Three Scoops,
       Three Flavors
By Primary Benchspiration
Jerrina Alverio, Andy Eggink, Caleb Fowler,
Allison Molleson
The Problem & The Challenge
Input: The Laurel Tree             Output: The Laurel
Charter School           Black     Tree Charter School
primary students         Box       primary students with
without a bench.                   a bench.



                         • Playable
                         • Safe
                         • Comfortable
                         • Aesthetically Pleasing
                         • Use of sustainable materials
The Specifications
• Size must fit a primary school student
• Seat a minimum of twenty
• Semi-Circular
• Playable
• Durable enough for adults
• Withstand Humboldt climate
• Functional after a rain storm
The Criteria Defined
        Criteria             Weight
         Safety                10
        Durability             10
       Playability             8
Level of Educational Value     5
 Level of Environmental
                               5
          Justice
        Comfort                4
    Cost Effectiveness         3
The Decision
       Design               Score
  Three Scoops, Three
                            1836
        Flavors
  TerraTiers to the Top     1828
   Bottles in a Bench       1768
  From Stone to Sand        1713

Grassy Day, Let’s Go Play   1552

  Cement to the Core        1534

Sittin’ Good on Firewood    1246

   Mountains of Mud         1123
Three Scoops, Three Flavors
         Overview
The Center Bench
Construction
• Urbanite
• Cement
• Lime Plaster
Features
• Rock Wall
• Xylophone
• Chalkboard
• Truth Windows
The Wing Benches
Construction
• Mirror Design
• Earthbags
• Ecoladrillo
Features
• Game boards
• Pipe-O-Phone        http://ocoaporlanueva.b
                      logspot.com/2012/07/c
                      ontruyendo-un-mejor-
                      medio-
                      ambiente.html?spref=fb
Three Scoops, Three Flavors
         Vs. Criteria
• Safe
• Durable
• Playable
• Educational Value
• Environmental Justice
• Comfort
• Cost
Maintenance
 Section Being    Cost ($)     Cost (Hours)
  Maintained      Annually      Annually
Lime Plaster           10.00                  2.00

Rock Wall               0.00                  1.00

Xylophone               0.00                  1.00

Game Boards            10.00                  2.00

Pipe-O-Phone            0.00                  0.00

Chalkboard              0.00                  1.00

TOTAL:                20.00               7.00
The Cost
                      Expenses
Item
Funnels
                      Source
                      Harbor Freight
                                         Quantit
                                         y
                                                   2
                                                          Cost
                                                          $3.00
                                                                  Estimated Value
                                                                    of Donation       Time Spent in
Tarp
PVC pipe
1/2 yard of sand
                      Harbor Freight
                      The Mill Yard
                      Eureka Ready Mix             1
                                                         $12.00
                                                         $17.00
                                                         $21.00
                                                                                         Hours
Cement                Ace                          4     $48.00
Root barrier fabric
Sandbags
                      Ace
                      United Rentals
                                                         $78.00
                                                         $81.00
                                                                                                       Defining the
River sand            Wes Green                    3    $120.00
                                                                                     6                 Problem
Yard of road base     Eureka Ready Mix             3    Donated           $120.00
Wood                  Miller Farms                      Donated           $200.00
Urbanite              Miller Farms                      Donated           $200.00
Tiles                 The Tile Center                   Donated            $35.00
                                                                                                       Gathering
Stakes                Miller Farms                      Donated            $20.00             100      Information
Rebar                 The Boiler Works                  Donated            $20.00
Plexiglass            Mollesons                         Donated            $60.00
Plastic bottles       Eureka Recycling                  Donated            $50.00   241
Lime powder           Jungle Mike                  3    Donated            $30.00                      Alternative
                                                                                                  68
Chicken wire
Cement
                      The Farm Store
                      Pierson's/Hensel         10
                                                        Donated
                                                        Donated
                                                                           $50.00
                                                                          $120.00
                                                                                                       Solutions
Barbed wire           Miller Farms                      Donated            $20.00
Earth pigment         ABC                                  N/A             $50.00
                                                                                             37
Aluminum pipe         Arcata Scrap                         N/A             $10.00                      Selecting a
Aluminum molding      Arcata Scrap                         N/A             $10.00
                                                                                                       Solution
Misc. hardware                                          On hand            $30.00
                                                       $380.00       $1,025.00
                                                                                    Total Hours: 452
                                                                                                       Implementing
                       Total Cost to Reproduce                      $1,405.00
                                                                                                       the Solution
Thank You!
• Miller Farms           • Pierson’s
• Eureka Ready Mix       • The Farm Store
• Jungle Mike            • Hensel Materials
• Laurel Tree Charter    • The Boiler Works
  School                 • The Lungstroms
• Staff of Laurel Tree   • Eureka Recycling
• The Tile Center

More Related Content

More from Design Your Future

More from Design Your Future (8)

Project growth 215 lt_f12
Project growth 215 lt_f12Project growth 215 lt_f12
Project growth 215 lt_f12
 
Ovenly inferno 215 lt_f12
Ovenly inferno 215 lt_f12Ovenly inferno 215 lt_f12
Ovenly inferno 215 lt_f12
 
Onderdonk’s box 215_lt_f12
Onderdonk’s box 215_lt_f12Onderdonk’s box 215_lt_f12
Onderdonk’s box 215_lt_f12
 
Newtons laws 215 lt_f12
Newtons laws 215 lt_f12Newtons laws 215 lt_f12
Newtons laws 215 lt_f12
 
Monitoring energy 215 lt_f12
Monitoring energy 215 lt_f12Monitoring energy 215 lt_f12
Monitoring energy 215 lt_f12
 
Human powered blender 215 lt_f12
Human powered blender 215 lt_f12Human powered blender 215 lt_f12
Human powered blender 215 lt_f12
 
Congratulations Rube Goldberg Fall 2009
Congratulations Rube Goldberg Fall 2009Congratulations Rube Goldberg Fall 2009
Congratulations Rube Goldberg Fall 2009
 
Importance of Engineering Education
Importance of Engineering EducationImportance of Engineering Education
Importance of Engineering Education
 

Three Scoops, Three Flavors Bench Wins Charter School Competition

  • 1. Three Scoops, Three Flavors By Primary Benchspiration Jerrina Alverio, Andy Eggink, Caleb Fowler, Allison Molleson
  • 2. The Problem & The Challenge Input: The Laurel Tree Output: The Laurel Charter School Black Tree Charter School primary students Box primary students with without a bench. a bench. • Playable • Safe • Comfortable • Aesthetically Pleasing • Use of sustainable materials
  • 3. The Specifications • Size must fit a primary school student • Seat a minimum of twenty • Semi-Circular • Playable • Durable enough for adults • Withstand Humboldt climate • Functional after a rain storm
  • 4. The Criteria Defined Criteria Weight Safety 10 Durability 10 Playability 8 Level of Educational Value 5 Level of Environmental 5 Justice Comfort 4 Cost Effectiveness 3
  • 5. The Decision Design Score Three Scoops, Three 1836 Flavors TerraTiers to the Top 1828 Bottles in a Bench 1768 From Stone to Sand 1713 Grassy Day, Let’s Go Play 1552 Cement to the Core 1534 Sittin’ Good on Firewood 1246 Mountains of Mud 1123
  • 6. Three Scoops, Three Flavors Overview
  • 7. The Center Bench Construction • Urbanite • Cement • Lime Plaster Features • Rock Wall • Xylophone • Chalkboard • Truth Windows
  • 8. The Wing Benches Construction • Mirror Design • Earthbags • Ecoladrillo Features • Game boards • Pipe-O-Phone http://ocoaporlanueva.b logspot.com/2012/07/c ontruyendo-un-mejor- medio- ambiente.html?spref=fb
  • 9. Three Scoops, Three Flavors Vs. Criteria • Safe • Durable • Playable • Educational Value • Environmental Justice • Comfort • Cost
  • 10. Maintenance Section Being Cost ($) Cost (Hours) Maintained Annually Annually Lime Plaster 10.00 2.00 Rock Wall 0.00 1.00 Xylophone 0.00 1.00 Game Boards 10.00 2.00 Pipe-O-Phone 0.00 0.00 Chalkboard 0.00 1.00 TOTAL: 20.00 7.00
  • 11. The Cost Expenses Item Funnels Source Harbor Freight Quantit y 2 Cost $3.00 Estimated Value of Donation Time Spent in Tarp PVC pipe 1/2 yard of sand Harbor Freight The Mill Yard Eureka Ready Mix 1 $12.00 $17.00 $21.00 Hours Cement Ace 4 $48.00 Root barrier fabric Sandbags Ace United Rentals $78.00 $81.00 Defining the River sand Wes Green 3 $120.00 6 Problem Yard of road base Eureka Ready Mix 3 Donated $120.00 Wood Miller Farms Donated $200.00 Urbanite Miller Farms Donated $200.00 Tiles The Tile Center Donated $35.00 Gathering Stakes Miller Farms Donated $20.00 100 Information Rebar The Boiler Works Donated $20.00 Plexiglass Mollesons Donated $60.00 Plastic bottles Eureka Recycling Donated $50.00 241 Lime powder Jungle Mike 3 Donated $30.00 Alternative 68 Chicken wire Cement The Farm Store Pierson's/Hensel 10 Donated Donated $50.00 $120.00 Solutions Barbed wire Miller Farms Donated $20.00 Earth pigment ABC N/A $50.00 37 Aluminum pipe Arcata Scrap N/A $10.00 Selecting a Aluminum molding Arcata Scrap N/A $10.00 Solution Misc. hardware On hand $30.00 $380.00 $1,025.00 Total Hours: 452 Implementing Total Cost to Reproduce $1,405.00 the Solution
  • 12. Thank You! • Miller Farms • Pierson’s • Eureka Ready Mix • The Farm Store • Jungle Mike • Hensel Materials • Laurel Tree Charter • The Boiler Works School • The Lungstroms • Staff of Laurel Tree • Eureka Recycling • The Tile Center