The document describes the winning design submission for a new bench at the Laurel Tree Charter School called "Three Scoops, Three Flavors". The bench design includes a center bench made of urbanite and cement with features like a rock wall and xylophone, and wing benches made of earthbags and ecoladrillo with game boards and a pipe-o-phone. The design scored highest based on criteria like safety, durability, playability, and environmental justice. Maintenance of the bench is estimated to cost $20 annually and take 7 hours. The total cost to build the bench was $1,405 but many materials were donated.
Three Scoops, Three Flavors Bench Wins Charter School Competition
1. Three Scoops,
Three Flavors
By Primary Benchspiration
Jerrina Alverio, Andy Eggink, Caleb Fowler,
Allison Molleson
2. The Problem & The Challenge
Input: The Laurel Tree Output: The Laurel
Charter School Black Tree Charter School
primary students Box primary students with
without a bench. a bench.
• Playable
• Safe
• Comfortable
• Aesthetically Pleasing
• Use of sustainable materials
3. The Specifications
• Size must fit a primary school student
• Seat a minimum of twenty
• Semi-Circular
• Playable
• Durable enough for adults
• Withstand Humboldt climate
• Functional after a rain storm
4. The Criteria Defined
Criteria Weight
Safety 10
Durability 10
Playability 8
Level of Educational Value 5
Level of Environmental
5
Justice
Comfort 4
Cost Effectiveness 3
5. The Decision
Design Score
Three Scoops, Three
1836
Flavors
TerraTiers to the Top 1828
Bottles in a Bench 1768
From Stone to Sand 1713
Grassy Day, Let’s Go Play 1552
Cement to the Core 1534
Sittin’ Good on Firewood 1246
Mountains of Mud 1123
11. The Cost
Expenses
Item
Funnels
Source
Harbor Freight
Quantit
y
2
Cost
$3.00
Estimated Value
of Donation Time Spent in
Tarp
PVC pipe
1/2 yard of sand
Harbor Freight
The Mill Yard
Eureka Ready Mix 1
$12.00
$17.00
$21.00
Hours
Cement Ace 4 $48.00
Root barrier fabric
Sandbags
Ace
United Rentals
$78.00
$81.00
Defining the
River sand Wes Green 3 $120.00
6 Problem
Yard of road base Eureka Ready Mix 3 Donated $120.00
Wood Miller Farms Donated $200.00
Urbanite Miller Farms Donated $200.00
Tiles The Tile Center Donated $35.00
Gathering
Stakes Miller Farms Donated $20.00 100 Information
Rebar The Boiler Works Donated $20.00
Plexiglass Mollesons Donated $60.00
Plastic bottles Eureka Recycling Donated $50.00 241
Lime powder Jungle Mike 3 Donated $30.00 Alternative
68
Chicken wire
Cement
The Farm Store
Pierson's/Hensel 10
Donated
Donated
$50.00
$120.00
Solutions
Barbed wire Miller Farms Donated $20.00
Earth pigment ABC N/A $50.00
37
Aluminum pipe Arcata Scrap N/A $10.00 Selecting a
Aluminum molding Arcata Scrap N/A $10.00
Solution
Misc. hardware On hand $30.00
$380.00 $1,025.00
Total Hours: 452
Implementing
Total Cost to Reproduce $1,405.00
the Solution
12. Thank You!
• Miller Farms • Pierson’s
• Eureka Ready Mix • The Farm Store
• Jungle Mike • Hensel Materials
• Laurel Tree Charter • The Boiler Works
School • The Lungstroms
• Staff of Laurel Tree • Eureka Recycling
• The Tile Center