4. Power in UAE..?
Production capacity – 18.74 GW. (lack in peak seasonal times)
Lack of natural gas
Gulf Cooperation Council – UAE, Kuwait, Qatar, Bahrain, Saudi Arabia & Oman
GCC began region-wide power grid – demand
UAE has no spare power capacity
Phase 3 of GCC grid to southern system of UAE
In Dec’2009 $20 billion contract to Korean Electric Power – 4 nuclear reactors
1st reactor may 2017 – each reactor 1400 MW
R.SARAVANAN, PGET, L&T UAE 4
5. Electric power transmission..?
The bulk transfer of electrical energy, from generating power
plants to substations
Power is usually transmitted through overhead power lines
Underground power transmission has a significantly higher cost
and greater operational limitations - urban & sensitive areas
Overhead Power lines..?
An electric power transmission line suspended by
towers
It is the lowest-cost method of transmission for large
quantities of electric energy (most of insulation by air)
The bare wire conductors on the line are generally
made of aluminum R.SARAVANAN, PGET, L&T UAE 5
6. Transmission tower..?
• Tall structure usually a Steel lattice tower, used
to support an overhead power line
• Electricity pylon – UK & parts of Europe
• Ironman – Australia
• Hydro tower in parts of Canada
R.SARAVANAN, PGET, L&T UAE 6
11. Bracings
Provided for interconnecting the legs
To afford desired slenderness ratio for economical tower
design
Framing angle b/w bracings & main leg members shall not
be < 15 degree
Patterns are
a) Single web system
b) Double web or warren system
c) Pratt system
d) Portal system
e) Diamond Bracing system
f) Multiple Bracing System
R.SARAVANAN, PGET, L&T UAE 11
12. 1.Struts are designed 1.Tension diagonal 1.Shear carried by
in compression & give eff.support to diagonal member(t)
Diagonals in tension compression one @ 2.Large deflection
2.NARROW BASE pt of connections under heavy loads
2.Used in both large 3.Unequal shears at
3.66Kv single circuit
and small towers top of four stubs for
design
R.SARAVANAN, PGET, L&T UAE 12
13. 1.1half of Horizontal 1. Similar to waran 1.Increse in strenght
member in T & system reducing member
another C 2.Horizontal member sizes
2.Advantageous to carry no primary 2.Increase in No.of
use it in BOTTOM loads designed as bolts, fabrication &
panel redundant supports erection cost,
3.Extensions & 3.Overal reduction in
Heavy river crossing Wt & cost of steel
R.SARAVANAN, PGET, L&T UAE 13
14. Body Extension
Tower Extension Leg Extension
Body Extension
Used to Increase the height of tower to obtain the reqd min Ground clearance & over
road crossings, river crossings, ground obstacles
Body extensions upto 7.5m height in steps 2.5m can be used & thus form a part of
standard tower
Extensions having greater heights (25m) the suitability is checked by reducing span
length and angle of deviation. Practice in tower industry is also to specify negative body
extension (portion of tower body is truncated)
R.SARAVANAN, PGET, L&T UAE 14
15. Leg Extension
Tower Leg extensions are required when the tower was spotted in the undulated
surface / Hilly terrain.
While spotting the tower locations in hilly areas requires more benching or revetment
or both are involved , but suitable hill side (leg extensions) can be used to minimize
benching or revetment or both.
Two types of Leg extension :
i) Universal leg extension
ii) Individual leg extension
R.SARAVANAN, PGET, L&T UAE 15
16. Types of Tower
1) Type of Insulator 5) No. of Circuits
• Suspension • Single Circuit
• Tension/Dead end • Double Circuit
• Transposition • Multi-Circuit
2) Type of Support 6) Deviation Angle.
• Self Supporting • Ranges from 0 to 90 deg.
• Guyed
3) Shape at the base
• Square
• Rectangle
4) kV Rating.
• Ranges from 33 to 1200
kV
• HVDC
EDRC-TL Design R.SARAVANAN, PGET, L&T UAE
23. Tower Nomenclature
Sr.
Nomenclature Deviation Remark
No.
1 A/DA/S/SLC/T0/TDL/QA/SA/V 0-20 Suspension Tower
•Used Small angle tower.
2 B/DB/AT/DLB/TD2/QB/X 0-300
• Used as a Section Tower
• Used as Medium Angle
3 C/DC/BAT/DLC/TD3/QC/CZ 30-60 Tower
•Used as a Transposition
60- •Used as a large angle Tower
4 D/DD/BAT/DE/TD6/TDT/QD/DE 900/Dead •Used as a Dead End
End Tower
R.SARAVANAN, PGET, L&T UAE 23
24. Height of Tower Structure
Height of tower is determine by-
H h1 h2 h3 h4
h1=Minimum permissible ground clearance
h2=Maximum sag
h3=Vertical spacing between conductors
h4=Vertical clearance between earth wire
and top conductor
R.SARAVANAN, PGET, L&T UAE 24
25. ELECTRICAL CLEARANCES
Sr.
Type of Clearance 132 kV 220 kV 400 kV 765 kV
No
1 Ground Clearance 6.1 m 7.0 m 8.84 m 15.5 m
2 Live Metal Clearance in mm Swing
132 / 400 /
220 765
•Suspension insulator 15 15 1530 1980 3050 4400 (25°)
30 30 1370 1830 1860 1300 (55°)
45 - 1220 1675 -
60 1070 - -
•Tension Insulator 0 0 1530 2130 3050
•Jumper 10 20 1530 2130 3050 4400
20 40 1070 1675 1860 1300
30 - 1070 - - -
3 Mid Span Clearance (m) 6.1 8.5 9.0 12.4
4 Shielding Angle (Deg) 30 30 20 20
5 Phase to Phase Clearance Vertical 3.9 m 4.9 m
Horizontal 6.8 m 8.4 m
R.SARAVANAN, PGET, L&T UAE 25
26. Right of Way :
Sr.
Type of Clearance 132 kV 220 kV 400 kV 765 kV
No
1 ROW width 27 m 35 m 52 m 85 m
R.SARAVANAN, PGET, L&T UAE 26
27. DESIGN PARAMETERS
Transmission Voltage
Number Of Circuits
Climatic Conditions
Environmental and Ecological Consideration
Conductor
Earth Wire
Insulators
Span
R.SARAVANAN, PGET, L&T UAE 27
28. Economic Voltage of Transmission of Power
L KVA E = Transmission voltage (KV) (L-L).
E 5 .5 L = Distance of transmission line in KM
1 .6 150 KVA=Power to be transferred
R.SARAVANAN, PGET, L&T UAE 28
29. Aluminum is used
it has about half the weight of copper for the
Conductor
same resistance, as well as being cheaper
Types:
AAC : All Aluminium conductors.
AAAC : All Aluminium Alloy conductors
ACSR : Aluminium conductors, Steel-Reinforced
ACAR : Aluminium conductor, Alloy-Reinforced
Bundle conductors are used to reduce corona
loses & audible noise
It consists of several conductors cables
connected by non-conducting spacers
It is used to increase the amount of current
that may be carried in line
As a disadvantage, the bundle conductors
have higher wind loading
Spacers must resist the forces due to wind,
and magnetic forces during a short-circuit
spacers
R.SARAVANAN, PGET, L&T UAE 29
31. Earth Wire
Earth wire provided above the phase conductor across the line and
grounded at every tower.
It shield the line conductor from direct strokes
Reduces voltage stress across the insulating strings during lightning strokes
Galvanized steel earth wires are used
Aerial marker balls (>600mm dia) (Red, Orange, White)
Shield angle
25 -30 up to 220 KV
20 for 400 KV and above
R.SARAVANAN, PGET, L&T UAE 31
33. Insulators
Insulator are required to support the line
conductor and provide clearance from
ground and structure.
Insulator material-
High grade Electrical Porcelain
Toughened Glass
Fiber Glass
Type of Insulator-
Disc Type
Strut Type
Long Rod Insulator
R.SARAVANAN, PGET, L&T UAE 33
34. single string
Insulator Strings
Disc insulator are joint by their ball
pins and socket in their caps to form
string.
No of insulator disc is decided by
system voltage, switching and lighting
over voltage amplitude and pollution
Double string
level.
Insulator string can be used either
suspension or tension.
Two suspension string in parallel
used at railways, road and river
crossing as statutory requirement.
Swing of suspension string due to
wind has to be taken into consider.
R.SARAVANAN, PGET, L&T UAE 34
35. Design Span lengths
1.Basic Span
Most economic span
Line is designed over level ground
The requisite ground clearance is obtained
at maximum specified temperature
R.SARAVANAN, PGET, L&T UAE 35
36. 2.Ruling Span 3.Average Span
Assumed design span that will produce,
between dead ends Mean span length between dead ends
It is used to calculate the horizontal It is assumed that the conductor is
component of tension (which is applied to all freely suspended such that each
spans b/w anchor pts) individual span reacts to change in
Tower spotting on the profile is done by tension as a single average span
means of sag template, (which is based on
ruling span) Average span = (L1+ L2+...+L6) /6
Ruling span = √ ( L1^3 + L2^3 +….+L6^3 / L1 + L2 + … + L6)
R.SARAVANAN, PGET, L&T UAE 36
37. 4.Wind Span 5.Weight Span
Half the sum of the two spans, Horizontal distance between the
adjacent to support lowest point of conductor, on the two
It is assumed that the conductor is spans adjacent to the tower
freely suspended such that each The lowest point is defined as point
individual span reacts to change in at which the tangent to sag curve
tension as a single average span It is used in design of cross-arms
Wind span = 0.5(L1 + L2)
Weight span = a1 + a2
R.SARAVANAN, PGET, L&T UAE 37
38. Determination of Base
Width
The base width(at the concrete level) is the distance between the centre of
gravity at one corner leg and the centre of gravity of the adjacent corner
leg.
A particular base width which gives the minimum total cost of the tower and
foundations.
Ryle
Formula
The ratio of base width to total tower height for most towers is generally
about one-fifth to one-tenth.
R.SARAVANAN, PGET, L&T UAE 38
38
39. Determination of Weight of
tower
Rough approximation
From knowledge of the positions of conductors & ground wire above ground level
& overturning moments
Ryle gives empirical formula in term of its height & maximum overturning moment
at base
Approximate values
132 kv – 1.7 metric tones
220 kv – 2.5 metric tones
400 kv – 7.7 metric tones
765 kv – 14 metric tones
R.SARAVANAN, PGET, L&T UAE 39
40. LOADINGS
Loads are applied in all three directions namely Transverse ( FX ),
Vertical ( FY) and Longitudinal (FZ) direction.
• Transverse loads consists of –
Wind on Conductor
Wind on Insulator
Component of Wire Tension in Transverse Direction
(Deviation Load)
Wind on Tower Body
• Vertical Load consists of –
Weight of Wire
Weight of Insulator
Weight of Line man & Tools
Self Weight of Tower
• Longitudinal Load Consist of –
Component of Unbalanced pull of the wire in the
longitudinal direction.
R.SARAVANAN, PGET, L&T UAE 40
41. Loads on Tower
Normal Condition
Broken Wire Condition
R.SARAVANAN, PGET, L&T UAE 41
42. •Loads are calculated as per the guide lines furnished in
specification/standard.
•Standards for Calculation of Loads
IS – 802 – 1977
IS – 802 – 1995
DIN – VDE 0210
ASCE Manual
IEC – 826
• The loads are calculated for following Conditions.
Reliability / Working condition
Security / Broken wire condition
Safety / Erection & maintenance Condition
R.SARAVANAN, PGET, L&T UAE 42
43. ANALYSIS & DESIGN
• Analysis is carried out by finite element software
STAAD
• Required FOS is provided in input file to find out ultimate
force
• The critical compression and tension in each member
group is found out
• Members and Connections are designed for these forces.
• Iterations are carried out for the optimum usage of tower.
R.SARAVANAN, PGET, L&T UAE 43
47. Data's for foundation design
FOUNDATION
It costs 10-30 % of overall cost of
tower
It is the last step in designing process
but precedes the construction
Overload factors assumed in designs
are 2.2 under Normal condition & 1.65
under broken-wire conditions
R.SARAVANAN, PGET, L&T UAE 47
48. 0.5 to 2m dia
Uplift loads are Non-cohesive soil
Shaft depth 3 to 15m
resisted by undistrube For non-cohesive soils
Skin friction between
material such as uncemented
ground & shaft resists
Develop uplift load of sand or gravel
uplift
2 to 3times that of an Provide pad footing
Used in usa,
iidentical footing without undercut
acceptance for wide
without undercut Usually followed in
use in India
INDIA at present
R.SARAVANAN, PGET, L&T UAE 48
49. Adopted in firm Hybrid design Augered footing with
cohesive soils Large uplift force are more than one bulb is
Undercut on the pads to be resisted used to increase the
Experience shows that SBC is low uplift capacity
this type of footing 35m long under
develop resistance to reamed to 2.5 times
uplift 2 to 3 times that dia of shaft
given footing without Clayey black cotton
undercut soils & medium dense
sandy soils
R.SARAVANAN, PGET, L&T UAE 49
50. In usa ,canada Suitable in areas with Special circumstances
Steel corroded, rock out crop River crossing towers
periodic excavation & Based on uplift, the & towers on
maintanence anchor be single bar embankments
Medium dry sand, clay or group of bars The raft at bottom
or sandy caly soils (no welded to tower leg makes the foundation
special precautions Vertical bars below substantially rigid to
necessary) stub angle form cage minimize differential
The steel is treated for footing settlement
with one coat of Grouted to a depth of
bituminous paint & about 50 times dia
top coat of asphalt into the rock
R.SARAVANAN, PGET, L&T UAE 50
52. Stub-setting
Important steps in tower
erection
The stubs are set with the help
of stub setting templates
Excavated pits are lean
concreted to correct level
Stubs are placed on lean
concrete pad
Alignment is carried by four
plumb bobs hung from centre of
the horizontal bracing
If any pit over excavated by
mistake, the extra depth should
be filled by concreting
After the stub is set, the heel
distance of four faces of the
tower and two diagonals should
be checked
R.SARAVANAN, PGET, L&T UAE 52