Extension of time in
Construction Contracts
Over-riding principles
● Employer must fully co-operate with contractor
● Employer cannot hinder the works of the contractor
○ Luxor (Eastbourne) Ltd v Cooper
○ William Cory & Sons Ltd v City of London Corporation
● Failing which, employer cannot insist on strict completion
date
○ Percy Bilton Ltd v Greater London Council
Importance of time
● Absolute obligation of contract to strictly complete works
on time
○ Trollope & Colls Ltd v North West Metropolitan
Regional Hospital Board
○ Percy Bilton v Greater London Council
● Contractor’s time obligation is waived if there are delays
caused by employer or neutral events
What happens if there are delays?
● Two options are available to employer if it has caused any
delay
○ Extend time
○ Instruct for acceleration of works
● Neutral events can also cause delays, eg events of force
majeure
Why should employers extend time?
● If delay caused by employer and employer does not extend time…
○ Time becomes at large
○ Contractor only required to complete within reasonable time, not
contracted time
○ What is reasonable depends on the circumstances
■ Hick v Raymond & Reid
○ LAD is no longer applicable
■ Holme v Guppy
■ Roberts v Bury Improvement Commissioners
○ But contractor can be liable for general damages for not completing
within reasonable time
■ Lian Soon Construction Pte Ltd v Guan Qian Realty Pte Ltd
Limits to extension of time
● Time CANNOT be extended:
○ Unless permitted by the contract and strictly on its terms (Peak
Construction (Liverpool) Ltd v McKinney Foundations Ltd)
○ By the employer for its own benefit if not permitted by contract
(Dodd v Churton)
○ By the contractor for any event not expressly set out in the
contract (Murdoch v Luckie)
○ Unless there is strict compliance to the procedures and pre-
conditions in the contract
What if the contract is not clear?
● The specific words of the contract are important because it determines the
power of the contract administrator to extend time (Wells v Army & Navy Co-
operative Society Ltd)
● In the absence of clear words to the contrary, extension of time should be
granted only for events which are likely or would actually cause a delay in
completion, not for events which merely disrupt the works (Syarikat Tan Kim
Beng & Rakan-Rakan v Pulai Jaya Sdn Bhd)
● If in doubt, the provisions of the contract will be read in favour of the
contractor by reason of contra proferentum rule (Miller v London County
Council)
Procedure for Extension
● Procedure is always set out in contract and must be complied
strictly
● Usually it includes:
○ Contractor to notify of delay
○ Contractor to apply for extension of time
○ Contract administrator assesses application
○ Contract administrator extends time if appropriate
● It is always the Contractor who must prove the need for
extension of time with the support of documents
What if Contractor Fails to Comply with Contract Procedures?
● Depends on whether procedures are directory or
mandatory
● If mandatory, his application for extension of time can be
denied
● If directory, his application can still be allowed but for a
lesser time extension
○ Syarikat Tan Kim Beng & Rakan-Rakan v Pulai Jaya
Sdn Bhd
The role of the contract administrator
● Contract administrator must decide on an extension of time application based
on:
○ Whether contract allows extension
○ Whether circumstances reasonable for extension
● In deciding, administrator must:
○ act fairly, reasonably and impartially, otherwise his decision may be
invalidated and he may even be sued
■ Holland Hannen & Cubitts (Northern) Ltd v Welsh Health Technical
Services Organisation
○ Apply the provisions of the contract
■ John Barker Construction Ltd v London Portman Hotel Ltd
Communicating the administrator’s decision
● Administrator must communicate his decision within the
contractual time (or within a reasonable time if no
contractual time), otherwise extension can be deemed
approved
○ Lion Engineering Sdn Bhd v Pauchuan Development
Sdn Bhd
● Usually decision conveyed by way of a certificate for
extension of time
Challenging the certificate for extension of time
● Certificate for extension of time can be invalidated
● Usually it will not be invalidated unless there is:
○ Disregard for the contract
○ Evidence of fraud, collusion or similar wrong doing
■ Lubenham Fidelities Investment Co Ltd v South
Pembrokeshire District Council
Examples of grounds for challenging extension of time certificate
● Certificate not given on time
● Certificate not in the correct format
● Certificate issued by unauthorised person
● Addressee of certificate not named
● Decision to extend time improperly delegated
● Certificate not given fairly
● Contractual procedures not followed
When to grant extension of time?
● EOTs are usually made prospectively
● Whether EOT can be granted retrospectively (ie after completion) depends on
the terms of the contract
● If contract is unclear, it will be read to benefit the contractor (Amalgamated
Building Contractors Ltd v Waltham Holy Cross UDC)
● Courts are strict to grant EOT to favour an employer, for example to reduce
LAD (Balfour Beatty Building Ltd v Chestermount Properties Ltd)
● Retrospective EOTs are allowed if it can only be reasonably done under the
circumstances (eg actual effect of intervening event on time cannot be
evaluated until after completion) (Engineering Construction Pte Ltd v AG)
Concurrent delays
● Concurrent delays happen when two or more causes of delay overlap in time
● There are different approaches to deal with concurrent delays
○ Approach One: What is the dominant cause? (used in Leyland Shipping
Co Ltd v Norwich Union Fire Insurance Society Ltd)
○ Approach Two: The “but-for” approach (used in Quinn v Burch Bros
(Builders) Ltd)
○ Approach Three: The apportionment/allocation approach (used in
Tennant Radian Heat v Warrington Development Corporation)
● Which approach to be applied very much depends on the facts and the judge
of each case
Multiple extensions
● Should ideally be handled separately
● Otherwise, if administrator elects to process multiple
applications for EOTs “one-go”, there may be risk of time
being made at large due to failure to adequately consider
any one application
Effect of Omissions on Time Extensions
● Contract administrator cannot reduce contract period or even
previously extended period even if there is any omission. The
contractor cannot be compelled to complete the contract earlier
than agreed (Glenlion Construction Ltd v The Guinness Trust)
● However, contract administrator can take into account omissions
when deciding on extension of time applications, provided the net
effect is that the completion date is not earlier than the one
previously fixed
Extension when contractor is also culpable
● If contractor has delayed, but at the same time employer has committed some
act of prevention, contractor is entitled to extension of time for net delay
(Balfour Beatty Building Ltd v Chestermount Properties Ltd; Amalgamated
Building Contractors Ltd v Waltham Holy Cross)
● However, if there was delay caused by neutral event, contractor who has
delayed will only be entitled to extension if he can prove that the neutral event
would have caused a delay even without his own delay
● However, some cases decided that a contractor who is culpable for delay is
not entitled to extension for neutral events (Balfour Beatty Building Ltd v
Chestermount Properties Ltd)
Reviewing extensions that are already granted
● Generally, this is not allowed
● However, can happen if allowed by the contract
● Any review is entirely the contract administrator’s discretion. He cannot be
compelled or mandated to do so (Temloc Ltd v Errill Properties Ltd)
● After review, the administrator can confirm the completion period or fix a
period that is later than the previous one, but not earlier
● Delay and extension of time for nominated subcontractors
○ Extensions of time sought by nominated subcontractors would usually be
facilitated by the contractors
○ It is still the contract administrator who makes the decision on any
application for extensions of time
Compensation following grant of time extension
● If an EOT is granted to the contractor, it does NOT mean
that the contractor is entitled to claim loss or expense
● Time entitlement and issue of compensation are separate
issues governed by different provisions of the contract
Acceleration of works
● Types and basis
○ Acceleration involves contractor taking deliberate steps to step up pace
of works to catch up on delay or reduce time period for completion
○ Generally encompasses re-programming of work and employment of
more resources
○ Acceleration can be “contractor initiated” or “instructed by contract
administrator”
○ Contractor may accelerate works to redress any delay for which he is
culpable, and he won’t be entitled to any costs
○ Contractor who is not in culpable delay may accelerate works
“constructively”, ie without any danger of delay/LAD being imposed
■ Firstly, when administrator fails to give decision on contractor’s
application for EOT
■ When administrator disputes contractor’s entitlement to EOT and it is
unclear at that point in time whether the administrator’s decision is
valid
○ For constructive acceleration, contractor is entitled to claim for loss and
expense if it is later established that contractor’s application for EOT was
valid
○ For acceleration that is directed by administrator, this can only happen if
the contract allows for it or by mutual agreement
○ Administrator cannot accelerate works without contractor’s consent
without express power to do so
○ Usually the contract will allow the administrator to accelerate works
where:
■ The administrator is of the view the contractor won’t be able to meet
the deadline
■ The contractor is entitled to EOT but administrator wants to maintain
the original completion period
● Acceleration in lieu of extension
○ It is becoming more commonplace for acceleration to be instructed in lieu
of extension of time
○ If acceleration fails, then there may be a limited extension of time granted
for the residual works
○ This requires either express provision in the contract or mutual
agreement
Extension of time in construction contracts

More Related Content

What's hot

Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in MalaysiaDayat Mohamad
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Tee Joanne
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 

What's hot (20)

Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
Contract Management
Contract Management Contract Management
Contract Management
 
Construction Contract in Malaysia
Construction Contract in MalaysiaConstruction Contract in Malaysia
Construction Contract in Malaysia
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Claims
ClaimsClaims
Claims
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Fidic
FidicFidic
Fidic
 
Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021Fundamentals of Construction Contracts - English, ver. 2021
Fundamentals of Construction Contracts - English, ver. 2021
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 

Similar to Extension of time in construction contracts

FM Forum - Termination & TUPE
FM Forum - Termination & TUPEFM Forum - Termination & TUPE
FM Forum - Termination & TUPELewis Silkin
 
CL Seminar
CL SeminarCL Seminar
CL Seminarkohwenqi
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Managementbrainquisitive
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
20091118 Construction Life cycle completion
20091118 Construction Life cycle completion20091118 Construction Life cycle completion
20091118 Construction Life cycle completionraymond_wan2005
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2JB Nartey
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITIONByishimoBTCChef
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractSHKLaw
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsFrancis Ho
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...SHKLaw
 
Terminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightTerminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightFrancis Ho
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
Adm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdibaBaves18
 

Similar to Extension of time in construction contracts (20)

FM Forum - Termination & TUPE
FM Forum - Termination & TUPEFM Forum - Termination & TUPE
FM Forum - Termination & TUPE
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
Seminar
SeminarSeminar
Seminar
 
Liquidated damages
Liquidated damagesLiquidated damages
Liquidated damages
 
20091118 Construction Life cycle completion
20091118 Construction Life cycle completion20091118 Construction Life cycle completion
20091118 Construction Life cycle completion
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
GCC2015 Course_Day2
GCC2015 Course_Day2GCC2015 Course_Day2
GCC2015 Course_Day2
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Prolongation and HOOH Costs
Prolongation and HOOH CostsProlongation and HOOH Costs
Prolongation and HOOH Costs
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Extra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the ContractExtra Work, Changes and Termination of the Contract
Extra Work, Changes and Termination of the Contract
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and Tactics
 
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
Nuts and bolts of builders liens (Independent Contractors and Businesses Asso...
 
Terminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightTerminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it Right
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Adm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.pptAdm proyek kontrak konstruksi.ppt
Adm proyek kontrak konstruksi.ppt
 

Recently uploaded

一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理e9733fc35af6
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubham Wadhonkar
 
一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理ss
 
一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理Fir La
 
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理F La
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理bd2c5966a56d
 
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理e9733fc35af6
 
Reason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in IndiaReason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in IndiaYash
 
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理e9733fc35af6
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理e9733fc35af6
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYJulian Scutts
 
judicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxjudicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxIshikaChauhan30
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategyJong Hyuk Choi
 
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书irst
 
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量acyefsa
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理e9733fc35af6
 
Performance of contract-1 law presentation
Performance of contract-1 law presentationPerformance of contract-1 law presentation
Performance of contract-1 law presentationKhushdeep Kaur
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Nilendra Kumar
 
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee
 

Recently uploaded (20)

一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理一比一原版悉尼科技大学毕业证如何办理
一比一原版悉尼科技大学毕业证如何办理
 
Shubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptxShubh_Burden of proof_Indian Evidence Act.pptx
Shubh_Burden of proof_Indian Evidence Act.pptx
 
一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)昆特兰理工大学毕业证如何办理
 
一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理一比一原版(Warwick毕业证书)华威大学毕业证如何办理
一比一原版(Warwick毕业证书)华威大学毕业证如何办理
 
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理一比一原版(UM毕业证书)密苏里大学毕业证如何办理
一比一原版(UM毕业证书)密苏里大学毕业证如何办理
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
一比一原版(OhioStateU毕业证书)美国俄亥俄州立大学毕业证如何办理
 
Reason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in IndiaReason Behind the Success of Law Firms in India
Reason Behind the Success of Law Firms in India
 
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
一比一原版(KPU毕业证书)加拿大昆特兰理工大学毕业证如何办理
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
judicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptxjudicial remedies against administrative actions.pptx
judicial remedies against administrative actions.pptx
 
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation StrategySmarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
Smarp Snapshot 210 -- Google's Social Media Ad Fraud & Disinformation Strategy
 
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy NovicesIt’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
It’s Not Easy Being Green: Ethical Pitfalls for Bankruptcy Novices
 
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
一比一原版(MelbourneU毕业证书)墨尔本大学毕业证学位证书
 
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
买(rice毕业证书)莱斯大学毕业证本科文凭证书原版质量
 
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
一比一原版(Carleton毕业证书)加拿大卡尔顿大学毕业证如何办理
 
Performance of contract-1 law presentation
Performance of contract-1 law presentationPerformance of contract-1 law presentation
Performance of contract-1 law presentation
 
Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.Cyber Laws : National and International Perspective.
Cyber Laws : National and International Perspective.
 
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
Sangyun Lee, Duplicate Powers in the Criminal Referral Process and the Overla...
 

Extension of time in construction contracts

  • 1. Extension of time in Construction Contracts
  • 2. Over-riding principles ● Employer must fully co-operate with contractor ● Employer cannot hinder the works of the contractor ○ Luxor (Eastbourne) Ltd v Cooper ○ William Cory & Sons Ltd v City of London Corporation ● Failing which, employer cannot insist on strict completion date ○ Percy Bilton Ltd v Greater London Council
  • 3. Importance of time ● Absolute obligation of contract to strictly complete works on time ○ Trollope & Colls Ltd v North West Metropolitan Regional Hospital Board ○ Percy Bilton v Greater London Council ● Contractor’s time obligation is waived if there are delays caused by employer or neutral events
  • 4. What happens if there are delays? ● Two options are available to employer if it has caused any delay ○ Extend time ○ Instruct for acceleration of works ● Neutral events can also cause delays, eg events of force majeure
  • 5. Why should employers extend time? ● If delay caused by employer and employer does not extend time… ○ Time becomes at large ○ Contractor only required to complete within reasonable time, not contracted time ○ What is reasonable depends on the circumstances ■ Hick v Raymond & Reid ○ LAD is no longer applicable ■ Holme v Guppy ■ Roberts v Bury Improvement Commissioners ○ But contractor can be liable for general damages for not completing within reasonable time ■ Lian Soon Construction Pte Ltd v Guan Qian Realty Pte Ltd
  • 6. Limits to extension of time ● Time CANNOT be extended: ○ Unless permitted by the contract and strictly on its terms (Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd) ○ By the employer for its own benefit if not permitted by contract (Dodd v Churton) ○ By the contractor for any event not expressly set out in the contract (Murdoch v Luckie) ○ Unless there is strict compliance to the procedures and pre- conditions in the contract
  • 7. What if the contract is not clear? ● The specific words of the contract are important because it determines the power of the contract administrator to extend time (Wells v Army & Navy Co- operative Society Ltd) ● In the absence of clear words to the contrary, extension of time should be granted only for events which are likely or would actually cause a delay in completion, not for events which merely disrupt the works (Syarikat Tan Kim Beng & Rakan-Rakan v Pulai Jaya Sdn Bhd) ● If in doubt, the provisions of the contract will be read in favour of the contractor by reason of contra proferentum rule (Miller v London County Council)
  • 8. Procedure for Extension ● Procedure is always set out in contract and must be complied strictly ● Usually it includes: ○ Contractor to notify of delay ○ Contractor to apply for extension of time ○ Contract administrator assesses application ○ Contract administrator extends time if appropriate ● It is always the Contractor who must prove the need for extension of time with the support of documents
  • 9. What if Contractor Fails to Comply with Contract Procedures? ● Depends on whether procedures are directory or mandatory ● If mandatory, his application for extension of time can be denied ● If directory, his application can still be allowed but for a lesser time extension ○ Syarikat Tan Kim Beng & Rakan-Rakan v Pulai Jaya Sdn Bhd
  • 10. The role of the contract administrator ● Contract administrator must decide on an extension of time application based on: ○ Whether contract allows extension ○ Whether circumstances reasonable for extension ● In deciding, administrator must: ○ act fairly, reasonably and impartially, otherwise his decision may be invalidated and he may even be sued ■ Holland Hannen & Cubitts (Northern) Ltd v Welsh Health Technical Services Organisation ○ Apply the provisions of the contract ■ John Barker Construction Ltd v London Portman Hotel Ltd
  • 11. Communicating the administrator’s decision ● Administrator must communicate his decision within the contractual time (or within a reasonable time if no contractual time), otherwise extension can be deemed approved ○ Lion Engineering Sdn Bhd v Pauchuan Development Sdn Bhd ● Usually decision conveyed by way of a certificate for extension of time
  • 12. Challenging the certificate for extension of time ● Certificate for extension of time can be invalidated ● Usually it will not be invalidated unless there is: ○ Disregard for the contract ○ Evidence of fraud, collusion or similar wrong doing ■ Lubenham Fidelities Investment Co Ltd v South Pembrokeshire District Council
  • 13. Examples of grounds for challenging extension of time certificate ● Certificate not given on time ● Certificate not in the correct format ● Certificate issued by unauthorised person ● Addressee of certificate not named ● Decision to extend time improperly delegated ● Certificate not given fairly ● Contractual procedures not followed
  • 14. When to grant extension of time? ● EOTs are usually made prospectively ● Whether EOT can be granted retrospectively (ie after completion) depends on the terms of the contract ● If contract is unclear, it will be read to benefit the contractor (Amalgamated Building Contractors Ltd v Waltham Holy Cross UDC) ● Courts are strict to grant EOT to favour an employer, for example to reduce LAD (Balfour Beatty Building Ltd v Chestermount Properties Ltd) ● Retrospective EOTs are allowed if it can only be reasonably done under the circumstances (eg actual effect of intervening event on time cannot be evaluated until after completion) (Engineering Construction Pte Ltd v AG)
  • 15. Concurrent delays ● Concurrent delays happen when two or more causes of delay overlap in time ● There are different approaches to deal with concurrent delays ○ Approach One: What is the dominant cause? (used in Leyland Shipping Co Ltd v Norwich Union Fire Insurance Society Ltd) ○ Approach Two: The “but-for” approach (used in Quinn v Burch Bros (Builders) Ltd) ○ Approach Three: The apportionment/allocation approach (used in Tennant Radian Heat v Warrington Development Corporation) ● Which approach to be applied very much depends on the facts and the judge of each case
  • 16. Multiple extensions ● Should ideally be handled separately ● Otherwise, if administrator elects to process multiple applications for EOTs “one-go”, there may be risk of time being made at large due to failure to adequately consider any one application
  • 17. Effect of Omissions on Time Extensions ● Contract administrator cannot reduce contract period or even previously extended period even if there is any omission. The contractor cannot be compelled to complete the contract earlier than agreed (Glenlion Construction Ltd v The Guinness Trust) ● However, contract administrator can take into account omissions when deciding on extension of time applications, provided the net effect is that the completion date is not earlier than the one previously fixed
  • 18. Extension when contractor is also culpable ● If contractor has delayed, but at the same time employer has committed some act of prevention, contractor is entitled to extension of time for net delay (Balfour Beatty Building Ltd v Chestermount Properties Ltd; Amalgamated Building Contractors Ltd v Waltham Holy Cross) ● However, if there was delay caused by neutral event, contractor who has delayed will only be entitled to extension if he can prove that the neutral event would have caused a delay even without his own delay ● However, some cases decided that a contractor who is culpable for delay is not entitled to extension for neutral events (Balfour Beatty Building Ltd v Chestermount Properties Ltd)
  • 19. Reviewing extensions that are already granted ● Generally, this is not allowed ● However, can happen if allowed by the contract ● Any review is entirely the contract administrator’s discretion. He cannot be compelled or mandated to do so (Temloc Ltd v Errill Properties Ltd) ● After review, the administrator can confirm the completion period or fix a period that is later than the previous one, but not earlier ● Delay and extension of time for nominated subcontractors ○ Extensions of time sought by nominated subcontractors would usually be facilitated by the contractors ○ It is still the contract administrator who makes the decision on any application for extensions of time
  • 20. Compensation following grant of time extension ● If an EOT is granted to the contractor, it does NOT mean that the contractor is entitled to claim loss or expense ● Time entitlement and issue of compensation are separate issues governed by different provisions of the contract
  • 21. Acceleration of works ● Types and basis ○ Acceleration involves contractor taking deliberate steps to step up pace of works to catch up on delay or reduce time period for completion ○ Generally encompasses re-programming of work and employment of more resources ○ Acceleration can be “contractor initiated” or “instructed by contract administrator” ○ Contractor may accelerate works to redress any delay for which he is culpable, and he won’t be entitled to any costs
  • 22. ○ Contractor who is not in culpable delay may accelerate works “constructively”, ie without any danger of delay/LAD being imposed ■ Firstly, when administrator fails to give decision on contractor’s application for EOT ■ When administrator disputes contractor’s entitlement to EOT and it is unclear at that point in time whether the administrator’s decision is valid ○ For constructive acceleration, contractor is entitled to claim for loss and expense if it is later established that contractor’s application for EOT was valid ○ For acceleration that is directed by administrator, this can only happen if the contract allows for it or by mutual agreement
  • 23. ○ Administrator cannot accelerate works without contractor’s consent without express power to do so ○ Usually the contract will allow the administrator to accelerate works where: ■ The administrator is of the view the contractor won’t be able to meet the deadline ■ The contractor is entitled to EOT but administrator wants to maintain the original completion period
  • 24. ● Acceleration in lieu of extension ○ It is becoming more commonplace for acceleration to be instructed in lieu of extension of time ○ If acceleration fails, then there may be a limited extension of time granted for the residual works ○ This requires either express provision in the contract or mutual agreement