Presentation on DIAGNOSTIC ANALYSIS OF DISTRESSED HYDRAULIC STRUCTURES: CASE STUDIES OF GUJARAT, INDIA by Er Vivek P Kapadiya, Chief Engineer & Additional Secretary, Government of Gujarat at #33NCCE #IEIGSC
4. DESIGN FEATURES OF MAIN CANAL
• LARGEST IN THE WORLD HAVING CARRYING CAPACITY OF 1133 CUBIC
METER PER SECOND AT THE OFF-TAKE POINT.
• AT CH. 195 KM BANK HEIGHT ABOVE THE GROUND LEVEL IS 12.5 M
• CANAL BED IS 70 M WIDE AND THE FULL SUPPLY DEPTH (FSD) IS 7.0 M
• DESIGNED DISCHARGE IS 825 M3
/S
• CANAL SIDE SLOPES ARE 2 (H) : 1 (V)
4
6. DIAGNOSIS OF THE PROBLEM
• BOILING AT SOME DISTANCE FROM THE TOE OF THE CANAL
EMBANKMENT
• SUBSURFACE FLOW DUE TO FAVORABLE HYDRAULIC GRADIENT -
COULD NOT BE ATTRIBUTED TO THE CANAL FLOW AS THE CANAL WAS
LINED AND THE BED BANKING WAS MORE THAN 3.5 METER
• SHALLOW LIVE AQUIFER - CUT DUE TO CONSTRUCTION OF THE CANAL
SIPHON IN THE DOWNSTREAM
8. DIAGNOSIS OF THE PROBLEM
• SEEPAGE ABOVE TOE - EITHER PHREATIC LINE DEVELOPED WITHIN THE
CANAL EMBANKMENT OR CAPILLARY ACTION DEVELOPED NEAR THE
TOE FROM WITHIN THE GROUND ITSELF OR BOTH TOGETHER
• LOAM TYPE OF SOIL - GENERALLY ERODIBLE AND PHREATIC LINE OR
CAPILLARY ACTION COULD BE EASILY DEVELOPED DUE TO HIGH
PERMEABILITY WHEN THE COMPACTION IS NOT SUFFICIENT
• DEEP RAIN-CUTS ON THE OUTER SIDE OF THE CANAL EMBANKMENTS
WERE ALSO OBSERVED WHICH ALSO SUGGESTED ERODIBLE SOIL
9. UNFOLDMENT OF SOLUTION OF THE PROBLEM
• EXIT TO THE SUBSURFACE FLOW BY PROVIDING A LATERAL DRAIN -
ESTABLISH A STEADY STATE OF THE SOIL BENEATH THE CANAL
EMBANKMENT SO THAT CRUMBLING OF THE FOUNDATION RESULTING IN
TO FAILURE OF THE EMBANKMENT COULD BE AVOIDED
• ALSO TO STOP THE CAPILLARY ACTION OF WATER IN TO THE CANAL
EMBANKMENT NEAR THE TOE IF ANY
• LATERAL DRAIN - A COLLECTING DRAIN WAS EXTENDED TO A FAR
SITUATED POND FOR THE DISPOSAL
• AIMED AT RELEASING THE WATER ACCUMULATED IN LARGE QUANTITY
WITHIN THE SOIL BENEATH THE CANAL EMBANKMENT
11. UNFOLDMENT OF SOLUTION OF THE PROBLEM
• OBSERVATION FOR SOME DAYS - BOILING PHENOMENON ALMOST DISAPPEARED -
SEEPAGE REDUCED BUT NOT COMPLETELY STOPPED WHICH SUGGESTED THAT THE
PHREATIC LINE HAD ESTABLISHED WITHIN THE EMBANKMENT
• ADDITIONAL BERM OF 5 METER WIDTH AND 5 METER HEIGHT
• JUTE TEXTILE BAGS WERE SPECIALLY DESIGNED IN THE FORM OF LONG ROLLS -
FILLED UP WITH CEMENT SOIL IN 1:9 RATIO AND NAILED ON THE OUTER SLOPE OF
THE CANAL EMBANKMENT
• AVOIDING ROLLING DOWN OF THE JUTE ROLLS, AN ANTI-EROSION SURFACE ON
THE OUTER SLOPE OF THE EMBANKMENT AND TO ADD EXTRA BURDEN TO PROVIDE
MORE STABILITY
14. INTRODUCTION
• SABARKANTHA DISTRICT I.E. IN NORTH GUJARAT IN INDIA - COMPLETED BEFORE 10
YEARS - RIVER MESHWO
• GROSS STORAGE CAPACITY - 146 MILLION CUBIC FEET
• CATCHMENT AREA IS 371 SQUARE KILOMETERS - DESIGNED FLOOD WITH 1 IN 50 YEAR
FREQUENCY IS 3774 CUBIC METER PER SECOND
• LENGTH OF THE SPILLWAY SECTION IS 101.80 METER - CONCRETE GRAVITY DAM WITH
PROVIDED 9 VERTICAL GATES - HYDRAULIC JUMP TYPE STILLING BASIN - UPSTREAM
AND DOWNSTREAM KEYS WERE 3.5 METER DEEP
15. INTRODUCTION
• SIGNS OF DISTRESS IN ONLY 2 YEARS
• DOWNSTREAM GLACIS SLOPE 1:3 - TOE GOT DISINTEGRATED AND THE
REINFORCEMENTS WERE PULLED OUT
• DOWNSTREAM APRON GOT DAMAGED BUT NOT IN THE ENTIRE LENGTH OF THE DAM,
ONLY IN THE RIGHT HALF OF THE LENGTH I.E. RIVER’S HALF WIDTH
18. DIAGNOSTIC ANALYSIS
• GLACIS WITH 1:3 SLOPE WAS INSUFFICIENT TO AVOID CAVITY FORMATION - THERE
SHOULD HAVE BEEN A MUCH FLATTER SLOPE OR AN OGEE
• SOME RECORD - ORIGINALLY A BASALT MINE AS THE RIVER WAS HAVING GOOD
QUALITY BASALT IN ITS BED - FOR PREPARATION OF THE SITE, THE DESIGN
INCLUDED LEAN CONCRETE FILLING WITH LARGE COARSE AGGREGATE I.E. PLUM
CONCRETE IN THE PIT
• SOME OTHER RECORDS WITH GEOLOGICAL MAPPING SUGGESTED THAT THE MINE
WAS ONLY IN THE RIGHT HALF WIDTH OF THE RIVER AND THE DEPTH WAS ABOUT 9
METER
19. DIAGNOSTIC ANALYSIS
• LARGE COARSE AGGREGATES WERE IN PLACE - CEMENT AND SAND WERE IN LOOSE
FORM - WATER BENEATH THE APRON IN THE VOIDS - DAM WAS FULL UP TO CREST
LEVEL - IT WAS THE WATER FROM THE RESERVOIR
• CONDITION WAS EXTREMELY DANGEROUS - SUBSURFACE FLOW COULD RESULT IN
TO UNDERMINING THE FOUNDATION AND COLLAPSE OF THE CONCRETE DAM
ITSELF.
• WHEN WATER WAS RELEASED, IMPACT OF THE WATER FALL WAS TAKEN UP BY THE
APRON WHICH REQUIRED A SOLID FOUNDATION WHICH ACTUALLY WAS NOT
THERE - CONCRETE APRON USED TO SETTLE - SAGGING RESULTING IN TO DAMAGE
AT THE BOTTOM AND TOP – BOTTOM DAMAGE WAS NOT VISIBLE BUT THE TOP WAS
20. RESTORATION
• PLUM CONCRETE REMOVED UP TO 1.5 METER DEPTH – RICH CEMENT SAND MIX 1:4
WITH POLYMER POURED TO PLUG VOIDS IN PLUM CONCRETE
• LAYER OF 1.5 METETR THICKNESS OF RICH CONCRETE
• ADDITIONAL PERIPHERAL KEY OF 5 METER – FOUNDATION OF ABUTMENT
STRENGTHENED
• CASTING OF APRON – REINFORCEMENT MESH AT TOP WELDED WITH TOE
REINFORCEMENT – SURFACE HARDENER TO PROVIDE IMPACT RESISTANT SURFACE –
FILLET AT TOE
• DOWNSTREAM RIVER CHANNEL REGRADED
23. CONCLUSION
• PROBLEMS IN CIVIL ENGINEERING ARE VERY COMPLEX AND UNDERSTANDING THE
REAL CAUSE OF THE PROBLEM IS THE MOST IMPORTANT ASPECT
• A SMALL ASPECT IGNORED AT THE CONSTRUCTION STAGE MAY LEAD TO DIFFICULT
PROBLEMS
• EXPERIENCE AND INSIGHT NEEDED AS MOSTLY THE FINDINGS CAN BE REACHED BY
WAY OF USING JUDGMENTAL AND INTUITIVE DECISIONS
24. CONCLUSION
• SOMETIME THE DIAGNOSIS IS REQUIRED TO BE DONE STAGE-WISE ALONG WITH STEP
BY STEP IMPLEMENTATION OF SOLUTION
• SEVERAL ACTIVITIES TO BE EXECUTED WITH PROPER SEQUENCE AND PROPER
MATERIALS