)
 AACE 29R-03 (Forensic Schedule Analysis)
© www.asia-masters.com
The SCL Protocol was
finalized in October 2002 after
several years of deliberations
and considerable debate and
agreement between experts
from different backgrounds
© www.asia-masters.com
The objective of the SCL Protocol
was to bring reasonableness and
fairness into the delay assessment
process and to eliminate
widespread manipulation of
complex delay issues
© www.asia-masters.com
The SCL Protocol tried to standardize
the issues such that disputes would be
reduced or eliminated
© www.asia-masters.com
It is recommended that;
should be adopted as a Standard
and should be, where possible,
incorporated in the Construction
Contracts
© www.asia-masters.com
The SCL Protocol can be downloaded from:
www.eotprotocol.com
© www.asia-masters.com
The remaining slides of this lecture will
review and discuss the basic Principles
suggested and recommended by the
SCL Protocol
© www.asia-masters.com
Basic Principles
suggested and recommended by
the SCL Protocol
© www.asia-masters.com
The Principles suggested by the
SCL Protocol are simple.
Some of the key principles suggested
by the Protocol are;
© www.asia-masters.com
RULE NO. 1
If there is an Employer’s delay, which is beyond the Contractor’s
control, and if this delay impacts the Completion Date of the Works,
the Contractor should be entitled to receive an
Extension of Time (EOT).
[This will effectively result in an extended Time for Completion and will
relieve the Contractor from having to pay penalties for delay (or
Delay Damages under FIDIC)]
© www.asia-masters.com
RULE NO. 2
For the case of recovery of delay (or prolongation) costs incurred due to
the Employer delays, the Contractor must be able to prove that there has
been no other delay, which is in his own control, and which is equally
(or partly) contributing for delaying the Time for Completion.
This category of delay is called a ‘Concurrent’
(or Contractor’s) Delay
[In order to win a Delay Costs Claim, the Contractor must be able to
prove that he has not been responsible for Concurrent Delays to
the Time for Completion]
© www.asia-masters.com
RULE NO. 3
Where Contractor’s Delay to Completion
occurs concurrently with Employer’s Delay
to Completion, the Contractor’s concurrent
delay should NOT reduce any
Extension of Time (EOT), which is due.
[Result of Rule No. 1 will not change and is irrespective of the result
of Rule No. 2]
© www.asia-masters.com
The foregoing Rules proposed by the SCL Protocol are
meant to bring fairness and reasonableness into the
delay assessment process.
[The emphasis of the SCL Protocol is that no one Party
should benefit from default of the other Party]
© www.asia-masters.com
The Illustrations demonstrating the principles of the SCL
Protocol are contained in the following Figures A to G
© www.asia-masters.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Path 1 Float = 3.5 Weeks
Path 2 Float = 5.5 Weeks
Path 2
Figure A - Accepted Contract Programme
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
© www.asia-masters.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Path 1 Float = 1.0 Week
Path 2 Float = 5.5 Weeks
(a) 2.0 Weeks (a) 5.5 Weeks
(b) 1.0 Weeks (b) 0 Weeks
(c) 0 Weeks (c) 1.0 Weeks
(d) 5.5 Weeks (d) 2.0 Weeks
(a) 2.0 Weeks (a) 0.1% of Contract Price
(b) 1.0 Weeks (b) Direct Costs of Excusable Delay
(c) 0 Weeks (c) NIL
(d) 5.5 Weeks (d) (a) plus (b)
<=Date of Excusable Delay
Figure B - Delay Impact 1
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Contract
Completion Date
Impact on Path 1
= 2.0 Weeks
Path 2
Path 1
Principles & Provisions of the SCL Protocol
relevant to Figure B
Core Principle No. 7 - Float as it relates to time
Unless there is express provision to the contrary in the contract, where there is remaining
float in the programme at the time of an Employer Risk Event, an EOT should only be
granted to the extent that the Employer Delay is predicted to reduce to below zero the total
float on the activity paths affected by the Employer Delay.
Guidance Section 1.12.1
If as a result of an Employer Delay, the Contractor is prevented from completing the works
by the Contractor’s planned completion date (being a date earlier than the contract
completion date), the Contractor should in principle be entitled to be paid the costs
directly caused by the Employer Delay, notwithstanding that there is no delay to the
contract completion date (and therefore no entitlement to an EOT), provided also that at
the time they enter into the contract, the Employer is aware of the Contractor’s intention to
complete the works prior to the contract completion date, and that intention is realistic and
achievable.
© www.asia-masters.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Float = -0.5 Week
(a) 0.5 Weeks (a) 5.5 Weeks
(b) 3.5 Weeks (b) 0.5 Weeks
(c) 0 Weeks (c) 3.5 Weeks
(d) 5.5 Weeks (d) 0 Weeks
(a) 3.5 Weeks (a) 0.15% of Contract Price
(b) 0.5 Weeks (b) Direct Costs of Excusable Delay
(c) 0 Weeks (c) (a) plus (b)
(d) 3.0 Weeks (d) NIL
Contract
Completion Date
Impact on Path 1
= 3.5 Weeks
Path 2
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
<=Date of Excusable Delay
Figure C - Delay Impact 2
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
Core Principle No. 4 - Procedure for granting extension of time
The EOT should be granted to the extent that the Employer Risk Event is
reasonably predicted to prevent the works being completed by the then
prevailing contract completion date…..The goal of the EOT procedure is
the ascertainment of the appropriate contractual entitlement to an EOT; the
procedure is not to be based on whether or not the Contractor needs an
EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event
already to have begun to affect the Contractor’s progress with the works,
or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocol
relevant to Figure C
© www.asia-masters.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Float = -0.5 Week
Excusable Delay
Impact on Path 2 = 6.0 Weeks
(a) 0 Weeks (a) 5.5 Weeks
(b) 6.0 Weeks (b) 0 Weeks
(c) 0.5 Weeks (c) 6.0 Weeks
(d) 5.5 Weeks (d) 0.5 Weeks
(a) 3.5 Weeks (a) (d) minus (c)
(b) 0.5 Weeks (b) Direct Costs of Excusable DelayNIL
(c) 6.0 Weeks (c) Direct Costs of Excusable Delay
(d) 3.0 Weeks (d) 0.2% of Contract Price
<=Date of Excusable Delay
Figure D - Delay Impact 3
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
Path 2
Path 1
Contract
Completion Date
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Core Principle No. 4 - Procedure for granting extension of time
The EOT should be granted to the extent that the Employer Risk Event is
reasonably predicted to prevent the works being completed by the then
prevailing contract completion date…..The goal of the EOT procedure is
the ascertainment of the appropriate contractual entitlement to an EOT; the
procedure is not to be based on whether or not the Contractor needs an
EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event
already to have begun to affect the Contractor’s progress with the works,
or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocol
relevant to Figure D
© www.asia-masters.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Excusable Delay
Impact on Path 1 = 2.0 Weeks
Float = -3.5 Weeks
(a) 3.5 Weeks (a) 2.0 Weeks
(b) 2.0 Weeks (b) 0 Weeks
(c) 1.5 Weeks (c) 3.5 Weeks
(d) 0 Weeks (d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)
(b) 2.0 Weeks (b) Direct Costs of Excusable DelayNIL
(c) 3.0 Weeks (c) Direct Costs of Excusable Delay
(d) 0 Weeks (d) 0.1% of Contract Price
Figure E - Delay Impact 4
Weeks
Path 1
Contract Start
Date
<=Date of Excusable Delay
Path 2
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Guidance Section 1.2.11
…an EOT should be granted to the extent that the Employer Risk Event is
predicted to prevent the works being completed by the then prevailing
contract completion date. This process requires consideration of the
available float…
Guidance Section 1.4.12
…Where there has been Employer Delay, this may prevent the Employer
charging the Contractor with LDs for failure to achieve a contract
completion date…
Principles & Provisions of the SCL Protocol
relevant to Figure E
© www.asia-masters.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Impact on Path 1 = 2.0 Weeks
Excusable Delay
Float = -3.5 Weeks
(a) 2.0 Weeks (a) 0 Weeks
(b) 3.5 Weeks (b) 2.0 Weeks
(c) 1.5 Weeks (c) 3.5 Weeks
(d) 0 Weeks (d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)
(b) 2.0 Weeks (b) Direct Costs of Excusable DelayNIL
(c) 3.0 Weeks (c) Direct Costs of Excusable Delay
(d) 0 Weeks (d) 0.1% of Contract Price
Figure F - Delay Impact 5
Weeks
Path 1
Contract Start
Date
Path 2
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Guidance Section 1.4.8
Where an Employer Risk Event occurs after the contract completion date, in a
situation where failure to complete by the contract completion date has been caused
by Contractor Delays, the principle set out in Section 1.4.7 above should apply,
except where the Employer Risk Event is a non-compensable Employer Risk Event.
In such an event, no EOT (or compensation) should be due. Where an EOT is due
after the contract completion date, the Employer Risk Event does not exonerate the
Contractor for all its delays prior to the Employer Risk Event occurring. The effect
of the Employer Risk Event should be assessed as described above and any EOT
found due should simply be added to the contract completion date.
Principles & Provisions of the SCL Protocol
relevant to Figure F
© www.asia-masters.com
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
Path 2 Float = 2.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Float = -1.5 Weeks
Excusable Delay = 3.5 Weeks
(a) 2.5 Weeks (a) 0 Weeks
(b) 3.5 Weeks (b) 2.5 Weeks
(c) 1.0 Weeks (c) 3.5 Weeks
(d) 1.5 Weeks (d) 1.5 Weeks
(a) 0 Weeks (a) (b) plus (d)
(b) 2.0 Weeks (b) Direct Costs of Excusable Delay
(c) 3.0 Weeks (c) NIL
(d) 3.5 Weeks (d) 0.2% of Contract Price
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Figure G - Delay Impact 6
Weeks
Path 1
Contract Start
Date
Path 2
Guidance Section 1.4.1
Where Contractor Delay to Completion occurs concurrently with Employer Delay to
Completion, the Contractor’s concurrent delay should not reduce any EOT due.
Guidance Section 1.4.7
Where Employer Risk Events and Contractor Risk Events occur sequentially but
have concurrent effects, here again any Contractor Delay should not reduce the
amount of EOT due to the Contractor as a result of the Employer Delay.
Concurrency (Appendix A – Definations and Glossary)
True concurrent delay is the occurrence of two or more delay events at the same
time, one an Employer Risk Event, the other a Contractor Risk Event and the effects
of which are felt at the same time. The term ‘concurrent delay’ is often used to
describe the situation where two or more delay events arise at different times, but
the effects of them are felt (in whole or in part) at the same time. To avoid
confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay
events.
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 1/2
© www.asia-masters.com
Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time
Where Contractor Delay to Completion occurs or has effect concurrently with Employer
Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT
due.
Core Principle No. 14 - Link between extension of time and compensation
Entitlement to an EOT does not automatically lead to entitlement to compensation (and
vice versa).
Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for
prolongation
If the Contractor incurs additional costs that are caused both by Employer Delay and
concurrent Contractor Delay, then the Contractor should only recover compensation to
the extent it is able to separately identify the additional costs caused by the Employer
Delay from those caused by the Contractor Delay. If it would have incurred the
additional costs in any event as a result of Contractor Delays, the Contractor will not be
entitled to recover those additional costs.
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 2/2
© www.asia-masters.com
Guidance Section 3.2.13
Although the programme should be the primary tool for guiding the
CA in his determination of EOT, it should be used in conjunction
with the contemporary evidence to ensure that the resulting EOT is
fair and reasonable. It will also be necessary for the parties to apply
common sense and experience to the process to ensure that all
relevant factors are taken into account, and that any anomalous
results generated by the programme analysis are managed properly.
Key Guideline, Suggestion and Advice of the
SCL Protocol
© www.asia-masters.com
Figure No. Question 1 Question 2 Question 3 Question 4
B (c) (b) (a) (b)
C (a) (b) (d) (b)
D (c) (d) (d) (c)
E (b) (a) (d) (c)
F (a) (b) (d) (c)
G (c) (a) (a) (b)
Correct Responses for Figures B to G
© www.asia-masters.com
Congratulations we
have come to the end of
the Lecture.
You are now a
Qualified and Certified
Delay Claims Analyst
and Expert.
© www.asia-masters.com
FIDIC and Construction Solutions
thank you for your attendance and contribution.
We wish you all Good Luck.
© www.asia-masters.com
THANK YOU!
© www.asia-masters.com

More Related Content

What's hot

Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptxssuserb337ce1
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...Gaurav Verma
 

What's hot (20)

Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Claims
ClaimsClaims
Claims
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
Cost value reconciliation (cvr)
Cost value reconciliation (cvr)Cost value reconciliation (cvr)
Cost value reconciliation (cvr)
 

Similar to Extension of Time (EOT) & Related Costs in Construction - Presentation Slides

FIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxFIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxJeff747294
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEssam Lotffy, PMP®, CCP®
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Matrix of responsibility
Matrix of responsibilityMatrix of responsibility
Matrix of responsibilityFarzana Amin
 

Similar to Extension of Time (EOT) & Related Costs in Construction - Presentation Slides (20)

FIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptxFIDIC Lecture - EOT & Related Costs in Construction.pptx
FIDIC Lecture - EOT & Related Costs in Construction.pptx
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigationSeb Oram - The 2015 CDM Regulations - changes and impact on litigation
Seb Oram - The 2015 CDM Regulations - changes and impact on litigation
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Matrix of responsibility
Matrix of responsibilityMatrix of responsibility
Matrix of responsibility
 

More from Asia Master Training آسيا ماسترز للتدريب والتطوير

More from Asia Master Training آسيا ماسترز للتدريب والتطوير (20)

Annual training plan 2018 2018
Annual training plan 2018 2018Annual training plan 2018 2018
Annual training plan 2018 2018
 
Human Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and PlanningHuman Resource Management : The Importance of Effective Strategy and Planning
Human Resource Management : The Importance of Effective Strategy and Planning
 
Purpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview LandscapePurpose of Contract CloseOuts - Overview Landscape
Purpose of Contract CloseOuts - Overview Landscape
 
Public Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground RulesPublic Meeting - Contract Close-Out - Ground Rules
Public Meeting - Contract Close-Out - Ground Rules
 
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACTNATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
NATIONAL AUDIT – FIDIC CONTRACTS: BASIS OF FAIR CONTRACT
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication TestingOPTICAL INDUSTRY - Design Engineering Fabrication Testing
OPTICAL INDUSTRY - Design Engineering Fabrication Testing
 
Microsoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills TrainingMicrosoft Word 2010 - Technical Skills Training
Microsoft Word 2010 - Technical Skills Training
 
Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training Microsoft® Office Word 2007 Skills & Compentencies Training
Microsoft® Office Word 2007 Skills & Compentencies Training
 
Competency Modeling v. Job Analysis
Competency Modeling v. Job AnalysisCompetency Modeling v. Job Analysis
Competency Modeling v. Job Analysis
 
Competency gaps for Professional Development
Competency gaps for Professional DevelopmentCompetency gaps for Professional Development
Competency gaps for Professional Development
 
Competency Approach to Human Resource Management
Competency Approach to Human Resource ManagementCompetency Approach to Human Resource Management
Competency Approach to Human Resource Management
 
Developing a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency FrameworkDeveloping a University-Wide Integrated Employee Core Competency Framework
Developing a University-Wide Integrated Employee Core Competency Framework
 
Organizational Change and Development
Organizational Change and DevelopmentOrganizational Change and Development
Organizational Change and Development
 
Competency-based Management for the DoD-wide Contracting Community
Competency-based Management for the   DoD-wide Contracting CommunityCompetency-based Management for the   DoD-wide Contracting Community
Competency-based Management for the DoD-wide Contracting Community
 
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & TeachingCOMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
COMPETENCY-BASED CURRICULUM DEVELOPMENT - Method & Teaching
 
The Counseling Interview - Principles & Practices
The Counseling Interview - Principles & PracticesThe Counseling Interview - Principles & Practices
The Counseling Interview - Principles & Practices
 
Behavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality OrganizationBehavioral Interview - Selecting Quality Employees for a Quality Organization
Behavioral Interview - Selecting Quality Employees for a Quality Organization
 
Effective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best PersonEffective Hiring Practices - Recruiting the Best Person
Effective Hiring Practices - Recruiting the Best Person
 
Industrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting EmployeesIndustrial & Organisational Psychology Selecting Employees
Industrial & Organisational Psychology Selecting Employees
 

Recently uploaded

The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditSkynet Technologies
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Mark Goldstein
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...panagenda
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...AliaaTarek5
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 

Recently uploaded (20)

The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance Audit
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 

Extension of Time (EOT) & Related Costs in Construction - Presentation Slides

  • 1. Extension of Time (EOT) and Related Costs in Construction © www.asia-masters.com
  • 2. •Time is of Essence •Delays are inevitable on construction projects •The only project to have completed on time is a Mosque. Divine intervention (or God’s help) was understood to be the force behind the timely completion of this Mosque. •Time and Money go hand-in-hand. When projects get late, additional costs are incurred. •This makes it imperative to take control of project delays; timely and effectively. © www.asia-masters.com
  • 3. •Majority of construction projects worldwide are administered by the FIDIC forms of contract. •FIDIC recognises delay and related costs and has provisions related thereto. For example;  Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)  Clauses 44 & 53 (FIDIC 1987 Edition) FIDIC FIDIC FIDIC FIDIC FIDIC © www.asia-masters.com
  • 4. The FIDIC Provisions define the conditions where delay may be claimed as the basis for an Extension of Time (EOT). Some examples are;  Late provision of design or drawings  Unforeseeable Physical Conditions encountered on Site  Inclement Weather  Variations instructed by the Engineer (Additional Works etc.) © www.asia-masters.com
  • 5. Meanwhile the principles of how delay and related costs should be calculated are not defined by FIDIC. This leads to issues; issues which are usually contentious due to various 'schools of thoughts' and varied interpretations existing worldwide. Disputes are the usual outcome. © www.asia-masters.com
  • 6. Contentious Issues in Delay Analysis resulting in Disputes – Critical Path – Who owns the Float? – Concurrent (or Contractor) Delays and how these effect Entitlement – EOT and its relation with Compensation for Delay – Which is the best Method of Delay Analysis? » As-Planned Vs. As-Built Comparison » Impacted As-Planned » Collapsed As-Built / But-For » Time Slice / Sub-Networks / Time-Impact » Etc. © www.asia-masters.com
  • 7. In order to eliminate disputes or facilitate settlement of disputes, there are now certain standards used worldwide. The leading standards are;  Society of Construction Law’s Delay and Disruption Protocol (SCL Protocol)  AACE 29R-03 (Forensic Schedule Analysis) © www.asia-masters.com
  • 8. The SCL Protocol was finalized in October 2002 after several years of deliberations and considerable debate and agreement between experts from different backgrounds © www.asia-masters.com
  • 9. The objective of the SCL Protocol was to bring reasonableness and fairness into the delay assessment process and to eliminate widespread manipulation of complex delay issues © www.asia-masters.com
  • 10. The SCL Protocol tried to standardize the issues such that disputes would be reduced or eliminated © www.asia-masters.com
  • 11. It is recommended that; should be adopted as a Standard and should be, where possible, incorporated in the Construction Contracts © www.asia-masters.com
  • 12. The SCL Protocol can be downloaded from: www.eotprotocol.com © www.asia-masters.com
  • 13. The remaining slides of this lecture will review and discuss the basic Principles suggested and recommended by the SCL Protocol © www.asia-masters.com
  • 14. Basic Principles suggested and recommended by the SCL Protocol © www.asia-masters.com
  • 15. The Principles suggested by the SCL Protocol are simple. Some of the key principles suggested by the Protocol are; © www.asia-masters.com
  • 16. RULE NO. 1 If there is an Employer’s delay, which is beyond the Contractor’s control, and if this delay impacts the Completion Date of the Works, the Contractor should be entitled to receive an Extension of Time (EOT). [This will effectively result in an extended Time for Completion and will relieve the Contractor from having to pay penalties for delay (or Delay Damages under FIDIC)] © www.asia-masters.com
  • 17. RULE NO. 2 For the case of recovery of delay (or prolongation) costs incurred due to the Employer delays, the Contractor must be able to prove that there has been no other delay, which is in his own control, and which is equally (or partly) contributing for delaying the Time for Completion. This category of delay is called a ‘Concurrent’ (or Contractor’s) Delay [In order to win a Delay Costs Claim, the Contractor must be able to prove that he has not been responsible for Concurrent Delays to the Time for Completion] © www.asia-masters.com
  • 18. RULE NO. 3 Where Contractor’s Delay to Completion occurs concurrently with Employer’s Delay to Completion, the Contractor’s concurrent delay should NOT reduce any Extension of Time (EOT), which is due. [Result of Rule No. 1 will not change and is irrespective of the result of Rule No. 2] © www.asia-masters.com
  • 19. The foregoing Rules proposed by the SCL Protocol are meant to bring fairness and reasonableness into the delay assessment process. [The emphasis of the SCL Protocol is that no one Party should benefit from default of the other Party] © www.asia-masters.com
  • 20. The Illustrations demonstrating the principles of the SCL Protocol are contained in the following Figures A to G © www.asia-masters.com
  • 21. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Path 1 Float = 3.5 Weeks Path 2 Float = 5.5 Weeks Path 2 Figure A - Accepted Contract Programme Weeks Path 1 Contract Start Date Contract Completion Date © www.asia-masters.com
  • 22. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 Float = 3.0 Weeks Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Excusable Delay Path 1 Float = 1.0 Week Path 2 Float = 5.5 Weeks (a) 2.0 Weeks (a) 5.5 Weeks (b) 1.0 Weeks (b) 0 Weeks (c) 0 Weeks (c) 1.0 Weeks (d) 5.5 Weeks (d) 2.0 Weeks (a) 2.0 Weeks (a) 0.1% of Contract Price (b) 1.0 Weeks (b) Direct Costs of Excusable Delay (c) 0 Weeks (c) NIL (d) 5.5 Weeks (d) (a) plus (b) <=Date of Excusable Delay Figure B - Delay Impact 1 Weeks Path 1 Contract Start Date Contract Completion Date Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation Contract Completion Date Impact on Path 1 = 2.0 Weeks Path 2 Path 1
  • 23. Principles & Provisions of the SCL Protocol relevant to Figure B Core Principle No. 7 - Float as it relates to time Unless there is express provision to the contrary in the contract, where there is remaining float in the programme at the time of an Employer Risk Event, an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the activity paths affected by the Employer Delay. Guidance Section 1.12.1 If as a result of an Employer Delay, the Contractor is prevented from completing the works by the Contractor’s planned completion date (being a date earlier than the contract completion date), the Contractor should in principle be entitled to be paid the costs directly caused by the Employer Delay, notwithstanding that there is no delay to the contract completion date (and therefore no entitlement to an EOT), provided also that at the time they enter into the contract, the Employer is aware of the Contractor’s intention to complete the works prior to the contract completion date, and that intention is realistic and achievable. © www.asia-masters.com
  • 24. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 Float = 3.0 Weeks Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Excusable Delay Float = -0.5 Week (a) 0.5 Weeks (a) 5.5 Weeks (b) 3.5 Weeks (b) 0.5 Weeks (c) 0 Weeks (c) 3.5 Weeks (d) 5.5 Weeks (d) 0 Weeks (a) 3.5 Weeks (a) 0.15% of Contract Price (b) 0.5 Weeks (b) Direct Costs of Excusable Delay (c) 0 Weeks (c) (a) plus (b) (d) 3.0 Weeks (d) NIL Contract Completion Date Impact on Path 1 = 3.5 Weeks Path 2 Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation <=Date of Excusable Delay Figure C - Delay Impact 2 Weeks Path 1 Contract Start Date Contract Completion Date
  • 25. Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 – Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended. Principles & Provisions of the SCL Protocol relevant to Figure C © www.asia-masters.com
  • 26. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 Float = 3.0 Weeks Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Float = -0.5 Week Excusable Delay Impact on Path 2 = 6.0 Weeks (a) 0 Weeks (a) 5.5 Weeks (b) 6.0 Weeks (b) 0 Weeks (c) 0.5 Weeks (c) 6.0 Weeks (d) 5.5 Weeks (d) 0.5 Weeks (a) 3.5 Weeks (a) (d) minus (c) (b) 0.5 Weeks (b) Direct Costs of Excusable DelayNIL (c) 6.0 Weeks (c) Direct Costs of Excusable Delay (d) 3.0 Weeks (d) 0.2% of Contract Price <=Date of Excusable Delay Figure D - Delay Impact 3 Weeks Path 1 Contract Start Date Contract Completion Date Path 2 Path 1 Contract Completion Date Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation
  • 27. Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 – Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended. Principles & Provisions of the SCL Protocol relevant to Figure D © www.asia-masters.com
  • 28. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Contract Completion Date Float = -1.5 Weeks AFTER EXCUSABLE DELAY Contract Completion Date Excusable Delay Impact on Path 1 = 2.0 Weeks Float = -3.5 Weeks (a) 3.5 Weeks (a) 2.0 Weeks (b) 2.0 Weeks (b) 0 Weeks (c) 1.5 Weeks (c) 3.5 Weeks (d) 0 Weeks (d) 1.5 Weeks (a) 3.5 Weeks (a) (c) plus (d) (b) 2.0 Weeks (b) Direct Costs of Excusable DelayNIL (c) 3.0 Weeks (c) Direct Costs of Excusable Delay (d) 0 Weeks (d) 0.1% of Contract Price Figure E - Delay Impact 4 Weeks Path 1 Contract Start Date <=Date of Excusable Delay Path 2 Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation
  • 29. Guidance Section 1.2.11 …an EOT should be granted to the extent that the Employer Risk Event is predicted to prevent the works being completed by the then prevailing contract completion date. This process requires consideration of the available float… Guidance Section 1.4.12 …Where there has been Employer Delay, this may prevent the Employer charging the Contractor with LDs for failure to achieve a contract completion date… Principles & Provisions of the SCL Protocol relevant to Figure E © www.asia-masters.com
  • 30. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) <=Date of Excusable Delay Contract Completion Date Float = -1.5 Weeks AFTER EXCUSABLE DELAY Contract Completion Date Impact on Path 1 = 2.0 Weeks Excusable Delay Float = -3.5 Weeks (a) 2.0 Weeks (a) 0 Weeks (b) 3.5 Weeks (b) 2.0 Weeks (c) 1.5 Weeks (c) 3.5 Weeks (d) 0 Weeks (d) 1.5 Weeks (a) 3.5 Weeks (a) (c) plus (d) (b) 2.0 Weeks (b) Direct Costs of Excusable DelayNIL (c) 3.0 Weeks (c) Direct Costs of Excusable Delay (d) 0 Weeks (d) 0.1% of Contract Price Figure F - Delay Impact 5 Weeks Path 1 Contract Start Date Path 2 Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation
  • 31. Guidance Section 1.4.8 Where an Employer Risk Event occurs after the contract completion date, in a situation where failure to complete by the contract completion date has been caused by Contractor Delays, the principle set out in Section 1.4.7 above should apply, except where the Employer Risk Event is a non-compensable Employer Risk Event. In such an event, no EOT (or compensation) should be due. Where an EOT is due after the contract completion date, the Employer Risk Event does not exonerate the Contractor for all its delays prior to the Employer Risk Event occurring. The effect of the Employer Risk Event should be assessed as described above and any EOT found due should simply be added to the contract completion date. Principles & Provisions of the SCL Protocol relevant to Figure F © www.asia-masters.com
  • 32. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) <=Date of Excusable Delay Contract Completion Date Float = -1.5 Weeks Path 2 Float = 2.5 Weeks AFTER EXCUSABLE DELAY Contract Completion Date Float = -1.5 Weeks Excusable Delay = 3.5 Weeks (a) 2.5 Weeks (a) 0 Weeks (b) 3.5 Weeks (b) 2.5 Weeks (c) 1.0 Weeks (c) 3.5 Weeks (d) 1.5 Weeks (d) 1.5 Weeks (a) 0 Weeks (a) (b) plus (d) (b) 2.0 Weeks (b) Direct Costs of Excusable Delay (c) 3.0 Weeks (c) NIL (d) 3.5 Weeks (d) 0.2% of Contract Price Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation Figure G - Delay Impact 6 Weeks Path 1 Contract Start Date Path 2
  • 33. Guidance Section 1.4.1 Where Contractor Delay to Completion occurs concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due. Guidance Section 1.4.7 Where Employer Risk Events and Contractor Risk Events occur sequentially but have concurrent effects, here again any Contractor Delay should not reduce the amount of EOT due to the Contractor as a result of the Employer Delay. Concurrency (Appendix A – Definations and Glossary) True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event and the effects of which are felt at the same time. The term ‘concurrent delay’ is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time. To avoid confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay events. Principles & Provisions of the SCL Protocol relevant to Figure G – Slide 1/2 © www.asia-masters.com
  • 34. Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time Where Contractor Delay to Completion occurs or has effect concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due. Core Principle No. 14 - Link between extension of time and compensation Entitlement to an EOT does not automatically lead to entitlement to compensation (and vice versa). Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for prolongation If the Contractor incurs additional costs that are caused both by Employer Delay and concurrent Contractor Delay, then the Contractor should only recover compensation to the extent it is able to separately identify the additional costs caused by the Employer Delay from those caused by the Contractor Delay. If it would have incurred the additional costs in any event as a result of Contractor Delays, the Contractor will not be entitled to recover those additional costs. Principles & Provisions of the SCL Protocol relevant to Figure G – Slide 2/2 © www.asia-masters.com
  • 35. Guidance Section 3.2.13 Although the programme should be the primary tool for guiding the CA in his determination of EOT, it should be used in conjunction with the contemporary evidence to ensure that the resulting EOT is fair and reasonable. It will also be necessary for the parties to apply common sense and experience to the process to ensure that all relevant factors are taken into account, and that any anomalous results generated by the programme analysis are managed properly. Key Guideline, Suggestion and Advice of the SCL Protocol © www.asia-masters.com
  • 36. Figure No. Question 1 Question 2 Question 3 Question 4 B (c) (b) (a) (b) C (a) (b) (d) (b) D (c) (d) (d) (c) E (b) (a) (d) (c) F (a) (b) (d) (c) G (c) (a) (a) (b) Correct Responses for Figures B to G © www.asia-masters.com
  • 37. Congratulations we have come to the end of the Lecture. You are now a Qualified and Certified Delay Claims Analyst and Expert. © www.asia-masters.com
  • 38. FIDIC and Construction Solutions thank you for your attendance and contribution. We wish you all Good Luck. © www.asia-masters.com