1. DCPL
NEW SOUTHWEST LIBRARY
SEPTEMBER 27, 2018 - COMMUNITY MEETING
AGENDA
• PROJECT TIMELINE
• INTERIM LIBRARY
• WHAT WE’VE HEARD
• BUILDING DESIGN UPDATE
• NEXT STEPS
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 1
2. DESIGN CONSTRUCTION
SPRING 2019 WINTER 2020
SPRING 2020
WINTER 2018SUMMER 2017
OPEN
INTERIM
LIBRARY
+ CLOSE
LIBRARY
OPEN
NEW
LIBRARY
PROJECT TIMELINE /
SPRING 2019
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 2
3. Sign up for periodic emails at:
dclibrary.org/newsouthwestlibrary
Email questions or comments to:
Martha.Saccocio@dc.gov
• CFA MEETING
• PERMITTING
• CONSTRUCTION
PROJECT TIMELINE / NEXT STEPS
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 3
5. INTERIM LIBRARY / TIMELINE
I STREET SW
K STREET SW K STREET SW
M STREET SW
3RDSTREETSW
4THSTREETSW
6THSTREETSW
WESLEYPLACE
MAINE
AVE
SW
N
Mmetro
DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 5
INTERIM LIBRARY
425 M STREET SW
EXISTING LIBRARY CLOSES
SPRING 2019
INTERIM LIBRARY OPENS
SPRING 2019
NEW LIBRARY OPENS
SPRING 2020
SPRING 2020SPRING 2019
9. • Welcoming entrance, canopy for weather protection,
• Connection between the playground and the library
• Outdoor programming space
COMMUNITY / WHAT WE’VE HEARD
• Meeting rooms of different sizes
• Space for hosting events like book clubs
• Acoustically appropriate meeting rooms
• Quiet spaces to study or read
• Area for children’s programs – reading stories, show
& tell
• Exploratory kids area
• Open sight lines in the children’s area
MEETING SPACES
CHILDREN’S AREA
OUTDOOR SPACE
JULY 11, 2017 MEETING
• Technology, more outlets and better WiFi
• More computers
• Informal areas for adults i.e., benches to have small
conversations
OTHER FEATURES
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 9
10. COMMUNITY / WHAT WE’VE HEARD
ENGAGEMENT
• Online Survey
248 responses
• Focus Groups
Adults
Parents of young children
Seniors
Greenleaf Residents
• Staff Visioning Exercise
• SWNA New Southwest Library
Task Force Report
• Visit to Area Libraries
To view all comments, visit dclibrary.org/newsouthwestlibrary
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 10
12. River Park Tiber Island Westminster Church Town Center
SITE / CONTEXT
MARYLAND
WASHINGTON DC
NW
SW
NE
SE
VIRGINIA
SOUTHWEST LIBRARY
N
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 12
13. Arena Stage United Methodist Church Duck PondSW Waterfront
I STREET SW
K STREET SW K STREET SW
M STREET SW
3RDSTREETSW
4THSTREETSW
6THSTREETSW
WESLEYPLACE
MAINE
AVE
SW
N
N
SITE / CONTEXT
DUCK POND
UNITED METHODIST CHURCH
SOUTHWEST LIBRARY
FUTURE DEVELOPMENTS
TOWN CENTER
WATERFRONT STATION
ARENA STAGE
Mmetro
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 13
14. NO CONNECTION TO ADJACENT PARK
NO ACCESS TO DAYLIGHT
NO VIEWS TO THE OUTDOORS
UNINVITING ENTRANCE
BASEMENT BELOW FLOODPLAIN
NO NEIGHBORHOOD CONNECTION
SITE / EXISTING
WESLEYPL.
3RDSTREETSW
K STREET SW
210’
105’
5’0’ 10’ 25’ 50’
Main Entrance Interior View From Park
N
PARKING
EXISTING
CURB CUT
EXISTING
CURB CUT
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 14
15. ADJACENT PARK
NEW CONNECTION TO PARK
MAXIMIZE OUTDOOR VIEWS +
DIFFUSE NORTHERN DAYLIGHT
FUNCTIONAL EXTERIOR SPACES
SENSE OF ARRIVAL
PEDESTRIAN PATH CONNECTION
BUILDING RAISED ON 3’ PODIUM
SUSTAINABLE SITE
SUSTAINABLE BUILDING
PERFORMANCE
NEW TWO-STORY
LIBRARY BUILDING
SITE / PROPOSED
N
7 PARKING SPACES
CURB CUT
NEWSIDEWALK
16’-0” SETBACK16’-0”SETBACK
47’-9”SETBACK
13’-0” SETBACK
TRASH/
RECYCLING
OUTLINE OF EXISTING BUILDING
NEW SIDEWALK
MULTIPURPOSE
PLAZA/PARKING
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 15
16. SIDEWALK + BIO-RETENTION ENTRANCE
BALCONY
SITE / PROPOSED
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 16
17. exposed aggregate
precast stair
c.i.p.concreteband
TERRACE| Paving Enlargement
12
SITE / LANDSCAPE PLAN
CANOPY TREES| Honeylocust FLOWERING TREE| Carolina Silverbell SHRUBS, GRASSES PERENNIALSBIO-RETENTION AREA
HEDGE TO SCREEN PARKING LOT
1. STEPS DOWN TO PARK
2. TERRACE/PORCH
3. ENTRY PLAZA/RAMP
4. BIO-RETENTION GARDEN
5. CANOPY TREES
6. FLOWERING TREES
7. ACCESS TO PARKING
8. MULTIFUNCTION PARKING
9. IMPROVED PLANTING HEDGE
10. BUILDING OVERHANG
11. MONUMENTAL SIGNAGE
12. TRASH ENCLOSURE
N
NEW TWO-STORY
LIBRARY BUILDING
7
8 9
10
11
6
6
5
5
5
4
4
4
3
2
1
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 17
18. SPACE PROGRAM / UPDATED SUMMARY
14,784,
67%
7,221,
33%
EXISTING PUBLIC/NONPUBLIC
15,768
83%
3,278
17%
NEW PUBLIC/NONPUBLIC
EXISTING LIBRARY NEW LIBRARY
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 18
19. 1. ENTRY
2. MARKET PLACE
3. FRONT DESK
4. MULTI-PURPOSE
5. STAFF SPACE
6. CHILDREN’S OUTDOOR
7. CHILDREN’S SERVICES
8. MEP
PUBLIC ENTRY
STAFF ENTRY
N
1 2
3
4
5
7
6
8
5
FLOOR PLAN / LEVEL 01
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 19
20. 1. SEATING
2. COMPUTERS
3. INNOVATION LAB
4. OPEN TO BELOW
5. STAFF SPACE
6. ADULT OUTDOOR
7. ADULT SERVICES
8. MEETING SPACE
9. TEEN/MIXED
EXITS
1
2
3
4
5
5
5
7
6
8
8
8
8
8
89
5
N
FLOOR PLAN / LEVEL 02
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 20
21. NORTH ELEVATION
SOUTH ELEVATION
BUILDING DESIGN / ELEVATIONS
TOP OF ROOF
55’ - 0”
TOP OF ROOF
55’ - 0”
LEVEL 02
30’ - 10”
LEVEL 02
30’ - 10”
LEVEL 01
16’ - 10”
LEVEL 01
16’ - 10”
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 21
22. EAST ELEVATION
WEST ELEVATION
BUILDING DESIGN / ELEVATIONS
TOP OF ROOF
55’ - 0”
TOP OF ROOF
55’ - 0”
LEVEL 02
30’ - 10”
LEVEL 02
30’ - 10”
LEVEL 01
16’ - 10”
LEVEL 01
16’ - 10”
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 22
23. BUILDING MATERIALS / TYPICAL NORTH BAY
5
METAL
PANEL
7
RIVER
ROCK
3
PHOTOVOLTAIC
PANELS
4
ULTRA CLEAR
GLASS
8
CONCRETE
6
WHITE ROOF
MEMBRANE
1
2 4
5
7
36
8
8
8
1
SPF DLT ROOF
SPRUCE, PINE, FIR
DOWEL LAMINATED
TIMBER 2
SPRUCE GLULAM
COLUMNS
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 23
26. BUILDING DESIGN / NORTH FACADE
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 26
27. MARKET PLACE / INTUITION
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 27
28. CHILDREN’S SERVICES / CURIOSITY + STIMULATION
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 28
29. CHILDREN’S SERVICES / CURIOSITY + STIMULATION
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 29
30. MEETING SPACES / LEVEL 01 MULTI-PURPOSE ROOM
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 30
31. No color scheme
assigned to view
FULL LECTURE:
108 PEOPLE IN CHAIRS
FULL RECEPTION:
60 PEOPLE AT TABLES
1/2 TRAINING: 40 PEOPLE
1/2 STORY TIME: FLEXIBLE
1/2 CONFERENCE: 28+
1/2 CHILDREN’S CRAFTS: 40
MULTI-PURPOSE ROOM / FLEXIBLE LAYOUT OPTIONS
No color scheme
assigned to view
No color scheme
assigned to view
No color scheme
assigned to view
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 31
32. MEETING SPACES / MULTI-PURPOSE ROOM
MULTI PURPOSE ROOM ENLARGED PLAN
NOT TO SCALE
1
MULTI PURPOSE ROOM WET BAR ELEVATION
NOT TO SCALE
2
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 32
33. ADULT SERVICES / SANCTUARY
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 33
34. MEETING SPACES / LEVEL 02 TRANSFORMATION LAB
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 34
35. MEETING / TRANSFORMATION LAB:
20 + 2-3 STOOLS
TRAINING / TRANSFORMATION LAB:
20 + 2-3 STOOLS
TRANSFORMATION LAB / FLEXIBLE LAYOUT OPTIONS
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 35
36. MEETING SPACES / TRANSFORMATION LAB
LAPTOP
P
P
CNC
F LC
TV
TRANSFORMATION LAB ENLARGED FLOOR PLAN
NOT TO SCALE
1
TRANSFORMATION LAB AXON VIEW
3
CNC ROUTER3D
PRINTER
3D
PRINTER
LASER CUTTER
PC
TRANSFORMATION LAB WEST ELEVATION
NOT TO SCALE
2
LAPTOP
P
P
CNC
F LC
TV
TRANSFORMATION LAB ENLARGED FLOOR PLAN
NOT TO SCALE
1
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 36
37. MEETING SPACES / LEVEL 02 STUDY ROOMS
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 37
38. MEETING SPACES / LEVEL 02 CONFERENCE ROOM
PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 38
39. PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 39
40. PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 40
41. PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 41
42. PERKINS+WILL / TURNER CONSTRUCTION COMPANY DCPL, NEW SOUTHWEST LIBRARY // COMMUNITY MEETING 5 // 09.27.18 // 42
43. NEXT STEPS
• CFA MEETING
• PERMITTING
• CONSTRUCTION
Sign up for periodic emails at:
dclibrary.org/newsouthwestlibrary
Email questions or comments to:
Martha.Saccocio@dc.gov