Earned	Value	
Management
Earned	Value	Management	topic	from	Control	Cost	– Cost	Management
BY	– Dilip Chaturvedi,	PMP
Email	Id	:	info@justpmp.com
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP
Agenda
§ What	is	Earned	Value	Management	
§ Explained	EVM	with	examples
§ Cost	Variances	(CV	)
§ Cost	Performance	Index(CPI)
§ Schedule	Variances(SV)
§ Schedule	Performance	Index(SPI)
§ Cost	Overrun	and	Project	Slip
§ Summary	
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 2
What	is	Earned	Value	Management
§ Earned	value	management	is	the	process	of	measuring	the	performance	of	work	against	
what	was	planned	to	identify	variances,	opportunities	to	improve	the	project	or	just	check	
the	project	health’s.
§ It	is	system	of	mathematical	formulas	that	compares	work	performed	against	work	planned,	
and	measures	the	cost	of	the	work	the	project	has	performed.
§ EVM	is	an	important	part	of	cost	control,	since	it	allows	a	project	manager	to	predict	future	
variances	from	the	expenses	to	date	within	the	project.
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 3
Examples:	Project	Plan	for	Planting	
trees	
Our	team	has	been	tasked	with	Planting	the	trees	on	the	Plot	of	land	behind	 our	company’s	new	factory.
The	Plan:
- 30	Batches	of	20	trees	(	600	trees)
- 5	batches	per	day	(	100	trees	)
- Budgeted	cost	per	tree	2.90	$(	2.50	$	per	baby	tree	/	0.40	$	for	the	slow	release	fertilizer	)
- ->	total	budget	1,740	$
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 4
After	the	first	day..
1. 70	Trees	were	planted(	the	team	hit	a	patch	with	stones	that	had	to	be	removed	before	the	trees	could	
be	planted.
2. Total	cost	was	$350	(	we	had	to	rent	a	special	machine	to	help	remove	the	stones	which	cost	$147	for	
the	day	)
Simple	EVM	calculation
- Earned	value	=	70	trees	planted	*	$2.90		=	$203	
- Budgeted	cost	=	100	trees	planned	per	day	*	$2.90		=	$290	
- Actual	cost	=	70	trees	planted	*	$2.90	+	$147	for	machine	=	$350	
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 5
First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 6
Regarding	Actual	Cost
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 7
Expected	Cost	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
We	should	have	
been	here
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 8
Cost	Variance(CV	=	EV-AC)	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
We	should	have	
been	here
Cost	variance(CV)	=	EV	– AC
=	203	– 350	=	-147$	<	0	
Confidential	and	Copyrighted	material	of	JustPMP
9
Cost	Performance	Index(CPI	=	EV÷AC	)
on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
We	should	have	
been	here
Cost	variance(CV)	=	EV	– AC
=	203	– 350	=	-147$	<	0	
CPI	=	EV	÷ AC	=	203	÷ 350
We	are	over	budget	and	have	
spent	203	÷ 350	=	58%	more	
budget	than	anticipated	(Cost	
Performance	Index	)
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 10
Regarding	Schedule	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 11
Regarding	Schedule	in	Duration	on	
First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Schedule	
variances
in	hours
Confidential	and	Copyrighted	material	of	JustPMP
Which	is	where	we	should	
have	then	been	here
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 112
Schedule	Variances(	SV	=	EV	- BC	)	on	
First	Day	
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Schedule	
variances
in	hours
Schedule	variance(SC)	in	dollars	=	EV	– BC
=	203	– 290	=	-87$	<	0	
Confidential	and	Copyrighted	material	of	JustPMP
Which	is	where	we	should	
have	then	been	here
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 13
Schedule	Performance	Index	
(SPI	=	EV÷ BC	)	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Schedule	
variances
in	hours
Schedule	variance(SC)	in	dollars	=	EV	– BC
=	203	– 290	=	-87$	<	0	
Confidential	and	Copyrighted	material	of	JustPMP
Which	is	where	we	should	
have	then	been	here
SPI	=	EV	÷ BC	=	203	÷ 290
We	are	late	and	have	only	
performed		203	÷ 290	=	70%	of	
the	work	planned	(	Our Schedule	
Performance	Index	)
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 14
The	Consequences..	Cost	Overrun
0
500
1000
1500
2000
2500
3000
3500
Start 1st	Day 2nd	Day 3rd	Day 4th	Day 5th	Day 6th	Day 7th	Day 8th	Day 9th	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
Confidential	and	Copyrighted	material	of	JustPMP
Estimate	at	
completion(EAC)	=	
$	3000	
Budget	at	completion
BAC	=		$	1740		
Cost	Overrun
Planned	end	date
=	6	days
Estimate	at	completion	
=	8.57	days
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 15
The	Consequences..	Project	Slip
0
500
1000
1500
2000
2500
3000
3500
Start 1st	Day 2nd	Day 3rd	Day 4th	Day 5th	Day 6th	Day 7th	Day 8th	Day 9th	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
Project	Slip
Confidential	and	Copyrighted	material	of	JustPMP
Estimate	at	
completion(EAC)	=	
3000	$
Budget	at	completion
BAC	=		1740	$	
Cost	Overrun
Planned	end	date
=	6	days
Estimate	at	completion	
=	8.57	days
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 16
Summary	of	the	Consequences
1. If	we	continue	at	this	rate,	we	will	need:	1740	÷ 58	=	$	3,000(Cost	Estimate	at	Completion)
and	6	days	÷ 70%	=	8.57	days	(Schedule	Estimate	at	Completion)to	finish	the	work
2. If	you	want	to	finish	on	budget,	we	need	to	work	at	(Planned	remaining	budget)	÷ (actual	
remaining	budget)	(	1740	– 290	)	÷ (	1740	– 350	)	=	104.3%	of	the	originally	performance	
3. If	we	want	to	finish	on	time,	we	need	to	work	at	(actual	remaining	work)	÷ (planned	
remaining	work)	(600	– 70)	÷ (600	- 100)	=	106%	of	the	originally	planned	performance
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 17
In	technical	terms…
1. In	real	life,	the	elements	we	calculated	have	slightly	different	names:
2. The	Actual	Cost	is	usually	referred	to	as	Actual	Cost	of	Works	Performed(ACWP)
3. The	Planned	Cost	=	Budgeted	Cost	for	Work	Schedules(BCWS)
4. The	Earned	Value	=	Budgeted	Cost	for	Work	Performed	(BCWP)		
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 18
Thank	you
Please	contact	us	for	PMP	Exam	Prep	Training,FREE	PMP	Notes,	FREE	Mock	PMP	Online	
test,	FREE	PMP	Application	assistance
Email	Id	:	info@justpmp.com
Website	:	www.justpmp.com
Follow	us	on	Twitter	for	latest	update:	https://twitter.com/just_pmp
Like	us	on	Facebook:	https://facebook.com/justpmp
Click	on	Subscribe	button	on	Our	Youtube	Channel	for	FREE	Videos	of	
PMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 19

More Related Content

What's hot

Project charter v2
Project charter v2Project charter v2
Project charter v2Stefan Csosz
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Ahmed Fouad, MCIArb, PMP, SP, RMP
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptxIkram192675
 
Non Linear Analysis of RCC Building with and Without Shear Wall
Non Linear Analysis of RCC Building with and Without Shear WallNon Linear Analysis of RCC Building with and Without Shear Wall
Non Linear Analysis of RCC Building with and Without Shear WallIRJET Journal
 
Project Management (CAPM) - Introduction
Project Management (CAPM) - IntroductionProject Management (CAPM) - Introduction
Project Management (CAPM) - IntroductionMohammad Tawfik
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter SummeryDerek Cooksey
 
Project on construction of 3 block house report
Project on construction of 3 block house reportProject on construction of 3 block house report
Project on construction of 3 block house reportHagi Sahib
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementAnand Bobade
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
Time & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project DeliveryTime & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project DeliveryShashank Arun
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr Bhavana Deshpande
 
Keo Projects
Keo ProjectsKeo Projects
Keo Projectsron75
 
Pert 7-manajemen-biaya
Pert 7-manajemen-biayaPert 7-manajemen-biaya
Pert 7-manajemen-biayaAnnisa Nagari
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniquesChander Parkash
 

What's hot (20)

PEB Steel Company profile
PEB Steel Company profilePEB Steel Company profile
PEB Steel Company profile
 
Project charter v2
Project charter v2Project charter v2
Project charter v2
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Project Human Resource Management.pptx
Project Human Resource Management.pptxProject Human Resource Management.pptx
Project Human Resource Management.pptx
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Non Linear Analysis of RCC Building with and Without Shear Wall
Non Linear Analysis of RCC Building with and Without Shear WallNon Linear Analysis of RCC Building with and Without Shear Wall
Non Linear Analysis of RCC Building with and Without Shear Wall
 
Project Management (CAPM) - Introduction
Project Management (CAPM) - IntroductionProject Management (CAPM) - Introduction
Project Management (CAPM) - Introduction
 
Project Charter Summery
Project Charter SummeryProject Charter Summery
Project Charter Summery
 
Project on construction of 3 block house report
Project on construction of 3 block house reportProject on construction of 3 block house report
Project on construction of 3 block house report
 
2.1 Engineering Societies (OCT 2020)
2.1 Engineering Societies (OCT 2020)2.1 Engineering Societies (OCT 2020)
2.1 Engineering Societies (OCT 2020)
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
PMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource managementPMP Chap9 - Project Human Resource management
PMP Chap9 - Project Human Resource management
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
Time & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project DeliveryTime & Cost optimization for Accelerated Project Delivery
Time & Cost optimization for Accelerated Project Delivery
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
Keo Projects
Keo ProjectsKeo Projects
Keo Projects
 
Pert 7-manajemen-biaya
Pert 7-manajemen-biayaPert 7-manajemen-biaya
Pert 7-manajemen-biaya
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 

Viewers also liked

Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingJustAcademy
 
Probability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun ProfilesProbability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun Profilespedlove
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value ManagementKristine Hejna
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
TBx Consulting Ltd
TBx Consulting LtdTBx Consulting Ltd
TBx Consulting Ltdbontoux
 
RIW-09 Presentations: Vimpelcom
RIW-09 Presentations: VimpelcomRIW-09 Presentations: Vimpelcom
RIW-09 Presentations: VimpelcomAlyona Podboronova
 

Viewers also liked (19)

Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Probability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun ProfilesProbability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun Profiles
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value Management
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Lost in transition
Lost in transitionLost in transition
Lost in transition
 
Tfs 2008 Overview
Tfs 2008 OverviewTfs 2008 Overview
Tfs 2008 Overview
 
TBx Consulting Ltd
TBx Consulting LtdTBx Consulting Ltd
TBx Consulting Ltd
 
RIW-09 Presentations: Vimpelcom
RIW-09 Presentations: VimpelcomRIW-09 Presentations: Vimpelcom
RIW-09 Presentations: Vimpelcom
 

Similar to Earned value management with Examples | Control Cost | PMBOK | PMP

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Roger H. Mandel
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaGlobalSkillup
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfVarunSubramanyam
 
Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15Sharath Sri Karan
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
L4_Cost Management.ppt
L4_Cost Management.pptL4_Cost Management.ppt
L4_Cost Management.pptMUST
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)Glen Alleman
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...JustAcademy
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...JustAcademy
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Managing service projects in a B2B environment
Managing service projects in a B2B environmentManaging service projects in a B2B environment
Managing service projects in a B2B environmentGideon Cohen
 

Similar to Earned value management with Examples | Control Cost | PMBOK | PMP (20)

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
L4_Cost Management.ppt
L4_Cost Management.pptL4_Cost Management.ppt
L4_Cost Management.ppt
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Managing service projects in a B2B environment
Managing service projects in a B2B environmentManaging service projects in a B2B environment
Managing service projects in a B2B environment
 

Recently uploaded

Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinojohnmickonozaleda
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptxmary850239
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxPoojaSen20
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 

Recently uploaded (20)

Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
FILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipinoFILIPINO PSYCHology sikolohiyang pilipino
FILIPINO PSYCHology sikolohiyang pilipino
 
4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx4.18.24 Movement Legacies, Reflection, and Review.pptx
4.18.24 Movement Legacies, Reflection, and Review.pptx
 
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptxCulture Uniformity or Diversity IN SOCIOLOGY.pptx
Culture Uniformity or Diversity IN SOCIOLOGY.pptx
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 

Earned value management with Examples | Control Cost | PMBOK | PMP