1. b.2.b Improving Project Delivery for Denver County Jail – East Housing Unit
Quality Assurance Specialist
Charles Rountree
InsideOut Consulting, Inc. / Civil Technology
Inc.
Background
The challenge was for a design-bid-build project delivery method to perform demolition of eight
buildings and a construct a new seven story, 104, 000 square feet of new inmate housing, such that
it connects with the remaining facility. The City & County of Denver (CCD), Denver Sheriff
Department’s (client) 24-7, 365 days County jail operations are not to be interrupted, without a 72
hour prior notification. The project is scheduled to be completed on time, per the 22 month
allotted time; on budget; and per the contract documents quality specifications (This means zero
defects). Lastly, the project is proposed to have zero lost-work time injuries and zero property
damage to the remaining facility.
Target Condition
Establish a collaborative environment with the project team, even thought written d-b-b
delivery method contracts have been signed.
Establish a collaborative QC/QA Management System that is integrated into the production
schedule to help achieve the zero defect client requested outcome, such that a target goal of
$230,000 (10% of the contract price) can be returned to the client.
Establish a collaborative Project Safety & Health Management System, integrated into the
production schedule. Thus, providing a greater opportunity to achieve zero lost-work time
injuries and zero property damage.
The Lean Strategic Approach Implemented.
Established clear Conditions of Satisfaction (CoS) from the owner and regulation agencies.
Implemented a Pull Planning process versus a Push Planning process when integrating the
QC/QA and the Beyond Zero Safety & Health Mgmt Plan requirements into the production
schedule.
Implemented a lean safety & quality performance indicator called Percentage of Safe and
Quality Work Packages (PSQW) System, similar to PPC tracked in Last Planner System to
monitor, and improve safety promises made. Daily used a 6S checklist form to observe, track
and record actual performance in the field. This information was later inserted into the PSQW.
The PSQW also acts a value stream indicator, such that value adding and non-value adding
activity is tracked.
Used 5-Why Root Cause Analysis for appropriate counter solutions for Actual
accidents/incidents & Near Miss Incidents (NMI)
Used A3 Thinking Processes for decision making, strategy development, and process
improvement.
Traditional Condition
Facilities that are constructed using the design-bid-build delivery methods usually minimize
collaboration, due to the owner having a separate contract with the Architect and a separate
contract with the Prime Contractor. This leads to great waste in the project.
Facilities that are constructed using this delivery method foster a “Blow & Go” attitude, such
that one should design & build as fast as they can, because someone else will fix the problems
later, since the designer and contractor were the lowest bidders.
Integrating safety and quality requirements should not be integrated into the production
schedule, because it will take extra time and extra money to implement.
There’s no way to have zero defects and zero injuries and zero property damage
“Charles is a valued member of the
Jacobs/Civil Tech team at the City. I rely on
Charles to be the eyes and ears at the County
Jail project which he does at a very high
degree. Charles is well liked by all members of
the team and successfully represents the City’s
interests while maintaining the goodwill of
the entire team.” – Dick Gillet, Program
Manager, Jacobs