Project Management 2017 Dr. Mahmoud Abbas Mahmoud
0
Project Management
Resource Allocation and Smoothing
Dr. Mahmoud Abbas Mahmoud
Assistant Professor
2017
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
1
Resource Allocation and Smoothing
1. Resource Planning
A resource may be defined as the machine or person who will perform the scope
of work. Resource planning is forecasting the resources required to perform the
scope of work within the time plan.
The resource constraint should be considered after the network diagram, schedule
bar chart and procurement schedule have been developed. But before the crash-
flow statement.
2. Resource Estimating
The resource estimates is linked directly to the scope of work and bill of materials
(BOM). The scope of work may be expressed as so many tons of steel, or so many
square meters of wall paint etc. From this description estimator can convert the
scope of work into manhours per unit ‘X’.
Consider the following, if the scope of work is to erect (assemble) 12 tons of steel
and the estimator knows from past experience that the work can be done in 150
manhours per ton and the men work 10 hour shifts, then the equation is:
( 12 tons × 150 manhours per ton )
10 hrs per day
= 180 mandays
Resource / Duration Trade-Off
3. Resource Forecasting
Resource forecasting is to forecast the total resource requirement by discipline or
interchangeable resource. An interchangeable resource is when you have a pool
(group) of workers and any one of them could perform the work. This is done by
compiling all the resource estimates and presenting them in a structured resource
table.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
2
Resource Table
Resource Forecast - Bar Chart
Resource Forecast – Histogram
Note: The bar chart shows the number of resources per activity per day, and the
histogram shows the total recourse required per day.
4. Resource Availability
In establishing the resource availability, the following points should be
considered:
a- Other resource commitments - if your company is involved in a number of
projects which all draw from a common labor pool, the other projects'
requirements must also be considered (also called multi-project resource
scheduling).
b- The anticipated sickness and absenteeism rate. For example: allow for a
25% absentee rate based on experience.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
3
Planning for a 25% Absenteeism
Keeping the above points in mind, the resource availability table will be
developed. Consider the following example:
5. Resource Histogram
The resource histogram is a popular planning tool because it gives a good visual
presentation which is easy to assimilate and understand. The prerequisites for
drawing the resource histogram are:
a- Early start bar chart (after considering the procurement requirements which
ensure the materials and equipment are available)
b- Resource forecast per activity.
Consider the following example:
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
4
Resource Table
Resource Bar chart and Histogram
6. Resource Loading
The resource forecast is now compared with the resources available. The ideal
situation is achieved when the resource requirement equals the resources
available. Unfortunately, in project management this seldom happens, because it
is not always possible to adjust supply with demand, so some form of compromise
is essential.
A resource overload is when the resource forecast exceeds the available
resources, while a resource under-load is when resource forecast is lower than the
available resource.
A resource overload will lead to some activities being delayed which could delay
the completion of the project.
A resource under-load will under-utilize the company's resources which could
have a detrimental effect on the company's profitability.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
5
Resource Loading (overloading and under-loading)
The overloads and under-loads can now be identified and addressed as follows:
a- Resource Smoothing: assign resources to critical activities first, then try
moving the other activities to ease any overload and under-utilization.
b- Time-Limited Resource Scheduling: the end date of the project is fixed,
so resources must be increased to address any overloads.
c- Resource-Limited Resource Scheduling: the maximum number of
resources is fixed, so the end date may need to be extended to address any
overload.
d- Increase Resources: to address an overload.
e- Reduce Resources: to address an under-load (under-utilized).
7. Resource Smoothing
Resource smoothing is the process of moving activities to improve the resource
loading profile.
The first step is to select the resource to be smoothed. To decide which resource
to smooth consider:
a- The resource that is most overloaded.
b- The resource that is most used on the project.
c- The least flexible resource - this could be the resource that comes from
overseas, is difficult to get hold of or is least available.
d- The most expensive resource to hire.
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
6
Example:
Resource Bar chart and Histogram
Project Management 2017 Dr. Mahmoud Abbas Mahmoud
7
Smoothed Bar chart and Histogram

More Related Content

What's hot

Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisBPUG Congress
 
Project management and control
Project management and controlProject management and control
Project management and controlShruti Pendharkar
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptJo Balucanag - Bitonio
 
Line of Balance
Line of BalanceLine of Balance
Line of BalanceIJMER
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisationCharul Sharma
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project managementMC Tubera
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
Project time management
Project time managementProject time management
Project time managementImran Jamil
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxssuser85ddaa
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 

What's hot (20)

project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Project Resource Management 3 Jon Lewis
Project Resource Management 3 Jon LewisProject Resource Management 3 Jon Lewis
Project Resource Management 3 Jon Lewis
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
Project management and control
Project management and controlProject management and control
Project management and control
 
Fast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.pptFast Tracking a Project and Project Crashing.ppt
Fast Tracking a Project and Project Crashing.ppt
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
 
Time cost optimisation
Time cost optimisationTime cost optimisation
Time cost optimisation
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Project time management
Project time managementProject time management
Project time management
 
ACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptxACT04Ch7PM - Project Crashing.pptx
ACT04Ch7PM - Project Crashing.pptx
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 

Viewers also liked

Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsMaria Erland, PMP
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMOTURKI , PMP
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsian jones
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingMashilo Kabedi
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementBob Zoller
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocationJatin Mandhyan
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Hussain Bandukwala
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation Riadh Mohammed Arif
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017Carol Smith
 

Viewers also liked (12)

Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
Resource management
Resource managementResource management
Resource management
 
PMO Frameworks
PMO FrameworksPMO Frameworks
PMO Frameworks
 
How To Build A PMO
How To Build A PMOHow To Build A PMO
How To Build A PMO
 
Resource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tipsResource capacity planning guide - best practice, hints, tips
Resource capacity planning guide - best practice, hints, tips
 
Resource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder MeetingResource Management Plan Stakeholder Meeting
Resource Management Plan Stakeholder Meeting
 
PMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_ManagementPMINEO_2010_03_Resource_Management
PMINEO_2010_03_Resource_Management
 
Planning, scheduling and resource allocation
Planning, scheduling and resource allocationPlanning, scheduling and resource allocation
Planning, scheduling and resource allocation
 
Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)Setting up a Project Management Office (PMO)
Setting up a Project Management Office (PMO)
 
Strategy and Resource Allocation
Strategy and Resource Allocation Strategy and Resource Allocation
Strategy and Resource Allocation
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
AI and Machine Learning Demystified by Carol Smith at Midwest UX 2017
 

Similar to Resource allocation and smoothing

Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocationVenu Yemul
 
Resource Planning
Resource PlanningResource Planning
Resource PlanningWajahat Ali
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...HIMADRI BANERJI
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)Peter Mello
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
The Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementThe Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementOrangescrum
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)danieljohn810
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docxaryan532920
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6IOSRJMCE
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling Nicola2903
 
pinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxpinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxIftikhar1985
 

Similar to Resource allocation and smoothing (20)

Resource planning and resource allocation
Resource planning and resource allocationResource planning and resource allocation
Resource planning and resource allocation
 
Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
 
SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)SDPM (Success Driven Project Management)
SDPM (Success Driven Project Management)
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
B012440511
B012440511B012440511
B012440511
 
The Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources ManagementThe Ultimate Guide To Project Resources Management
The Ultimate Guide To Project Resources Management
 
Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)Certificate IV Project Management - Activity Duration Estimating (Inputs)
Certificate IV Project Management - Activity Duration Estimating (Inputs)
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 MBA 6951, Managing Complex Projects 1 Course Learning.docx MBA 6951, Managing Complex Projects 1 Course Learning.docx
MBA 6951, Managing Complex Projects 1 Course Learning.docx
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Managing Project Success
Managing Project SuccessManaging Project Success
Managing Project Success
 
pinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptxpinto_pm5_inppt_12.pptx
pinto_pm5_inppt_12.pptx
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptxCE427-Chp6-Resource-Allocation-24Apr2019.pptx
CE427-Chp6-Resource-Allocation-24Apr2019.pptx
 

More from Dr. Mahmoud Al-Naimi

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfDr. Mahmoud Al-Naimi
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-NaimiDr. Mahmoud Al-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعDr. Mahmoud Al-Naimi
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةDr. Mahmoud Al-Naimi
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...Dr. Mahmoud Al-Naimi
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)Dr. Mahmoud Al-Naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1Dr. Mahmoud Al-Naimi
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsDr. Mahmoud Al-Naimi
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Dr. Mahmoud Al-Naimi
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationDr. Mahmoud Al-Naimi
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق Dr. Mahmoud Al-Naimi
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Dr. Mahmoud Al-Naimi
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing Dr. Mahmoud Al-Naimi
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةDr. Mahmoud Al-Naimi
 

More from Dr. Mahmoud Al-Naimi (20)

أسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdfأسلوب تقييم ومراجعة المشروع (بيرت).pdf
أسلوب تقييم ومراجعة المشروع (بيرت).pdf
 
Certificate - Dr. Mahmoud AL-Naimi
Certificate  - Dr. Mahmoud AL-NaimiCertificate  - Dr. Mahmoud AL-Naimi
Certificate - Dr. Mahmoud AL-Naimi
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفةكيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
كيفية حساب إحتمالية إنجاز المشروع باستخدام طرق وجدوال مختلفة
 
(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...(AOA) and (AON) Network construction and critical path calculations (using fo...
(AOA) and (AON) Network construction and critical path calculations (using fo...
 
أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)أسلوب تقييم ومراجعة المشروع (PERT)
أسلوب تقييم ومراجعة المشروع (PERT)
 
(Aoa) and (aon) networks
(Aoa) and (aon) networks(Aoa) and (aon) networks
(Aoa) and (aon) networks
 
Applications dr. mahmoud al-naimi
Applications   dr. mahmoud al-naimiApplications   dr. mahmoud al-naimi
Applications dr. mahmoud al-naimi
 
Product design and manufacture lecture 1
Product design and manufacture lecture  1Product design and manufacture lecture  1
Product design and manufacture lecture 1
 
Easy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projectsEasy steps to critical path determination and floats calculations for projects
Easy steps to critical path determination and floats calculations for projects
 
Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations Step by step network construction and (cpm) calculations
Step by step network construction and (cpm) calculations
 
Easy steps to network construction and critical path determination
Easy steps to network construction and critical path determinationEasy steps to network construction and critical path determination
Easy steps to network construction and critical path determination
 
ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق ألأستدامة والتصنيع الرشيق
ألأستدامة والتصنيع الرشيق
 
Control charts for variables
Control charts for variables Control charts for variables
Control charts for variables
 
Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)Just in time (jit), lean, and toyota production system (tps)
Just in time (jit), lean, and toyota production system (tps)
 
Evolution of mrp type systems
Evolution of mrp type systemsEvolution of mrp type systems
Evolution of mrp type systems
 
Computer in Design and Manufacturing
Computer in Design and Manufacturing Computer in Design and Manufacturing
Computer in Design and Manufacturing
 
إنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكيةإنشاء ورسم المخططات الشبكية
إنشاء ورسم المخططات الشبكية
 
Network construction
Network construction  Network construction
Network construction
 
Production planning hierarchy
Production planning hierarchyProduction planning hierarchy
Production planning hierarchy
 

Recently uploaded

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 

Recently uploaded (20)

VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 

Resource allocation and smoothing

  • 1. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 0 Project Management Resource Allocation and Smoothing Dr. Mahmoud Abbas Mahmoud Assistant Professor 2017
  • 2. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 1 Resource Allocation and Smoothing 1. Resource Planning A resource may be defined as the machine or person who will perform the scope of work. Resource planning is forecasting the resources required to perform the scope of work within the time plan. The resource constraint should be considered after the network diagram, schedule bar chart and procurement schedule have been developed. But before the crash- flow statement. 2. Resource Estimating The resource estimates is linked directly to the scope of work and bill of materials (BOM). The scope of work may be expressed as so many tons of steel, or so many square meters of wall paint etc. From this description estimator can convert the scope of work into manhours per unit ‘X’. Consider the following, if the scope of work is to erect (assemble) 12 tons of steel and the estimator knows from past experience that the work can be done in 150 manhours per ton and the men work 10 hour shifts, then the equation is: ( 12 tons × 150 manhours per ton ) 10 hrs per day = 180 mandays Resource / Duration Trade-Off 3. Resource Forecasting Resource forecasting is to forecast the total resource requirement by discipline or interchangeable resource. An interchangeable resource is when you have a pool (group) of workers and any one of them could perform the work. This is done by compiling all the resource estimates and presenting them in a structured resource table.
  • 3. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 2 Resource Table Resource Forecast - Bar Chart Resource Forecast – Histogram Note: The bar chart shows the number of resources per activity per day, and the histogram shows the total recourse required per day. 4. Resource Availability In establishing the resource availability, the following points should be considered: a- Other resource commitments - if your company is involved in a number of projects which all draw from a common labor pool, the other projects' requirements must also be considered (also called multi-project resource scheduling). b- The anticipated sickness and absenteeism rate. For example: allow for a 25% absentee rate based on experience.
  • 4. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 3 Planning for a 25% Absenteeism Keeping the above points in mind, the resource availability table will be developed. Consider the following example: 5. Resource Histogram The resource histogram is a popular planning tool because it gives a good visual presentation which is easy to assimilate and understand. The prerequisites for drawing the resource histogram are: a- Early start bar chart (after considering the procurement requirements which ensure the materials and equipment are available) b- Resource forecast per activity. Consider the following example:
  • 5. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 4 Resource Table Resource Bar chart and Histogram 6. Resource Loading The resource forecast is now compared with the resources available. The ideal situation is achieved when the resource requirement equals the resources available. Unfortunately, in project management this seldom happens, because it is not always possible to adjust supply with demand, so some form of compromise is essential. A resource overload is when the resource forecast exceeds the available resources, while a resource under-load is when resource forecast is lower than the available resource. A resource overload will lead to some activities being delayed which could delay the completion of the project. A resource under-load will under-utilize the company's resources which could have a detrimental effect on the company's profitability.
  • 6. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 5 Resource Loading (overloading and under-loading) The overloads and under-loads can now be identified and addressed as follows: a- Resource Smoothing: assign resources to critical activities first, then try moving the other activities to ease any overload and under-utilization. b- Time-Limited Resource Scheduling: the end date of the project is fixed, so resources must be increased to address any overloads. c- Resource-Limited Resource Scheduling: the maximum number of resources is fixed, so the end date may need to be extended to address any overload. d- Increase Resources: to address an overload. e- Reduce Resources: to address an under-load (under-utilized). 7. Resource Smoothing Resource smoothing is the process of moving activities to improve the resource loading profile. The first step is to select the resource to be smoothed. To decide which resource to smooth consider: a- The resource that is most overloaded. b- The resource that is most used on the project. c- The least flexible resource - this could be the resource that comes from overseas, is difficult to get hold of or is least available. d- The most expensive resource to hire.
  • 7. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 6 Example: Resource Bar chart and Histogram
  • 8. Project Management 2017 Dr. Mahmoud Abbas Mahmoud 7 Smoothed Bar chart and Histogram