Effective Risk Management, 
  Measurement, Monitoring & Control
                 Project Management Focus




                                                                           Presented by:
                                                                Karen Yvonne Lucas, PMP  
© 2009, Karen Yvonne Lucas, PMP – ALL RIGHTS RESERVED
  2009, Karen Yvonne Lucas, PMP –                       kylucas@gmail.com |  202‐352‐4397
Slide: 2


Effective Risk Management, Measurement, Monitoring & Control
Risk Cycle
 Effective Risk Management, 
 Effective Risk Management, 
 Measurement, Monitoring & Control is 
 Measurement, Monitoring & Control is                             1
 the process of:
 the process of:                                                Risk 
      proactively planning for risks                          Planning
      proactively planning for risks
     identifying risks
      identifying risks                           6
                                                                                   2




                                                                                                    © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
     diligently conducting sound risk 
     diligently conducting sound risk            Risk 
                                                                                  Risk 
     management, 
     management,                              Monitoring 
                                                                              Identification
                                               & Control
     fully analyzing risk
     fully analyzing risk
                                                            Effective Risk 




                                                                                                      2009, Karen Yvonne Lucas, PMP –
     customizing risk response being 
     customizing risk response being                        Management, 
     sensitive to the 1st impact and the                    Measurement,  
     sensitive to the 1st impact and the 
                                                            Monitoring & 
     earliest timing
     earliest timing                                           Control
     Monitoring risks until they no longer 
     Monitoring risks until they no longer 
     exist &/or the project objectives are 
     exist &/or the project objectives are        5                                 3
     achieved or cancelled
     achieved or cancelled                      Risk                          Qualitative 
                                              Response                        Risk Analysis
     Effectively and Efficiently 
     Effectively and Efficiently 
     controlling risk outcomes
     controlling risk outcomes
                                                                  4
 Each of the above are done with a keen 
 Each of the above are done with a keen                     Quantitative 
 focus to further the mission, goal and 
 focus to further the mission, goal and                     Risk Analysis
 objectives of a 
 objectives of a 
 project/program/initiative.
 project/program/initiative.
Slide: 3


Effective Risk Management, Measurement, Monitoring & Control
Risk Cycle
                                                   Risk Management
                                                   Risk Management          1   5   6
                      1                              Involves planning for Risk ahead of its 
                                                      Involves planning for Risk ahead of its 
                    Risk                             occurrence.
                                                      occurrence.
                  Planning
                                                     Involves making Risk an integral part 
                                                      Involves making Risk an integral part 
      6                                              of all project meetings as opposed to 
                                                      of all project meetings as opposed to 
                                       2




                                                                                                    © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
     Risk                                            an afterthought or separate meeting.
                                                      an afterthought or separate meeting.
                                      Risk 
  Monitoring                                         NOTE:  Included in Risk Planning is the:
                                                     NOTE:  Included in Risk Planning is the:
                                  Identification
   & Control
                                                          Setup of the Probability & Impact 
                                                          Setup of the Probability & Impact 
                Effective Risk 




                                                                                                      2009, Karen Yvonne Lucas, PMP –
                                                          Measurement (PIM) Scale.  The 
                                                          Measurement (PIM) Scale.  The 
                Management, 
                Measurement,                              PIM Scale is “quantitative” & 
                                                          PIM Scale is “quantitative” & 
                Monitoring &                              shows the weight the business 
                                                          shows the weight the business 
                   Control                                places on pain/gain by threshold.  
                                                          places on pain/gain by threshold.  
                                                          Request the PIM from Senior 
                                                          Request the PIM from Senior 
      5                                3                  Management or question them to 
                                                          Management or question them to 
     Risk                         Qualitative             create the PIM Scale.
                                                          create the PIM Scale.
   Response                       Risk Analysis
                                                          Identification of Risk Responses
                                                           Identification of Risk Responses
                                                          based on predicted Risk PIM 
                                                           based on predicted Risk PIM 
                      4                                   scores.
                                                           scores.
                Quantitative 
                Risk Analysis                             Planned inclusion of Risk 
                                                          Planned inclusion of Risk 
                                                          Discussion within the course of the 
                                                          Discussion within the course of the 
                                                          meeting topics.  
                                                          meeting topics.  
Slide: 4


Effective Risk Management, Measurement, Monitoring & Control
Risk Cycle
                                                   Risk Measurement          2   3   4
                      1                             • Involves proactive identification of 
                    Risk 
                                                      the Risk
                  Planning
                                                    • Involves Qualitatively Identifying the 
      6                                               Probability & Impact of the Risk
                                       2




                                                                                                   © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
     Risk 
                                      Risk          • Involves Quantitatively Identifying 
  Monitoring 
                                  Identification      the Probability and Impact of the Risk
   & Control
                Effective Risk                      • Involves Calculating the Probability & 




                                                                                                     2009, Karen Yvonne Lucas, PMP –
                Management,                           Impact Measurement (PIM) Score.
                Measurement,  
                Monitoring & 
                   Control

      5                                3            • NOTE:  All PIM calculations must also 
    Risk                          Qualitative         include:
  Response                        Risk Analysis
                                                           Identifying the Risk Trigger(s):
                                                           the WBS Item where the impact 
                      4                                    will be 1st realized.
                Quantitative                               Identifying the Risk Trigger 
                Risk Analysis
                                                           Date(s): the Earliest Date when 
                                                           the impact will be realized where  
                                                           action can effect the outcome.
Slide: 5


Effective Risk Management, Measurement, Monitoring & Control
Risk Cycle
                      1
                    Risk                           Risk Monitoring & Control
                                                   Risk Monitoring & Control        6   5
                  Planning
                                                    • Involves accurate perception of Risk 
                                                    • Involves accurate perception of Risk 
      6                                               Status as the project timeline 
                                                       Status as the project timeline 
                                       2




                                                                                                   © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
     Risk                                             progresses.
                                                       progresses.
                                      Risk 
  Monitoring                                        • Involves active control of time, cost, 
                                                    • Involves active control of time, cost, 
                                  Identification
   & Control                                          resources, quality & circumstances to 
                                                       resources, quality & circumstances to 
                Effective Risk                        influence the impact of a Risk to the 
                                                       influence the impact of a Risk to the 




                                                                                                     2009, Karen Yvonne Lucas, PMP –
                Management,                           project objective.
                                                       project objective.
                Measurement,  
                Monitoring &                        • Involves the timely implementation
                                                    • Involves the timely implementation
                   Control                            of Risk Response to ensure the best 
                                                       of Risk Response to ensure the best 
                                                      outcome for a Risk to a project 
                                                       outcome for a Risk to a project 
      5                                3              objective.
                                                       objective.
     Risk                         Qualitative 
   Response                       Risk Analysis


                      4
                Quantitative 
                Risk Analysis
Slide: 6


Effective Risk Management, Measurement, Monitoring & Control
PIM Scale, Risk Log, Risk Triggers & Risk Trigger Dates
Once risks have been 
identified, planned for, 
and measured –
monitoring and 
controlling occurs. 
During monitoring & 




                                                               © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
controlling – Risk 
Triggers and Risk Trigger 
Dates are used in 
conjunction with the 
PIM score.  




                                                                 2009, Karen Yvonne Lucas, PMP –
Should a risk elevate 
into a PIM score which 
requires as Risk 
Response, the Risk 
Triggers will indicate the 
impacted area and the 
Risk Trigger Date will 
indicate when the 
planned risk response 
will be started (whether 
proactively planned or 
done as a risk is 
identified).
Slide: 7


Effective Risk Management, Measurement, Monitoring & Control
Risk Response ‐ THREATS
Once risks have been identified, planned for, and measured – monitoring and controlling occurs.  During monitoring & controlling 
– Risk Triggers and Risk Trigger Dates are used in conjunction with the PIM score.  Should a risk elevate into a PIM score which 
requires as Risk Response, the Risk Triggers will indicate the impacted area and the Risk Trigger Date will indicate when the 
planned risk response (whether proactively planned or done as a risk is identified) will be started.
As discussed, Risks have two faces – OPPORTUNITIES and THREATS.  Key in the approach to a THREAT is the Risk Response that 
is designed to manage a risk into an acceptable level that best benefits the project objective.
Examples of RISK RESPONSES to THREATS are:




                                                                                                                                                               © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
                 Avoid ‐ Includes not performing an activity that                                     Transfer ‐ Includes assigning the THREAT to 
                 could carry risk; and vigorously eliminating the                                     another entity; or, if required, keeping the impact 
                 possibility of the THREAT.  Actively seek to                                         of the THREAT while assigning the responsibility 
                 eliminate any uncertainty. This type of THREAT                                       for the THREAT to another entity.  It is best, 
                 is placed in the schedule and plans are made                                         however, to not take responsibility for the THREAT 




                                                                                                                                                                 2009, Karen Yvonne Lucas, PMP –
                 based on its occurrence, until (if the avoidance                                     or any activity associated with it in order to insure 
                 was successful) it is overcome.                                                      that the THREAT’s affects are not experienced on 
                                                                                                      your project’s Success Metrics.

                 Mitigate (reduce)  ‐ Includes employing                                              Accept – Includes (as a rule) accepting small risks 
                 approaches to the risk that reduce the severity                                      right away, and large catastrophic risks, because 
                 of the loss or the likelihood of the loss from                                       the cost of guarding against them is greater than 
                 occurring (mitigation); and, reducing the                                            the total loss from them or the projected gain.  For 
                 exposure to unwated outcomes. This type of                                           this type of THREAT retain the risk in your 
                 THREAT is placed on the schedule and the                                             schedule and budget for it’s certainty within its 
                 mitigation steps are as well until (if they are                                      working packages.  In the subsequent working 
                 successful) the threat has passed.                                                   packages, revise your schedule to achieve the 
                                                                                                      success metric regardless of the certain THREAT.
      Some of the above risk approaches may not be possible because the trade‐offs will not be are 
       acceptable to senior management.  Be sure to socialize your risk responses with your senior 
                             management and obtain their buy‐in/direction. 
Slide: 8


Effective Risk Management, Measurement, Monitoring & Control
Risk Response ‐ OPPORTUNITIES
 As discussed, Risks have two faces – OPPORTUNITIES and THREATS. Key in the approach to an OPPORTUNITY is the Risk 
 Response that is designed to encourage the certainty of is occurrence in order to ensure that the project benefits.
 OPPORTUNITIES in Risk Management are, then, “those future events that, if they happen, can reduce project cost and/or 
 schedule, or improve project technical performance.”1

 Examples of RISK RESPONSES to OPPORTUNITIES are:




                                                                                                                                                          © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
                  EXPLOIT – Includes aggressively pursuing in order                                       ENHANCE – Includes encouraging 
                  to eliminate any possibility that this will not happen.                                 situations, by modifying your 
                  This type of opportunity is planned, followed in                                        outcomes and exposure as to 
                  weekly/day‐to‐day action items, until it is caused to                                   encourage the opportunities to 




                                                                                                                                                            2009, Karen Yvonne Lucas, PMP –
                  occur or it fails.  The activity to exploit and the                                     evolve).  This type of opportunity is 
                  decision on the opportunity are reflected in the                                        planned and only included in the 
                  schedule; the  opportunity itself is only reflected in                                  schedule if it occurs. 
                  the schedule if it occurs.


                 SHARE – Includes sharing the opportunity that                                            Accept ‐ Includes accepting the 
                 mutually benefits another organization with that                                         opportunity as it comes (sometimes 
                 organization in order to join teams to ensure it                                         with little to no effort on the project 
                 occurs. You may either assign the ownership and                                          team’s part).  This type of 
                 credit for the benefits to that team, while realizing                                    opportunity is to be included in the 
                 the benefits only; or divide the credit & work                                           project baseline as it is “expected to 
                 between the two teams.  This then helps to ensure                                        occur with certainty.”) 
                 the likelihood of success.
       1   “ENTERPRISE RISK AND OPPORTUNITY MANAGEMENT – The Dream & The Reality”, Northrop Grumman Space Technology, Stephen L. Carman, May 2004.
Slide: 9


Effective Risk Management, Measurement, Monitoring & Control
Risk Response – MITIGATION & CONTINGENCY
 It will not be enough to simply know the risks your project faces.  After identifying them and recording the risk responses, you
 will need to develop well though out MITIGATION and CONTINGENCY plans to pursue in case the RISK occurs.  
 OBJECTIVE:       Mitigation is designed to reduce the probability that a risk will occur for THREATS.
                  Mitigation is designed to increase the probability that a risk will occur for OPPORTUNITIES. 
 REMEMBER: Both OPPORTUNITIES and THREATS have MITIGATION and CONTINGENCY plans. 
                  MITIGATION and CONTINGENCY plans are ONLY applied to RISKS with a HIGH or MEDIUM PIM Score.

 EXAMPLE:       There is a RISK that includes a TIME CONSTRAINT
                Example:  Orders for materials not placed before December 15th may be shipped after January 5th.




                                                                                                                                    © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
                MITIGATION        Schedule the item associated with the risk to start earlier in the schedule.  
                                  This will be beneficial because…
                                      FOR A THREAT it increases the time to accomplish.  
                                      FOR AN OPPORTUNITY it will clear the obstacle, ensuring the OPPORTUNITY occurs.




                                                                                                                                      2009, Karen Yvonne Lucas, PMP –
 EXAMPLE:       There is a RISK that includes a RESOURCE CONSTRAINT (and therefore a COST CONSTRAINT) 
                Example: Your company is planning a Reduction In Force (RIF) in the Spring which is mid‐lifecycle in your 
                EXECUTION phase.  Your expenditures will be expected to reduce coinciding with the RIF.
                CONTINGENCY: You may choose to enter into a CONTRACT for resources to perform the EXECUTION phase.
                                  You may choose to also request they push the project into the next phase.  
                                  FOR A THREAT & FOR AN OPPORTUNITY
                                  (1)  Guard costs with a FIRM FIXED PRICE contract.  
                                  (2)  Bring the team aboard early to push the project’s planned value versus earned value.
                                  (3)  Request that you obtain billing for the resources before the end of the current phase.  
                                  (4)  For TIME & MATERIALS guard costs by requesting a performance based contract.
                                  (5)  Request work in a 24/7 teamed iterative method where metrics are measured weekly.  
                                  This will be beneficial because …
                                      Your costs will increase during this time as will your earned value.  
                                       Your expenditures will be inflated in the billing summary.
                                       Your reduction in billables will be easier as less resources will be needed for the next 
                                            phase.
Slide: 10


Effective Risk Management, Measurement, Monitoring & Control
RISK EXERCISE
         EXAMPLE: Christmas Present Delivery via XYZ Special Delivery  (PROJECT)
         Story:     1 month before Christmas we ordered presents on‐line. The delivery
                    carrier selected was XYZ Special Delivery because of their cost and 
                    customer service (quality decision) .  XYZ Special Delivery is known for 
                    great customer service because they allow customers to re‐route their




                                                                                                         © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
                    delivery choices (at a fee) to Overnight for emergency circumstances
                    when there are not 4 business days available.  XYZ Special Delivery has 
                    shipped all packages and have provided us an expected delivery
                    timeine within 3‐5 business days and not later than 1 week before
                    Christmas (Thur. 12/25/08).  This is very important to us because in our




                                                                                                           2009, Karen Yvonne Lucas, PMP –
                    GrandMom’s house all presents must be wrapped and under the tree
                    before Christmas Day (project objective).  If we get them under the tree
                    early, GrandMom often gives out cash as a Thank You (performance 
                    incentive).  So, at the latest delivery time, we can still wrap the presents
                    (the work packages) in time for Christmas Day.  
Slide: 11


Effective Risk Management, Measurement, Monitoring & Control
RISK EXERCISE ‐ TOGETHER
        EXAMPLE:   Christmas Present Delivery via XYZ Special Delivery  (PROJECT)
        Story:     1 month before Christmas we ordered presents on‐line. The delivery carrier selected was XYZ 
                   Special Delivery because of their cost and customer service (quality decision) .  XYZ Special
                   Delivery is known for great customer service because they allow customers to re‐route their
                   delivery choices (at a fee) to Overnight for emergency circumstances when there are not 4 
                   business days available.  XYZ Special Delivery has shipped all packages and have provided us 
                   an expected delivery timeine within 3‐5 business days and not later than 1 week before
                   Christmas (Thur. 12/25/08).  This is very important to us because in our GrandMom’s house 
                   all presents must be wrapped and under the tree before Christmas Day (project objective).  If 




                                                                                                                           © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
                   we get them under the tree early, GrandMom often gives out cash as a Thank You 
                   (performance incentive).  So, at the latest delivery time, we can still wrap the presents (the 
                   work packages) in time for Christmas Day.
        Risk 1:    XYZ Special Delivery does not deliver after 5pm or on weekends.  




                                                                                                                             2009, Karen Yvonne Lucas, PMP –
        Risk 2:    XYZ Special Delivery has experienced a surge of delivery requests for the Christmas Holiday 
                   but has not increased delivery personnel for the surge (potential resource constraint).
        Risk 3:    XYZ company allows customers to re‐route their delivery choices (at a fee) to Overnight for 
                   emergency circumstances when there are not 4 business days available.
        Risk 4:    If we meet the project objective we get a performance incentive:  in our GrandMom’s house 
                   all presents must be wrapped and under the tree before Christmas Day (project objective).  If 
                   we get them under the tree early, GrandMom often gives out cash as a Thank You 
                   (performance incentive).
Slide: 12


Effective Risk Management, Measurement, Monitoring & Control
RISK EXERCISE – EXPLANATIONS
         EVALUATION & ANALYSIS:
         Question: When is the Risk Trigger?
         Answer:   The milestone in the schedule for DELIVERY.  DELIVERY is the Risk Trigger because all 
                   subsequent work packages that lead to the objective hinge on us receiving the 
                   presents.

         Question:   When is the Risk Trigger Date?




                                                                                                                   © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
         Answer:     The Risk Trigger Date should be the EARLIEST date where the Risk can be realized AND 
                     a Risk Response can effect the outcome.  Therefore, the Risk Trigger Date IS NOT 1 
                     week prior to Christmas (Thur. 12/18/08) because there are 4 business days available.  
                     Chosing this date will allow us no risk response except ACCEPT.  If the Risk Trigger Date 
                     is 12/17/08, we could receive packages as early as 12/18/08 (overnight) and – if we
                     waited until the close of business ofn 12/17/08 we would receive them 12/22/08 –




                                                                                                                     2009, Karen Yvonne Lucas, PMP –
                     each providing us time to wrap the presents and place them under the tree.  

         RECOMMENDATION:
         Question: What is the Risk Response?
         Answer:   The Risk Response is MITIGATE.  In this instance, the risk can be anticipated.  As a 
                   result, the risk response can be properly planned.  The Risk Response action would
                   then be:  REQUEST OVERNIGHT SHIPPING @ EMERGENCY FEE on 12/17/08.
Slide: 13


Effective Risk Management, Measurement, Monitoring & Control
RISK EXERCISE – ON YOUR OWN
          EXAMPLE:   Christmas Present Delivery via XYZ Special Delivery  (PROJECT)
          Story:     1 month before Christmas we ordered presents on‐line. The delivery carrier selected was XYZ Special
                     Delivery because of their cost and customer service (quality decision) .  XYZ Special Delivery is known
                     for great customer service because they allow customers to re‐route their delivery choices (at a fee) 
                     to Overnight for emergency circumstances when there are not 4 business days available.  XYZ Special
                     Delivery has shipped all packages and have provided us an expected delivery timeine within 3‐5 
                     business days and not later than 1 week before Christmas (Thur. 12/25/08).  This is very important to 
                     us because in our GrandMom’s house all presents must be wrapped and under the tree before
                     Christmas Day (project objective).  If we get them under the tree early, GrandMom often gives out 
                     cash as a Thank You (performance incentive).  So, at the latest delivery time, we can still wrap the 




                                                                                                                                     © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED
                     presents (the work packages) in time for Christmas Day.
          Risk 1:    XYZ Special Delivery does not deliver after 5pm or on weekends.  
          Risk 2:    XYZ Special Delivery has experienced a surge of delivery requests for the Christmas Holiday but has 
                     not increased delivery personnel for the surge (potential resource constraint).




                                                                                                                                       2009, Karen Yvonne Lucas, PMP –
          Risk 3:    XYZ company allows customers to re‐route their delivery choices (at a fee) to Overnight for 
                     emergency circumstances when there are not 4 business days available.
          Risk 4:    If we meet the project objective we get a performance incentive:  in our GrandMom’s house all 
                     presents must be wrapped and under the tree before Christmas Day (project objective).  If we get
                     them under the tree early, GrandMom often gives out cash as a Thank You (performance incentive).

   ON YOUR OWN       Create the RISK LOG from the above story, selecting 1 of the above 4 identified risks.  
                     Use the PIM in this presentation.  Be sure to:
                      (1) Provide the Risk Impact, Risk Description, Risk PIM, Risk Category, Risk Status, 
                           Risk Owner, Risk Trigger and Risk Trigger Date
                      (2) Indicate your RISK’s Mitigation Response and Contingency Response, if 
                           applicable.
Questions & Answers




                                                                                 Contact:
                                                                Karen Yvonne Lucas, PMP  
© 2009, Karen Yvonne Lucas, PMP – ALL RIGHTS RESERVED
  2009, Karen Yvonne Lucas, PMP –                       kylucas@gmail.com |  202‐352‐4397

More Related Content

What's hot

Severe Weather Preparedness and Resiliency
Severe Weather Preparedness and ResiliencySevere Weather Preparedness and Resiliency
Severe Weather Preparedness and ResiliencyMissionMode
 
Cynthia.calhoun
Cynthia.calhounCynthia.calhoun
Cynthia.calhounNASAPMC
 
Florida Association of Community Colleges, Council of Student Affairs Present...
Florida Association of Community Colleges, Council of Student Affairs Present...Florida Association of Community Colleges, Council of Student Affairs Present...
Florida Association of Community Colleges, Council of Student Affairs Present...Margolis Healy
 
Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...
Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...
Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...Ricky Smith CMRP, CMRT
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.jNASAPMC
 
January 2010 Control Your Most Precious Asset
January 2010   Control Your Most Precious AssetJanuary 2010   Control Your Most Precious Asset
January 2010 Control Your Most Precious Assetgatelyw396
 
Managing Risk in e-Learning
Managing Risk in e-LearningManaging Risk in e-Learning
Managing Risk in e-LearningKnowledgeWorking
 
Behaviour Observation Process
Behaviour Observation ProcessBehaviour Observation Process
Behaviour Observation ProcessWilliam Wootton
 
Agile Network India | Risk Management in Agile World | Dipti Trivedi
Agile Network India | Risk Management in Agile World | Dipti TrivediAgile Network India | Risk Management in Agile World | Dipti Trivedi
Agile Network India | Risk Management in Agile World | Dipti TrivediAgileNetwork
 
Tech Ed 2009 Practical Tips To Manage Projects Productively
Tech Ed 2009   Practical Tips To Manage Projects ProductivelyTech Ed 2009   Practical Tips To Manage Projects Productively
Tech Ed 2009 Practical Tips To Manage Projects Productivelyrsnarayanan
 
Doug brown
Doug brownDoug brown
Doug brownNASAPMC
 

What's hot (18)

Severe Weather Preparedness and Resiliency
Severe Weather Preparedness and ResiliencySevere Weather Preparedness and Resiliency
Severe Weather Preparedness and Resiliency
 
Cynthia.calhoun
Cynthia.calhounCynthia.calhoun
Cynthia.calhoun
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Florida Association of Community Colleges, Council of Student Affairs Present...
Florida Association of Community Colleges, Council of Student Affairs Present...Florida Association of Community Colleges, Council of Student Affairs Present...
Florida Association of Community Colleges, Council of Student Affairs Present...
 
Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...
Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...
Advanced Maintenance And Reliability (Best Maintenance and Reliability Practi...
 
Risk management
Risk managementRisk management
Risk management
 
Canga.m.wood.j
Canga.m.wood.jCanga.m.wood.j
Canga.m.wood.j
 
January 2010 Control Your Most Precious Asset
January 2010   Control Your Most Precious AssetJanuary 2010   Control Your Most Precious Asset
January 2010 Control Your Most Precious Asset
 
Srm
SrmSrm
Srm
 
Managing Risk in e-Learning
Managing Risk in e-LearningManaging Risk in e-Learning
Managing Risk in e-Learning
 
Behaviour Observation Process
Behaviour Observation ProcessBehaviour Observation Process
Behaviour Observation Process
 
Agile risk management
Agile risk managementAgile risk management
Agile risk management
 
Agile Network India | Risk Management in Agile World | Dipti Trivedi
Agile Network India | Risk Management in Agile World | Dipti TrivediAgile Network India | Risk Management in Agile World | Dipti Trivedi
Agile Network India | Risk Management in Agile World | Dipti Trivedi
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
InTechnology InSpire Newsletter - Issue 4
InTechnology InSpire Newsletter - Issue 4InTechnology InSpire Newsletter - Issue 4
InTechnology InSpire Newsletter - Issue 4
 
Tech Ed 2009 Practical Tips To Manage Projects Productively
Tech Ed 2009   Practical Tips To Manage Projects ProductivelyTech Ed 2009   Practical Tips To Manage Projects Productively
Tech Ed 2009 Practical Tips To Manage Projects Productively
 
Agile Risk Management
Agile Risk ManagementAgile Risk Management
Agile Risk Management
 
Doug brown
Doug brownDoug brown
Doug brown
 

Viewers also liked

How to monitor your project progress
How to monitor your project progressHow to monitor your project progress
How to monitor your project progressAsif A. Kabani
 
Risk Management
Risk ManagementRisk Management
Risk Managementcgeorgeo
 
Risk mangement
Risk mangementRisk mangement
Risk mangementcollege
 
Quality Control and Measurement Uncertainty
Quality Control and Measurement UncertaintyQuality Control and Measurement Uncertainty
Quality Control and Measurement UncertaintyCLEEN_Ltd
 
PM Session 7
PM Session 7PM Session 7
PM Session 7dmdk12
 
Credit Risk Management Primer
Credit Risk Management PrimerCredit Risk Management Primer
Credit Risk Management Primerav vedpuriswar
 
Credit risk management (2)
Credit risk management (2)Credit risk management (2)
Credit risk management (2)Ujjwal 'Shanu'
 
Transportation dubai
Transportation dubaiTransportation dubai
Transportation dubaimbaslides
 
Risk Management
Risk ManagementRisk Management
Risk Managementrajuinstru
 
Credit monitoring & early alert process
Credit monitoring & early alert processCredit monitoring & early alert process
Credit monitoring & early alert processSandip Kar
 
ملخص عمليات إدارة مشروعات التشييد
ملخص عمليات إدارة مشروعات التشييدملخص عمليات إدارة مشروعات التشييد
ملخص عمليات إدارة مشروعات التشييدTamer El-Bagoury, PMP
 
21.risk management concept By Allah Dad Khan
21.risk management concept  By Allah Dad Khan21.risk management concept  By Allah Dad Khan
21.risk management concept By Allah Dad KhanMr.Allah Dad Khan
 
Risk Matrix, definition, theory and practice/DRM Series/Bijan Yavar
Risk Matrix, definition, theory and practice/DRM Series/Bijan YavarRisk Matrix, definition, theory and practice/DRM Series/Bijan Yavar
Risk Matrix, definition, theory and practice/DRM Series/Bijan YavarBijan Yavar
 

Viewers also liked (20)

How to monitor your project progress
How to monitor your project progressHow to monitor your project progress
How to monitor your project progress
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
Project management
Project managementProject management
Project management
 
Risk mangement
Risk mangementRisk mangement
Risk mangement
 
Risk management
Risk managementRisk management
Risk management
 
Quality Control and Measurement Uncertainty
Quality Control and Measurement UncertaintyQuality Control and Measurement Uncertainty
Quality Control and Measurement Uncertainty
 
PM Session 7
PM Session 7PM Session 7
PM Session 7
 
Credit Risk Management Primer
Credit Risk Management PrimerCredit Risk Management Primer
Credit Risk Management Primer
 
Credit Monitoring
Credit MonitoringCredit Monitoring
Credit Monitoring
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
Credit risk management (2)
Credit risk management (2)Credit risk management (2)
Credit risk management (2)
 
The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010The Effective Program Management Office (PgMO) (c) 2010
The Effective Program Management Office (PgMO) (c) 2010
 
Transportation dubai
Transportation dubaiTransportation dubai
Transportation dubai
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Credit monitoring & early alert process
Credit monitoring & early alert processCredit monitoring & early alert process
Credit monitoring & early alert process
 
ملخص عمليات إدارة مشروعات التشييد
ملخص عمليات إدارة مشروعات التشييدملخص عمليات إدارة مشروعات التشييد
ملخص عمليات إدارة مشروعات التشييد
 
21.risk management concept By Allah Dad Khan
21.risk management concept  By Allah Dad Khan21.risk management concept  By Allah Dad Khan
21.risk management concept By Allah Dad Khan
 
Risk Matrix, definition, theory and practice/DRM Series/Bijan Yavar
Risk Matrix, definition, theory and practice/DRM Series/Bijan YavarRisk Matrix, definition, theory and practice/DRM Series/Bijan Yavar
Risk Matrix, definition, theory and practice/DRM Series/Bijan Yavar
 
Risk Measurement in practice
Risk Measurement in practiceRisk Measurement in practice
Risk Measurement in practice
 

Similar to Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved

Dynamic risk assessment lrg
Dynamic risk assessment lrgDynamic risk assessment lrg
Dynamic risk assessment lrgLance Grindley
 
Shared Services for Finance & Accounting - Wheelhouse Advisors 7.15.08
Shared Services for Finance & Accounting -  Wheelhouse Advisors 7.15.08Shared Services for Finance & Accounting -  Wheelhouse Advisors 7.15.08
Shared Services for Finance & Accounting - Wheelhouse Advisors 7.15.08Wheelhouse Advisors LLC
 
HML Risk Transformation
HML Risk TransformationHML Risk Transformation
HML Risk TransformationAndrew Smart
 
Microsoft power point risk governance-schreckenberg_swissre_idrc_2012
Microsoft power point   risk governance-schreckenberg_swissre_idrc_2012Microsoft power point   risk governance-schreckenberg_swissre_idrc_2012
Microsoft power point risk governance-schreckenberg_swissre_idrc_2012Global Risk Forum GRFDavos
 
سيمينار إدارة المخاطر (1).pptx
سيمينار إدارة المخاطر (1).pptxسيمينار إدارة المخاطر (1).pptx
سيمينار إدارة المخاطر (1).pptxAhmadHassanein
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk managementKannan Subbiah
 
Risk Management: One CRO’s thoughts
Risk Management: One CRO’s thoughtsRisk Management: One CRO’s thoughts
Risk Management: One CRO’s thoughtsCapco
 
CONF. 404- Effective risk management and avoiding project disasters. A pragma...
CONF. 404- Effective risk management and avoiding project disasters. A pragma...CONF. 404- Effective risk management and avoiding project disasters. A pragma...
CONF. 404- Effective risk management and avoiding project disasters. A pragma...PMI-Montréal
 
Tools &Techniques for Effective Risk Management V3.0
Tools &Techniques for Effective Risk Management V3.0Tools &Techniques for Effective Risk Management V3.0
Tools &Techniques for Effective Risk Management V3.0cgautam
 
Audit Manager Whitepaper - CAMMS
Audit Manager Whitepaper - CAMMSAudit Manager Whitepaper - CAMMS
Audit Manager Whitepaper - CAMMSCAMMS
 
LINKIES. NEWS II / 2009
LINKIES. NEWS II / 2009LINKIES. NEWS II / 2009
LINKIES. NEWS II / 2009LINKIES.
 
Unified Comms Exploring Attitudes Towards Risk
Unified  Comms   Exploring Attitudes Towards RiskUnified  Comms   Exploring Attitudes Towards Risk
Unified Comms Exploring Attitudes Towards Riskrosiegregory
 
Risk management in software engineering
Risk management in software engineeringRisk management in software engineering
Risk management in software engineeringdeep sharma
 
5 easy steps of contingency planning
5 easy steps of contingency planning5 easy steps of contingency planning
5 easy steps of contingency planningKaren Dworaczyk
 
Risk Management and Remediation
Risk Management and RemediationRisk Management and Remediation
Risk Management and RemediationCarahsoft
 

Similar to Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved (20)

Dynamic risk assessment lrg
Dynamic risk assessment lrgDynamic risk assessment lrg
Dynamic risk assessment lrg
 
Shared Services for Finance & Accounting - Wheelhouse Advisors 7.15.08
Shared Services for Finance & Accounting -  Wheelhouse Advisors 7.15.08Shared Services for Finance & Accounting -  Wheelhouse Advisors 7.15.08
Shared Services for Finance & Accounting - Wheelhouse Advisors 7.15.08
 
Riskopecredience 10 05 Final_Version
Riskopecredience 10 05 Final_VersionRiskopecredience 10 05 Final_Version
Riskopecredience 10 05 Final_Version
 
HML Risk Transformation
HML Risk TransformationHML Risk Transformation
HML Risk Transformation
 
Microsoft power point risk governance-schreckenberg_swissre_idrc_2012
Microsoft power point   risk governance-schreckenberg_swissre_idrc_2012Microsoft power point   risk governance-schreckenberg_swissre_idrc_2012
Microsoft power point risk governance-schreckenberg_swissre_idrc_2012
 
سيمينار إدارة المخاطر (1).pptx
سيمينار إدارة المخاطر (1).pptxسيمينار إدارة المخاطر (1).pptx
سيمينار إدارة المخاطر (1).pptx
 
Presentation qrm shc
Presentation qrm shcPresentation qrm shc
Presentation qrm shc
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
 
Risk Management: One CRO’s thoughts
Risk Management: One CRO’s thoughtsRisk Management: One CRO’s thoughts
Risk Management: One CRO’s thoughts
 
CONF. 404- Effective risk management and avoiding project disasters. A pragma...
CONF. 404- Effective risk management and avoiding project disasters. A pragma...CONF. 404- Effective risk management and avoiding project disasters. A pragma...
CONF. 404- Effective risk management and avoiding project disasters. A pragma...
 
Tools &Techniques for Effective Risk Management V3.0
Tools &Techniques for Effective Risk Management V3.0Tools &Techniques for Effective Risk Management V3.0
Tools &Techniques for Effective Risk Management V3.0
 
Audit Manager Whitepaper - CAMMS
Audit Manager Whitepaper - CAMMSAudit Manager Whitepaper - CAMMS
Audit Manager Whitepaper - CAMMS
 
Home brew module 8 advanced systems & processes
Home brew module 8   advanced systems & processesHome brew module 8   advanced systems & processes
Home brew module 8 advanced systems & processes
 
Operational risks
Operational risksOperational risks
Operational risks
 
LINKIES. NEWS II / 2009
LINKIES. NEWS II / 2009LINKIES. NEWS II / 2009
LINKIES. NEWS II / 2009
 
Unified Comms Exploring Attitudes Towards Risk
Unified  Comms   Exploring Attitudes Towards RiskUnified  Comms   Exploring Attitudes Towards Risk
Unified Comms Exploring Attitudes Towards Risk
 
Risk management in software engineering
Risk management in software engineeringRisk management in software engineering
Risk management in software engineering
 
5 easy steps of contingency planning
5 easy steps of contingency planning5 easy steps of contingency planning
5 easy steps of contingency planning
 
Risk Management and Remediation
Risk Management and RemediationRisk Management and Remediation
Risk Management and Remediation
 
Praxiom Overview
Praxiom OverviewPraxiom Overview
Praxiom Overview
 

Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved

  • 1. Effective Risk Management,  Measurement, Monitoring & Control Project Management Focus Presented by: Karen Yvonne Lucas, PMP   © 2009, Karen Yvonne Lucas, PMP – ALL RIGHTS RESERVED 2009, Karen Yvonne Lucas, PMP – kylucas@gmail.com |  202‐352‐4397
  • 2. Slide: 2 Effective Risk Management, Measurement, Monitoring & Control Risk Cycle Effective Risk Management,  Effective Risk Management,  Measurement, Monitoring & Control is  Measurement, Monitoring & Control is  1 the process of: the process of: Risk  proactively planning for risks Planning proactively planning for risks identifying risks identifying risks 6 2 © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED diligently conducting sound risk  diligently conducting sound risk  Risk  Risk  management,  management,  Monitoring  Identification & Control fully analyzing risk fully analyzing risk Effective Risk  2009, Karen Yvonne Lucas, PMP – customizing risk response being  customizing risk response being  Management,  sensitive to the 1st impact and the  Measurement,   sensitive to the 1st impact and the  Monitoring &  earliest timing earliest timing Control Monitoring risks until they no longer  Monitoring risks until they no longer  exist &/or the project objectives are  exist &/or the project objectives are  5 3 achieved or cancelled achieved or cancelled Risk  Qualitative  Response  Risk Analysis Effectively and Efficiently  Effectively and Efficiently  controlling risk outcomes controlling risk outcomes 4 Each of the above are done with a keen  Each of the above are done with a keen  Quantitative  focus to further the mission, goal and  focus to further the mission, goal and  Risk Analysis objectives of a  objectives of a  project/program/initiative. project/program/initiative.
  • 3. Slide: 3 Effective Risk Management, Measurement, Monitoring & Control Risk Cycle Risk Management Risk Management 1 5 6 1 Involves planning for Risk ahead of its  Involves planning for Risk ahead of its  Risk  occurrence. occurrence. Planning Involves making Risk an integral part  Involves making Risk an integral part  6 of all project meetings as opposed to  of all project meetings as opposed to  2 © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED Risk  an afterthought or separate meeting. an afterthought or separate meeting. Risk  Monitoring  NOTE:  Included in Risk Planning is the: NOTE:  Included in Risk Planning is the: Identification & Control Setup of the Probability & Impact  Setup of the Probability & Impact  Effective Risk  2009, Karen Yvonne Lucas, PMP – Measurement (PIM) Scale.  The  Measurement (PIM) Scale.  The  Management,  Measurement,   PIM Scale is “quantitative” &  PIM Scale is “quantitative” &  Monitoring &  shows the weight the business  shows the weight the business  Control places on pain/gain by threshold.   places on pain/gain by threshold.   Request the PIM from Senior  Request the PIM from Senior  5 3 Management or question them to  Management or question them to  Risk  Qualitative  create the PIM Scale. create the PIM Scale. Response  Risk Analysis Identification of Risk Responses Identification of Risk Responses based on predicted Risk PIM  based on predicted Risk PIM  4 scores. scores. Quantitative  Risk Analysis Planned inclusion of Risk  Planned inclusion of Risk  Discussion within the course of the  Discussion within the course of the  meeting topics.   meeting topics.  
  • 4. Slide: 4 Effective Risk Management, Measurement, Monitoring & Control Risk Cycle Risk Measurement 2 3 4 1 • Involves proactive identification of  Risk  the Risk Planning • Involves Qualitatively Identifying the  6 Probability & Impact of the Risk 2 © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED Risk  Risk  • Involves Quantitatively Identifying  Monitoring  Identification the Probability and Impact of the Risk & Control Effective Risk  • Involves Calculating the Probability &  2009, Karen Yvonne Lucas, PMP – Management,  Impact Measurement (PIM) Score. Measurement,   Monitoring &  Control 5 3 • NOTE:  All PIM calculations must also  Risk  Qualitative  include: Response  Risk Analysis Identifying the Risk Trigger(s): the WBS Item where the impact  4 will be 1st realized. Quantitative  Identifying the Risk Trigger  Risk Analysis Date(s): the Earliest Date when  the impact will be realized where   action can effect the outcome.
  • 5. Slide: 5 Effective Risk Management, Measurement, Monitoring & Control Risk Cycle 1 Risk  Risk Monitoring & Control Risk Monitoring & Control 6 5 Planning • Involves accurate perception of Risk  • Involves accurate perception of Risk  6 Status as the project timeline  Status as the project timeline  2 © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED Risk  progresses. progresses. Risk  Monitoring  • Involves active control of time, cost,  • Involves active control of time, cost,  Identification & Control resources, quality & circumstances to  resources, quality & circumstances to  Effective Risk  influence the impact of a Risk to the  influence the impact of a Risk to the  2009, Karen Yvonne Lucas, PMP – Management,  project objective. project objective. Measurement,   Monitoring &  • Involves the timely implementation • Involves the timely implementation Control of Risk Response to ensure the best  of Risk Response to ensure the best  outcome for a Risk to a project  outcome for a Risk to a project  5 3 objective. objective. Risk  Qualitative  Response  Risk Analysis 4 Quantitative  Risk Analysis
  • 6. Slide: 6 Effective Risk Management, Measurement, Monitoring & Control PIM Scale, Risk Log, Risk Triggers & Risk Trigger Dates Once risks have been  identified, planned for,  and measured – monitoring and  controlling occurs.  During monitoring &  © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED controlling – Risk  Triggers and Risk Trigger  Dates are used in  conjunction with the  PIM score.   2009, Karen Yvonne Lucas, PMP – Should a risk elevate  into a PIM score which  requires as Risk  Response, the Risk  Triggers will indicate the  impacted area and the  Risk Trigger Date will  indicate when the  planned risk response  will be started (whether  proactively planned or  done as a risk is  identified).
  • 7. Slide: 7 Effective Risk Management, Measurement, Monitoring & Control Risk Response ‐ THREATS Once risks have been identified, planned for, and measured – monitoring and controlling occurs.  During monitoring & controlling  – Risk Triggers and Risk Trigger Dates are used in conjunction with the PIM score.  Should a risk elevate into a PIM score which  requires as Risk Response, the Risk Triggers will indicate the impacted area and the Risk Trigger Date will indicate when the  planned risk response (whether proactively planned or done as a risk is identified) will be started. As discussed, Risks have two faces – OPPORTUNITIES and THREATS.  Key in the approach to a THREAT is the Risk Response that  is designed to manage a risk into an acceptable level that best benefits the project objective. Examples of RISK RESPONSES to THREATS are: © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED Avoid ‐ Includes not performing an activity that  Transfer ‐ Includes assigning the THREAT to  could carry risk; and vigorously eliminating the  another entity; or, if required, keeping the impact  possibility of the THREAT.  Actively seek to   of the THREAT while assigning the responsibility  eliminate any uncertainty. This type of THREAT  for the THREAT to another entity.  It is best,  is placed in the schedule and plans are made  however, to not take responsibility for the THREAT  2009, Karen Yvonne Lucas, PMP – based on its occurrence, until (if the avoidance  or any activity associated with it in order to insure  was successful) it is overcome.  that the THREAT’s affects are not experienced on  your project’s Success Metrics. Mitigate (reduce)  ‐ Includes employing  Accept – Includes (as a rule) accepting small risks  approaches to the risk that reduce the severity  right away, and large catastrophic risks, because  of the loss or the likelihood of the loss from  the cost of guarding against them is greater than  occurring (mitigation); and, reducing the  the total loss from them or the projected gain.  For  exposure to unwated outcomes. This type of  this type of THREAT retain the risk in your  THREAT is placed on the schedule and the  schedule and budget for it’s certainty within its  mitigation steps are as well until (if they are  working packages.  In the subsequent working  successful) the threat has passed.  packages, revise your schedule to achieve the  success metric regardless of the certain THREAT. Some of the above risk approaches may not be possible because the trade‐offs will not be are  acceptable to senior management.  Be sure to socialize your risk responses with your senior  management and obtain their buy‐in/direction. 
  • 8. Slide: 8 Effective Risk Management, Measurement, Monitoring & Control Risk Response ‐ OPPORTUNITIES As discussed, Risks have two faces – OPPORTUNITIES and THREATS. Key in the approach to an OPPORTUNITY is the Risk  Response that is designed to encourage the certainty of is occurrence in order to ensure that the project benefits. OPPORTUNITIES in Risk Management are, then, “those future events that, if they happen, can reduce project cost and/or  schedule, or improve project technical performance.”1 Examples of RISK RESPONSES to OPPORTUNITIES are: © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED EXPLOIT – Includes aggressively pursuing in order  ENHANCE – Includes encouraging  to eliminate any possibility that this will not happen.   situations, by modifying your  This type of opportunity is planned, followed in  outcomes and exposure as to  weekly/day‐to‐day action items, until it is caused to  encourage the opportunities to  2009, Karen Yvonne Lucas, PMP – occur or it fails.  The activity to exploit and the  evolve).  This type of opportunity is  decision on the opportunity are reflected in the  planned and only included in the  schedule; the  opportunity itself is only reflected in  schedule if it occurs.  the schedule if it occurs. SHARE – Includes sharing the opportunity that  Accept ‐ Includes accepting the  mutually benefits another organization with that  opportunity as it comes (sometimes  organization in order to join teams to ensure it  with little to no effort on the project  occurs. You may either assign the ownership and  team’s part).  This type of  credit for the benefits to that team, while realizing  opportunity is to be included in the  the benefits only; or divide the credit & work  project baseline as it is “expected to  between the two teams.  This then helps to ensure  occur with certainty.”)  the likelihood of success. 1 “ENTERPRISE RISK AND OPPORTUNITY MANAGEMENT – The Dream & The Reality”, Northrop Grumman Space Technology, Stephen L. Carman, May 2004.
  • 9. Slide: 9 Effective Risk Management, Measurement, Monitoring & Control Risk Response – MITIGATION & CONTINGENCY It will not be enough to simply know the risks your project faces.  After identifying them and recording the risk responses, you will need to develop well though out MITIGATION and CONTINGENCY plans to pursue in case the RISK occurs.   OBJECTIVE: Mitigation is designed to reduce the probability that a risk will occur for THREATS. Mitigation is designed to increase the probability that a risk will occur for OPPORTUNITIES.  REMEMBER: Both OPPORTUNITIES and THREATS have MITIGATION and CONTINGENCY plans.  MITIGATION and CONTINGENCY plans are ONLY applied to RISKS with a HIGH or MEDIUM PIM Score. EXAMPLE: There is a RISK that includes a TIME CONSTRAINT Example:  Orders for materials not placed before December 15th may be shipped after January 5th. © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED MITIGATION Schedule the item associated with the risk to start earlier in the schedule.   This will be beneficial because… FOR A THREAT it increases the time to accomplish.   FOR AN OPPORTUNITY it will clear the obstacle, ensuring the OPPORTUNITY occurs. 2009, Karen Yvonne Lucas, PMP – EXAMPLE: There is a RISK that includes a RESOURCE CONSTRAINT (and therefore a COST CONSTRAINT)  Example: Your company is planning a Reduction In Force (RIF) in the Spring which is mid‐lifecycle in your  EXECUTION phase.  Your expenditures will be expected to reduce coinciding with the RIF. CONTINGENCY: You may choose to enter into a CONTRACT for resources to perform the EXECUTION phase. You may choose to also request they push the project into the next phase.   FOR A THREAT & FOR AN OPPORTUNITY (1)  Guard costs with a FIRM FIXED PRICE contract.   (2)  Bring the team aboard early to push the project’s planned value versus earned value. (3)  Request that you obtain billing for the resources before the end of the current phase.   (4)  For TIME & MATERIALS guard costs by requesting a performance based contract. (5)  Request work in a 24/7 teamed iterative method where metrics are measured weekly.   This will be beneficial because … Your costs will increase during this time as will your earned value.   Your expenditures will be inflated in the billing summary. Your reduction in billables will be easier as less resources will be needed for the next  phase.
  • 10. Slide: 10 Effective Risk Management, Measurement, Monitoring & Control RISK EXERCISE EXAMPLE: Christmas Present Delivery via XYZ Special Delivery  (PROJECT) Story: 1 month before Christmas we ordered presents on‐line. The delivery carrier selected was XYZ Special Delivery because of their cost and  customer service (quality decision) .  XYZ Special Delivery is known for  great customer service because they allow customers to re‐route their © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED delivery choices (at a fee) to Overnight for emergency circumstances when there are not 4 business days available.  XYZ Special Delivery has  shipped all packages and have provided us an expected delivery timeine within 3‐5 business days and not later than 1 week before Christmas (Thur. 12/25/08).  This is very important to us because in our 2009, Karen Yvonne Lucas, PMP – GrandMom’s house all presents must be wrapped and under the tree before Christmas Day (project objective).  If we get them under the tree early, GrandMom often gives out cash as a Thank You (performance  incentive).  So, at the latest delivery time, we can still wrap the presents (the work packages) in time for Christmas Day.  
  • 11. Slide: 11 Effective Risk Management, Measurement, Monitoring & Control RISK EXERCISE ‐ TOGETHER EXAMPLE: Christmas Present Delivery via XYZ Special Delivery  (PROJECT) Story: 1 month before Christmas we ordered presents on‐line. The delivery carrier selected was XYZ  Special Delivery because of their cost and customer service (quality decision) .  XYZ Special Delivery is known for great customer service because they allow customers to re‐route their delivery choices (at a fee) to Overnight for emergency circumstances when there are not 4  business days available.  XYZ Special Delivery has shipped all packages and have provided us  an expected delivery timeine within 3‐5 business days and not later than 1 week before Christmas (Thur. 12/25/08).  This is very important to us because in our GrandMom’s house  all presents must be wrapped and under the tree before Christmas Day (project objective).  If  © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED we get them under the tree early, GrandMom often gives out cash as a Thank You  (performance incentive).  So, at the latest delivery time, we can still wrap the presents (the  work packages) in time for Christmas Day. Risk 1: XYZ Special Delivery does not deliver after 5pm or on weekends.   2009, Karen Yvonne Lucas, PMP – Risk 2: XYZ Special Delivery has experienced a surge of delivery requests for the Christmas Holiday  but has not increased delivery personnel for the surge (potential resource constraint). Risk 3: XYZ company allows customers to re‐route their delivery choices (at a fee) to Overnight for  emergency circumstances when there are not 4 business days available. Risk 4: If we meet the project objective we get a performance incentive:  in our GrandMom’s house  all presents must be wrapped and under the tree before Christmas Day (project objective).  If  we get them under the tree early, GrandMom often gives out cash as a Thank You  (performance incentive).
  • 12. Slide: 12 Effective Risk Management, Measurement, Monitoring & Control RISK EXERCISE – EXPLANATIONS EVALUATION & ANALYSIS: Question: When is the Risk Trigger? Answer: The milestone in the schedule for DELIVERY.  DELIVERY is the Risk Trigger because all  subsequent work packages that lead to the objective hinge on us receiving the  presents. Question: When is the Risk Trigger Date? © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED Answer: The Risk Trigger Date should be the EARLIEST date where the Risk can be realized AND  a Risk Response can effect the outcome.  Therefore, the Risk Trigger Date IS NOT 1  week prior to Christmas (Thur. 12/18/08) because there are 4 business days available.   Chosing this date will allow us no risk response except ACCEPT.  If the Risk Trigger Date  is 12/17/08, we could receive packages as early as 12/18/08 (overnight) and – if we waited until the close of business ofn 12/17/08 we would receive them 12/22/08 – 2009, Karen Yvonne Lucas, PMP – each providing us time to wrap the presents and place them under the tree.   RECOMMENDATION: Question: What is the Risk Response? Answer: The Risk Response is MITIGATE.  In this instance, the risk can be anticipated.  As a  result, the risk response can be properly planned.  The Risk Response action would then be:  REQUEST OVERNIGHT SHIPPING @ EMERGENCY FEE on 12/17/08.
  • 13. Slide: 13 Effective Risk Management, Measurement, Monitoring & Control RISK EXERCISE – ON YOUR OWN EXAMPLE: Christmas Present Delivery via XYZ Special Delivery  (PROJECT) Story: 1 month before Christmas we ordered presents on‐line. The delivery carrier selected was XYZ Special Delivery because of their cost and customer service (quality decision) .  XYZ Special Delivery is known for great customer service because they allow customers to re‐route their delivery choices (at a fee)  to Overnight for emergency circumstances when there are not 4 business days available.  XYZ Special Delivery has shipped all packages and have provided us an expected delivery timeine within 3‐5  business days and not later than 1 week before Christmas (Thur. 12/25/08).  This is very important to  us because in our GrandMom’s house all presents must be wrapped and under the tree before Christmas Day (project objective).  If we get them under the tree early, GrandMom often gives out  cash as a Thank You (performance incentive).  So, at the latest delivery time, we can still wrap the  © 2009, Karen Yvonne Lucas, PMP  – ALL RIGHTS RESERVED presents (the work packages) in time for Christmas Day. Risk 1: XYZ Special Delivery does not deliver after 5pm or on weekends.   Risk 2: XYZ Special Delivery has experienced a surge of delivery requests for the Christmas Holiday but has  not increased delivery personnel for the surge (potential resource constraint). 2009, Karen Yvonne Lucas, PMP – Risk 3: XYZ company allows customers to re‐route their delivery choices (at a fee) to Overnight for  emergency circumstances when there are not 4 business days available. Risk 4: If we meet the project objective we get a performance incentive:  in our GrandMom’s house all  presents must be wrapped and under the tree before Christmas Day (project objective).  If we get them under the tree early, GrandMom often gives out cash as a Thank You (performance incentive). ON YOUR OWN Create the RISK LOG from the above story, selecting 1 of the above 4 identified risks.   Use the PIM in this presentation.  Be sure to: (1) Provide the Risk Impact, Risk Description, Risk PIM, Risk Category, Risk Status,  Risk Owner, Risk Trigger and Risk Trigger Date (2) Indicate your RISK’s Mitigation Response and Contingency Response, if  applicable.
  • 14. Questions & Answers Contact: Karen Yvonne Lucas, PMP   © 2009, Karen Yvonne Lucas, PMP – ALL RIGHTS RESERVED 2009, Karen Yvonne Lucas, PMP – kylucas@gmail.com |  202‐352‐4397