SlideShare a Scribd company logo
1 of 28
Length Of Road= 79 km
No. Of Culverts = 44
No. Of Bridges = 2
Widening and
Strengthening of Kowar
Kodarma Road
• The Road Passes through
many thickly populated
villages.
• Width of the existing crust
is 3 m.
• Which is to be widened up
to 7 m.
• The improvement of this
road will uplift the social and
economic condition of the
area.
The materials used in
the above layers has to
go through various
quality control checks
•Granular Sub Base (GSB)
•Wet Mix Macadam (WMM)
•Bituminous macadam (BM)
•Semi dense bituminous concrete (SDBC)
Water Absorption test
Aggregate Impact test
Flakiness Index
Sieve analysis
Bitumen content test
A traffic census had been conducted previously at three points on the
road continuously for 7 days to get average daily traffic. Number of CV/day
is obtained from it, denoted by ‘P’
Cumulative Traffic is
found out as given in IRC
37 -2001.
From the Cumulative
Traffic, and known CBR
value ; we use the
Pavement design
Catalogue and obtain
thickness of all the layers
required in the Road.
N = {365*(1+r)^n -1} *D*F*P(1+r)^x
r
The portion to be widened beyond the existing crust
was excavated using the excavator.
The GSB was brought from the mixing plant in Dumpers and Dumped
at the Site. It was then spread uniformly with the Motor Grader
• The GSB was then
compacted in layers such
that each layer did not
exceed 100 mm compacted
thickness.
• Next the layer of WMM was
spread over the GSB and was
compacted in layers.
• To fill the voids remaining,
stone dust was used, rolling
was continued until no more
dust could be forced into the
voids.
•Sprinkling of water is done
with continued rolling to
obtain well bounded and
firmly set surface.
Compacted WMM is allowed to completely dry and set before
the next pavement is laid.
Surface of WMM
is swept clean
and dust is blown
of using
compressed air.
Once the surface
is clean, the
Prime coat is
sprayed over the
surface using
sprayer. The
surface is allowed
to cure for 24
hours.
After 24 hours the Tack coat or binder is uniformly sprayed over the
surface. Emulsion is used as binder shall have temperature 20 c to 50 c.
Immediately after spraying the tack coat, the layer of BM is laid over
it. The BM is brought at site by a Dumper, at that time the
temperature of BM should be 120 c.
The Dumper is slowly tilted over the Rack of the Paving machine
while both paver and dumper slowly moves forward.
The conveyor Belt arrangement in the Paver and leveling plate spreads
the BM neatly behind as both Dumper and paver moves forward. The
Camber is provided by adjusting the leveling plate.
Paving is accompanied with rolling. Any high spots or depressions
noticed are corrected by removing or adding material and rolling done
over it again. Water is sprinkled over roller wheels to prevent sticking
of materials to it.
Rolling must be complete before the temperature of BM falls below 90 c
A tack coat is again applied over the BM course. The top wearing
course of SDBC is also applied with the same process as BM.
Tolerance level for BM = 6mm
Tolerance level for SDBC = 4 mm
The rolling is done as such
each pass overlaps with at
least one third of the track
made in preceding pass.
The layer of SDBC is
immediately sprinkled with
Stone Dust to prevent the
sticking of materials to shoes
or wheels.
Traffic is allowed 24 hours
after laying SDBC
Hot Thermoplastic compound is used for marking, which is laid with
the help of a Road Marking Machinery.
Thermoplastic material is homogenously composed of pigments,
reflecting glass beads and resins.
Binder - 18%
Glass beads - 40 %
Titanium dioxide - 10%
Calcium carbonate - 42%
Mostly two types of culverts were constructed along the
road. RCC Culvert and Stone Masonry Culvert.
First excavation pit for the Foundation slab was dug. Foundation slab
for both the abutments were casted as one unit.
Series of parallel bars 8 mm dia @
200 mm c/c are laid on the slab
First 400 mm of the bar is made to
rest on the slab and rest part is
folded above at right angles.
These bars are called Skin
Reinforcement.
Formwork for further casting of
substructure is fixed.
Casting is done in two layers of 200
mm, hence casting of 400 mm was
done in one day.
According to the shape of the abutment, the skin reinforcements
were bent at the desired angle where ever necessary , fixing of
formwork and casting was done as usual.
At 0.5 m above the ground level, weep holes are provided.
Weep holes drain the water that accumulates on either side of the
abutment. Diameter of weep holes = 75 mm @ 1m c/c
The construction till Dirt wall is completed in following the usual
procedure.
Lets see how Stone masonry Culvert was completed till here.
Stone Masonry Culverts are built where good quality stones are
readily available. Stones of standard size are joined using mortar
one by one.
• A string is stretched along the
length of the culvert which is used to
keep the alignment of the stones
correct while placing them.
•The stones are placed at the edges
first, the flat surface of the stone is
kept facing outward to get a good
finished surface.
• Weep Holes are provided in
the same way as in RCC Culvert.
Dirl wall is also made up of
stones, smaller size of stones
are used in it.
After construction till dirt wall is complete, the process for further
construction in both types of Culvert is same.
o The reinforcement for the
abutment cap is tied and form
work is fixed.
o Then casting of abutment cap
is done.
o Abutment cap is cured for at least
1 week then the formwork for slab
is fixed.
o The reinforcement for slab is tied
while keeping the necessary
camber.
o Concreting of slab is done as
usual.
o The slab is now cured for 28 days
• The old bridge was narrow,
damaged and insufficient to
carry present traffic load.
• It was a five span bridge with
total length 123 m.
• Hard strata was found at a
depth of 20 m
• The construction was just
started and the location of first
pile was well marked.
• A metal sheet was folded with
the help of a machine into a
desired diameter of 1.2 m.
• This metal cylinder was used
as a casing for the pile
• A large tripod is centered
over the point of piling
• The cylinder is driven at
that point and water is filled
to make the strata loose.
• Next a pile hammer is
mounted over the tripod
with a system of pulley and
cables.
• The diameter of the
hammer is just enough to fit
in the casing.
• The hammer is then
constantly made to drop
from a height of 5 m inside
the casing.
• This breaks the strata
below.
• When enough strata is
broken down, the mud
collected inside the pile
gutter, is taken out with
the help of one way
valve.
• This process is
continued and it takes
near about 5 days to
complete the excavation
of 20 m.
• The reinforcement bars are
then tied
• 30 bars of 25 mm dia were
provided as main steel
• Helical Stirrups are provided
of dia 10 mm with a spacing of
150 mm c/c.
• This reinforcement is then
placed inside the pile casing
with the help of a crane.
• Concrete is then placed inside
the pile with Tremie method.
•The tremie pipes are coupled
together and inserted inside
the pile.
•It is fitted with a Hopper on
top.
•The concrete is placed on the
top of the Hopper.
• whole length of pipe is filled
with concrete.
• The tremie pipe is lifted up
and a slight jerk is given by
pulley and cable arrangement.
• The concrete gets discharged
in the pile, the end of the
tremie pipe remains dipped in
the concrete so no mud enters
the tremie pipe.
• This method is continued until
concreting for whole of the pile
is complete.
•The concrete does not get
affected due to mud except the
top layer.
Road, Culvert & Bridge Training

More Related Content

What's hot (20)

Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Box culvert
Box culvertBox culvert
Box culvert
 
CONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROADCONSTRUCTION OF CEMENT CONCRETE ROAD
CONSTRUCTION OF CEMENT CONCRETE ROAD
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
Tunnel construction
Tunnel constructionTunnel construction
Tunnel construction
 
Setting out work
Setting out workSetting out work
Setting out work
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
PERMANANT WAY
PERMANANT WAYPERMANANT WAY
PERMANANT WAY
 
Under ground railway
Under ground railwayUnder ground railway
Under ground railway
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
3.alignment of railway lines
3.alignment of railway lines3.alignment of railway lines
3.alignment of railway lines
 
Tunneling
Tunneling Tunneling
Tunneling
 
Bridge survey
Bridge surveyBridge survey
Bridge survey
 
Rail gauge
Rail gaugeRail gauge
Rail gauge
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Tunnel engineering
  Tunnel engineering  Tunnel engineering
Tunnel engineering
 
Box culverts
Box culvertsBox culverts
Box culverts
 
Hydraulic structures
Hydraulic structuresHydraulic structures
Hydraulic structures
 
Setting out of bridges unit 6
Setting out of bridges unit 6Setting out of bridges unit 6
Setting out of bridges unit 6
 

Viewers also liked

Rcc Design Sheets
Rcc Design SheetsRcc Design Sheets
Rcc Design Sheetsklecivil
 
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...Communications Branding
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsCommunications Branding
 
Residential Electricity Consumption
Residential Electricity ConsumptionResidential Electricity Consumption
Residential Electricity ConsumptionElectricityMatch.com
 
Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...
Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...
Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...Jesse Yates
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions Agata Woźniak
 
Webinar: Storm Sewer & Culvert Solutions: Applications & Best Practices
Webinar: Storm Sewer & Culvert Solutions: Applications & Best PracticesWebinar: Storm Sewer & Culvert Solutions: Applications & Best Practices
Webinar: Storm Sewer & Culvert Solutions: Applications & Best PracticesCommunications Branding
 
Going green with glogs TexTESOL 2013
Going green with glogs TexTESOL 2013Going green with glogs TexTESOL 2013
Going green with glogs TexTESOL 2013sabinethepaut
 

Viewers also liked (12)

Rcc Design Sheets
Rcc Design SheetsRcc Design Sheets
Rcc Design Sheets
 
Internship Team 4
Internship Team 4Internship Team 4
Internship Team 4
 
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
Let it Flow! Culvert Design 101 – Basic Hydraulics, Culvert Location & End Tr...
 
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & ApplicationsKeep it Flowing! Culvert Design 20: Design, Durability & Applications
Keep it Flowing! Culvert Design 20: Design, Durability & Applications
 
Team 19
Team 19Team 19
Team 19
 
Iso kpi
Iso kpiIso kpi
Iso kpi
 
Residential Electricity Consumption
Residential Electricity ConsumptionResidential Electricity Consumption
Residential Electricity Consumption
 
Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...
Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...
Culvert: A Robust Framework for Secondary Indexing of Structured and Unstruct...
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
 
Webinar: Storm Sewer & Culvert Solutions: Applications & Best Practices
Webinar: Storm Sewer & Culvert Solutions: Applications & Best PracticesWebinar: Storm Sewer & Culvert Solutions: Applications & Best Practices
Webinar: Storm Sewer & Culvert Solutions: Applications & Best Practices
 
Going green with glogs TexTESOL 2013
Going green with glogs TexTESOL 2013Going green with glogs TexTESOL 2013
Going green with glogs TexTESOL 2013
 
Human Impact on the natural Environment
Human Impact on the natural EnvironmentHuman Impact on the natural Environment
Human Impact on the natural Environment
 

Similar to Road, Culvert & Bridge Training

Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionShyam Anandjiwala
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentationPravin Gaurav
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxJaySinghchib1
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover projectKriShna Sharma
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2AJEETH B
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksKumarS250747
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationKumarS250747
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigidKumarS250747
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSreemajadwani
 

Similar to Road, Culvert & Bridge Training (20)

training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Cement Manufacturing Plant Construction
Cement Manufacturing Plant ConstructionCement Manufacturing Plant Construction
Cement Manufacturing Plant Construction
 
signature bridge short presentation
signature bridge short presentationsignature bridge short presentation
signature bridge short presentation
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptxCONSTRUCTION_OF_RIGID_PAVEMENT.pptx
CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Precast Six lane flyover project
Precast Six lane flyover projectPrecast Six lane flyover project
Precast Six lane flyover project
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2Railway Construction and Maintenance RHTA Module 2
Railway Construction and Maintenance RHTA Module 2
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Lining in tunnels
Lining in tunnelsLining in tunnels
Lining in tunnels
 
CASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil worksCASE STUDY of remedial measure of civil works
CASE STUDY of remedial measure of civil works
 
CASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitationCASE STUDY. on Restoration and rehabilitation
CASE STUDY. on Restoration and rehabilitation
 
Anantpur Report
Anantpur ReportAnantpur Report
Anantpur Report
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigid
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
 

Recently uploaded

Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxsomshekarkn64
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Recently uploaded (20)

Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
lifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptxlifi-technology with integration of IOT.pptx
lifi-technology with integration of IOT.pptx
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 

Road, Culvert & Bridge Training

  • 1.
  • 2. Length Of Road= 79 km No. Of Culverts = 44 No. Of Bridges = 2 Widening and Strengthening of Kowar Kodarma Road • The Road Passes through many thickly populated villages. • Width of the existing crust is 3 m. • Which is to be widened up to 7 m. • The improvement of this road will uplift the social and economic condition of the area.
  • 3. The materials used in the above layers has to go through various quality control checks •Granular Sub Base (GSB) •Wet Mix Macadam (WMM) •Bituminous macadam (BM) •Semi dense bituminous concrete (SDBC)
  • 4. Water Absorption test Aggregate Impact test Flakiness Index Sieve analysis Bitumen content test
  • 5. A traffic census had been conducted previously at three points on the road continuously for 7 days to get average daily traffic. Number of CV/day is obtained from it, denoted by ‘P’ Cumulative Traffic is found out as given in IRC 37 -2001. From the Cumulative Traffic, and known CBR value ; we use the Pavement design Catalogue and obtain thickness of all the layers required in the Road. N = {365*(1+r)^n -1} *D*F*P(1+r)^x r
  • 6. The portion to be widened beyond the existing crust was excavated using the excavator.
  • 7. The GSB was brought from the mixing plant in Dumpers and Dumped at the Site. It was then spread uniformly with the Motor Grader • The GSB was then compacted in layers such that each layer did not exceed 100 mm compacted thickness. • Next the layer of WMM was spread over the GSB and was compacted in layers. • To fill the voids remaining, stone dust was used, rolling was continued until no more dust could be forced into the voids. •Sprinkling of water is done with continued rolling to obtain well bounded and firmly set surface.
  • 8. Compacted WMM is allowed to completely dry and set before the next pavement is laid.
  • 9. Surface of WMM is swept clean and dust is blown of using compressed air. Once the surface is clean, the Prime coat is sprayed over the surface using sprayer. The surface is allowed to cure for 24 hours. After 24 hours the Tack coat or binder is uniformly sprayed over the surface. Emulsion is used as binder shall have temperature 20 c to 50 c.
  • 10. Immediately after spraying the tack coat, the layer of BM is laid over it. The BM is brought at site by a Dumper, at that time the temperature of BM should be 120 c. The Dumper is slowly tilted over the Rack of the Paving machine while both paver and dumper slowly moves forward.
  • 11. The conveyor Belt arrangement in the Paver and leveling plate spreads the BM neatly behind as both Dumper and paver moves forward. The Camber is provided by adjusting the leveling plate.
  • 12. Paving is accompanied with rolling. Any high spots or depressions noticed are corrected by removing or adding material and rolling done over it again. Water is sprinkled over roller wheels to prevent sticking of materials to it. Rolling must be complete before the temperature of BM falls below 90 c
  • 13. A tack coat is again applied over the BM course. The top wearing course of SDBC is also applied with the same process as BM. Tolerance level for BM = 6mm Tolerance level for SDBC = 4 mm The rolling is done as such each pass overlaps with at least one third of the track made in preceding pass. The layer of SDBC is immediately sprinkled with Stone Dust to prevent the sticking of materials to shoes or wheels. Traffic is allowed 24 hours after laying SDBC
  • 14. Hot Thermoplastic compound is used for marking, which is laid with the help of a Road Marking Machinery. Thermoplastic material is homogenously composed of pigments, reflecting glass beads and resins. Binder - 18% Glass beads - 40 % Titanium dioxide - 10% Calcium carbonate - 42%
  • 15. Mostly two types of culverts were constructed along the road. RCC Culvert and Stone Masonry Culvert.
  • 16. First excavation pit for the Foundation slab was dug. Foundation slab for both the abutments were casted as one unit. Series of parallel bars 8 mm dia @ 200 mm c/c are laid on the slab First 400 mm of the bar is made to rest on the slab and rest part is folded above at right angles. These bars are called Skin Reinforcement. Formwork for further casting of substructure is fixed. Casting is done in two layers of 200 mm, hence casting of 400 mm was done in one day.
  • 17. According to the shape of the abutment, the skin reinforcements were bent at the desired angle where ever necessary , fixing of formwork and casting was done as usual.
  • 18. At 0.5 m above the ground level, weep holes are provided. Weep holes drain the water that accumulates on either side of the abutment. Diameter of weep holes = 75 mm @ 1m c/c The construction till Dirt wall is completed in following the usual procedure.
  • 19. Lets see how Stone masonry Culvert was completed till here. Stone Masonry Culverts are built where good quality stones are readily available. Stones of standard size are joined using mortar one by one.
  • 20. • A string is stretched along the length of the culvert which is used to keep the alignment of the stones correct while placing them. •The stones are placed at the edges first, the flat surface of the stone is kept facing outward to get a good finished surface. • Weep Holes are provided in the same way as in RCC Culvert. Dirl wall is also made up of stones, smaller size of stones are used in it.
  • 21. After construction till dirt wall is complete, the process for further construction in both types of Culvert is same. o The reinforcement for the abutment cap is tied and form work is fixed. o Then casting of abutment cap is done.
  • 22. o Abutment cap is cured for at least 1 week then the formwork for slab is fixed. o The reinforcement for slab is tied while keeping the necessary camber. o Concreting of slab is done as usual. o The slab is now cured for 28 days
  • 23. • The old bridge was narrow, damaged and insufficient to carry present traffic load. • It was a five span bridge with total length 123 m. • Hard strata was found at a depth of 20 m • The construction was just started and the location of first pile was well marked. • A metal sheet was folded with the help of a machine into a desired diameter of 1.2 m. • This metal cylinder was used as a casing for the pile
  • 24. • A large tripod is centered over the point of piling • The cylinder is driven at that point and water is filled to make the strata loose. • Next a pile hammer is mounted over the tripod with a system of pulley and cables. • The diameter of the hammer is just enough to fit in the casing. • The hammer is then constantly made to drop from a height of 5 m inside the casing. • This breaks the strata below.
  • 25. • When enough strata is broken down, the mud collected inside the pile gutter, is taken out with the help of one way valve. • This process is continued and it takes near about 5 days to complete the excavation of 20 m.
  • 26. • The reinforcement bars are then tied • 30 bars of 25 mm dia were provided as main steel • Helical Stirrups are provided of dia 10 mm with a spacing of 150 mm c/c. • This reinforcement is then placed inside the pile casing with the help of a crane. • Concrete is then placed inside the pile with Tremie method. •The tremie pipes are coupled together and inserted inside the pile. •It is fitted with a Hopper on top.
  • 27. •The concrete is placed on the top of the Hopper. • whole length of pipe is filled with concrete. • The tremie pipe is lifted up and a slight jerk is given by pulley and cable arrangement. • The concrete gets discharged in the pile, the end of the tremie pipe remains dipped in the concrete so no mud enters the tremie pipe. • This method is continued until concreting for whole of the pile is complete. •The concrete does not get affected due to mud except the top layer.