1. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
A
B
HARD LANDSCAPE WORKS
Construct and complete including where necessary,
excavation, lay and subgrade, lean concrete and related
works which deem necessary for proper completion of
the whole construction to the satisfaction of the
Landscape Architect for the following items:
Brick Works
Pavement Pattern
To construct and complete pavement pattern with
150mm thick R.C slab with BRC A8 Grade 30 to Engineer’s
detail complete with concrete imprint pattern and colour
to Landscape Architect drawing and specification.
Brick Wall
110mm Thick in common clay bricks as described in
composition mortar as described reinforced with and
including brick reinforcement.
m2
m2
54
30
160
110
8640
3300
Total to Hardscape Summary Page 11 940
BILLS OF QUANTITIES
2. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
A
B
C
HARD LANDSCAPE WORKS
Construct and complete including where necessary,
excavation, lay and subgrade, lean concrete and related
works which deem necessary for proper completion of
the whole construction to the satisfaction of the
Landscape Architect for the following items:-
Open Space
Benches
To construct and complete 1500mm length × 1200mm
width × 500mm high concrete benches with 100mm thick
R.C benches top with pebble wash finish to Engineer’s
detail inclusive of light brown broken stone cladding to
L.A approval with 100mm thick brick wall to Engineer’s
detail and R.C Slab to Engineer’s detail and all other
related works as per L.A drawing and specification.
Rubbish Bin
To supply and install 540mmØ × 900mm high rubbish bin
with 50mm × 10mm stainless steel at top and 50mm ×
10mm stainless steel with 10mm dustbin stainless steel at
the bottom to be bolt and nut with 20mm × 50mm ×
575mm H.W complete with MPSJ logo in the 130mm ×
145mm plate steel inclusive of 60mm dia. hollow stainless
steel with 10mm dustbin stainless steel base and all other
related works as per Landscape Architect drawing and
specification and to Local Authority approval.
Bug Zapper
To supply, deliver to site, and install Flowtron BK-15D
Electronic Insect Killer.
m2
No.
No.
7
1
3
5228
1600
272
36 596
1600
816
Total to Hardscape Summary Page 39 012
BILLS OF QUANTITIES
3. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
HARD LANDSCAPE WORKS
SUMMARY PAGE
Brick Works
Open Space
11 940
39 012
Total to Project Summary Page 50 952
BILLS OF QUANTITIES
4. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
A
1
1
2
1
SOFT LANDSCAPE WORKS
To supply nursery grown plants material as listed below,
deliver to the site, provide labour and execute planting
works as per planting details. All plants shall be free from
pest, disease, discoloration and damage.
Planting Materials
Trees
Peltophorum Pterocarpum ( Yellow Flame Tree )
( 2.0m trunk height, 50-75mm trunk diameter )
Shrubs
Aglaia Odorata ( Chinese Perfume Plant )
( 350-500mm overall height, 250-350mm spread )
Murraya Paniculata ( Orange Jessamine )
( 350-500mm overall height, 250-350mm spread )
Turfing
Zoysia Matrella ( Manilla Grass )
( 300mm × 300mm sodding size, 20mm thick topsoil )
No.
No.
No.
No.
1
10
22
41
800
20
20
28
800
200
440
1148
Total to Softscape Summary Page 2588
BILLS OF QUANTITIES
5. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
A
1
2
1
2
3
1
2
SOFT LANDSCAPE WORKS
To supply nursery grown plants material as listed below,
deliver to the site, provide labour and execute planting
works as per planting details. All plants shall be free from
pest, disease, discoloration and damage.
Planting Operation
Hole Excavation
To supply all labour, equipment, tool, transportation and
excavation holes as following :-
Trees ( 1.0m × 1.0m × 1.0m )
Shrubs ( 0.45m × 0.45m × 0.45m )
Topsoil & Soil Mixtures
To prepare the ratio of 3 : 2 : 1 topsoil and mixtures :-
3 part is good quality top soil, 2 part is river sand and 1
part is organic fertilizer of well-rooted farmyard manure
Trees ( 1.0m × 1.0m × 1.0m ) x 1 nos
Shrubs ( 0.45m × 0.45m × 0.45m ) x 32 nos
Turfing (0.20m x 41 m2)
Tree Protection
To supply all labour, materials and provide 50mm × 50mm
Wooden stakes buried min. 900mm deep 2 per Tree and 4
nos per palm. Do not drive stake root ball. Nail wire to
stakes to prevent down movement wire completed with
encase galvanised wire in rubber at points of contact with
tree. Nylon rope may be used in liew of wire as per
Landscape Architect Drawing.
Tree staking with ( 500mm × 50mm × 2.0m ) × 1 nos
Mulching for trees and shrubs
No.
No.
m3
m3
m3
No.
m2
1
32
1
2.9
8.2
1
33
30
10
60
60
60
20
5
30
320
60
174
492
20
165
Total to Softscape Summary Page 1261
BILLS OF QUANTITIES
6. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
SOFT LANDSCAPE WORKS
SUMMARY PAGE
Planting Materials
Planting Operation
2588
1261
Total to Project Summary Page 3849
BILLS OF QUANTITIES
7. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
MAINTENANCE
The maintenance shall be carried during planting works
and defect liability period which includes watering,
fertilizing, pruning, aerifying the soil, site cleaning, pest
control, thriving the unhealthy, replacing dead plants and
other maintenance works and procedures plant as
specified.
During the maintenance period, Contractors to provide
the following matters:
i. 3 full time maintenance workers
ii. Fertilizer, insecticide
iii. Provision of maintenance machineries
iv. To remove landscape debris away from the
site to contractor’s own dumping ground.
During warranty period, Landscape Contractors to
prepare the following mater:
i. Monthly maintenance work programme
ii. Maintenance daily work programme or site
iii. Attendance to be recorded and acknowledges
by the project management, client
representative and verify by Landscape
Architect at site for monthly maintenance
claim procedure.
Note:
Contractor to provide competent person to report to
Landscape Architect during implementation and
maintenance.
mth 12 1500 18 000
Total to Project Summary Page 18 000
BILLS OF QUANTITIES
8. APJ SURVEYING
ITEM DESCRIPTION UNIT QTY
RATE AMOUNT
RM RM
PROJECT SUMMARY
Hardscape Works
Softscape Works
Maintenance
50 952
3849
18 000
Total Project Cost 72 801