SlideShare a Scribd company logo
1 of 55
FORT WASHINGTON WAY
2000
A project managed by the City of Cincinnati
with the cooperation of thousands
1956 1998 2000
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
Project Management Team:
John Deatrick, P.E., AICP,
Dire cto r o f Transpo rtatio n
Bob Richardson, AIA,
City Archite ct
Don Gindling, P.E.,
Co nstructio n Manag e r
Project Management Consultant:
Fred Craig, PE
Are a Manag e r, Se nio r Vice Pre side nt
Parso ns Brincke rho ff
Project Team:
• Parsons Brinckerhoff Project Management
Consultants
• Contributing PB Offices: Cincinnati,
Baltimore, Boston, San Francisco, Miami,
Tampa, Las Vegas, Denver and Louisville
O the r Te am Me m be rs:
•JMA Consultants
•KZF Incorporated
•Resource International
•TEC Engineers
•U.S. Cost, Inc.
•Vivian Llambi & Associates
•Wallace Floyd Associates
•Wilson & Associates
•Balke Engineers
•BRW
•Burgess & Niple
•Chan Krieger & Associates
•Dan Pinger Public Relations
•H. C. Nutting Company
•Hargreaves Associates
•Infrastructure Servcies
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT TIMELINE
November 1995
City of Cincinnati requests the Ohio-Kentucky-
Indiana Regional Council of Governments
(OKI) to conduct a sub-corridor analysis for
Fort Washington Way
January 1996
OKI begins Fort Washington Way sub-
corridor analysis
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT TIMELINE (continued)
January 1997
OKI produces plan for reconstructing
Fort Washington Way as a locally
preferred alternative to address traffic
congestion along Fort Washington Way
May 1997
Members of the Fort Washington Way
project team meet to plan cooperative
effort for accomplishing the work.
Public meetings are held to obtain input
on the plan
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT TIMELINE (continued)
July 1997
Project team presents Fort Washington Way
reconstruction plan during a public forum at
Cincinnati City Hall
September 1997
First formal design contracts let
October 1997
State of Ohio approves the FWW Major
Investment Study and commits $80 million in
project funding
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT TIMELINE (continued)
October 15, 1997
City Council approves total funding package
November 1997
Ohio Governor George Voinovich visits
Cincinnati to announce a $20 million funding
advance for the Fort Washington Way project
January 1998
Fort Washington Way Project Design Manual
drafted
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT TIMELINE (continued)
April 1998
Value Engineering Workshops held
July 1998
Fort Washington Way reconstruction
begins with the first construction
contract let on July 2
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT TIMELINE (continued)
August 1998
Fort Washington Washington detour
constructed; all traffic shifted to old
eastbound lanes
October 1999
First section of new Fort Washington
Way open and traffic shifted to future
westbound lanes
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT TIMELINE (continued)
August 2000
Fort Washington Way completed and
open to traffic
December 2000
Fort Washington Way dedication
ceremony
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT PARTNERS:
Metro
City of Cincinnati
Hamilton County
Ohio Department of
Transportation
Kentucky Transportation Cabinet
Federal Highway Administration
Ohio-Kentucky-Indiana Regional
Council of Governments
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT GOALS
• Provide safer through and local
network roadway for motorists and
pedestrians
• Improve local and regional access
and re-connect downtown with
riverfront
• Provide economic development
opportunities by reclaiming
highway rights of way
TOTAL COST: $328 MILLION
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
BROADCOMMUNITY SUPPORT
• Team of communications
professionals developed a
strategic communications plan
with a comprehensive package of
communications tools
• Community support arose from
the public’s involvement in the
decision to do the work as quickly
as possible
• Emphasized message that the
benefits were worth the wait
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
SUPPORT FROMCOMMUNITY
ORGANIZATIONS
• The Greater Cincinnati Convention
and Visitors Bureau
• The Northern Kentucky Convention
and Visitors Bureau
• The City of Newport, Kentucky
• The City of Covington, Kentucky
• Chamber of Commerce
• The Reds and Bengals
• Cincinnati Business Committee
• Transit Authority of Northern Kentucky
(TANK)
• Building Owners and Managers
Association
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT COMPONENTS
• Reconfiguration of mainline
• Construction of 27 new
bridges
• Creation of new landscape
boulevard by construction of
second street and
reconstruction of Third
Street
• Reconstruction of Third
Street Viaduct
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT COMPONENTS
(continued)
• Relocation of floodwall
• Construction of new
riverfront transit center
• Installation of combined
sewer overflow mitigation
system
• Installation of foundations
for future decks
• Fiber optic backbone
FWW Project Facts
• Nearly 230 presentations given to downtown
businesses, organizations and parkers to update
them on traffic pattern changes
• 500 different highway signs placed in more than 300
locations throughout Cincinnati
• Nearly 70,000 detour maps distributed to area
businesses, organizations and parking garages to
update visitors and commuters of traffic pattern
changes
• Approximately three million pounds of structural
steel from bridges and roadways removed and
recycled for use in other construction projects
• 4.1 million lbs. of structural steel placed at the Fort
Washington Way project, which is 20 times the
weight of the Statue of Liberty in New York
• 24,402 cubic yards of concrete placed
• Nearly 130,000 cubic yards of earth moved in
preparation for the new Fort Washington Way
• Piles driven a total of approximately 655,000 feet
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
DEFINING FEATURES
• Detailed Maintenance of
Access Plan agreed during
the environmental document
• Access maintained through
phased and staged fast
tracked construction, and
with detailed manuals guiding
all aspects of project
• Project management
structure with unique
blending of City of Cincinnati
staff with consultant teams
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
DEFININGFEATURES (continued)
• Innovative materials including stone
mastic asphalt driving surface
• Bi-state funding accord
• Accelerated time frame
• Heavy emphasis on urban design and
landscaping
• Innovative bridge types
• Well financed citizen involvement group
• Constructability and value
engineering reviews
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
THE TRENCH
• Narrowed
mainline area,
but now with
through lane
continuity to
reduce weaving
and merging
and improved
capacity
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
NEWBOULEVARD
•Providing improved access
and new front door for city
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
THE THIRDSTREET
VIADUCT- CONNECTION TO
US 50 ON THE EAST
• Provides dramatically
improved traffic capacity to
the East
• First use of steel box girder
construction in Ohio
• New substructure
constructed under old bridge,
retaining access
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
NEWFWWFLOODWALL
• Provides flood protection
for new project while
freeing 14 acres of land
for future development
by eliminating earthen
levee
• Below grade pump
house for highway trench
storm water during
extreme river flood
conditions
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
RIVERFRONT
TRANSIT CENTER
• Grade separated transit and
pedestrian access for major
riverfront events
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
COMBINEDSEWEROVERFLOWSYSTEM
• New water pollution mitigation system
• Measurable improvements to Ohio River
water quality by reducing overflows to near
zero
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
FOUNDATION PILES FOR
FUTURE DECKS
• Allows for the future
placement of parks or other
public spaces over
highway facility
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
FOSTEREDREDEVELOPMENT OF
TWOVACANT WAREHOUSES
FORT WASHINGTON WAY 2000
Pro je ct O ve rvie w
PROJECT
COORDINATION
• Typical example
illustrates City contracts
for new Second Street
(Contract 22a) and the
Elm Street Bridge over
the FWW trench
(Contracts 8 and 17d),
and Hamilton County
contracts for the Bengals
stadium and new Elm
Street
FORT WASHINGTON WAY 2000
Urban De sig n
PROJECT DESIGN MANUAL
• Examined urban design in
each aspect of the project
• Produced in conjunction with
overall civil engineering
design manual
• Controlled the overall project
aesthetics
• Captured best value for
dollars spent
FORT WASHINGTON WAY 2000
Urban De sig n
Linked the riverfront to downtown by
extending the street grid overthe highway.
FORT WASHINGTON WAY 2000
Urban De sig n
HIGHQUALITY ANDVALUE-
MAXIMUMIMPACT
• Custom made pre-cast panels
• Unique lighting using standard
fixtures
• Decorative vandal screens
• Multi-colored bridge beams
FORT WASHINGTON WAY 2000
De sig n and Co nstructio n
ENVIRONMENTAL
DOCUMENTATION FWW
CATEGORICAL EXCLUSION
• Document approved in record time
• Model for the Federal Highway
Administration for highway reconfiguration
• Concurrent approval by ODOT and the
state historical preservation office
• ODOT & SHPO approved on-site
archeologist as appropriate mitigation
considering site characteristics and
construction methodology
• Accelerated OEPA review process
FORT WASHINGTON WAY 2000
De sig n and Co nstructio n
THE FWWPROJECT:
• 31 design contracts
• 27 construction contracts
• Work broken down
to fast-track design and
construction and
encourage smaller
contractors and
minorities to bid
• Phasing and fast-track
allowed quick response to
changing regional priorities
FORT WASHINGTON WAY 2000
De sig n and Co nstructio n
IN PREPARATION FOR
CONSTRUCTION
• Early implementation of
comprehensive vehicular and
pedestrian way-finding signage
system
• Construction of temporary exit ramps
to provide alternate access to
downtown
• Construction of temporary bridge to
maintain access to Kentucky
FORT WASHINGTON WAY 2000
De sig n and Co nstructio n
IN PREPARATION FOR
CONSTRUCTION (continued)
• Adaptation of new temporary street
on then existing flood levee
• Revitalization of existing groups to
insure strong communication
networks
• Establishment of web site and list-
service
FORT WASHINGTON WAY 2000
De sig n and Co nstructio n
IN PREPARATION FOR
CONSTRUCTION (continued)
• Constructed two new temporary
off ramps to serve the CBD
(central business district), one
from I-75 North and one from I-71
South to replace access provided
by FWW
• Re-striped two other exit ramps to
add lanes
FORT WASHINGTON WAY 2000
Inno vative Bridg e Type s
Firsts in Ohio:
• Steel Box Girder
• Cast-in-Place Box Girder
• Concrete Integral Piers
FORT WASHINGTON WAY 2000
Inno vative Bridg e Type s
27 Bridges Built In 42 Stages
• 4 Steel Rolled Beam
• 16 Steel Curved Plate Girder
• 5 Steel Box Girder
• 7 Cast-in-Place Post-Tensioned
Concrete Slab
• 3 Cast-in-Place Post-Tensioned
Concrete Box Girder
• 1 Pre-Stressed Concrete “I” girder
• 2 Pre-Stressed Concrete Adjacent
Box Beams
• 4 Cable-Stay Pedestrian Bridges
Innovative staged construction
techniques used to maintain traffic
while building bridges
FORT WASHINGTON WAY 2000
Inno vative Bridg e Type s
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
PROCUREMENT MANUAL
• Assembled a manual of procedures
combining federal, state and local
requirements
• Established expedited pre-
qualification process including MBE,
WBE, DBE, SBE vendors, as the
laws changed during the project
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
PROCUREMENT MANUAL
(continued)
• All contracts locally advertised and
bid by City using ODOT procedures
• Established a contract compliance
officer on the job site
• Maintain pace of construction during
law suite on MBE regulations and
provided basis of consent decree
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
AGGRESSIVE OUTREACHTOPOTENTIAL
BIDDERS ANDSUBCONTRACTORS
• Contractors encouraged to use minority
contractors, pre-approved sub-consultants
and suppliers
• Early notification to contractors of
upcoming bids, including postings on the
FWW Web site and pre-bid seminars
• Established a comprehensive data base of
vendors to assist bidders
• MBE/WBE/DBE/SBE workshops held to
encourage participation
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
THE BIDDING PROCESS
• Bid dates posted on the project Web
site
• Bids advertised in local newspapers,
ODOT and city of Cincinnati bulletins
• Bid many items lump sum to simplify
bid and award process
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
THE BIDDING PROCESS
(continued)
• Answers for pre-bid questions
available through e-mail
• Contracts went from bid to award in
one week or less
• OCIP (owner controlled insurance
program) reduced bickering over
damage and field claims
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
COST/CONTROL PROCEDURES
• Value engineering workshop
sponsored by ODOT reviewed entire
project design and finalized civil and
urban design manuals
• Pre-approved design manuals
simplified preparation of plans and
specifications
• Preliminary constructability reviews
by consultant, city, and state team
reduced construction costs and
enabled phased construction
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
COST/CONTROL PROCEDURES
(continued)
• Contingency amounts added to
contracts to enable field decisions to
minor problems and focus on cost
containment
• Innovative change order approval
process using monthly FWW
Construction Board to provide
oversight and hear claims
FORT WASHINGTON WAY 2000
Bidding and Co nstructio n Manag e m e nt
MEETING THE SCHEDULE
• Conventionally bid construction
contracts with liquidated damages
• No incentives
• Master schedule and traffic
management defined early and
included in project manuals bid
documents
FORT WASHINGTON WAY 2000
Public Invo lve m e nt
COMPREHENSIVE
OUTREACH
• Established graphics
standards for all materials
• Revitalized existing regional
coordination committees
• “Connection to the Future”
newsletter distributed to
project stakeholdershttp://www.fww2000.com/
FORT WASHINGTON WAY 2000
Public Invo lve m e nt
Outreach (continued)
• Over 200 meetings held prior
to start of construction to
establish dialogue
• More than 400 community
meetings held throughout
project construction to
maintain contact
• Distributed more than
200,000 motorist and
pedestrian detour maps
FORT WASHINGTON WAY 2000
Public Invo lve m e nt
OUTREACH(continued)
• Regular events to mark significant
project milestones and maintain
media contact
• Regularly scheduled meetings with
community support groups
• Suggestions and comments taken
through telephone, web sites, and e-
mail
http://www.fww2000.com/
FORT WASHINGTON WAY 2000
Public Invo lve m e nt
OUTREACH(continued)
Innovative Tools included:
• Roving information display
• ‘Connection to the future’ video
• www.FWW2000.com with three
live cameras
• Interpretive site observation
display
• Community events
• Traffic alert e-mail messages
FORT WASHINGTON WAY 2000
Public Invo lve m e nt
AGGRESSIVE
MEDIA RELATIONS
• Daily traffic updates
• Regular updates and tours
of project site
• Open lines of
communication
• Regular feedback sessions
with police, fire and traffic
helicopters
FORT WASHINGTON WAY 2000
Awards
• ACEC- American Council of Engineering Companies of
Ohio - 2002 Engineering Excellence Award 
• CMAA - Construction Management Association of
America - 2001 Construction Management Project
Achievement Award  
• ARTBA - American Road & Transportation Builders
Association - 2000 PRIDE in Transportation Construction
Award -  
• ASCE Ohio OCEA - American Society of Civil Engineers -
Ohio - 2001 Outstanding Civil Engineering Achievement
Award  
• Parsons Brinckerhoff - Project of the Year 2001  
• SEGD- 2001 Award Outstanding Project fromSociety of
Environmental Graphic Design  
• Crystal Award for Fort Washington Way “Connection to
the Future” Video
• ICMA - 2001 International City Council Management
Association of America Award
• IRF - 2001 IRF Global Road Achievement Award -
International Road Federation - Honorable mention
FORT WASHINGTON WAY 2000
August
2000
May
2000November
1999
March
1999
FORT WASHINGTON WAY
2000
A project managed by the City of Cincinnati
with the cooperation of thousands
1956 1998 2000

More Related Content

What's hot

Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)DC Department of General Services
 
Item # 1 - Sept. 27, 2021 City Council Meeting Minutes
Item # 1 - Sept. 27, 2021 City Council Meeting MinutesItem # 1 - Sept. 27, 2021 City Council Meeting Minutes
Item # 1 - Sept. 27, 2021 City Council Meeting Minutesahcitycouncil
 
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014Island Health
 
Public Open House - Finch West LRT
Public Open House - Finch West LRTPublic Open House - Finch West LRT
Public Open House - Finch West LRTCrosstown TO
 
Donald J resume Word 2 copy
Donald J resume Word 2 copyDonald J resume Word 2 copy
Donald J resume Word 2 copydon rawson
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Daniel X. O'Neil
 
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014Island Health
 
North Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot ImprovementNorth Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot ImprovementFairfax County
 
CV_Long_STENSON Adrian 26-11-2015
CV_Long_STENSON Adrian 26-11-2015CV_Long_STENSON Adrian 26-11-2015
CV_Long_STENSON Adrian 26-11-2015Adrian Stenson
 
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampReston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampFairfax County
 
Stephen parish c.v. 14 03-17
Stephen parish c.v. 14 03-17Stephen parish c.v. 14 03-17
Stephen parish c.v. 14 03-17stephen parish
 
Item # 6 - PPT 2021 Street Maintenance Program (SMP)
Item # 6 - PPT 2021 Street Maintenance Program (SMP)Item # 6 - PPT 2021 Street Maintenance Program (SMP)
Item # 6 - PPT 2021 Street Maintenance Program (SMP)ahcitycouncil
 
Old Mount Vernon Road Walkway
Old Mount Vernon Road WalkwayOld Mount Vernon Road Walkway
Old Mount Vernon Road WalkwayFairfax County
 
Braddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside LaneBraddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside LaneFairfax County
 
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz RoadDolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz RoadFairfax County
 
Chichester Lane Sidewalk Improvements
Chichester Lane Sidewalk ImprovementsChichester Lane Sidewalk Improvements
Chichester Lane Sidewalk ImprovementsFairfax County
 
Campbell River Community Meeting October 22, 2013
Campbell River Community Meeting October 22, 2013Campbell River Community Meeting October 22, 2013
Campbell River Community Meeting October 22, 2013Island Health
 
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleSunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleFairfax County
 

What's hot (20)

A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...
A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...
A Progressive Concrete Pavement Preservation Strategy Improves City Streets i...
 
Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)Friendship Recreation Center - ANC Presentation (January 12, 2017)
Friendship Recreation Center - ANC Presentation (January 12, 2017)
 
Item # 1 - Sept. 27, 2021 City Council Meeting Minutes
Item # 1 - Sept. 27, 2021 City Council Meeting MinutesItem # 1 - Sept. 27, 2021 City Council Meeting Minutes
Item # 1 - Sept. 27, 2021 City Council Meeting Minutes
 
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
NIHP Campbell River Community Information Meeting presentation, Dec. 4, 2014
 
Public Open House - Finch West LRT
Public Open House - Finch West LRTPublic Open House - Finch West LRT
Public Open House - Finch West LRT
 
Donald J resume Word 2 copy
Donald J resume Word 2 copyDonald J resume Word 2 copy
Donald J resume Word 2 copy
 
Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010Congress Parkway Construction Overview, January 2010
Congress Parkway Construction Overview, January 2010
 
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
NIHP Comox Valley Community Information Meeting presentation Dec. 3, 2014
 
North Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot ImprovementNorth Beauregard Street at North Chambliss Street Spot Improvement
North Beauregard Street at North Chambliss Street Spot Improvement
 
Center Road sidewalk
Center Road sidewalkCenter Road sidewalk
Center Road sidewalk
 
CV_Long_STENSON Adrian 26-11-2015
CV_Long_STENSON Adrian 26-11-2015CV_Long_STENSON Adrian 26-11-2015
CV_Long_STENSON Adrian 26-11-2015
 
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-RampReston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
Reston Parkway at Dulles Toll Road Westbound On-Ramp and Eastbound Off-Ramp
 
Stephen parish c.v. 14 03-17
Stephen parish c.v. 14 03-17Stephen parish c.v. 14 03-17
Stephen parish c.v. 14 03-17
 
Item # 6 - PPT 2021 Street Maintenance Program (SMP)
Item # 6 - PPT 2021 Street Maintenance Program (SMP)Item # 6 - PPT 2021 Street Maintenance Program (SMP)
Item # 6 - PPT 2021 Street Maintenance Program (SMP)
 
Old Mount Vernon Road Walkway
Old Mount Vernon Road WalkwayOld Mount Vernon Road Walkway
Old Mount Vernon Road Walkway
 
Braddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside LaneBraddock Road Walkway - Carlbern Drive to Clubside Lane
Braddock Road Walkway - Carlbern Drive to Clubside Lane
 
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz RoadDolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
Dolley Madison Sidewalk - Chain Bridge Road to Kurtz Road
 
Chichester Lane Sidewalk Improvements
Chichester Lane Sidewalk ImprovementsChichester Lane Sidewalk Improvements
Chichester Lane Sidewalk Improvements
 
Campbell River Community Meeting October 22, 2013
Campbell River Community Meeting October 22, 2013Campbell River Community Meeting October 22, 2013
Campbell River Community Meeting October 22, 2013
 
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy CircleSunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
Sunrise Valley Dr. Sidewalk Improvements -River Birch Rd. to Legacy Circle
 

Viewers also liked (20)

Great City Design Team Elliott Park Ppt
Great City Design Team Elliott Park PptGreat City Design Team Elliott Park Ppt
Great City Design Team Elliott Park Ppt
 
Habilidades gerenciales laura aguilar
Habilidades gerenciales laura aguilarHabilidades gerenciales laura aguilar
Habilidades gerenciales laura aguilar
 
Evaluacion formativa o de procesos
Evaluacion formativa o de procesosEvaluacion formativa o de procesos
Evaluacion formativa o de procesos
 
DEMOSTRACIÓN
DEMOSTRACIÓNDEMOSTRACIÓN
DEMOSTRACIÓN
 
Aspectos preliminares
Aspectos preliminaresAspectos preliminares
Aspectos preliminares
 
UCDAAP9NOV16
UCDAAP9NOV16UCDAAP9NOV16
UCDAAP9NOV16
 
Word debate
Word debateWord debate
Word debate
 
Abhishek Kr Rao resume
Abhishek Kr Rao resumeAbhishek Kr Rao resume
Abhishek Kr Rao resume
 
People Development
People DevelopmentPeople Development
People Development
 
Riesgos físicos
Riesgos físicosRiesgos físicos
Riesgos físicos
 
BM CV 2014 final
BM CV 2014 finalBM CV 2014 final
BM CV 2014 final
 
El portafolio
El portafolioEl portafolio
El portafolio
 
Evaluacion breve
Evaluacion breveEvaluacion breve
Evaluacion breve
 
Rúbrica de evaluación
Rúbrica de evaluaciónRúbrica de evaluación
Rúbrica de evaluación
 
Frank sebastian-chaparro-zarta
Frank sebastian-chaparro-zartaFrank sebastian-chaparro-zarta
Frank sebastian-chaparro-zarta
 
Entrevista
EntrevistaEntrevista
Entrevista
 
mfe_our services
mfe_our servicesmfe_our services
mfe_our services
 
Aspectos principales al escribir un ensayo
Aspectos principales al escribir un ensayoAspectos principales al escribir un ensayo
Aspectos principales al escribir un ensayo
 
Habilidades gerenciales laura aguilar
Habilidades gerenciales laura aguilarHabilidades gerenciales laura aguilar
Habilidades gerenciales laura aguilar
 
Conclusión Unidad III
Conclusión Unidad IIIConclusión Unidad III
Conclusión Unidad III
 

Similar to fwwPP.PPT

228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010Daniel X. O'Neil
 
Rio Vista Drive Channel Stabilization
Rio Vista Drive Channel StabilizationRio Vista Drive Channel Stabilization
Rio Vista Drive Channel StabilizationFairfax County
 
Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & ResumeRichard Rask
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park NorthFairfax County
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017melissanatech
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting Fairfax County
 
2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bond2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bondF. X. Flinn
 
02 cta yellow line station evanston cc 04.16.12
02   cta yellow line station evanston cc 04.16.1202   cta yellow line station evanston cc 04.16.12
02 cta yellow line station evanston cc 04.16.12cityofevanston
 
State of the Trails 2015
State of the Trails 2015State of the Trails 2015
State of the Trails 2015Paul Schumann
 
Rick presentation about central artery for stephaine pollocks class
Rick presentation about central artery for stephaine pollocks classRick presentation about central artery for stephaine pollocks class
Rick presentation about central artery for stephaine pollocks classDorothyFennell
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Fairfax County
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationFairfax County
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Fairfax County
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road RealignmentFairfax County
 
Sunset Hills Road Walkway
Sunset Hills Road WalkwaySunset Hills Road Walkway
Sunset Hills Road WalkwayFairfax County
 

Similar to fwwPP.PPT (20)

228 congressparkway overview_jan2010
228 congressparkway overview_jan2010228 congressparkway overview_jan2010
228 congressparkway overview_jan2010
 
Rio Vista Drive Channel Stabilization
Rio Vista Drive Channel StabilizationRio Vista Drive Channel Stabilization
Rio Vista Drive Channel Stabilization
 
WALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom CompWALID_TANBEDAWY_2016 R Dom Comp
WALID_TANBEDAWY_2016 R Dom Comp
 
Cover Letter & Resume
Cover Letter & ResumeCover Letter & Resume
Cover Letter & Resume
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park North
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Final acec design summit pres 2017
Final acec design summit pres 2017Final acec design summit pres 2017
Final acec design summit pres 2017
 
Huntington Levee Community Meeting
Huntington Levee Community Meeting Huntington Levee Community Meeting
Huntington Levee Community Meeting
 
2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bond2017 Info Night Presentation - TIF bond
2017 Info Night Presentation - TIF bond
 
02 cta yellow line station evanston cc 04.16.12
02   cta yellow line station evanston cc 04.16.1202   cta yellow line station evanston cc 04.16.12
02 cta yellow line station evanston cc 04.16.12
 
State of the Trails 2015
State of the Trails 2015State of the Trails 2015
State of the Trails 2015
 
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
DC Buys 2018 - DDOT Infrastructure Project Management Division - Full Present...
 
Rick presentation about central artery for stephaine pollocks class
Rick presentation about central artery for stephaine pollocks classRick presentation about central artery for stephaine pollocks class
Rick presentation about central artery for stephaine pollocks class
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
Lee Chapel Rd. Walkway Burke Lake Rd. to Britford Dr. July 2020
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream Restoration
 
Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016Huntington Levee Community Meeting: Oct. 26. 2016
Huntington Levee Community Meeting: Oct. 26. 2016
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
 
2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review2017 Comp Plan/UDO Review
2017 Comp Plan/UDO Review
 
Sunset Hills Road Walkway
Sunset Hills Road WalkwaySunset Hills Road Walkway
Sunset Hills Road Walkway
 

fwwPP.PPT

  • 1. FORT WASHINGTON WAY 2000 A project managed by the City of Cincinnati with the cooperation of thousands 1956 1998 2000
  • 2. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w Project Management Team: John Deatrick, P.E., AICP, Dire cto r o f Transpo rtatio n Bob Richardson, AIA, City Archite ct Don Gindling, P.E., Co nstructio n Manag e r Project Management Consultant: Fred Craig, PE Are a Manag e r, Se nio r Vice Pre side nt Parso ns Brincke rho ff
  • 3. Project Team: • Parsons Brinckerhoff Project Management Consultants • Contributing PB Offices: Cincinnati, Baltimore, Boston, San Francisco, Miami, Tampa, Las Vegas, Denver and Louisville O the r Te am Me m be rs: •JMA Consultants •KZF Incorporated •Resource International •TEC Engineers •U.S. Cost, Inc. •Vivian Llambi & Associates •Wallace Floyd Associates •Wilson & Associates •Balke Engineers •BRW •Burgess & Niple •Chan Krieger & Associates •Dan Pinger Public Relations •H. C. Nutting Company •Hargreaves Associates •Infrastructure Servcies
  • 4. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT TIMELINE November 1995 City of Cincinnati requests the Ohio-Kentucky- Indiana Regional Council of Governments (OKI) to conduct a sub-corridor analysis for Fort Washington Way January 1996 OKI begins Fort Washington Way sub- corridor analysis
  • 5. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT TIMELINE (continued) January 1997 OKI produces plan for reconstructing Fort Washington Way as a locally preferred alternative to address traffic congestion along Fort Washington Way May 1997 Members of the Fort Washington Way project team meet to plan cooperative effort for accomplishing the work. Public meetings are held to obtain input on the plan
  • 6. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT TIMELINE (continued) July 1997 Project team presents Fort Washington Way reconstruction plan during a public forum at Cincinnati City Hall September 1997 First formal design contracts let October 1997 State of Ohio approves the FWW Major Investment Study and commits $80 million in project funding
  • 7. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT TIMELINE (continued) October 15, 1997 City Council approves total funding package November 1997 Ohio Governor George Voinovich visits Cincinnati to announce a $20 million funding advance for the Fort Washington Way project January 1998 Fort Washington Way Project Design Manual drafted
  • 8. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT TIMELINE (continued) April 1998 Value Engineering Workshops held July 1998 Fort Washington Way reconstruction begins with the first construction contract let on July 2
  • 9. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT TIMELINE (continued) August 1998 Fort Washington Washington detour constructed; all traffic shifted to old eastbound lanes October 1999 First section of new Fort Washington Way open and traffic shifted to future westbound lanes
  • 10. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT TIMELINE (continued) August 2000 Fort Washington Way completed and open to traffic December 2000 Fort Washington Way dedication ceremony
  • 11. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT PARTNERS: Metro City of Cincinnati Hamilton County Ohio Department of Transportation Kentucky Transportation Cabinet Federal Highway Administration Ohio-Kentucky-Indiana Regional Council of Governments
  • 12. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT GOALS • Provide safer through and local network roadway for motorists and pedestrians • Improve local and regional access and re-connect downtown with riverfront • Provide economic development opportunities by reclaiming highway rights of way TOTAL COST: $328 MILLION
  • 13. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w BROADCOMMUNITY SUPPORT • Team of communications professionals developed a strategic communications plan with a comprehensive package of communications tools • Community support arose from the public’s involvement in the decision to do the work as quickly as possible • Emphasized message that the benefits were worth the wait
  • 14. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w SUPPORT FROMCOMMUNITY ORGANIZATIONS • The Greater Cincinnati Convention and Visitors Bureau • The Northern Kentucky Convention and Visitors Bureau • The City of Newport, Kentucky • The City of Covington, Kentucky • Chamber of Commerce • The Reds and Bengals • Cincinnati Business Committee • Transit Authority of Northern Kentucky (TANK) • Building Owners and Managers Association
  • 15. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT COMPONENTS • Reconfiguration of mainline • Construction of 27 new bridges • Creation of new landscape boulevard by construction of second street and reconstruction of Third Street • Reconstruction of Third Street Viaduct
  • 16. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT COMPONENTS (continued) • Relocation of floodwall • Construction of new riverfront transit center • Installation of combined sewer overflow mitigation system • Installation of foundations for future decks • Fiber optic backbone
  • 17. FWW Project Facts • Nearly 230 presentations given to downtown businesses, organizations and parkers to update them on traffic pattern changes • 500 different highway signs placed in more than 300 locations throughout Cincinnati • Nearly 70,000 detour maps distributed to area businesses, organizations and parking garages to update visitors and commuters of traffic pattern changes • Approximately three million pounds of structural steel from bridges and roadways removed and recycled for use in other construction projects • 4.1 million lbs. of structural steel placed at the Fort Washington Way project, which is 20 times the weight of the Statue of Liberty in New York • 24,402 cubic yards of concrete placed • Nearly 130,000 cubic yards of earth moved in preparation for the new Fort Washington Way • Piles driven a total of approximately 655,000 feet
  • 18. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w DEFINING FEATURES • Detailed Maintenance of Access Plan agreed during the environmental document • Access maintained through phased and staged fast tracked construction, and with detailed manuals guiding all aspects of project • Project management structure with unique blending of City of Cincinnati staff with consultant teams
  • 19. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w DEFININGFEATURES (continued) • Innovative materials including stone mastic asphalt driving surface • Bi-state funding accord • Accelerated time frame • Heavy emphasis on urban design and landscaping • Innovative bridge types • Well financed citizen involvement group • Constructability and value engineering reviews
  • 20. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w THE TRENCH • Narrowed mainline area, but now with through lane continuity to reduce weaving and merging and improved capacity
  • 21. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w NEWBOULEVARD •Providing improved access and new front door for city
  • 22. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w THE THIRDSTREET VIADUCT- CONNECTION TO US 50 ON THE EAST • Provides dramatically improved traffic capacity to the East • First use of steel box girder construction in Ohio • New substructure constructed under old bridge, retaining access
  • 23. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w NEWFWWFLOODWALL • Provides flood protection for new project while freeing 14 acres of land for future development by eliminating earthen levee • Below grade pump house for highway trench storm water during extreme river flood conditions
  • 24. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w RIVERFRONT TRANSIT CENTER • Grade separated transit and pedestrian access for major riverfront events
  • 25. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w COMBINEDSEWEROVERFLOWSYSTEM • New water pollution mitigation system • Measurable improvements to Ohio River water quality by reducing overflows to near zero
  • 26. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w FOUNDATION PILES FOR FUTURE DECKS • Allows for the future placement of parks or other public spaces over highway facility
  • 27. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w FOSTEREDREDEVELOPMENT OF TWOVACANT WAREHOUSES
  • 28. FORT WASHINGTON WAY 2000 Pro je ct O ve rvie w PROJECT COORDINATION • Typical example illustrates City contracts for new Second Street (Contract 22a) and the Elm Street Bridge over the FWW trench (Contracts 8 and 17d), and Hamilton County contracts for the Bengals stadium and new Elm Street
  • 29. FORT WASHINGTON WAY 2000 Urban De sig n PROJECT DESIGN MANUAL • Examined urban design in each aspect of the project • Produced in conjunction with overall civil engineering design manual • Controlled the overall project aesthetics • Captured best value for dollars spent
  • 30. FORT WASHINGTON WAY 2000 Urban De sig n Linked the riverfront to downtown by extending the street grid overthe highway.
  • 31. FORT WASHINGTON WAY 2000 Urban De sig n HIGHQUALITY ANDVALUE- MAXIMUMIMPACT • Custom made pre-cast panels • Unique lighting using standard fixtures • Decorative vandal screens • Multi-colored bridge beams
  • 32. FORT WASHINGTON WAY 2000 De sig n and Co nstructio n ENVIRONMENTAL DOCUMENTATION FWW CATEGORICAL EXCLUSION • Document approved in record time • Model for the Federal Highway Administration for highway reconfiguration • Concurrent approval by ODOT and the state historical preservation office • ODOT & SHPO approved on-site archeologist as appropriate mitigation considering site characteristics and construction methodology • Accelerated OEPA review process
  • 33. FORT WASHINGTON WAY 2000 De sig n and Co nstructio n THE FWWPROJECT: • 31 design contracts • 27 construction contracts • Work broken down to fast-track design and construction and encourage smaller contractors and minorities to bid • Phasing and fast-track allowed quick response to changing regional priorities
  • 34. FORT WASHINGTON WAY 2000 De sig n and Co nstructio n IN PREPARATION FOR CONSTRUCTION • Early implementation of comprehensive vehicular and pedestrian way-finding signage system • Construction of temporary exit ramps to provide alternate access to downtown • Construction of temporary bridge to maintain access to Kentucky
  • 35. FORT WASHINGTON WAY 2000 De sig n and Co nstructio n IN PREPARATION FOR CONSTRUCTION (continued) • Adaptation of new temporary street on then existing flood levee • Revitalization of existing groups to insure strong communication networks • Establishment of web site and list- service
  • 36. FORT WASHINGTON WAY 2000 De sig n and Co nstructio n IN PREPARATION FOR CONSTRUCTION (continued) • Constructed two new temporary off ramps to serve the CBD (central business district), one from I-75 North and one from I-71 South to replace access provided by FWW • Re-striped two other exit ramps to add lanes
  • 37. FORT WASHINGTON WAY 2000 Inno vative Bridg e Type s Firsts in Ohio: • Steel Box Girder • Cast-in-Place Box Girder • Concrete Integral Piers
  • 38. FORT WASHINGTON WAY 2000 Inno vative Bridg e Type s 27 Bridges Built In 42 Stages • 4 Steel Rolled Beam • 16 Steel Curved Plate Girder • 5 Steel Box Girder • 7 Cast-in-Place Post-Tensioned Concrete Slab • 3 Cast-in-Place Post-Tensioned Concrete Box Girder • 1 Pre-Stressed Concrete “I” girder • 2 Pre-Stressed Concrete Adjacent Box Beams • 4 Cable-Stay Pedestrian Bridges
  • 39. Innovative staged construction techniques used to maintain traffic while building bridges FORT WASHINGTON WAY 2000 Inno vative Bridg e Type s
  • 40. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt PROCUREMENT MANUAL • Assembled a manual of procedures combining federal, state and local requirements • Established expedited pre- qualification process including MBE, WBE, DBE, SBE vendors, as the laws changed during the project
  • 41. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt PROCUREMENT MANUAL (continued) • All contracts locally advertised and bid by City using ODOT procedures • Established a contract compliance officer on the job site • Maintain pace of construction during law suite on MBE regulations and provided basis of consent decree
  • 42. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt AGGRESSIVE OUTREACHTOPOTENTIAL BIDDERS ANDSUBCONTRACTORS • Contractors encouraged to use minority contractors, pre-approved sub-consultants and suppliers • Early notification to contractors of upcoming bids, including postings on the FWW Web site and pre-bid seminars • Established a comprehensive data base of vendors to assist bidders • MBE/WBE/DBE/SBE workshops held to encourage participation
  • 43. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt THE BIDDING PROCESS • Bid dates posted on the project Web site • Bids advertised in local newspapers, ODOT and city of Cincinnati bulletins • Bid many items lump sum to simplify bid and award process
  • 44. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt THE BIDDING PROCESS (continued) • Answers for pre-bid questions available through e-mail • Contracts went from bid to award in one week or less • OCIP (owner controlled insurance program) reduced bickering over damage and field claims
  • 45. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt COST/CONTROL PROCEDURES • Value engineering workshop sponsored by ODOT reviewed entire project design and finalized civil and urban design manuals • Pre-approved design manuals simplified preparation of plans and specifications • Preliminary constructability reviews by consultant, city, and state team reduced construction costs and enabled phased construction
  • 46. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt COST/CONTROL PROCEDURES (continued) • Contingency amounts added to contracts to enable field decisions to minor problems and focus on cost containment • Innovative change order approval process using monthly FWW Construction Board to provide oversight and hear claims
  • 47. FORT WASHINGTON WAY 2000 Bidding and Co nstructio n Manag e m e nt MEETING THE SCHEDULE • Conventionally bid construction contracts with liquidated damages • No incentives • Master schedule and traffic management defined early and included in project manuals bid documents
  • 48. FORT WASHINGTON WAY 2000 Public Invo lve m e nt COMPREHENSIVE OUTREACH • Established graphics standards for all materials • Revitalized existing regional coordination committees • “Connection to the Future” newsletter distributed to project stakeholdershttp://www.fww2000.com/
  • 49. FORT WASHINGTON WAY 2000 Public Invo lve m e nt Outreach (continued) • Over 200 meetings held prior to start of construction to establish dialogue • More than 400 community meetings held throughout project construction to maintain contact • Distributed more than 200,000 motorist and pedestrian detour maps
  • 50. FORT WASHINGTON WAY 2000 Public Invo lve m e nt OUTREACH(continued) • Regular events to mark significant project milestones and maintain media contact • Regularly scheduled meetings with community support groups • Suggestions and comments taken through telephone, web sites, and e- mail http://www.fww2000.com/
  • 51. FORT WASHINGTON WAY 2000 Public Invo lve m e nt OUTREACH(continued) Innovative Tools included: • Roving information display • ‘Connection to the future’ video • www.FWW2000.com with three live cameras • Interpretive site observation display • Community events • Traffic alert e-mail messages
  • 52. FORT WASHINGTON WAY 2000 Public Invo lve m e nt AGGRESSIVE MEDIA RELATIONS • Daily traffic updates • Regular updates and tours of project site • Open lines of communication • Regular feedback sessions with police, fire and traffic helicopters
  • 53. FORT WASHINGTON WAY 2000 Awards • ACEC- American Council of Engineering Companies of Ohio - 2002 Engineering Excellence Award  • CMAA - Construction Management Association of America - 2001 Construction Management Project Achievement Award   • ARTBA - American Road & Transportation Builders Association - 2000 PRIDE in Transportation Construction Award -   • ASCE Ohio OCEA - American Society of Civil Engineers - Ohio - 2001 Outstanding Civil Engineering Achievement Award   • Parsons Brinckerhoff - Project of the Year 2001   • SEGD- 2001 Award Outstanding Project fromSociety of Environmental Graphic Design   • Crystal Award for Fort Washington Way “Connection to the Future” Video • ICMA - 2001 International City Council Management Association of America Award • IRF - 2001 IRF Global Road Achievement Award - International Road Federation - Honorable mention
  • 54. FORT WASHINGTON WAY 2000 August 2000 May 2000November 1999 March 1999
  • 55. FORT WASHINGTON WAY 2000 A project managed by the City of Cincinnati with the cooperation of thousands 1956 1998 2000

Editor's Notes

  1. Introduction
  2. Time: 20 minutes Brief introduction about John Deatrick Professional Experience Education Etc. John to give brief overview of each part of the presentation, including Project Overview, Design and Construction, Urban Design, Bidding and Construction Management and Public Involvement.
  3. Quickly cover the timeline over the next few slides FWW was born out of the I-71 Major Investment Study in 1995, after the City of Cincinnati requested that OKI include this portion of the highway in their study. The study was conducted by the Ohio-Kentucky-Indiana Regional Council of Governments and the sub-analysis of Fort Washington Way began in May, 1996. The purpose of the study was to determine solutions to addressing the traffic congestion along the I-71 corridor, including Fort Washington Way, where urban design would also be considered for the central riverfront area.
  4. In January, 1997, when OKI produced the plan for reconstructing Fort Washington Way, the project was planned to only be the resurfacing of the one-mile stretch of interstate that runs directly through the heart of downtown Cincinnati. This stretch of highway carries more than 150,000 vehicles each day. Public involvement grew as the central riverfront planning came together with the desire to do something about Fort Washington Way, tired dysfunctional roadway. ODOT was receptive.
  5. But, project planners in the region saw a great opportunity. They saw the chance to accomplish much more than a highway resurfacing. Fort Washington Way soon became the umbrella under which many smaller projects came to life. (We will cover this in a few minutes). It became an opportunity to reconnect Cincinnati to its riverfront. When the concept of Fort Washington Way became more of a reality, something unusual happened.
  6. For the first time in history, ODOT gave a local agency control of an interstate project of this size. From that point on, Fort Washington Way was managed by the City of Cincinnati. I like to think this happened only because ODOT trusted the local authorities to be able to accomplish the task before them. The Team Approach- The City of Cincinnati partnered with Hamilton County, ODOT, KYTC, SORTA, TANK, MSD and CWW.
  7. For the first time in history, ODOT gave a local agency control of an interstate project of this size. From that point on, Fort Washington Way was managed by the City of Cincinnati. I like to think this happened only because ODOT trusted the local authorities to be able to accomplish the task before them. The Team Approach- The City of Cincinnati partnered with Hamilton County, ODOT, KYTC, SORTA, TANK, MSD and CWW.
  8. August 1998 First detour October 1999 Westbound lanes open August 2000 Eastbound lanes, Second and Third streets open
  9. They had to cultivate an elaborate project team, which included input from multiple stakeholders such as Hamilton County, the Kentucky Transportation Cabinet; Southwestern Ohio’s transit agency – Metro, the Federal Highway Administration and the Ohio-Kentucky-Indiana Regional Council of Governments. Together these agencies would develop a spirit of cooperation unlike anything seen in the region before. When working on FWW, each of these groups left personal agendas aside in order to accomplish the enormous task at hand. Project partnership was put together in the original OKI MIS. The city was able to take the project partnership and convert it into an actual design and construction team. The transition point was the partnering workshop which formalized the project goals and deadlines.
  10. But as the project grew in scope – from a $146.9 million job to more than $316 million, the schedule remained the same. The City of Cincinnati was committed to open the Fort Washington Way mainline by August 2000 -- a nearby impossible task even without all of the project additions. Making Fort Washington Way better was the major thrust of the project. Numerous steps were taken to make it a safer roadway for motorists and pedestrians. The previous north/south configuration of FWW ramps created increased congestion and proved to be a safety hazard for motorists with an inordinate number of left exit ramps and traffic weaves. Project designers changed those ramps to an east/west configuration, thereby making the roadway safety and improving traffic flow.
  11. The project team also solicited the support and involvement of community groups such as the two area chambers of commerce and convention and visitors’ bureaus; nearby cities of Newport and Covington; the Transit Authority of Northern Kentucky and even the Cincinnati Reds and Cincinnati Bengals.
  12. Why was it important to have so many people involved in the project? Because from the time the first concept of Fort Washington Way was discussed until construction began, the project became an umbrella under which not only a major reconstruction of the highway would take place, but also several other components. The addition of these new components made just about everyone in the Greater Cincinnati and Northern Kentucky region have a stake in the new Fort Washington Way.
  13. Including the reconfiguration and paving of the Fort Washington Mainline.
  14. The reconstruction of Third Street and the Third Street Viaduct.
  15. The Third Street Viaduct
  16. The new Fort Washington Way Floodwall
  17. The new Riverfront Transit Center, located below the new Second Street.
  18. The installation of a combined sewer overflow system.
  19. The installation of piles for Fort Washington Way Decking.
  20. The installation of piles for Fort Washington Way Decking.
  21. The first step in this undertaking was the development of project design manual so that urban design of the project would not be an afterthought, but would be examined during each step of design and construction.
  22. Project planners also were forward thinking throughout the design process. One example -- instead of building the new Second Street on a mound of fill, planners instead built the roadway on structure, which enabled the Riverfront Transit Center to be constructed underneath.
  23. The urban design features used throughout the project were of the highest quality. Instead of flat concrete retaining walls lining Fort Washington Way , the design manual called for pre-cast, decorative concrete panels to be erected the entire length of the trench. Instead of standard run-of-the-mill streetlights, designers instead selected low-cost, low-maintenance; high-intensity street lights which would illuminate not only the roadway, but the adjacent streets as well. Even the colors of the paint selected for the bridge structures were cutting edge – no standard gray here – instead periwinkle and teal were chosen.
  24. The project team compiled a model environmental document, which the Federal Highway Administration uses as an example of how environmental work should be done. The document itself was approved in record time – eight months, partly because ODOT and the State Historic Preservation Office of Ohio approved the document concurrently instead of sequentially. In addition, ODOT approved an on-site archeologist instead of the normal pre-construction excavation because of the aggressive schedule. In the case of Fort Washington Way, some aspects of the environmental were done at the same time as right-of-way and design, also to meet the tight schedule.
  25. Fort Washington Way became a project with 28 design contracts and 25 construction contracts, which were broken down to speed up construction and to encourage smaller contractors and minorities to bid. Numerous steps were taken in the initial design process to ensure that once into construction, work would proceed as smoothly as possible, including constructability reviews.
  26. Before construction could begin, major steps were taken to upgrade detour routes. An extensive way finding signage program was implemented. Traffic maintenance measures even included the construction of a temporary bridge to restore access from Northern Kentucky to downtown Cincinnati that was cut off due to construction. The project team got special permission from ODOT to construct a new temporary ramp to provide motorists which additional access from I-71 into downtown.
  27. Before construction could begin, major steps were also taken to upgrade detour routes: A new ramp from I-75 North to Fifth Street. New Eggleston Avenue ramp from I-71 South. Re-striped Sixth Street entrance ramp from I-471 to include new lane. Re-striped Reading/Gilbert exit from I-71 to accommodate more traffic.
  28. The construction of 25 new bridges.
  29. Time: 20 minutes Brief introduction about Don Gindling Professional Experience Education Etc.
  30. The bidding process was also unique. The project team performed aggressive outreach to small business throughout the region in an attempt to encourage bidding on the project. General contractors were provided a comprehensive list of minority contractors and pre-approved sub-consultants and suppliers to encourage their participation.
  31. Bid dates were posted on the project web site and contractors with pre-bid questions could have those answered via the Internet as well. Contractors could have pre-bid questions answered by e-mail. The bidding process also was different. The typical 4-6 week period in which construction contracts go from bid to award was reduced to one week or less for Fort Washington Way.
  32. Construction management and procurement manual. Contingency amounts added to contracts. Board of controls established detailed monthly activity reports. External and Internal audits done throughout construction. Project team consisted of BE, OE, Inspectors secretary.
  33. Due to the multiple start dates and multiple contracts of the job, FWW did not lend itself to incentives. Master schedule and traffic management plan clearly defined before any construction began. Completion in August 2000. Schedule included in bid documents. Instead, the project management team implemented liquidated damages on all major contracts as a means to meet the tough completion schedule.
  34. More than 200,000 Motorist and Pedestrian Detour Maps distributed. More than 300 community meetings. ‘Connection to the Future’ newsletter distributed to project stakeholders.
  35. Roving Information Display which was exhibited at nearly 40 locations. ‘Connection to the Future’ Video was distributed to video rental stores and libraries across the entire region. The Web site, www.FWW2000.com- was accessed by thousands of community members. The Observation Display on the Walnut Street pedestrian bridge, over the Fort Washington Way mainline. Community events such as the ‘Halfway There’ event on Fountain Square and public ribbon cuttings, as the project neared completion.
  36. Traffic alert e-mail distribution. Regular updates and tours of project site. Consistent open lines of communication.
  37. Introduction