SlideShare a Scribd company logo
1 of 13
Kaizen
Event
Assembly of Power Drive Units
Team Members
Greg Williams and 7 other team members who
shall remain nameless for this version of the
presentation. Those chosen had considerable
experience with the existing power drive
manufacturing and assembly process and had
some exposure to a previous Kaizen event
Previous state
The team recorded:
• Area = 80sq/m
• Working environment was a small area in the aisle
between assembly benches and racking.
• Limited access for forklift into racking when assembling
Power Drives.
• Walking distances 650 metres per PD x 2.5 PD a day =
1.62km per day
• No of operators = 4 required by ST point scheduling
• Cycle time = 260min
Previous state
Packing crates as benches,
cubicles stored on floor
Components difficult to access
Components strewn in various
non-defined locations.
Batching of assemblies
Previous state
Recorded times were transferred to bar charts
Version 3 - New two operator sequencing
Version 3 with a further 30 minute reduction in cycle time. Now 135 minutes.
Further reductions were expected by reduced walking times with new cell layout
Previous state
Parts retrieval spaghetti chart
Previous state
650 mtrs walked for each
Power Drive assembled equated to
1.62klms per day
Version 4 - New two operator sequencing
NOTE: Further reductions expected by reduced walking times with new cell layout.
Recording of new times still required to show 15 minute reduction in cycle time.
The target of 4 Power Drives a day was achieved.
Cell design
• The team used a combination work chart to:
– Reduce cycle time
– Decide the correct sequence of standard work
– Synchronise sub assembly and main assembly operations
• Decide on U shaped counterclockwise cell layout
• Right sized part racks and buckets within easy reach
• Modified jigs and fixtures
• Dedicated pedestal and bench drills for eliminating jig setup times
• Lift trolleys for one piece flow assembly providing easier access
and manipulation of assemblies
• Fastener and tool trolleys
• Crane for ease of lifting into cabinet and crates
White board was installed for operators and
management walk around to track progress
Dedicated drills to
eliminate
jig setup times
Dedicated tool
and fastener
trolleys
Component buckets
positioned for ease of
access
Adjustable trolley heights reduced operator
movement when accessing heavy parts
Result of New Cell Design
4
Complete
main
mech assy
3
Drill
motor
and auxy
switch
2
Start
main
mech assy
1
Drill
gearbox
8
Pack
7
Install
main assy
into
cubicle
6
Prepare
cubicle
5
Electrics
installed
overnight
Results
Before After Improvement
Area 80sq/m 61sq/m 24% reduction
Cycle time 260min 135min 48% reduction
Crew size
2 req normal
scheduling
4 req for EA
schedule planning
3 in training
Target of 2
25% reduction in ST
planned crew size
Target is 50% crew size
reduction
WIP = = None
Inventory = = None
Productivity
12
PDs per week
20
PDs per week
66% increase
To Do
• Further gains are anticipated through investigation of
the following:
– Shaft and stop design to remove welding process
– Chain cut to length by subcontractor
– Breather gauze and foam cut by subcontractor
– Din rail cutter which has been implemented already
– Wire handle cap retaining chain made outside
– Crane required – Sharing with Ergon cell at present
– Supply and install of the wiring loom. This is essentially our
drum beat.
– Hand over to continuous improvement team/cell operators
– Cell operators have already listed various other
improvements on their whiteboard

More Related Content

What's hot

Bearing loading conditions: shaft - bearing - housing approach
Bearing loading conditions: shaft - bearing - housing approachBearing loading conditions: shaft - bearing - housing approach
Bearing loading conditions: shaft - bearing - housing approachAndrea Bacchetto
 
bearing loading conditions: traditional approach
bearing loading conditions: traditional approachbearing loading conditions: traditional approach
bearing loading conditions: traditional approachAndrea Bacchetto
 
Updated cv shailendra 11.05.16
Updated cv shailendra 11.05.16Updated cv shailendra 11.05.16
Updated cv shailendra 11.05.16shailendra kumar
 
Citrus-College-CDR-Presentation
Citrus-College-CDR-PresentationCitrus-College-CDR-Presentation
Citrus-College-CDR-PresentationJoseph Molina
 
Gearless transmission
Gearless transmissionGearless transmission
Gearless transmissionk10481
 
Senlogic Automation Private Limited, Chennai, Industrial Weighing System
Senlogic Automation Private Limited, Chennai, Industrial Weighing SystemSenlogic Automation Private Limited, Chennai, Industrial Weighing System
Senlogic Automation Private Limited, Chennai, Industrial Weighing SystemIndiaMART InterMESH Limited
 
aotomated guided vehicle
aotomated guided vehicleaotomated guided vehicle
aotomated guided vehicleAlamkhan Pathan
 

What's hot (13)

Bearing loading conditions: shaft - bearing - housing approach
Bearing loading conditions: shaft - bearing - housing approachBearing loading conditions: shaft - bearing - housing approach
Bearing loading conditions: shaft - bearing - housing approach
 
bearing loading conditions: traditional approach
bearing loading conditions: traditional approachbearing loading conditions: traditional approach
bearing loading conditions: traditional approach
 
JANARDAN
JANARDANJANARDAN
JANARDAN
 
Updated cv shailendra 11.05.16
Updated cv shailendra 11.05.16Updated cv shailendra 11.05.16
Updated cv shailendra 11.05.16
 
Citrus-College-CDR-Presentation
Citrus-College-CDR-PresentationCitrus-College-CDR-Presentation
Citrus-College-CDR-Presentation
 
pranay
pranaypranay
pranay
 
Gearless transmission
Gearless transmissionGearless transmission
Gearless transmission
 
Senlogic Automation Private Limited, Chennai, Industrial Weighing System
Senlogic Automation Private Limited, Chennai, Industrial Weighing SystemSenlogic Automation Private Limited, Chennai, Industrial Weighing System
Senlogic Automation Private Limited, Chennai, Industrial Weighing System
 
Gearless mechanism
Gearless mechanismGearless mechanism
Gearless mechanism
 
Chen_CV
Chen_CVChen_CV
Chen_CV
 
aotomated guided vehicle
aotomated guided vehicleaotomated guided vehicle
aotomated guided vehicle
 
Orscheln Brake Damper - Team 4
Orscheln Brake Damper - Team 4Orscheln Brake Damper - Team 4
Orscheln Brake Damper - Team 4
 
Gearless transmission
Gearless transmissionGearless transmission
Gearless transmission
 

Viewers also liked

青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」
青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」
青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」青森県立郷土館
 
3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...
3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...
3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...Spencer Bliven
 
平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」
平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」
平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」青森県立郷土館
 
χρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματα
χρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματαχρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματα
χρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματαRia Anastas
 
Bba 1 be 1 u-1.2 goods
Bba 1 be 1 u-1.2 goodsBba 1 be 1 u-1.2 goods
Bba 1 be 1 u-1.2 goodsRai University
 
Прикладная эконометрика. Лекция 9
Прикладная эконометрика. Лекция 9Прикладная эконометрика. Лекция 9
Прикладная эконометрика. Лекция 9Vladimir Tcherniak
 
Прикладная эконометрика. Лекция 12
Прикладная эконометрика. Лекция 12Прикладная эконометрика. Лекция 12
Прикладная эконометрика. Лекция 12Vladimir Tcherniak
 
El diseño industrial
El diseño industrialEl diseño industrial
El diseño industrialraveldi
 
UD1 Los origenes del arte parte1: Prehistoria
UD1 Los origenes del arte parte1: PrehistoriaUD1 Los origenes del arte parte1: Prehistoria
UD1 Los origenes del arte parte1: PrehistoriaFueradeclase Vdp
 
οδύσσεια ορέστης όλια
οδύσσεια ορέστης όλιαοδύσσεια ορέστης όλια
οδύσσεια ορέστης όλιαnikzoit
 
οδύσσεια θάνος μαρφένια
οδύσσεια θάνος μαρφένιαοδύσσεια θάνος μαρφένια
οδύσσεια θάνος μαρφένιαnikzoit
 

Viewers also liked (15)

青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」
青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」
青森県立郷土館土曜セミナー「本県が生んだ無名の偉人・ 佐々木多門とその周辺の人々」
 
Thesis Defense
Thesis DefenseThesis Defense
Thesis Defense
 
3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...
3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...
3DSIG 2016 Presentation: Exploring Internal Symmetry and Structural Repeats w...
 
平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」
平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」
平成21年度青森県博物館大会「青森県立郷土館における広報活動の取り組みについて」
 
χρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματα
χρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματαχρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματα
χρήση βασικών εργαλείων πληροφορικής στα φιλολογικά μαθήματα
 
Fpb1 predicado cd
Fpb1  predicado cdFpb1  predicado cd
Fpb1 predicado cd
 
Power marysol
Power marysolPower marysol
Power marysol
 
Bba 1 be 1 u-1.2 goods
Bba 1 be 1 u-1.2 goodsBba 1 be 1 u-1.2 goods
Bba 1 be 1 u-1.2 goods
 
Прикладная эконометрика. Лекция 9
Прикладная эконометрика. Лекция 9Прикладная эконометрика. Лекция 9
Прикладная эконометрика. Лекция 9
 
Прикладная эконометрика. Лекция 12
Прикладная эконометрика. Лекция 12Прикладная эконометрика. Лекция 12
Прикладная эконометрика. Лекция 12
 
Fpb1 sujeto y predicado
Fpb1 sujeto y predicadoFpb1 sujeto y predicado
Fpb1 sujeto y predicado
 
El diseño industrial
El diseño industrialEl diseño industrial
El diseño industrial
 
UD1 Los origenes del arte parte1: Prehistoria
UD1 Los origenes del arte parte1: PrehistoriaUD1 Los origenes del arte parte1: Prehistoria
UD1 Los origenes del arte parte1: Prehistoria
 
οδύσσεια ορέστης όλια
οδύσσεια ορέστης όλιαοδύσσεια ορέστης όλια
οδύσσεια ορέστης όλια
 
οδύσσεια θάνος μαρφένια
οδύσσεια θάνος μαρφένιαοδύσσεια θάνος μαρφένια
οδύσσεια θάνος μαρφένια
 

Similar to PD cell Kaizen event presentation

FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013Donna Skala
 
Pack Line Process Improvement Project-Cart-VideoWall
Pack Line Process Improvement Project-Cart-VideoWallPack Line Process Improvement Project-Cart-VideoWall
Pack Line Process Improvement Project-Cart-VideoWallDavid Thacker, MBA
 
Meenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.pptMeenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.ppttommychauhan
 
S Warwick CV 20150521
S Warwick CV 20150521S Warwick CV 20150521
S Warwick CV 20150521Steve Warwick
 
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
Product, process, fixed and group layouts
Product, process, fixed and group layoutsProduct, process, fixed and group layouts
Product, process, fixed and group layoutsAjith Antony
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsWIGreenBuilding
 
Senior Project Presentation_Final
Senior Project Presentation_FinalSenior Project Presentation_Final
Senior Project Presentation_FinalKate Mays
 
2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)MICHAEL MORGAN
 
bottle neck operation through critical path method
bottle neck operation through critical path methodbottle neck operation through critical path method
bottle neck operation through critical path methodSaurav Kumar
 
Herding Cats Using Lean Six Sigma
Herding Cats Using Lean Six SigmaHerding Cats Using Lean Six Sigma
Herding Cats Using Lean Six SigmaJohn Pettit
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aRai University
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...
PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...
PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...GoLeanSixSigma.com
 

Similar to PD cell Kaizen event presentation (20)

FC VSM Presentation Future State Aug 5 -7 2013
FC VSM Presentation Future State Aug 5 -7  2013FC VSM Presentation Future State Aug 5 -7  2013
FC VSM Presentation Future State Aug 5 -7 2013
 
Pack Line Process Improvement Project-Cart-VideoWall
Pack Line Process Improvement Project-Cart-VideoWallPack Line Process Improvement Project-Cart-VideoWall
Pack Line Process Improvement Project-Cart-VideoWall
 
Meenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.pptMeenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.ppt
 
Project review
Project reviewProject review
Project review
 
Matt Hallead - Lean Projects Overview
Matt Hallead - Lean Projects OverviewMatt Hallead - Lean Projects Overview
Matt Hallead - Lean Projects Overview
 
Creative journey
Creative journeyCreative journey
Creative journey
 
S Warwick CV 20150521
S Warwick CV 20150521S Warwick CV 20150521
S Warwick CV 20150521
 
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptxAminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
Aminullah Assagaf_P5-Ch.7_Capacity and Facility_32.pptx
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Product, process, fixed and group layouts
Product, process, fixed and group layoutsProduct, process, fixed and group layouts
Product, process, fixed and group layouts
 
Retrocommissioning of Existing Buildings
Retrocommissioning of Existing BuildingsRetrocommissioning of Existing Buildings
Retrocommissioning of Existing Buildings
 
Senior Project Presentation_Final
Senior Project Presentation_FinalSenior Project Presentation_Final
Senior Project Presentation_Final
 
54 paul gibbs_helioscope
54 paul gibbs_helioscope54 paul gibbs_helioscope
54 paul gibbs_helioscope
 
2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)
 
bottle neck operation through critical path method
bottle neck operation through critical path methodbottle neck operation through critical path method
bottle neck operation through critical path method
 
Herding Cats Using Lean Six Sigma
Herding Cats Using Lean Six SigmaHerding Cats Using Lean Six Sigma
Herding Cats Using Lean Six Sigma
 
Mba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection aMba ii pmom_unit-1.4 process design, analysis & selection a
Mba ii pmom_unit-1.4 process design, analysis & selection a
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
Final presentation
Final presentationFinal presentation
Final presentation
 
PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...
PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...
PROJECT STORYBOARD: Herding Cats Using Lean Six Sigma: How to Plan for and Ma...
 

PD cell Kaizen event presentation

  • 2. Team Members Greg Williams and 7 other team members who shall remain nameless for this version of the presentation. Those chosen had considerable experience with the existing power drive manufacturing and assembly process and had some exposure to a previous Kaizen event
  • 3. Previous state The team recorded: • Area = 80sq/m • Working environment was a small area in the aisle between assembly benches and racking. • Limited access for forklift into racking when assembling Power Drives. • Walking distances 650 metres per PD x 2.5 PD a day = 1.62km per day • No of operators = 4 required by ST point scheduling • Cycle time = 260min
  • 4. Previous state Packing crates as benches, cubicles stored on floor Components difficult to access Components strewn in various non-defined locations. Batching of assemblies
  • 5. Previous state Recorded times were transferred to bar charts Version 3 - New two operator sequencing Version 3 with a further 30 minute reduction in cycle time. Now 135 minutes. Further reductions were expected by reduced walking times with new cell layout
  • 6. Previous state Parts retrieval spaghetti chart Previous state 650 mtrs walked for each Power Drive assembled equated to 1.62klms per day
  • 7. Version 4 - New two operator sequencing NOTE: Further reductions expected by reduced walking times with new cell layout. Recording of new times still required to show 15 minute reduction in cycle time. The target of 4 Power Drives a day was achieved.
  • 8. Cell design • The team used a combination work chart to: – Reduce cycle time – Decide the correct sequence of standard work – Synchronise sub assembly and main assembly operations • Decide on U shaped counterclockwise cell layout • Right sized part racks and buckets within easy reach • Modified jigs and fixtures • Dedicated pedestal and bench drills for eliminating jig setup times • Lift trolleys for one piece flow assembly providing easier access and manipulation of assemblies • Fastener and tool trolleys • Crane for ease of lifting into cabinet and crates
  • 9. White board was installed for operators and management walk around to track progress
  • 10. Dedicated drills to eliminate jig setup times Dedicated tool and fastener trolleys Component buckets positioned for ease of access Adjustable trolley heights reduced operator movement when accessing heavy parts
  • 11. Result of New Cell Design 4 Complete main mech assy 3 Drill motor and auxy switch 2 Start main mech assy 1 Drill gearbox 8 Pack 7 Install main assy into cubicle 6 Prepare cubicle 5 Electrics installed overnight
  • 12. Results Before After Improvement Area 80sq/m 61sq/m 24% reduction Cycle time 260min 135min 48% reduction Crew size 2 req normal scheduling 4 req for EA schedule planning 3 in training Target of 2 25% reduction in ST planned crew size Target is 50% crew size reduction WIP = = None Inventory = = None Productivity 12 PDs per week 20 PDs per week 66% increase
  • 13. To Do • Further gains are anticipated through investigation of the following: – Shaft and stop design to remove welding process – Chain cut to length by subcontractor – Breather gauze and foam cut by subcontractor – Din rail cutter which has been implemented already – Wire handle cap retaining chain made outside – Crane required – Sharing with Ergon cell at present – Supply and install of the wiring loom. This is essentially our drum beat. – Hand over to continuous improvement team/cell operators – Cell operators have already listed various other improvements on their whiteboard

Editor's Notes

  1. Reason for Kaizen event Due to the high demand of deliveries for Energy Australia earlier this year, a decision was made to run a Kaizen event on the assembly of Power Drives. As with the Ergon cell the focus was on the one piece flow cell concept, the sequencing of operations, reduction in cycle time and the identification and reduction of waste.
  2. Team members A team was chosen who have had considerable experience with Power Drive design, manufacture and assembly and also Kaizen experience.
  3. Previous State The team recorded: Total area used was = 80sq/mtrs. Walking distances for retrieval of components was 650 metres per Power drive. 4 operators were required by ST Point scheduling software. The times of each process were recorded and the cycle time for one Power Drive was calculated as 260 minutes although some versions are up to 297 minutes.
  4. Previous State Working environment was cluttered, with packing crates as assembly benches. Components were difficult to access or strewn in various locations. Batching of assemblies was common practice. Assemblies in various stages of completion. Limited access for forklift into adjacent racking.
  5. Recorded times were transferred to bar charts by hand. Operator sequencing was determined by transferring those times to a series of combination work charts. Some operations were combined for ease of operator sequencing 3 versions of operator sequencing reduced the cycle time from 260 minutes to 135 minutes.
  6. A Spaghetti chart was created to determine the movements staff required to assemble. Each Power Drive required approx 650 meters of walking to retrieve components from Stores, yard area and Factory 1 at 27 Walker St for nameplate engraving. This equated to 1.62 klms per day.
  7. Version 4 of Operator Sequencing Further reductions were expected when the walking distances were reduced with the new cell layout. The team used the combination work chart and spaghetti chart To reduce cycle time Decide correct sequence of standard work Synchronise sub assembly and main assembly operations Reduce operator movement
  8. Cell design The team decided on a U shaped counterclockwise cell layout Ergonomically positioned part racks in easy reach of operators Modified jigs and fixtures Dedicated drilling machines for each operation to reduce jig set up times Lift trolleys for ease of access and movement of the assembly around the cell
  9. A white board was introduced to allow the management walk around and operators to track orders to ensure progress was on time.
  10. Improvements included: Dedicated drills to eliminate jig set up time Dedicated fastener and tool trolleys New benches for component storage and ease of access. Adjustable trolleys for ease of operators to manipulate components from storage locations.
  11. Result of the new cell design and counterclockwise one piece flow layout.
  12. Results Results allowed the cell operators to keep up with the required TAKT time for Energy Australia deliveries. The more significant results were: Required area reduction of 24% Cycle time reduction of 48% Crew size reduction of 25% and will hopefully soon reach 50% reduction Inventory and WIP remained the same as the scheduling process still operates to purchase components Productivity increase of 66%.
  13. Greg - Slide 13 To do There are still further improvements to be investigated such as: Shaft and stop design to remove the welding process Chain cut to length by subcontractor Din rail cutter which has already been implemented New crane to eliminate sharing with Ergon Supply and install of the electrical loom which is our main constraint or our ‘Drum beat’ Hand over to continuous improvement team The cell operators have already listed various other improvements on their whiteboard.