Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Sea Port Construction, Project Execution Plan
1. David H Moloney
14th August 2016
Sea Port Construction, Project Execution Plan
Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled.
Also the measures to ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant
and Sequence to construct a Sea Port .
This presentation can be used to engage Stakeholders and to get the Site Teams
commitment to the programme. Also can be used for Induction Training and as a
way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and
controlled.
High in Educational Value and easily understood. Recommended for Continuing
Professional Development (CPD)
This Video Presentation is innovative and has many beneficial uses.
Video https://www.youtube.com/watch?v=6_Aco_GPO8I
5. Quay Wall
QuayWall
Brief Description
The quay wall is constructed using precast reinforced concrete hollow
blocks that weigh up to 160 tonnes. The blocks were cast in the on-site
precast yard and loaded onto barges at the temporary loading jetty that
had a 200 tonne capacity gantry crane.
A screeding frame that extended from the sea bet to above water was
used to place the bedding layer to the correct level.
Up to 22 blocks were placed per day using a barge with a crane.
Part of the coping beam was cast in-sit-u in sections using concrete pumps
positioned on the reclaimed land behind the quay wall.
14. Breakwater & Wavewall
Breakwater&Wavewall
Brief Description
The breakwater is constructed using core rock, rock armour, precast
armour units and geotextile.
The core rock is placed using split hopper barges in deep water and
by lorry tipping and dozers in shallow water where the risk of
slippage is minimal.
The precast armour units are placed using crawler cranes fitted with
a real-time visual aid system that enabled 70 placements per day.
The wave wall is cast in-sit-u in 6 metre long sections.
15. Sequence & Methods to Construct Breakwater & Wavewall
Breakwater&Wavewall
16. Breakwaters
ⓒ David H Moloney
Filling Barge with Rock – Temporary Jetty Placing Rock Fill
Breakwater under Construction Placing Rock Armour
26. Precast Yard & Loading Jetty
PrecastYard&LoadingJetty
Brief Description
Full-scale sample castings are constructed to demonstrate and
document that all the requirements of the concrete and the
execution of the work are fulfilled using the actual methods and
performed by personnel that will carry out the future castings. One
concrete component of each type is produced for approval. The
approved castings were retained in a dedicated area for quality
assurance purposes.
All works were inspected in accordance with the Inspection & Test
Plan on an ongoing basis, in accordance with the site Project Quality
Plan. The ITP set out in matrix form the sequence of inspection
steps, the governing document (specification, standards), the
standard to be achieved, the persons witnessing and the supporting
documents to be produced.
34. Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins
and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks.
The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage
capacity to match two days concrete production
36. Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
38. Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
40. Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
43. Dredging & Reclamation
Dredging&Reclamation
Brief Description
Dredgers are marine vessels used to excavate and fill under water.
Types
1. Cutter Suction Dredgers are used to dredge hard soils by cutting
and breaking up the soil using a rotating head at the end of a pipe
which is lowered onto the sea bed. The fragmented material is
sucked and pumped either into a hopper barge or through a floating
pipeline. During operation the dredger is anchored by a spud that
allows the cutting head to swing in an arc.
2. Trailing Suction Hopper Dredgers are used to dredge soft and
loose soils, gravels and silts. There are two suction drag heads
which are lowered onto the sea bed. These move with the dredger
along the sea bed. The dredged material is sucked and pumped
either into the hopper or through a floating pipeline to a discharge
area.
48. Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness.
This diagram shows excavation methods for rock of various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
50. Vibro Compaction - Fill behind Quay
Ground Improvement using deep vibro-compaction.
Purpose is to provide protection against liquefaction during a seismic
event. Also to provide a specified minimum ground bearing capacity.
Vibro-compaction was use to compact the Dubai man made islands
that were constructed from dredged sand.
Equipment.
Vibroflot with extension tube, hydraulic power pack mounted on crane,
diesel engine driven water jetting pumps, compressors, crawler cranes
60 tonne capacity, water tank, de-watering pump
51. Vibro Compaction - Fill behind Quay
3D image to show Sequence, Method & Plant.
David H Moloney
ⓒ David H Moloney
75. Personal Protective Equipment (PPE)
Health,Safety&Environment
Personal protective
equipment (PPE) is
protective clothing,
helmets, goggles, or other
garments or equipment
designed to protect the
wearer from injury or
infection
76. Safety Training on Site
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
85. Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
95. Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
96. Histogram Charts for Resources & Outputs
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
117. Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
My Port Construction YouTube link https://www.youtube.com/watch?v=6_Aco_GPO8I