The new point-of-reference tool for Electricity
Transmission Asset and Operation Management
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Marcus Stenstrand
Program Manager for Fingrid 's Elvis project
Jens Dalsgaard
Principal Business process Consultant & SME in Electric Utility and GIS
Presenting the Presenters
Marcus has a vast experience that is based on various responsibilities from manager positions in maintenance and asset
management, in addition with business and strategy development at Fingrid.
Been active in bringing in new methods of working and operating such us knowledge and performance management with
service providers.
Worked with international benchmarking for several years and worked on the PAS55 adaption team at Fingrid and the Finnish
ISO55000 review committee.
http://fi.linkedin.com/in/stenstrand/en
In the ELVIS project Jens Dalsgaard has been responsible for planning, leading and documenting clarification workshops, data
modelling and data migration, and the close cooperation with Fingrid and IBM gave invaluable insight into business processes
throughout the life cycle of grid operation and asset management.
https://www.linkedin.com/in/jensdalsgaard
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Power Transmission Network
The
main electricity
transmission network,
to which major power plants,
factories and regional
distribution networks are mainly
linked.
Also connects Finland to
international electricity
markets.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
The main grid in numbers
113 substations
14 400 km of power lines
300 km of submarine cable
48 000 towers
10 reserve power plants
> 935 MW reserve
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Fingrid 's tariff is among the lowest in Europe
Norway Finland Belgium Denmark Czech
Republic
Ireland Slovakia
€/MWh
Source: Entso-E
The comparison includes European main grid companies with responsibility for
110 kV and 400 kV electricity grids.
Great Britain
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
We make sure that Finland obtains electricity without disturbances
There are
525,600
minutes
in a year. *The average duration of
transmission disturbances for
Fingrid main grid customers is
3 minutes per year.
3 min*
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Fingrid
According to international benchmarks,
cost effectiveness and grid reliability are
among the best in the industry.
One of the
world's best electricity companies
since 1995.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
1988 First Computerized
maintenance
management system
(CMMS) application (in-
house, called KUNTO) into
use, data collected by
paper form in-hand
1992 First Enterprise Asset Mgmt
system (EAM) into use (fully
integrated between applications.
In-house, called ELNET), UNIX
based
○ Asset register
○ CMMS with Condition
prediction models and work
package mgmt
○ Mobile handhelds for
inspection results
○ GIS
○ Relay settings, out-
age mgmt, grid calc.
1997-1999 ELNET user
interface updated from
UNIX to Windows
2002 FgPartners Extranet
for Service Providers
where all asset related
data available (Citrix),
same tools and data for
Fingrid and service
providers
2001 Project Portfolio and
project mgmt tool
introduced (Artemis
CmPro)
2003 Paperless office
reached 100 %, last
drawings and technical
documents scanned into
DMS (Bentley ProjectWise)
2006 Work order follow -
up and cost supervision
tool introduced (in-house,
called TOSU)
2005 Buisness Intelligence
(BI) tools introduced for
combining financial data
with asset data (IBM
Cognos). Performance
mgmt dashboards
introduced for all roles
2005 Time series database
for history data from SCADA
(OSIsoft PI)
2012 Condition history and
on-line monitoring plus asset
health indices (OSIsoft
ProcessBook)
2013 ELVIS part 1: Substation
asset register and
maintenencae (Maximo) plus
ProjectPortfolio update
(Primavera)
ELVIS
part 2 & 3.
The
next
step
2007 First on-line
condition monitoring
meters in to use (in-
house)
History lane for Asset mgmt support tools at Fingrid
Knowledge Management has been of high importance in strategy for decades
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Fingrid's next generation Asset Management solution
ELectricity
Verkko (Finnish word for Grid)
Information
System
• Solution planning started in 2008
• Project kick-off in 2012
• Final parts in to be deployed in 2015
• Solution provider IBM, ESRI, Informi GIS, Siemens, IPS, Electrocon,
Project Institute Finland,
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
ELVIS main goals
Increasing operative efficiency, lowering risk and improving decision making
Process
Digitization
Big
Data
Master
Data
• Next generation streamlining of asset
management processes
• 2nd generation performance
dashboards
• Integrating all business data
• Combining asset mgmt data with IoT
generated data
• Enabling industry wide data analytics
• Single source for power system
information → One version of the truth
• Data entered only ONCE into ONE
system, other systems uses this data
ELVIS is part of Asset Mgmt strategy, not part of IT
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Asset Management and Grid Optimization
A high data quality is the foundation
for any qualified decision making.
Fingrid has established a coherent setup
establishing / guaranteeing the data needed
in asset management, in grid optimization,
as well as in many other business processes.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Two Fundamental Architectural Strategies
Data should be entered once
and distributed as needed
Standard software products should be used
with a minimum of customization required.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
An Overview of the ELVIS Solution
GIS
Maximo
PSS®ODMS PSS®E
IPS CAPEPrimavera
1. Complete grid documentation in one place
2. Integrated with asset and work management
3. Integrated project planning
4. CIM based electrical grid model generated
from GIS model
5. Electrical calculations and analysis
6. Relay management and calculations
Standard Software
Packages
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
GIS
Maximo
PSS®ODMS
1. Complete grid documentation in one place
2. Integrated with asset and work management
3.
4. CIM based electrical grid model generated
from GIS model
Let’s Focus on Central Parts of Elvis
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
The PowerGrid Data Model in GIS
The objectives / requirements behind the PowerGrid data model are:
 Holds complete and topologically correct documentation of the grid
 Supports asset management in cooperation with 3rd party EAM solution
 Supports extract to CIM for subsequent complex analyses
 Supports life cycles from planning till decommissioning
 Requires a minimum of customization
GIS
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
The Grid is Documented in GIS
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
GIS data supporting business processes
Through integrations GIS data is made available to:
• The Maximo asset management solution
• The PSS®ODMS / PSS®E power system planning and analysis solution
Reversely relevant data from Maximo and the PSS solutions is made available in GIS.
Data is entered once and distributed as needed
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Integrated with the Asset Management System
In Maximo assets are related to locations originating from GIS.
 This allows not only benefitting from the ‘hierarchical’ / relational information from GIS.
 As locations are geometric the asset manager may also search and visualize intuitively /
efficiently using maps.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
The Asset Management System
The Maximo solution handles tasks related to:
 Asset life cycle tracking
 Maintenance planning and documenting
 Work management
 Inventory management
 Procurement management
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Business value as of now – asset management-wise
• Previous Elnet Grid Information System, which has been in use for more than 20 years, has
been replaced by ELVIS
• With better business process support and lots of flexibility it is now
• Easier to calculate the value of the grid
• Possible to make more accurate calculating and assessment of life-cycle costs.
• Easier and quicker to access relevant and updated information for Fingrid personnel –
centrally as well as in the field using mobile devices.
• The consolidated data strategy ensures the high data quality that is the foundation for any
qualified decision making.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Right of Way Management – work order management
Another great example of GIS and Maximo co-existence is with respect to the
Right of Way management.
• Right of Way aims at protecting property (overhead lines)
• Tree trimming has been out-sourced
• The solution eases
– Tendering
– Contract management
– Access to data for external parties
– Tracking the progress of work
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Grid Documentation from GIS used in grid planning
The same GIS data is used for advanced network analyses and grid planning using
PSS®ODMS / PSS®E.
This is enabled using an integration based on the IEC CIM standard as
recommended by ENTSO-E.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Results Visualized in The Map
Visualizing results in a map
reveals patterns / contexts
that often are hard to
deduct from spreadsheets /
KPI’s etc.
These examples of GIS
visualizing results from
network analyses speak for
themselves.
GIS heat maps using PSS analysis results
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Business value as of now – network analysis-wise
• Grid planning and grid optimization in electric transmission always means big expenditures
/ big potential savings.
• The consolidated data strategy and corresponding standard-based integration between GIS
and analysis tools ensures the data required for planning / analysis
• By providing the very high quality of data that is required for analyses, power engineers
may focus their time on actually analyzing rather than providing data.
• By subsequently applying the analysis data in GIS
• Patterns become clear
• Assets exposed to heavy loading may be pinpointed and offered extra attention.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Ensuring a High Data Quality
With GIS responsible for these crucial data,
ensuring high data quality becomes a central concern.
 The recent data migration from various sources led to impressive results.
 The chosen Esri ArcGIS solution holds inherent functionality streamlining the
ongoing processes maintaining the required data quality at the source.
Keeping in mind that
A high data quality is the foundation for any qualified decision making
this is pivotal.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Concluding so far…
With the ELVIS project
Fingrid has established a setup
streamlining crucial business processes related to
asset management and to grid analysis
The success is to a large extent based on a coherent use of data from GIS.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Concluding so far…
At Fingrid spatial information now constitutes key
corporate data that is used by all business functions,
i.e. planning, operation, construction, maintenance,
accounting, etc.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
And there is more to come
Fingrid has plans for further developing the ELVIS solution.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
By bringing real time - and historical data originating from SCADA into ELVIS Fingrid plan on further
streamlining:
• Outage switching planning and execution
• Asset management and fault predicting
• More widespread access to and use of
this essential set of data
Real Time Data / Big Data
Electron CAPE
Relay simulation
Maximo Spatial
SAP
Work Manager
Oracle Primavera
Project Management
IBM Maximo
Asset Management
ESRI ArcGIS
GIS
Siemens PSS®ODMS
Grid modeling
Primavera Adapter
Siemens PSS®E
Grid Calculation
IPS Relex
Relay Management
OSIsoft
PI AF &
ProcessBook
OSIsoft PI
Real-time &
data storage
SCADA
Buzz word alarm
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Summary and Conclusion
• The fundamental electrical grid model is documented in GIS.
GIS
• Integration between GIS and the Maximo asset management solution
ensures
• optimized grid design
• optimized maintenance processes
• data consistency throughout the asset life cycle.
Asset Management
• Integration between GIS and ODMS ensures grid data for electrical design,
analysis and calculation
Network Analysis
Data is entered once and distributed as needed
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Summary and Conclusion
GIS
Maximo
PSS®ODMS PSS®E
IPS CAPEPrimavera
1. Complete grid documentation in one place
2. Integrated with asset and work management
3. Integrated project planning
4. CIM based electrical grid model generated
from GIS model
5. Electrical calculations and analysis
6. Relay management and calculations
Data is entered once and distributed as needed
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Summary and Conclusion
The clue regarding business process optimization
lies in seeing the big picture
and implementing a data sharing strategy.
Behind the Fingrid success lie
a thorough analysis and description of business processes in their entirety
and the subsequent consolidated system architecture being based here upon.
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Any transmission or large distribution company
aiming at optimizing processes across GIS, enterprise asset
management and electrical grid calculation / design
should take a look at the Fingrid ELVIS solution.
Summary and Conclusion
2015
Copyright Powel. Do not use content or parts hereof without written consent by Powel.
Thank You for Your Interest
The new point-of-reference tool
for Electricity Transmission
Asset and Operation
Management
Please feel free to contact us after the session.

More Related Content

What's hot

Google Cloud Platform Tutorial | GCP Fundamentals | Edureka
Google Cloud Platform Tutorial | GCP Fundamentals | EdurekaGoogle Cloud Platform Tutorial | GCP Fundamentals | Edureka
Google Cloud Platform Tutorial | GCP Fundamentals | EdurekaEdureka!
 
Data Mesh Part 4 Monolith to Mesh
Data Mesh Part 4 Monolith to MeshData Mesh Part 4 Monolith to Mesh
Data Mesh Part 4 Monolith to MeshJeffrey T. Pollock
 
Google BigQuery Best Practices
Google BigQuery Best PracticesGoogle BigQuery Best Practices
Google BigQuery Best PracticesMatillion
 
Modernizing to a Cloud Data Architecture
Modernizing to a Cloud Data ArchitectureModernizing to a Cloud Data Architecture
Modernizing to a Cloud Data ArchitectureDatabricks
 
Google Vertex AI
Google Vertex AIGoogle Vertex AI
Google Vertex AIVikasBisoi
 
Five Things to Consider About Data Mesh and Data Governance
Five Things to Consider About Data Mesh and Data GovernanceFive Things to Consider About Data Mesh and Data Governance
Five Things to Consider About Data Mesh and Data GovernanceDATAVERSITY
 
Democratizing Data Quality Through a Centralized Platform
Democratizing Data Quality Through a Centralized PlatformDemocratizing Data Quality Through a Centralized Platform
Democratizing Data Quality Through a Centralized PlatformDatabricks
 
Gartner: Master Data Management Functionality
Gartner: Master Data Management FunctionalityGartner: Master Data Management Functionality
Gartner: Master Data Management FunctionalityGartner
 
What is Object storage ?
What is Object storage ?What is Object storage ?
What is Object storage ?Nabil Kassi
 
Google Anthos - Azure Stack - AWS Outposts :Comparison
Google Anthos - Azure Stack - AWS Outposts :ComparisonGoogle Anthos - Azure Stack - AWS Outposts :Comparison
Google Anthos - Azure Stack - AWS Outposts :ComparisonKrishna-Kumar
 
Agile & Data Modeling – How Can They Work Together?
Agile & Data Modeling – How Can They Work Together?Agile & Data Modeling – How Can They Work Together?
Agile & Data Modeling – How Can They Work Together?DATAVERSITY
 
클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표, 대한항공ERP 재무담당 과장:: AWS Summit...
클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표,  대한항공ERP 재무담당 과장::  AWS Summit...클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표,  대한항공ERP 재무담당 과장::  AWS Summit...
클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표, 대한항공ERP 재무담당 과장:: AWS Summit...Amazon Web Services Korea
 
Data Lakehouse Symposium | Day 4
Data Lakehouse Symposium | Day 4Data Lakehouse Symposium | Day 4
Data Lakehouse Symposium | Day 4Databricks
 
Emerging Trends in Hybrid-Cloud & Multi-Cloud Strategies
Emerging Trends in Hybrid-Cloud & Multi-Cloud StrategiesEmerging Trends in Hybrid-Cloud & Multi-Cloud Strategies
Emerging Trends in Hybrid-Cloud & Multi-Cloud StrategiesChaitanya Atreya
 
Cloud Journey Roadmap: Capgemini's Cloud Readiness Assessment
Cloud Journey Roadmap: Capgemini's Cloud Readiness AssessmentCloud Journey Roadmap: Capgemini's Cloud Readiness Assessment
Cloud Journey Roadmap: Capgemini's Cloud Readiness AssessmentCapgemini
 
FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...
FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...
FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...Amazon Web Services
 
Building a centralized observability platform
Building a centralized observability platformBuilding a centralized observability platform
Building a centralized observability platformElasticsearch
 

What's hot (20)

Google Cloud Platform Tutorial | GCP Fundamentals | Edureka
Google Cloud Platform Tutorial | GCP Fundamentals | EdurekaGoogle Cloud Platform Tutorial | GCP Fundamentals | Edureka
Google Cloud Platform Tutorial | GCP Fundamentals | Edureka
 
Data Mesh Part 4 Monolith to Mesh
Data Mesh Part 4 Monolith to MeshData Mesh Part 4 Monolith to Mesh
Data Mesh Part 4 Monolith to Mesh
 
Tech Mahindra - Connected Engineering
Tech Mahindra - Connected EngineeringTech Mahindra - Connected Engineering
Tech Mahindra - Connected Engineering
 
Google BigQuery Best Practices
Google BigQuery Best PracticesGoogle BigQuery Best Practices
Google BigQuery Best Practices
 
Modernizing to a Cloud Data Architecture
Modernizing to a Cloud Data ArchitectureModernizing to a Cloud Data Architecture
Modernizing to a Cloud Data Architecture
 
FinOps introduction
FinOps introductionFinOps introduction
FinOps introduction
 
Google Vertex AI
Google Vertex AIGoogle Vertex AI
Google Vertex AI
 
Five Things to Consider About Data Mesh and Data Governance
Five Things to Consider About Data Mesh and Data GovernanceFive Things to Consider About Data Mesh and Data Governance
Five Things to Consider About Data Mesh and Data Governance
 
Democratizing Data Quality Through a Centralized Platform
Democratizing Data Quality Through a Centralized PlatformDemocratizing Data Quality Through a Centralized Platform
Democratizing Data Quality Through a Centralized Platform
 
Gartner: Master Data Management Functionality
Gartner: Master Data Management FunctionalityGartner: Master Data Management Functionality
Gartner: Master Data Management Functionality
 
What is Object storage ?
What is Object storage ?What is Object storage ?
What is Object storage ?
 
Google Anthos - Azure Stack - AWS Outposts :Comparison
Google Anthos - Azure Stack - AWS Outposts :ComparisonGoogle Anthos - Azure Stack - AWS Outposts :Comparison
Google Anthos - Azure Stack - AWS Outposts :Comparison
 
Agile & Data Modeling – How Can They Work Together?
Agile & Data Modeling – How Can They Work Together?Agile & Data Modeling – How Can They Work Together?
Agile & Data Modeling – How Can They Work Together?
 
클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표, 대한항공ERP 재무담당 과장:: AWS Summit...
클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표,  대한항공ERP 재무담당 과장::  AWS Summit...클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표,  대한항공ERP 재무담당 과장::  AWS Summit...
클라우드를 활용한 기업 가치 극대화- 방희란 AWS시니어 어카운트 매니저/ 정재표, 대한항공ERP 재무담당 과장:: AWS Summit...
 
Cloud assessment approach
Cloud assessment approachCloud assessment approach
Cloud assessment approach
 
Data Lakehouse Symposium | Day 4
Data Lakehouse Symposium | Day 4Data Lakehouse Symposium | Day 4
Data Lakehouse Symposium | Day 4
 
Emerging Trends in Hybrid-Cloud & Multi-Cloud Strategies
Emerging Trends in Hybrid-Cloud & Multi-Cloud StrategiesEmerging Trends in Hybrid-Cloud & Multi-Cloud Strategies
Emerging Trends in Hybrid-Cloud & Multi-Cloud Strategies
 
Cloud Journey Roadmap: Capgemini's Cloud Readiness Assessment
Cloud Journey Roadmap: Capgemini's Cloud Readiness AssessmentCloud Journey Roadmap: Capgemini's Cloud Readiness Assessment
Cloud Journey Roadmap: Capgemini's Cloud Readiness Assessment
 
FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...
FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...
FinOps: A Culture Transformation to Bring DevOps, Finance and the Business To...
 
Building a centralized observability platform
Building a centralized observability platformBuilding a centralized observability platform
Building a centralized observability platform
 

Viewers also liked

Power markets, Power prices & Data Centers
Power markets, Power prices & Data CentersPower markets, Power prices & Data Centers
Power markets, Power prices & Data CentersRien Dijkstra
 
Refocusing on regional cooperation
Refocusing on regional cooperationRefocusing on regional cooperation
Refocusing on regional cooperationFingrid Oyj
 
Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.
Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.
Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.Fingrid Oyj
 
Fingrid Oyj, Investor Presentation December 2014
Fingrid Oyj, Investor Presentation December 2014Fingrid Oyj, Investor Presentation December 2014
Fingrid Oyj, Investor Presentation December 2014Fingrid Oyj
 
Talven tehotilanne - hiilitiedon seminaari 2016
Talven tehotilanne - hiilitiedon seminaari 2016Talven tehotilanne - hiilitiedon seminaari 2016
Talven tehotilanne - hiilitiedon seminaari 2016Fingrid Oyj
 
Electricity Market Day 2015 - Anne-Marit Rudby, Nasdaq Commodities - How to ...
Electricity Market Day 2015 -  Anne-Marit Rudby, Nasdaq Commodities - How to ...Electricity Market Day 2015 -  Anne-Marit Rudby, Nasdaq Commodities - How to ...
Electricity Market Day 2015 - Anne-Marit Rudby, Nasdaq Commodities - How to ...Fingrid Oyj
 
Smart grids development in india, Team Finland Future Watch Report
Smart grids development in india, Team Finland Future Watch ReportSmart grids development in india, Team Finland Future Watch Report
Smart grids development in india, Team Finland Future Watch ReportTeam Finland Future Watch
 
Singapore Energy Scenerio
Singapore Energy ScenerioSingapore Energy Scenerio
Singapore Energy ScenerioJasbir Arora
 
Innovaatiokulttuuria kehittämässä
Innovaatiokulttuuria kehittämässäInnovaatiokulttuuria kehittämässä
Innovaatiokulttuuria kehittämässäFingrid Oyj
 
A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...
A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...
A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...Fingrid Oyj
 

Viewers also liked (11)

Power markets, Power prices & Data Centers
Power markets, Power prices & Data CentersPower markets, Power prices & Data Centers
Power markets, Power prices & Data Centers
 
Refocusing on regional cooperation
Refocusing on regional cooperationRefocusing on regional cooperation
Refocusing on regional cooperation
 
Fingrid ja yhteiskäyttöinen tieto
Fingrid ja yhteiskäyttöinen tieto Fingrid ja yhteiskäyttöinen tieto
Fingrid ja yhteiskäyttöinen tieto
 
Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.
Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.
Nordic energy management seminar. 10 June 2015, by Jukka Ruusunen.
 
Fingrid Oyj, Investor Presentation December 2014
Fingrid Oyj, Investor Presentation December 2014Fingrid Oyj, Investor Presentation December 2014
Fingrid Oyj, Investor Presentation December 2014
 
Talven tehotilanne - hiilitiedon seminaari 2016
Talven tehotilanne - hiilitiedon seminaari 2016Talven tehotilanne - hiilitiedon seminaari 2016
Talven tehotilanne - hiilitiedon seminaari 2016
 
Electricity Market Day 2015 - Anne-Marit Rudby, Nasdaq Commodities - How to ...
Electricity Market Day 2015 -  Anne-Marit Rudby, Nasdaq Commodities - How to ...Electricity Market Day 2015 -  Anne-Marit Rudby, Nasdaq Commodities - How to ...
Electricity Market Day 2015 - Anne-Marit Rudby, Nasdaq Commodities - How to ...
 
Smart grids development in india, Team Finland Future Watch Report
Smart grids development in india, Team Finland Future Watch ReportSmart grids development in india, Team Finland Future Watch Report
Smart grids development in india, Team Finland Future Watch Report
 
Singapore Energy Scenerio
Singapore Energy ScenerioSingapore Energy Scenerio
Singapore Energy Scenerio
 
Innovaatiokulttuuria kehittämässä
Innovaatiokulttuuria kehittämässäInnovaatiokulttuuria kehittämässä
Innovaatiokulttuuria kehittämässä
 
A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...
A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...
A Nordic vision for 2025, Nordic TSOs Cooperation – more focused and effectiv...
 

Similar to Powel presenting the Fingrid ELVIS solution at IAM Infrastructure Asset Management Exchange 2015

DWS15 - Future networks forum - Virtualisation - Atos -Cedric Carel
DWS15 - Future networks forum - Virtualisation - Atos -Cedric CarelDWS15 - Future networks forum - Virtualisation - Atos -Cedric Carel
DWS15 - Future networks forum - Virtualisation - Atos -Cedric CarelIDATE DigiWorld
 
How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...
How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...
How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...MuleSoft
 
Jens Dalsgaard resume (auto generated from LinkedIn profile)
Jens Dalsgaard resume (auto generated from LinkedIn profile)Jens Dalsgaard resume (auto generated from LinkedIn profile)
Jens Dalsgaard resume (auto generated from LinkedIn profile)Jens Dalsgaard
 
Virtual Property vs. Digital Twin
Virtual Property vs. Digital TwinVirtual Property vs. Digital Twin
Virtual Property vs. Digital TwinTero Järvinen
 
Utilities Digital Data Driven Innovation
Utilities Digital Data Driven Innovation Utilities Digital Data Driven Innovation
Utilities Digital Data Driven Innovation Riccardo Romani
 
Standardized Service Layering for IoT in oneM2M
Standardized Service Layering for IoT in oneM2MStandardized Service Layering for IoT in oneM2M
Standardized Service Layering for IoT in oneM2MNicolas Damour
 
CyberVille® DHC System - May 12th, 2015
CyberVille® DHC System - May 12th, 2015CyberVille® DHC System - May 12th, 2015
CyberVille® DHC System - May 12th, 2015Ville Mickelsson
 
Application Value Assessment
Application Value AssessmentApplication Value Assessment
Application Value AssessmentGerry Appeltants
 
Inet Smart Hospitality Solution
Inet Smart Hospitality SolutionInet Smart Hospitality Solution
Inet Smart Hospitality SolutionFahmi Kausar
 
150601 gartner cloud_summit_vfinal
150601 gartner cloud_summit_vfinal150601 gartner cloud_summit_vfinal
150601 gartner cloud_summit_vfinalMichael Burian
 
5g-rev-a-external-141009084954-conversion-gate02 (1).pptx
5g-rev-a-external-141009084954-conversion-gate02 (1).pptx5g-rev-a-external-141009084954-conversion-gate02 (1).pptx
5g-rev-a-external-141009084954-conversion-gate02 (1).pptxAnEarthling
 
Wed Sponsor Press Conf - 10.15
Wed Sponsor Press Conf - 10.15Wed Sponsor Press Conf - 10.15
Wed Sponsor Press Conf - 10.15Bessie Wang
 
European Utility Week 2015: OMNETRIC Group Overview
European Utility Week 2015: OMNETRIC Group Overview European Utility Week 2015: OMNETRIC Group Overview
European Utility Week 2015: OMNETRIC Group Overview OMNETRIC
 
RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...
RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...
RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...IRJET Journal
 
Infozech tower xchange-africa-dossier-2015
Infozech tower xchange-africa-dossier-2015Infozech tower xchange-africa-dossier-2015
Infozech tower xchange-africa-dossier-2015Vishal Gajjar
 
Company Profile Setel_Eng
Company Profile Setel_EngCompany Profile Setel_Eng
Company Profile Setel_EngGiuseppe Frullo
 
HP Iot platform and solution plans
HP Iot platform and solution plansHP Iot platform and solution plans
HP Iot platform and solution plansJeff Edlund
 
Engineering Enablement for Connected and Intelligent Systems
Engineering Enablement for Connected and Intelligent SystemsEngineering Enablement for Connected and Intelligent Systems
Engineering Enablement for Connected and Intelligent SystemsCyient
 
Patterns for Monetizing the IoT
Patterns for Monetizing the IoTPatterns for Monetizing the IoT
Patterns for Monetizing the IoTFlexera
 

Similar to Powel presenting the Fingrid ELVIS solution at IAM Infrastructure Asset Management Exchange 2015 (20)

DWS15 - Future networks forum - Virtualisation - Atos -Cedric Carel
DWS15 - Future networks forum - Virtualisation - Atos -Cedric CarelDWS15 - Future networks forum - Virtualisation - Atos -Cedric Carel
DWS15 - Future networks forum - Virtualisation - Atos -Cedric Carel
 
How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...
How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...
How a Leading Brand Achieved Digital Transformation at a Global Scale - Jeff ...
 
Jens Dalsgaard resume (auto generated from LinkedIn profile)
Jens Dalsgaard resume (auto generated from LinkedIn profile)Jens Dalsgaard resume (auto generated from LinkedIn profile)
Jens Dalsgaard resume (auto generated from LinkedIn profile)
 
Virtual Property vs. Digital Twin
Virtual Property vs. Digital TwinVirtual Property vs. Digital Twin
Virtual Property vs. Digital Twin
 
Utilities Digital Data Driven Innovation
Utilities Digital Data Driven Innovation Utilities Digital Data Driven Innovation
Utilities Digital Data Driven Innovation
 
Standardized Service Layering for IoT in oneM2M
Standardized Service Layering for IoT in oneM2MStandardized Service Layering for IoT in oneM2M
Standardized Service Layering for IoT in oneM2M
 
CyberVille® DHC System - May 12th, 2015
CyberVille® DHC System - May 12th, 2015CyberVille® DHC System - May 12th, 2015
CyberVille® DHC System - May 12th, 2015
 
Application Value Assessment
Application Value AssessmentApplication Value Assessment
Application Value Assessment
 
Inet Smart Hospitality Solution
Inet Smart Hospitality SolutionInet Smart Hospitality Solution
Inet Smart Hospitality Solution
 
150601 gartner cloud_summit_vfinal
150601 gartner cloud_summit_vfinal150601 gartner cloud_summit_vfinal
150601 gartner cloud_summit_vfinal
 
5g-rev-a-external-141009084954-conversion-gate02 (1).pptx
5g-rev-a-external-141009084954-conversion-gate02 (1).pptx5g-rev-a-external-141009084954-conversion-gate02 (1).pptx
5g-rev-a-external-141009084954-conversion-gate02 (1).pptx
 
Wed Sponsor Press Conf - 10.15
Wed Sponsor Press Conf - 10.15Wed Sponsor Press Conf - 10.15
Wed Sponsor Press Conf - 10.15
 
European Utility Week 2015: OMNETRIC Group Overview
European Utility Week 2015: OMNETRIC Group Overview European Utility Week 2015: OMNETRIC Group Overview
European Utility Week 2015: OMNETRIC Group Overview
 
RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...
RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...
RICE INDUSTRY AUTOMATION TECHNIQUE USING IoT WITH RASPBERRY PI AND PHYTON LAN...
 
SP 5G: Unified Enablement Platform
SP 5G: Unified Enablement Platform  SP 5G: Unified Enablement Platform
SP 5G: Unified Enablement Platform
 
Infozech tower xchange-africa-dossier-2015
Infozech tower xchange-africa-dossier-2015Infozech tower xchange-africa-dossier-2015
Infozech tower xchange-africa-dossier-2015
 
Company Profile Setel_Eng
Company Profile Setel_EngCompany Profile Setel_Eng
Company Profile Setel_Eng
 
HP Iot platform and solution plans
HP Iot platform and solution plansHP Iot platform and solution plans
HP Iot platform and solution plans
 
Engineering Enablement for Connected and Intelligent Systems
Engineering Enablement for Connected and Intelligent SystemsEngineering Enablement for Connected and Intelligent Systems
Engineering Enablement for Connected and Intelligent Systems
 
Patterns for Monetizing the IoT
Patterns for Monetizing the IoTPatterns for Monetizing the IoT
Patterns for Monetizing the IoT
 

Recently uploaded

My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Baileyhlharris
 
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfSOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfMahamudul Hasan
 
Digital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalDigital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalFabian de Rijk
 
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfThe workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfSenaatti-kiinteistöt
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaKayode Fayemi
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatmentnswingard
 
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfAWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfSkillCertProExams
 
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...amilabibi1
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoKayode Fayemi
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar TrainingKylaCullinane
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lodhisaajjda
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxraffaeleoman
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...David Celestin
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIINhPhngng3
 

Recently uploaded (15)

My Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle BaileyMy Presentation "In Your Hands" by Halle Bailey
My Presentation "In Your Hands" by Halle Bailey
 
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdfSOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
SOLID WASTE MANAGEMENT SYSTEM OF FENI PAURASHAVA, BANGLADESH.pdf
 
Digital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of DrupalDigital collaboration with Microsoft 365 as extension of Drupal
Digital collaboration with Microsoft 365 as extension of Drupal
 
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdfThe workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
The workplace ecosystem of the future 24.4.2024 Fabritius_share ii.pdf
 
If this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New NigeriaIf this Giant Must Walk: A Manifesto for a New Nigeria
If this Giant Must Walk: A Manifesto for a New Nigeria
 
Dreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video TreatmentDreaming Marissa Sánchez Music Video Treatment
Dreaming Marissa Sánchez Music Video Treatment
 
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdfAWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
AWS Data Engineer Associate (DEA-C01) Exam Dumps 2024.pdf
 
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
Bring back lost lover in USA, Canada ,Uk ,Australia ,London Lost Love Spell C...
 
Uncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac FolorunsoUncommon Grace The Autobiography of Isaac Folorunso
Uncommon Grace The Autobiography of Isaac Folorunso
 
Report Writing Webinar Training
Report Writing Webinar TrainingReport Writing Webinar Training
Report Writing Webinar Training
 
ICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdfICT role in 21st century education and it's challenges.pdf
ICT role in 21st century education and it's challenges.pdf
 
lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.lONG QUESTION ANSWER PAKISTAN STUDIES10.
lONG QUESTION ANSWER PAKISTAN STUDIES10.
 
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptxChiulli_Aurora_Oman_Raffaele_Beowulf.pptx
Chiulli_Aurora_Oman_Raffaele_Beowulf.pptx
 
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
Proofreading- Basics to Artificial Intelligence Integration - Presentation:Sl...
 
Dreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio IIIDreaming Music Video Treatment _ Project & Portfolio III
Dreaming Music Video Treatment _ Project & Portfolio III
 

Powel presenting the Fingrid ELVIS solution at IAM Infrastructure Asset Management Exchange 2015

  • 1. The new point-of-reference tool for Electricity Transmission Asset and Operation Management
  • 2. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Marcus Stenstrand Program Manager for Fingrid 's Elvis project Jens Dalsgaard Principal Business process Consultant & SME in Electric Utility and GIS Presenting the Presenters Marcus has a vast experience that is based on various responsibilities from manager positions in maintenance and asset management, in addition with business and strategy development at Fingrid. Been active in bringing in new methods of working and operating such us knowledge and performance management with service providers. Worked with international benchmarking for several years and worked on the PAS55 adaption team at Fingrid and the Finnish ISO55000 review committee. http://fi.linkedin.com/in/stenstrand/en In the ELVIS project Jens Dalsgaard has been responsible for planning, leading and documenting clarification workshops, data modelling and data migration, and the close cooperation with Fingrid and IBM gave invaluable insight into business processes throughout the life cycle of grid operation and asset management. https://www.linkedin.com/in/jensdalsgaard
  • 3. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Power Transmission Network The main electricity transmission network, to which major power plants, factories and regional distribution networks are mainly linked. Also connects Finland to international electricity markets.
  • 4. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. The main grid in numbers 113 substations 14 400 km of power lines 300 km of submarine cable 48 000 towers 10 reserve power plants > 935 MW reserve
  • 5. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Fingrid 's tariff is among the lowest in Europe Norway Finland Belgium Denmark Czech Republic Ireland Slovakia €/MWh Source: Entso-E The comparison includes European main grid companies with responsibility for 110 kV and 400 kV electricity grids. Great Britain
  • 6. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. We make sure that Finland obtains electricity without disturbances There are 525,600 minutes in a year. *The average duration of transmission disturbances for Fingrid main grid customers is 3 minutes per year. 3 min*
  • 7. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Fingrid According to international benchmarks, cost effectiveness and grid reliability are among the best in the industry. One of the world's best electricity companies since 1995.
  • 8. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. 1988 First Computerized maintenance management system (CMMS) application (in- house, called KUNTO) into use, data collected by paper form in-hand 1992 First Enterprise Asset Mgmt system (EAM) into use (fully integrated between applications. In-house, called ELNET), UNIX based ○ Asset register ○ CMMS with Condition prediction models and work package mgmt ○ Mobile handhelds for inspection results ○ GIS ○ Relay settings, out- age mgmt, grid calc. 1997-1999 ELNET user interface updated from UNIX to Windows 2002 FgPartners Extranet for Service Providers where all asset related data available (Citrix), same tools and data for Fingrid and service providers 2001 Project Portfolio and project mgmt tool introduced (Artemis CmPro) 2003 Paperless office reached 100 %, last drawings and technical documents scanned into DMS (Bentley ProjectWise) 2006 Work order follow - up and cost supervision tool introduced (in-house, called TOSU) 2005 Buisness Intelligence (BI) tools introduced for combining financial data with asset data (IBM Cognos). Performance mgmt dashboards introduced for all roles 2005 Time series database for history data from SCADA (OSIsoft PI) 2012 Condition history and on-line monitoring plus asset health indices (OSIsoft ProcessBook) 2013 ELVIS part 1: Substation asset register and maintenencae (Maximo) plus ProjectPortfolio update (Primavera) ELVIS part 2 & 3. The next step 2007 First on-line condition monitoring meters in to use (in- house) History lane for Asset mgmt support tools at Fingrid Knowledge Management has been of high importance in strategy for decades
  • 9. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Fingrid's next generation Asset Management solution ELectricity Verkko (Finnish word for Grid) Information System • Solution planning started in 2008 • Project kick-off in 2012 • Final parts in to be deployed in 2015 • Solution provider IBM, ESRI, Informi GIS, Siemens, IPS, Electrocon, Project Institute Finland,
  • 10. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. ELVIS main goals Increasing operative efficiency, lowering risk and improving decision making Process Digitization Big Data Master Data • Next generation streamlining of asset management processes • 2nd generation performance dashboards • Integrating all business data • Combining asset mgmt data with IoT generated data • Enabling industry wide data analytics • Single source for power system information → One version of the truth • Data entered only ONCE into ONE system, other systems uses this data ELVIS is part of Asset Mgmt strategy, not part of IT
  • 11. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Asset Management and Grid Optimization A high data quality is the foundation for any qualified decision making. Fingrid has established a coherent setup establishing / guaranteeing the data needed in asset management, in grid optimization, as well as in many other business processes.
  • 12. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Two Fundamental Architectural Strategies Data should be entered once and distributed as needed Standard software products should be used with a minimum of customization required.
  • 13. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. An Overview of the ELVIS Solution GIS Maximo PSS®ODMS PSS®E IPS CAPEPrimavera 1. Complete grid documentation in one place 2. Integrated with asset and work management 3. Integrated project planning 4. CIM based electrical grid model generated from GIS model 5. Electrical calculations and analysis 6. Relay management and calculations Standard Software Packages
  • 14. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. GIS Maximo PSS®ODMS 1. Complete grid documentation in one place 2. Integrated with asset and work management 3. 4. CIM based electrical grid model generated from GIS model Let’s Focus on Central Parts of Elvis
  • 15. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. The PowerGrid Data Model in GIS The objectives / requirements behind the PowerGrid data model are:  Holds complete and topologically correct documentation of the grid  Supports asset management in cooperation with 3rd party EAM solution  Supports extract to CIM for subsequent complex analyses  Supports life cycles from planning till decommissioning  Requires a minimum of customization GIS
  • 16. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. The Grid is Documented in GIS
  • 17. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. GIS data supporting business processes Through integrations GIS data is made available to: • The Maximo asset management solution • The PSS®ODMS / PSS®E power system planning and analysis solution Reversely relevant data from Maximo and the PSS solutions is made available in GIS. Data is entered once and distributed as needed
  • 18. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Integrated with the Asset Management System In Maximo assets are related to locations originating from GIS.  This allows not only benefitting from the ‘hierarchical’ / relational information from GIS.  As locations are geometric the asset manager may also search and visualize intuitively / efficiently using maps.
  • 19. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. The Asset Management System The Maximo solution handles tasks related to:  Asset life cycle tracking  Maintenance planning and documenting  Work management  Inventory management  Procurement management
  • 20. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Business value as of now – asset management-wise • Previous Elnet Grid Information System, which has been in use for more than 20 years, has been replaced by ELVIS • With better business process support and lots of flexibility it is now • Easier to calculate the value of the grid • Possible to make more accurate calculating and assessment of life-cycle costs. • Easier and quicker to access relevant and updated information for Fingrid personnel – centrally as well as in the field using mobile devices. • The consolidated data strategy ensures the high data quality that is the foundation for any qualified decision making.
  • 21. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Right of Way Management – work order management Another great example of GIS and Maximo co-existence is with respect to the Right of Way management. • Right of Way aims at protecting property (overhead lines) • Tree trimming has been out-sourced • The solution eases – Tendering – Contract management – Access to data for external parties – Tracking the progress of work
  • 22. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Grid Documentation from GIS used in grid planning The same GIS data is used for advanced network analyses and grid planning using PSS®ODMS / PSS®E. This is enabled using an integration based on the IEC CIM standard as recommended by ENTSO-E.
  • 23. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Results Visualized in The Map Visualizing results in a map reveals patterns / contexts that often are hard to deduct from spreadsheets / KPI’s etc. These examples of GIS visualizing results from network analyses speak for themselves. GIS heat maps using PSS analysis results
  • 24. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Business value as of now – network analysis-wise • Grid planning and grid optimization in electric transmission always means big expenditures / big potential savings. • The consolidated data strategy and corresponding standard-based integration between GIS and analysis tools ensures the data required for planning / analysis • By providing the very high quality of data that is required for analyses, power engineers may focus their time on actually analyzing rather than providing data. • By subsequently applying the analysis data in GIS • Patterns become clear • Assets exposed to heavy loading may be pinpointed and offered extra attention.
  • 25. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Ensuring a High Data Quality With GIS responsible for these crucial data, ensuring high data quality becomes a central concern.  The recent data migration from various sources led to impressive results.  The chosen Esri ArcGIS solution holds inherent functionality streamlining the ongoing processes maintaining the required data quality at the source. Keeping in mind that A high data quality is the foundation for any qualified decision making this is pivotal.
  • 26. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Concluding so far… With the ELVIS project Fingrid has established a setup streamlining crucial business processes related to asset management and to grid analysis The success is to a large extent based on a coherent use of data from GIS.
  • 27. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Concluding so far… At Fingrid spatial information now constitutes key corporate data that is used by all business functions, i.e. planning, operation, construction, maintenance, accounting, etc.
  • 28. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. And there is more to come Fingrid has plans for further developing the ELVIS solution.
  • 29. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. By bringing real time - and historical data originating from SCADA into ELVIS Fingrid plan on further streamlining: • Outage switching planning and execution • Asset management and fault predicting • More widespread access to and use of this essential set of data Real Time Data / Big Data Electron CAPE Relay simulation Maximo Spatial SAP Work Manager Oracle Primavera Project Management IBM Maximo Asset Management ESRI ArcGIS GIS Siemens PSS®ODMS Grid modeling Primavera Adapter Siemens PSS®E Grid Calculation IPS Relex Relay Management OSIsoft PI AF & ProcessBook OSIsoft PI Real-time & data storage SCADA Buzz word alarm
  • 30. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Summary and Conclusion • The fundamental electrical grid model is documented in GIS. GIS • Integration between GIS and the Maximo asset management solution ensures • optimized grid design • optimized maintenance processes • data consistency throughout the asset life cycle. Asset Management • Integration between GIS and ODMS ensures grid data for electrical design, analysis and calculation Network Analysis Data is entered once and distributed as needed
  • 31. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Summary and Conclusion GIS Maximo PSS®ODMS PSS®E IPS CAPEPrimavera 1. Complete grid documentation in one place 2. Integrated with asset and work management 3. Integrated project planning 4. CIM based electrical grid model generated from GIS model 5. Electrical calculations and analysis 6. Relay management and calculations Data is entered once and distributed as needed
  • 32. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Summary and Conclusion The clue regarding business process optimization lies in seeing the big picture and implementing a data sharing strategy. Behind the Fingrid success lie a thorough analysis and description of business processes in their entirety and the subsequent consolidated system architecture being based here upon.
  • 33. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Any transmission or large distribution company aiming at optimizing processes across GIS, enterprise asset management and electrical grid calculation / design should take a look at the Fingrid ELVIS solution. Summary and Conclusion
  • 34. 2015 Copyright Powel. Do not use content or parts hereof without written consent by Powel. Thank You for Your Interest The new point-of-reference tool for Electricity Transmission Asset and Operation Management Please feel free to contact us after the session.

Editor's Notes

  1. I believe we may all agree that a high data quality is the foundation for any qualified decision making. But often data is considered from a siloed approach. We meet lots of skilled people out there, but they’re typically focused on their own specific domain and need for data. This tends to lead to a situation where different departments work secluded from each other data wise. Fingrid took a bird’s-eye look at business processes and data needed, and documented the resulting picture in close to one thousand requirements. The solution acquired complies with these requirement and Fingrid has established a coherent setup establishing / guaranteeing the data needed in asset management, in grid optimization, as well as in many other business processes.  
  2. The solution is established based on two fundamental architectural strategies We already discussed the coherent use of data. Establishing a solution based on standard software products and a minimum of customization minimizes risks during implementation as well as in subsequent operation / upgrading / … Honestly – anyone is able to say: We can develop that… At Fingrid we did it.
  3. But let’s zoom in and focus on GIS as one of the crucial components It is GIS the grid is documented And made available to the asset management solution As well as extracted in standard format for use in grid planning and grid operation  
  4. Acquiring the data needed to support business processes must be based on the right data model ArcGIS allows anyone to create data models, and there are thus many data models out there. The Powel PowerGrid data model was implemented at Fingrid
  5. Example from Fingrid – an advanced 400 / 110 / 21 /0,4 kV substation Connected to overhead lines Advanced neutral network documentation This substation and the entire Fingrid grid is the starting point based on data migration.
  6. The real gain / value lies in the architectural decision that data should be entered once and distributed as needed Through integration the data in GIS is made available throughout the ELVIS solution And – as you’ll see later – data from other parts of ELVIS is made available in GIS
  7. Fingrid has myriads of assets throughout Finland. In order to locate the right asset these are related to locations ordered hierarchically. This location / hierarchy is documented in GIS from where it’s made available to Maximo. Besides saving the asset management team from lots of work it ensures validated data quality. Besides it eases validation that no assets have been omitted / forgotten Besides – the geometric dimension offers users intuitive ways of locating / accessing assets and detecting patterns
  8. The geometric dimension plays a natural role in asset management Especially with respect to: Maintenance planning Work management
  9. So what are some of the immediate business values in the Fingrid setup with respect to asset management Replacing outdated solution architecture with this new ELVIS solution ensures support of a very high number of requirements improved flexibility and ways of extending use thus allowing Fingrid to continuously improve performance It safeguards the very high data quality needed in decision making
  10. Another essential – and costly – business process is Right of Way management. In the Fingrid case naturally focused on tree trimming in order to protect assets and prevent outages. (But it might also relate to parcel owner negotiating.) Streamlining outsourcing and field crew access / feedback minimizes manual work. Potentially refining tree trimming needs holds potential for minimizing quite big costs. Approximately 11 000 kilometers of forest land under Fingrid transmission lines (this is about 76 % from Fingrid overhead lines). Satellite image analysis Drone surveying
  11. Another important use of GIS data is in the grid planning tools and grid operation optimization Through integration the entire grid has been made available for advanced analyses.
  12. Analysis results are available in GIS I believe these examples speak for themselves. In a world of overwhelming amounts of data solutions revealing patterns and extracting the decisive information may make the difference between having information and obtaining knowledge.
  13. And again the business value is evident By providing the very high data quality allowing analyses throughout the grid, Fingrid specialists may focus on their main competence rather than working with providing data May perform analyses throughout the grid foreseeing issues and analyzing potential mitigations / actions And why not go even further using the analyses results in asset management?
  14. Above we had a glimpse of the Fingrid ELVIS solution and the coherent and consolidated use of data. A setup in which ArcGIS and the PowerGrid data model holds a crucial role It is therefore pivotal that ArcGIS holds comprehensive functionality streamlining the ongoing establishing and upholding a high data quality. Bad data costs money
  15. !
  16. !
  17. And with the ELVIS setup there’s more to come. Fingrid has established a setup allowing them to further develop and optimize business processes
  18. One way to do so, is by utilizing more data Real time data / big data Still just scratching the surface with respect to potential benefits this may offer business value in More streamlined handling of outage planning and execution Fault predicting and asset management Preventing one crash in a transmission system means lots of saved expenses …
  19. Summarizing Data is entered once and distributed as needed ArcGIS holds a crucial role
  20. Or – as we started out: with the complete solution architecture
  21. Behind the Fingrid success lie a thorough analysis and description of business processes in their entirety a subsequent consolidated system architecture being based here upon.
  22. Having worked with electric utilities and IT solutions for more than 20 years I would truly encourage any electric transmission or large distribution company to take a close look at the approach and the solution established at Fingrid
  23. I fully agree with Fingrid in stating that ELVIS is The new point-of-reference tool for Electricity Transmission Asset and Operation Management