SlideShare a Scribd company logo
1 of 53
Download to read offline
Updating a Schedule
    December 13, 2007

     Chris Carson, PSP
         Project Controls Manager
            Alpha Corporation
   chris.carson@alphacorporation.com
Schedule Updating
Determine Frequency of Updates
Data Collection
Status Schedule
Calculate
Check for Out-of-Sequence Work
Verify Schedule
Analysis – On Time Completion
Historical Trending & Statistics
Analysis – Late Completion
Reporting - Internal
Narrative – External Reporting
Schedule Updating
Determine Frequency of Updates
Schedule Updating
Frequency of Updates
  Based on schedule purpose
    Management tool
    Meeting a specification requirement
    Internal reporting and predictions
    Limited management use
    Budget
  Based on size of schedule
    Large schedule requires frequent updates
    Overview schedule allows fewer updates
Schedule Updating
Data Collection
Schedule Updating
Data Collection
  Field information – should be kept on a daily basis
    Actual Start Dates
    Actual Finish Dates
    Predicted Finish for any activity started but not finished
    Percent Complete if schedule is cost loaded
    Use Remaining Duration, not Percent Complete, for time
    reporting
      • Superintendents cannot provide accurate Percent
        Complete
      • Superintendents cannot provide accurate Remaining
        Durations
    Recommend Superintendents walk job with update report
Schedule Updating
Standard Field Update Report
Schedule Updating
Data Collection
  Office information
    Gather status of buyout process; purchase orders &
    subcontracts – what is not bought out
    Gather Submittal & Approval status
    Gather status of administrative tasks
      • Utility paperwork status

      • Permits – site, building, right-of-way, Health Department

      • Environmental releases, etc.

    Gather status of materials fabrication and order time - “Lead
    Time”
Schedule Updating
Data Collection
  Owner information
    Gather Status of Owner controlled activities
     • Owner utility applications & progress

               Electricity
           -
               Gas service
           -
               Water & sewer
           -
               Telephone
           -
               Cable or data
           -
               Security system
           -
          Delivery dates for Owner furnished equipment
      •

          Other Owner contractual work
      •

          Verify coordination with Owner work
      •
Schedule Updating
Data Collection
  Subcontractor information
    Gather Status of subcontractor activities
     • Lead Times for subcontractors’ materials

     • Lead Times for subcontractors’ equipment

     • Lead Times for subcontractor mobilization on job (field?)

            - Are they committed to scheduled start date?
            - Are the other trades out of the work area?
            - What is the materials lay-down area availability?
          Resource availability for subcontractors
      •

            - Do the subcontractors have adequate workmen on site?
Schedule Updating
Status Schedule
Schedule Updating
Status Schedule
  Simple progress stage of process
    Make no logic changes during this stage, only progress
    Use standard input layout to record progress
    Input Actual Start and Finish Dates
    Choose Data Date – use last actual dates provided
    If activities are started, set Remaining Durations so
    predicted finish dates are met
Schedule Updating
Calculate Schedule & Check for Out-of-Sequence
 Work
Schedule Updating
Calculate Schedule
  Ensure software setting is Retained Logic
  Set Data Date to date chosen during Schedule
  Status stage
  Calculate schedule
Check for Out-of-Sequence Work
  Change setting temporarily to Progress Override
  If the completion date changes significantly, then
  there is a lot of out-of-sequence work needing
  correcting
  If minimal change, no significant out-of-sequence
  work
  Change the setting back to Retained Logic (default)
Schedule Updating
Verify Schedule
Schedule Updating
Verify Schedule
  Internal verification
     Check that Early Finish dates match predicted finish dates
     provided by Superintendent
     Check on any out-of-sequence work to see if those dates
     were input correctly
  External verification
     Change to verification layout
      • Two week look-ahead filter (only starts & finishes within
        2W)
      • Send to Superintendent to verify that Early Start dates for
        planned activities for the next two weeks are accurate
      • Get feedback & correct any discrepancies

This is a reasonableness check, look it over
Schedule Updating
Prepare for Schedule Analysis
Schedule Updating
Prepare for Schedule Analysis
  Use standard Layout with comparison to last
  update
  Check for slippage in Substantial Completion
  date
    If no slippage, project predicts on time completion
         Perform Standard Analysis, use standard reports and
     •
         publish
    If slippage, go to Analysis of Slipped Schedule
Schedule Updating
Standard Schedule Analysis (On-Time
 Completion)
Schedule Updating
Standard Schedule Analysis (On-Time
Completion)
  Three basic components
    Critical Path progress
     • Slippage will directly delay work

    Near Critical progress
     • Slippage could easily overtake Critical Path and delay
         work
    Non-Critical (“mass volume”) work
     • Lack of progress will cause trade stacking and over-
         crowding of work space at a later date
     • Could easily allow too much work for areas available

     • Good place to use Earned Value for monitoring

     • Can use Float Dissipation to monitor

     • Can use other methods to monitor
Schedule Updating
Standard Schedule Analysis (On-Time
Completion)
  Two types of paths to watch
     Critical Path to end of project (Substantial Completion)
     Critical Path to Interim Milestones
  Critical Path
     Ideally use Longest Path
     Monitor minimum Total Float value Critical Path
  Interim Milestones
     One path per each Milestone to watch
Schedule Updating
Standard Schedule Analysis (On-Time
Completion)
  Identify current period Critical Path (Longest Path)
  Identify current period Near-Critical activities
  Identify easily identified Milestones for between this
  update and next update
    Concrete pours
    Inspections
    Trade mobilizations
  Identify historical trends and statistics (mass volume)
  Identify resource problems or concerns
Schedule Updating
Historical Trends
Schedule Updating
Historical Comparisons & Statistics
  Run Tipper (TPR) reports
  Run Total Float dissipation (Erosion of Float) reports
  Run Free Float dissipation reports (monitors
  disruption)
  Review Out-of-Sequence work by trade
     Which trade is causing most out-of-sequence work?
     Are they working out-of-sequence due to other trade
     failures to complete?
     Or working in open areas without regard for planning?
  Run Resource reports
     Are appropriate resources working?
     Check against Tipper reports
Schedule Updating
      Review (TPR) Time Performance Ratio trending
       (AD/OD)

                                     Time Performance Ratio

      8.00
      7.00
      6.00
      5.00
TPR




      4.00
      3.00
      2.00
      1.00
      0.00
             31-   30- 31-     28-  31-    30-   31- 30-   31-    31-  30- 31-    30-   31-  31- 28- Total
             Oct   Nov- Jan-   Feb- Mar-   Apr- May- Jun- Jul-06 Aug- Sep- Oct-   Nov- Dec- Jan- Feb-
                    05   06     06   06     06   06   06          06   06   06     06   06   07   07

                                                     Period Ending
Schedule Updating
Review (TPR) Time Performance Ratio trending by
 Milestone by Responsible Contractor (AD/OD)
TPR




                                         0.0
                                               2.0
                                                     4.0
                                                           6.0
                                                                 8.0
                                                                       10.0
                                                                              12.0
                            Ad
                                m
                                  in
                        Si
                           te
                              wo
                                  rk
                        C
                                                                                                               (AD/OD)

                          on
                              cr
                                 et
                                    e
                         M
                           as
                               on
                                   ry
                           M
                              et
                       C         al
                                    s
                         ar
                            pe
                                nt
                                   ry
               D          R
                 oo         oo
                    rs
                      / W fing
                           in
                              do
                                  ws
                         Fi
                           ni
                              s


Type of Work
                      E q h es
                         ui
                            p
                                                                                     Time Performance Ratio




                     Fu me
                                   nt
                        rn
                           ish
                               in
                                  g
                       El
                          ev s
                                                                                                                                                              Schedule Updating




                              at
                     M           or
                                    s
                       ec
                          ha
                              ni
                        El cal
                          ec
                                                                                                              Review (TPR) Time Performance Ratio per trade




                              tri
                                 ca
                                     l
Schedule Updating
Review (TPR) Time Performance Ratio trending by
 trade (AD/OD)
                                    Time Performance Ratio (Concrete)

      8.00
      7.00
      6.00
      5.00
TPR




      4.00
      3.00
      2.00
      1.00
      0.00
                                                  6




                                                                        07




                                                                                       7
                 6




                                                             6




                                                                                                l
                                6




                                                                                              ta
                                               -0




                                                                                    -0
                  0




                                                              0
                              -0




                                                                      n-




                                                                                           To
               p-




                                                           c-
                                             ov




                                                                                  eb
                            ct




                                                                    Ja
             Se




                                                        De
                          -O




                                           -N




                                                                                -F
                                                                     -
            -




                                                         -




                                                                  31
                       31




                                        30




                                                                             28
         30




                                                      31




                                                       Period Ending
Schedule Updating
Trade Monitoring by Crew – no resource loading
  available, load single crew resources into activities


  AMP Terminals Yard Project
Schedule Updating
                                  Watch erosion of float, do not let it continue
                                          Print by trade when assessing available resources
                                     •



                                                 Relative Total Float of Area Completion Milestones
                       200




                       150
Relative Total Float




                                                                                                                                                                SCAC
                                                                                                                                                                RCA
                       100
                                                                                                                                                                  WH
                                                                                                                                                                MCAC/CCAC

                                                                                                                                                                Utility Bldg

                                                                                                                                                                  NBB
                                                                                                                                                                MSGQ
                        50
                                                                                                                                                                  WBN
                                                                                                                                                                NOB

                                                                                                                                                                Subst Comp

                         0




                                                                                                                                      22
                             BL


                                    08


                                           09


                                                  10


                                                         11


                                                                12


                                                                       13


                                                                              14


                                                                                     15


                                                                                            16


                                                                                                   17


                                                                                                          18


                                                                                                                 19


                                                                                                                        20


                                                                                                                               21




                                                                                                                                             23


                                                                                                                                                    24


                                                                                                                                                           25
                                                                                                                                    SI
                                  KN


                                         KN


                                                KN


                                                       KN


                                                              KN


                                                                     KN


                                                                            KN


                                                                                   KN


                                                                                          KN


                                                                                                 KN


                                                                                                        KN


                                                                                                               KN


                                                                                                                      KN


                                                                                                                             KN




                                                                                                                                                  KN


                                                                                                                                                         KN
                                                                                                                                           SS
                       -50
Schedule Updating
                         Earned Value Management Reporting
                                  Earned Value and Actual Costs
                             •

                                  See separate training session
                             •

                                             Ciudad Juarez Earned Value
                                          Project Update Earned Value
                 $70,000,000.00

                 $60,000,000.00

                 $50,000,000.00
B illing Value




                 $40,000,000.00
                                                                          Early Curve
                                                                          Late Curve
                 $30,000,000.00
                                                                          Actual Curve
                 $20,000,000.00

                 $10,000,000.00

                         $0.00
                             De v-0 5




                             De v-0 6




                             De -0 7
                             Fe 0 6




                              Ju 0 6




                             Fe -0 7




                              Ju 0 7




                             Fe -0 8
                             M - 06
                             A p - 06




                             A u l-06




                             M 07
                             A p - 07




                             A u l-07




                             M 08
                                      8
                             O - 05



                             J a -0 5




                             M r- 06




                             S e - 06
                             O - 06



                             J a -0 6




                             M r- 07




                             S e - 07
                             O - 07



                             Ja 07
                             J u -06




                             J u -07
                             No - 05




                             No - 06




                             No - 07




                                   -0
                                 n-




                                 n-




                                 n-
                                 b-




                                 b-
                                 c-
                                 v
                                 n




                                 n
                                ar




                                ar




                                ar
                                 b
                                 c




                                 c
                                p




                                g
                                p




                                g
                                p
                               ay




                               ay
                               ct




                               ct




                               ct
                           Se




                                                    Period Ending
Schedule Updating
                             Earned Value Management Reporting
                                     SPI and CPI
                                 •

                                     Watch trending
                                 •


                                                                       Schedule Performance Index

                 1.20

                 1.00
S PI (E V/P V)




                 0.80

                 0.60

                 0.40

                 0.20

                 0.00
                                        05




                                                                                                                                                   06
                                                        06




                                                                                                      06




                                                                                                                                                                   07
                                                                  06


                                                                           6




                                                                                                                6




                                                                                                                                                                             07
                                                                                    6
                        05




                                                05




                                                                                                                         06

                                                                                                                                   06




                                                                                                                                                           06
                                                                                               6
                                 5




                                                                                                                                            6
                                                                         -0




                                                                                                            l-0
                                                                                r- 0


                                                                                            -0
                               -0




                                                                                                                                          -0
                                      v-




                                                                                                                                                 v-
                                                      n-




                                                                                                    n-




                                                                                                                                                                 n-
                                                              b-




                                                                                                                                                                         b-
                        p-




                                              c-




                                                                                                                     g-

                                                                                                                               p-




                                                                                                                                                         c-
                                                                       ar




                                                                                        ay
                             ct




                                                                                                                                        ct
                                                                                                           Ju
                                                                               Ap
                                     No




                                                                                                                                                No
                                                     Ja




                                                                                                   Ju




                                                                                                                                                                Ja
                                                             Fe




                                                                                                                                                                        Fe
                   Se




                                             De




                                                                                                                    Au

                                                                                                                              Se




                                                                                                                                                        De
                                                                       M
                             O




                                                                                                                                        O
                                                                                        M




                                                                                        Period Ending
Schedule Updating
Schedule Analysis – Sequencing Review
  Set up a Layout for Sequence
    Group by Phase or Location
     • Look for out-of-sequence work by trade

    Summarize to Phase
    Neck for non-work periods
    Review the sequence shown by the summary bars
  Set up a Layout for Responsibility
    Group by Responsibility
    Summarize to Responsibility
    Neck for non-work periods
    Review trade workload
Schedule Updating
Schedule Analysis – Constructability
  Set up a Layout for weekly work
    Group by Early Start
    Order by Week
    Sort by ES, EF , TF
    Zoom in to weekly week
    Set Major Vertical Sight Lines to one week
    Expose column for Responsibility and Location
    Review work to be done weekly over the next few months
    for reasonableness
Schedule Updating
Schedule Analysis (Slipped Completion)
Schedule Updating
Schedule Analysis (Slipped Completion)
  If slippage is due to the Owner, then a time
  extension is owed to the Contractor
  If slippage is due to a Subcontractor
    The Subcontractor owes the GC a Recovery Schedule
    effort
    The Contractor (GC) still owes the Owner a Recovery
    Schedule
  If slippage is due to the Contractor, then the
  Contractor owes the Owner a Recovery Schedule
  If the Owner causes the delay and the Sub or GC
  causes a concurrent delay, then a time extension is
  owed to the Contractor; no recovery schedule
  required
Schedule Updating
Schedule Analysis (Slipped Completion)
  Identify previous period Critical Path (Longest Path)
  Use layout to compare against current schedule
  Identify current Critical Path & changes from
  previous
  Identify which activities slipped and drove progress
     Causal Activities drive progress
     Identify Start Gain or Loss
     Identify Production Gain or Loss
  Identify specific Causal Activity or Activities for delay
  Develop process for dealing with slipped completion
  before needed
Collect Admin                        Verify All
                 Progress Data                         Data

                                                                                                                                 No
Request for         Collect Field               Status              Update            Compare to               Critical Path
Update Data         Progress Data              Schedule            Schedule            Baseline                  Delay?


                                                                                                                      Yes
                                 Identify Contract
                                    Changes

                                                                                                             Identify Previous
                                                                                                                  Period
                                                                                                               Critical Path
                                                                                                                                            Publish
            Research                                                                                                                        Updated
                                        Quantify            Identify Causal         Identify Changes
          Documents For                                                                                                                     Schedule
                                         Delays             Delay Activities         To Critical Path
          Driving Delays


                                                                                        Is the
                Assess                  Any                    Perform                 Owner
                                                     Yes                                                Yes
                                                                                                                                 Prepare
              Responsibility         Concurrent            Concurrent Delay          Responsible
                                                                                                                                 Recovery
               For Delays             Delays?                 Analysis                For Delay?
                                                                                                                                 Schedule

                                              No
                                                                                              No
                                                                                                                          Resolve
                                                                                                                        Subcontractor
                                                                                         Is a
                                                              Is the
                                                                                                                        Contributions
                                                                               No                       No
                                    Verify Single                                    Subcontractor
                                                             Owner
                                    Source Delay                                     Responsible
                                                           Responsible
                                    Responsibility                                    For Delay?
                                                            For Delay?
                                                                                                               Discuss Delay &
                                                                                                                Mitigation with
                                                                                               Yes
                                                                                                                Subcontractor
                                                                   Yes
    Proposed Schedule Update
     Including Delay Analysis                                                                      Discuss Delay                   Prepare Delay
                                                                                                    & Mitigation                     Analysis
                                                                                                    With Owner                    & Change Order
Schedule Updating
Schedule Analysis (Slipped Completion)
  Quantify Four Delay/Gain Changes for Each Causal
  Activity by Working From the Beginning of the Period,
  Using a Standard Layout with Current Baseline as
  Schedule Target
  Verify That the Totals Add Up to the Total CP Change
  Research the Issues that Caused the Changes to the
  Causal Activities
     Interview Project Management Team
     Review Project Documents; Issue Files, Minutes,
     RFI/Submittal Logs, Field Reports, Photographs
     This Research is Usually a Discussion About Reasonably
     Current Problems – Quick, Painless, and Easy
Schedule Updating
Schedule Analysis (Slipped Completion)
  Identify the Driving Issues that Affect the Causal Activities
  Assess Responsibility for Driving Issues
  Review Concurrency of Driving Issues– Can Be Delay and/or
  Acceleration/Mitigation
  Work Through Concurrent Driving Issues from the Beginning of
  the Period, Identifying First Driving Issue, Establishing any
  Concurrency with Next Driving Issue
  Perform a Careful Concurrent Delay Analysis, Record in Clear
  Graphical Format
  Assign Responsibilities for All Driving Concurrent Delays
Schedule Updating
Schedule Analysis (Slipped Completion)
  If Subcontractors are Responsible for any Driving Delays, or
  Portions of Concurrent Delay, Meet Face-to-Face
     Provide Clear Documentation with Approximate Costs for Delays
     Discuss Ramifications & Options
     Collaborate and Gain Commitment for Mitigation/Acceleration
  If Owner is Responsible for Any Driving Delays, or Portions of
  Concurrent Delay, Meet Face-to-Face
     Provide Clear Documentation with Approximate Costs for Delays
     Discuss Ramifications & Options
     Collaborate and Determine Best Approach; Owner Mitigation,
     paid Contractor Mitigation, or Time Extension
Schedule Updating
Reporting - Internal
Schedule Updating
Senior Management Report
Schedule Updating
Developing senior management reports is crucial
Schedule Updating
Best to keep update & report weekly (full metrics monthly)
Report should include general status summaries:
Schedule Updating
Provide project managers with additional standard reports -
Earned Value metrics
Schedule Updating
Customized reports – PM - myPrimavera
Schedule Updating
Customized reports – PM - myPrimavera
Schedule Updating
Narrative - External Reporting
Schedule Updating
Narrative - External Reporting Checklist


         Checklist for an Update Schedule Narrative
Schedule Updating
Narrative - External Reporting Format
“Project Management is what you
 are forced to do when you don’t
           Schedule!”
              (Chris Carson, ~1986)
Questions?
Updating a Schedule
    December 13, 2007
     Chris Carson, PSP
         Project Controls Manager
            Alpha Corporation
    chris.carson@alphacorporation.co
                    m

More Related Content

What's hot

Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricksp6academy
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2Abdelhay Ghanem
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11PMA Consultants
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3Matiwos Tsegaye
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Interview questions-for-planning-engineers
Interview questions-for-planning-engineersInterview questions-for-planning-engineers
Interview questions-for-planning-engineersworkbreakdown
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 

What's hot (20)

Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2How to prepare recovery or revised schedule rev.2
How to prepare recovery or revised schedule rev.2
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Interview questions-for-planning-engineers
Interview questions-for-planning-engineersInterview questions-for-planning-engineers
Interview questions-for-planning-engineers
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 

Viewers also liked

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
The analysis and valuation of disruption
The analysis and valuation of disruptionThe analysis and valuation of disruption
The analysis and valuation of disruptionDr Ezzat Mansour
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Strategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowStrategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowAbdullah Ahmed, PMP, RMP
 
Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Alexander Decker
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Introduction of pharmaceutical jurisprudence
Introduction of pharmaceutical jurisprudenceIntroduction of pharmaceutical jurisprudence
Introduction of pharmaceutical jurisprudenceSwarnakshi Upadhyay
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 

Viewers also liked (20)

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
The analysis and valuation of disruption
The analysis and valuation of disruptionThe analysis and valuation of disruption
The analysis and valuation of disruption
 
Ph pharmacy act (ra 5921)
Ph pharmacy act (ra 5921)Ph pharmacy act (ra 5921)
Ph pharmacy act (ra 5921)
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
CPM-Updating
CPM-UpdatingCPM-Updating
CPM-Updating
 
Strategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowStrategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should know
 
Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
Time overruns
Time overrunsTime overruns
Time overruns
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Introduction of pharmaceutical jurisprudence
Introduction of pharmaceutical jurisprudenceIntroduction of pharmaceutical jurisprudence
Introduction of pharmaceutical jurisprudence
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Introduction to hospital pharmacy
Introduction to hospital pharmacyIntroduction to hospital pharmacy
Introduction to hospital pharmacy
 
Hospital pharmacy slides.
Hospital pharmacy slides.Hospital pharmacy slides.
Hospital pharmacy slides.
 

Similar to Schedule Updates

CooperMS Resume 05272016
CooperMS Resume 05272016CooperMS Resume 05272016
CooperMS Resume 05272016Maryann Cooper
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Metrics-Based Process Mapping: Part 2 of 3
Metrics-Based Process Mapping: Part 2 of 3Metrics-Based Process Mapping: Part 2 of 3
Metrics-Based Process Mapping: Part 2 of 3TKMG, Inc.
 
How to analyze your sap data and optimize your workforce
How to analyze your sap data and optimize your workforceHow to analyze your sap data and optimize your workforce
How to analyze your sap data and optimize your workforcerobgirvan
 
Project management
Project managementProject management
Project managementervinod
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping ProcessAnand Subramaniam
 
Uni t Schedul i ng and Cos t Control Due Date Sat, .docx
Uni t  Schedul i ng and Cos t Control  Due Date  Sat, .docxUni t  Schedul i ng and Cos t Control  Due Date  Sat, .docx
Uni t Schedul i ng and Cos t Control Due Date Sat, .docxmarilucorr
 
8-step Problem Solving (Management)V2 (2)
8-step Problem Solving (Management)V2 (2)8-step Problem Solving (Management)V2 (2)
8-step Problem Solving (Management)V2 (2)Steve Nails
 
SigmaFlow Well Delivery Solution
SigmaFlow Well Delivery SolutionSigmaFlow Well Delivery Solution
SigmaFlow Well Delivery Solutionrnaramore
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & ControlingDarshana Viduranga
 
Cms Solution 07162010
Cms Solution 07162010Cms Solution 07162010
Cms Solution 07162010larrybaker90
 
Past Project A3 - Lean Six Sigma Green Belt
Past Project A3 - Lean Six Sigma Green BeltPast Project A3 - Lean Six Sigma Green Belt
Past Project A3 - Lean Six Sigma Green BeltJohnny Gong
 
Medrium Karvy And Dashboards Overview Morristown April 2007
Medrium Karvy And Dashboards Overview   Morristown April 2007Medrium Karvy And Dashboards Overview   Morristown April 2007
Medrium Karvy And Dashboards Overview Morristown April 2007John Mortenson CPA
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls FrameworkReuben Gonzales
 
Operatiional Audit
Operatiional AuditOperatiional Audit
Operatiional AuditMalay Paul
 

Similar to Schedule Updates (20)

CooperMS Resume 05272016
CooperMS Resume 05272016CooperMS Resume 05272016
CooperMS Resume 05272016
 
Remade Slides.pptx
Remade Slides.pptxRemade Slides.pptx
Remade Slides.pptx
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Metrics-Based Process Mapping: Part 2 of 3
Metrics-Based Process Mapping: Part 2 of 3Metrics-Based Process Mapping: Part 2 of 3
Metrics-Based Process Mapping: Part 2 of 3
 
How to analyze your sap data and optimize your workforce
How to analyze your sap data and optimize your workforceHow to analyze your sap data and optimize your workforce
How to analyze your sap data and optimize your workforce
 
Project management
Project managementProject management
Project management
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping Process
 
Uni t Schedul i ng and Cos t Control Due Date Sat, .docx
Uni t  Schedul i ng and Cos t Control  Due Date  Sat, .docxUni t  Schedul i ng and Cos t Control  Due Date  Sat, .docx
Uni t Schedul i ng and Cos t Control Due Date Sat, .docx
 
8-step Problem Solving (Management)V2 (2)
8-step Problem Solving (Management)V2 (2)8-step Problem Solving (Management)V2 (2)
8-step Problem Solving (Management)V2 (2)
 
LeanSixSigmaProjectPresentation
LeanSixSigmaProjectPresentationLeanSixSigmaProjectPresentation
LeanSixSigmaProjectPresentation
 
SigmaFlow Well Delivery Solution
SigmaFlow Well Delivery SolutionSigmaFlow Well Delivery Solution
SigmaFlow Well Delivery Solution
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & Controling
 
Cms Solution 07162010
Cms Solution 07162010Cms Solution 07162010
Cms Solution 07162010
 
Past Project A3 - Lean Six Sigma Green Belt
Past Project A3 - Lean Six Sigma Green BeltPast Project A3 - Lean Six Sigma Green Belt
Past Project A3 - Lean Six Sigma Green Belt
 
Schedule Review
Schedule ReviewSchedule Review
Schedule Review
 
Medrium Karvy And Dashboards Overview Morristown April 2007
Medrium Karvy And Dashboards Overview   Morristown April 2007Medrium Karvy And Dashboards Overview   Morristown April 2007
Medrium Karvy And Dashboards Overview Morristown April 2007
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls Framework
 
Operatiional Audit
Operatiional AuditOperatiional Audit
Operatiional Audit
 

More from Chris Carson

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMIChris Carson
 

More from Chris Carson (20)

Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 
Schedule Design PMI
Schedule Design PMISchedule Design PMI
Schedule Design PMI
 

Recently uploaded

Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 

Recently uploaded (20)

Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 

Schedule Updates

  • 1. Updating a Schedule December 13, 2007 Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.com
  • 2. Schedule Updating Determine Frequency of Updates Data Collection Status Schedule Calculate Check for Out-of-Sequence Work Verify Schedule Analysis – On Time Completion Historical Trending & Statistics Analysis – Late Completion Reporting - Internal Narrative – External Reporting
  • 4. Schedule Updating Frequency of Updates Based on schedule purpose Management tool Meeting a specification requirement Internal reporting and predictions Limited management use Budget Based on size of schedule Large schedule requires frequent updates Overview schedule allows fewer updates
  • 6. Schedule Updating Data Collection Field information – should be kept on a daily basis Actual Start Dates Actual Finish Dates Predicted Finish for any activity started but not finished Percent Complete if schedule is cost loaded Use Remaining Duration, not Percent Complete, for time reporting • Superintendents cannot provide accurate Percent Complete • Superintendents cannot provide accurate Remaining Durations Recommend Superintendents walk job with update report
  • 8. Schedule Updating Data Collection Office information Gather status of buyout process; purchase orders & subcontracts – what is not bought out Gather Submittal & Approval status Gather status of administrative tasks • Utility paperwork status • Permits – site, building, right-of-way, Health Department • Environmental releases, etc. Gather status of materials fabrication and order time - “Lead Time”
  • 9. Schedule Updating Data Collection Owner information Gather Status of Owner controlled activities • Owner utility applications & progress Electricity - Gas service - Water & sewer - Telephone - Cable or data - Security system - Delivery dates for Owner furnished equipment • Other Owner contractual work • Verify coordination with Owner work •
  • 10. Schedule Updating Data Collection Subcontractor information Gather Status of subcontractor activities • Lead Times for subcontractors’ materials • Lead Times for subcontractors’ equipment • Lead Times for subcontractor mobilization on job (field?) - Are they committed to scheduled start date? - Are the other trades out of the work area? - What is the materials lay-down area availability? Resource availability for subcontractors • - Do the subcontractors have adequate workmen on site?
  • 12. Schedule Updating Status Schedule Simple progress stage of process Make no logic changes during this stage, only progress Use standard input layout to record progress Input Actual Start and Finish Dates Choose Data Date – use last actual dates provided If activities are started, set Remaining Durations so predicted finish dates are met
  • 13. Schedule Updating Calculate Schedule & Check for Out-of-Sequence Work
  • 14. Schedule Updating Calculate Schedule Ensure software setting is Retained Logic Set Data Date to date chosen during Schedule Status stage Calculate schedule Check for Out-of-Sequence Work Change setting temporarily to Progress Override If the completion date changes significantly, then there is a lot of out-of-sequence work needing correcting If minimal change, no significant out-of-sequence work Change the setting back to Retained Logic (default)
  • 16. Schedule Updating Verify Schedule Internal verification Check that Early Finish dates match predicted finish dates provided by Superintendent Check on any out-of-sequence work to see if those dates were input correctly External verification Change to verification layout • Two week look-ahead filter (only starts & finishes within 2W) • Send to Superintendent to verify that Early Start dates for planned activities for the next two weeks are accurate • Get feedback & correct any discrepancies This is a reasonableness check, look it over
  • 17. Schedule Updating Prepare for Schedule Analysis
  • 18. Schedule Updating Prepare for Schedule Analysis Use standard Layout with comparison to last update Check for slippage in Substantial Completion date If no slippage, project predicts on time completion Perform Standard Analysis, use standard reports and • publish If slippage, go to Analysis of Slipped Schedule
  • 19. Schedule Updating Standard Schedule Analysis (On-Time Completion)
  • 20. Schedule Updating Standard Schedule Analysis (On-Time Completion) Three basic components Critical Path progress • Slippage will directly delay work Near Critical progress • Slippage could easily overtake Critical Path and delay work Non-Critical (“mass volume”) work • Lack of progress will cause trade stacking and over- crowding of work space at a later date • Could easily allow too much work for areas available • Good place to use Earned Value for monitoring • Can use Float Dissipation to monitor • Can use other methods to monitor
  • 21. Schedule Updating Standard Schedule Analysis (On-Time Completion) Two types of paths to watch Critical Path to end of project (Substantial Completion) Critical Path to Interim Milestones Critical Path Ideally use Longest Path Monitor minimum Total Float value Critical Path Interim Milestones One path per each Milestone to watch
  • 22. Schedule Updating Standard Schedule Analysis (On-Time Completion) Identify current period Critical Path (Longest Path) Identify current period Near-Critical activities Identify easily identified Milestones for between this update and next update Concrete pours Inspections Trade mobilizations Identify historical trends and statistics (mass volume) Identify resource problems or concerns
  • 24. Schedule Updating Historical Comparisons & Statistics Run Tipper (TPR) reports Run Total Float dissipation (Erosion of Float) reports Run Free Float dissipation reports (monitors disruption) Review Out-of-Sequence work by trade Which trade is causing most out-of-sequence work? Are they working out-of-sequence due to other trade failures to complete? Or working in open areas without regard for planning? Run Resource reports Are appropriate resources working? Check against Tipper reports
  • 25. Schedule Updating Review (TPR) Time Performance Ratio trending (AD/OD) Time Performance Ratio 8.00 7.00 6.00 5.00 TPR 4.00 3.00 2.00 1.00 0.00 31- 30- 31- 28- 31- 30- 31- 30- 31- 31- 30- 31- 30- 31- 31- 28- Total Oct Nov- Jan- Feb- Mar- Apr- May- Jun- Jul-06 Aug- Sep- Oct- Nov- Dec- Jan- Feb- 05 06 06 06 06 06 06 06 06 06 06 06 07 07 Period Ending
  • 26. Schedule Updating Review (TPR) Time Performance Ratio trending by Milestone by Responsible Contractor (AD/OD)
  • 27. TPR 0.0 2.0 4.0 6.0 8.0 10.0 12.0 Ad m in Si te wo rk C (AD/OD) on cr et e M as on ry M et C al s ar pe nt ry D R oo oo rs / W fing in do ws Fi ni s Type of Work E q h es ui p Time Performance Ratio Fu me nt rn ish in g El ev s Schedule Updating at M or s ec ha ni El cal ec Review (TPR) Time Performance Ratio per trade tri ca l
  • 28. Schedule Updating Review (TPR) Time Performance Ratio trending by trade (AD/OD) Time Performance Ratio (Concrete) 8.00 7.00 6.00 5.00 TPR 4.00 3.00 2.00 1.00 0.00 6 07 7 6 6 l 6 ta -0 -0 0 0 -0 n- To p- c- ov eb ct Ja Se De -O -N -F - - - 31 31 30 28 30 31 Period Ending
  • 29. Schedule Updating Trade Monitoring by Crew – no resource loading available, load single crew resources into activities AMP Terminals Yard Project
  • 30. Schedule Updating Watch erosion of float, do not let it continue Print by trade when assessing available resources • Relative Total Float of Area Completion Milestones 200 150 Relative Total Float SCAC RCA 100 WH MCAC/CCAC Utility Bldg NBB MSGQ 50 WBN NOB Subst Comp 0 22 BL 08 09 10 11 12 13 14 15 16 17 18 19 20 21 23 24 25 SI KN KN KN KN KN KN KN KN KN KN KN KN KN KN KN KN SS -50
  • 31. Schedule Updating Earned Value Management Reporting Earned Value and Actual Costs • See separate training session • Ciudad Juarez Earned Value Project Update Earned Value $70,000,000.00 $60,000,000.00 $50,000,000.00 B illing Value $40,000,000.00 Early Curve Late Curve $30,000,000.00 Actual Curve $20,000,000.00 $10,000,000.00 $0.00 De v-0 5 De v-0 6 De -0 7 Fe 0 6 Ju 0 6 Fe -0 7 Ju 0 7 Fe -0 8 M - 06 A p - 06 A u l-06 M 07 A p - 07 A u l-07 M 08 8 O - 05 J a -0 5 M r- 06 S e - 06 O - 06 J a -0 6 M r- 07 S e - 07 O - 07 Ja 07 J u -06 J u -07 No - 05 No - 06 No - 07 -0 n- n- n- b- b- c- v n n ar ar ar b c c p g p g p ay ay ct ct ct Se Period Ending
  • 32. Schedule Updating Earned Value Management Reporting SPI and CPI • Watch trending • Schedule Performance Index 1.20 1.00 S PI (E V/P V) 0.80 0.60 0.40 0.20 0.00 05 06 06 06 07 06 6 6 07 6 05 05 06 06 06 6 5 6 -0 l-0 r- 0 -0 -0 -0 v- v- n- n- n- b- b- p- c- g- p- c- ar ay ct ct Ju Ap No No Ja Ju Ja Fe Fe Se De Au Se De M O O M Period Ending
  • 33. Schedule Updating Schedule Analysis – Sequencing Review Set up a Layout for Sequence Group by Phase or Location • Look for out-of-sequence work by trade Summarize to Phase Neck for non-work periods Review the sequence shown by the summary bars Set up a Layout for Responsibility Group by Responsibility Summarize to Responsibility Neck for non-work periods Review trade workload
  • 34. Schedule Updating Schedule Analysis – Constructability Set up a Layout for weekly work Group by Early Start Order by Week Sort by ES, EF , TF Zoom in to weekly week Set Major Vertical Sight Lines to one week Expose column for Responsibility and Location Review work to be done weekly over the next few months for reasonableness
  • 35. Schedule Updating Schedule Analysis (Slipped Completion)
  • 36. Schedule Updating Schedule Analysis (Slipped Completion) If slippage is due to the Owner, then a time extension is owed to the Contractor If slippage is due to a Subcontractor The Subcontractor owes the GC a Recovery Schedule effort The Contractor (GC) still owes the Owner a Recovery Schedule If slippage is due to the Contractor, then the Contractor owes the Owner a Recovery Schedule If the Owner causes the delay and the Sub or GC causes a concurrent delay, then a time extension is owed to the Contractor; no recovery schedule required
  • 37. Schedule Updating Schedule Analysis (Slipped Completion) Identify previous period Critical Path (Longest Path) Use layout to compare against current schedule Identify current Critical Path & changes from previous Identify which activities slipped and drove progress Causal Activities drive progress Identify Start Gain or Loss Identify Production Gain or Loss Identify specific Causal Activity or Activities for delay Develop process for dealing with slipped completion before needed
  • 38. Collect Admin Verify All Progress Data Data No Request for Collect Field Status Update Compare to Critical Path Update Data Progress Data Schedule Schedule Baseline Delay? Yes Identify Contract Changes Identify Previous Period Critical Path Publish Research Updated Quantify Identify Causal Identify Changes Documents For Schedule Delays Delay Activities To Critical Path Driving Delays Is the Assess Any Perform Owner Yes Yes Prepare Responsibility Concurrent Concurrent Delay Responsible Recovery For Delays Delays? Analysis For Delay? Schedule No No Resolve Subcontractor Is a Is the Contributions No No Verify Single Subcontractor Owner Source Delay Responsible Responsible Responsibility For Delay? For Delay? Discuss Delay & Mitigation with Yes Subcontractor Yes Proposed Schedule Update Including Delay Analysis Discuss Delay Prepare Delay & Mitigation Analysis With Owner & Change Order
  • 39. Schedule Updating Schedule Analysis (Slipped Completion) Quantify Four Delay/Gain Changes for Each Causal Activity by Working From the Beginning of the Period, Using a Standard Layout with Current Baseline as Schedule Target Verify That the Totals Add Up to the Total CP Change Research the Issues that Caused the Changes to the Causal Activities Interview Project Management Team Review Project Documents; Issue Files, Minutes, RFI/Submittal Logs, Field Reports, Photographs This Research is Usually a Discussion About Reasonably Current Problems – Quick, Painless, and Easy
  • 40. Schedule Updating Schedule Analysis (Slipped Completion) Identify the Driving Issues that Affect the Causal Activities Assess Responsibility for Driving Issues Review Concurrency of Driving Issues– Can Be Delay and/or Acceleration/Mitigation Work Through Concurrent Driving Issues from the Beginning of the Period, Identifying First Driving Issue, Establishing any Concurrency with Next Driving Issue Perform a Careful Concurrent Delay Analysis, Record in Clear Graphical Format Assign Responsibilities for All Driving Concurrent Delays
  • 41. Schedule Updating Schedule Analysis (Slipped Completion) If Subcontractors are Responsible for any Driving Delays, or Portions of Concurrent Delay, Meet Face-to-Face Provide Clear Documentation with Approximate Costs for Delays Discuss Ramifications & Options Collaborate and Gain Commitment for Mitigation/Acceleration If Owner is Responsible for Any Driving Delays, or Portions of Concurrent Delay, Meet Face-to-Face Provide Clear Documentation with Approximate Costs for Delays Discuss Ramifications & Options Collaborate and Determine Best Approach; Owner Mitigation, paid Contractor Mitigation, or Time Extension
  • 44. Schedule Updating Developing senior management reports is crucial
  • 45. Schedule Updating Best to keep update & report weekly (full metrics monthly) Report should include general status summaries:
  • 46. Schedule Updating Provide project managers with additional standard reports - Earned Value metrics
  • 47. Schedule Updating Customized reports – PM - myPrimavera
  • 48. Schedule Updating Customized reports – PM - myPrimavera
  • 49. Schedule Updating Narrative - External Reporting
  • 50. Schedule Updating Narrative - External Reporting Checklist Checklist for an Update Schedule Narrative
  • 51. Schedule Updating Narrative - External Reporting Format
  • 52. “Project Management is what you are forced to do when you don’t Schedule!” (Chris Carson, ~1986)
  • 53. Questions? Updating a Schedule December 13, 2007 Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.co m