SlideShare a Scribd company logo
1 of 32
Lecture No:01
Dt:7th Jan 2014
Theory Max. Marks 100
Sessional Marks 20
– Attendance 10
– Test(s) 05
– Assignments 05
• Mid Semester Exam: 20
• Final Semester Exam: 60
• Practical Max. Marks 50
– Attendance 05
– Lab Evaluation Work 15
– Semester Lab Exam: 30 (Test + Viva)
Final Semester Examination will be of 3-hours duration for 3 CHs
course and each question paper will contain 5 questions without any
choice.
Lecture No:01
Dt:7th Jan 2014
 Theodolite Traversing
 General, Types & Use of Theodolite.
 Adjustment of Transit Theodolite.
 Measurements of Bearings, Horizontal & Vertical.
 Traversing with Theodolite.
 Principles & Methods of Theodolite Traversing.
 Traverse computations, close error & its adjustments.
 Tachometric surveying
 System of tachometry, Principles & field procedures of tachometry.
 Use of tachometry for Traversing.
 Curves
 Field Astronomy
 Introduction of Geographical & Astronomical terms.
 Determination of True Meridian, Latitude & Longitude & Time for astronomical
observations.
 Hydrographic Surveying
 Photographic Surveying, Principles of Aerial & Terrestrial Photogrammetry, Arial
surveying.
 Trigonometric Surveying
 Tunnel Surveying
Lecture No:01
Dt:7th Jan 2014
1. Introduction to Surveying by: Jmes.M.Anderson
2. Surveying Vol (II + III) by: BC Punmia, 9th Edition
3. Surveying by: R.Agore, 4th Edition, Khanna publisher
India.
4. Surveying & Levelling by: T.P Kanetkar & S.V Kulkarni
Lecture No:01
Dt:7th Jan 2014
So far we have been measuring horizontal angles
by using a Compass with respect to meridian, which is
less accurate and also it is not possible to measure
vertical angles with a Compass.
So when the objects are at a considerable distance
or situated at a considerable elevation or depression ,it
becomes necessary to measure horizontal and vertical
angles more precisely. So these measurements are taken
by an instrument known as a Theodolite.
Lecture No:01 Dt:7th Jan 2014
THEODOLITE SURVEYING
The system of surveying in which the angles are
measured with the help of a theodolite, is called
Theodolite surveying.
Lecture No:01 Dt:7th Jan 2014
 Theodolite is the most accurate instrument
used for measurement of horizontal and
vertical angles.
 It consist of a telescope by means of which
distant object can be sighted.
 Telescope has two different motions one in
the horizontal plane and the other in the
vertical plane.
 Theodolites are primarly classified as
 Transit and
 Non-Transit.
Lecture No:01
Dt:7th Jan 2014
Lecture No:01
Dt:7th Jan 2014
THEODOLITE USED FOR:
The Theodolite is a most accurate surveying
instrument mainly used for :
 Measuring horizontal and vertical angles.
 Locating points on a line.
 Prolonging survey lines.
 Finding difference of level.
 Setting out grades
 Ranging curves
 Tacheometric Survey
Lecture No:01
Dt:7th Jan 2014
Lecture No:01
Dt:7th Jan 2014
Theodolite Traversing Lecture No:01
Dt:7th Jan 2014
CLASSIFICATION OF THEODOLITES
Theodolites may be classified as ;
A.
i) Transit Theodolite.
ii) Non Transit Theodolite.
B.
i) Vernier Theodolites.
ii) Micrometer Theodolites.
Lecture No:01
Dt:7th Jan 2014
A. Transit Theodolite: A theodolite is called a transit
theodolite when its telescope can be transited i.e
revolved through a complete revolution about its
horizontal axis in the vertical plane, whereas in a-
Non-Transit type, the telescope cannot be transited.
They are inferior in utility and have now become
obsolete.
CLASSIFICATION OF THEODOLITES
Lecture No:01
Dt:7th Jan 2014
B. Vernier Theodolite: For reading the graduated circle if
verniers are used ,the theodolite is called as a Vernier
Theodolite.
Whereas, if a micrometer is provided to read the
graduated circle the same is called as a Micrometer
Theodolite.
Vernier type theodolites are commonly used.
CLASSIFICATION OF THEODOLITES
Lecture No:01
Dt:7th Jan 2014
SIZE OF THEODOLITE
A theodolite is designated by diameter of the
graduated circle on the lower plate.
The common sizes are 8cm to 12 cm while 14 cm to
25 cm instrument are used for triangulation work.
Greater accuracy is achieved with larger theodolites as
they have bigger graduated circle with larger divisions
hence used where the survey works require high degree
of accuracy.
Lecture No:01
Dt:7th Jan 2014
DESCRIPTION OF A
TRANSIT VERNIER THEODOLITE
A Transit vernier theodolite essentially consist of the
following :
1. Levelling Head. 6. T- Frame.
2. Lower Circular Plate. 7. Plumb –bob.
3. Upper Plate. 8. Tripod Stand.
4. Telescope.
5. Vernier Scale.
Lecture No:01
Dt:7th Jan 2014
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
1.Centering: Centering means setting the
theodolite exactly over an instrument- station
so that its vertical axis lies immediately above
the station- mark. It can be done by means of
plumb bob suspended from a small hook
attached to the vertical axis of the theodolite.
The centre shifting arrangement if provided
with the instrument helps in easy and rapid
performance of the centering.
Lecture No:01
Dt:7th Jan 2014
2. Transiting :
Transiting is also known as plunging or reversing.
It is the process of turning the telescope about its
horizontal axis through 1800 in the vertical plane
thus bringing it upside down and making it point ,
exactly in opposite direction.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:01
Dt:7th Jan 2014
3. Swinging the telescope
It means turning the telescope about its vertical
axis in the horizontal plane.
A swing is called right or left according as the
telescope is rotated clockwise or counter
clockwise.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:02
Dt:8th Jan 2014
4. Face Left
If the vertical circle of the instrument is on the
left side of the observer while taking a reading ,the
position is called the face left and
the observation taken on the horizontal or
vertical circle in this position, is known as the face
left observation
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:02
Dt: 8th Jan 2014
5. Face Right
If the vertical circle of the instrument is on the
right side of the observer while taking a reading
,the position is called the face right and
The observation taken on the horizontal or
vertical circle in this position, is known as the face
right observation.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:01
Dt:7th Jan 2014
6. Changing Face
It is the operation of bringing the vertical circle to
the right of the observer, if originally it is to the left ,
and vice – versa.
It is done in two steps; Firstly revolve the telescope
through 1800 in a vertical plane and then rotate it
through 1800 in the horizontal plane i.e first transit the
telescope and then swing it through 1800.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:01
Dt:7th Jan 2014
7. Line of Collimation
LINE OF
COLLIMATION
DIAPHRAGM
TELESCOPE
It is also known as the line of sight .It is an
imaginary line joining the intersection of the cross-
hairs of the diaphragm to the optical centre of the
object- glass and its continuation.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:02
Dt:8th Jan 2014
8. Axis of the telescope
AXIS OF THE TELESCOPE
TELESCOPE
It is also known an imaginary line joining the
optical centre of the object- glass to the centre of
eye piece.
OBJECT GLASS
.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:02
Dt:8th Jan 2014
9. Axis of the Level Tube
It is also called the bubble line.
It is a straight line tangential to the longitudinal
curve of the level tube at the centre of the tube. It
is horizontal when the bubble is in the centre.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:02
Dt:8th Jan 2014
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:02
Dt:8th Jan 2014
10. Vertical Axis
It is the axis about which the telescope can be
rotated in the horizontal plane.
11. Horizontal Axis
It is the axis about which the telescope can be
rotated in the vertical plane.
It is also called the trunnion axis.
TERMS USED IN MANIPULATING
A TRANSIT VERNIER THEODOLITE.
Lecture No:02
Dt:8th Jan 2014
The horizontal angle which the line makes with some reference direction
or meridian is called bearing of a line. There are two types;
1. Whole Circle Bearing (WCB) 2. Quadrantal/Reduced Bearing
(RB)
1. WCB: In WCB, the angle measured clockwise from North to wards the
line.
2. RB: The angle measured clockwise or anticlockwise from North or
South towards the line.
Rule for conversion WCB into RB
In first quadrant RB = WCB
In 2nd quadrant RB = 180-WCB
In 3rd quadrant RB = WCB-180
In 4th quadrant RB = 360-WCB
Bearings Lecture No:02
Dt:8th Jan 2014
Convert the following WCB to quadrant bearing by using rules of RB.
1. 680 32’
2. 1320 12’
3. 2360 37’
4. 3340 52’
Home work Lecture No:02
Dt:8th Jan 2014
It is series of connected lines.
There are two types of traverse;
1. Open traverse 2. Close traverse
1. Open traverse: In open traverse
the last point does not meet
with the starting point.
2. Close traverse: In close traverse
the last point meet with the
starting point.
Traverse Lecture No:02
Dt:8th Jan 2014
Sum of interior angles should be equal to
(2n-4) x90
Problem No:01:
The following are the interior angles of a closed traverse ABCDE
< A = 960 53’ 15”
< B = 750 03’ 17”
< C = 1590 05’ 15”
< D = 1280 33’ 43”
< E = 800 25’ 30”
Bearing of a line AB is 2870 54’ 10”, calculate the bearing of the
remaining sides of a traverse.
Check of Traverse Lecture No:02
Dt:8th Jan 2014
Lecture No:02
Dt:8th Jan 2014

More Related Content

What's hot (20)

Triangulation survey
Triangulation surveyTriangulation survey
Triangulation survey
 
Minor instruments in surveying
Minor instruments in surveyingMinor instruments in surveying
Minor instruments in surveying
 
Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
 
Trigonometric leveling 02
Trigonometric leveling  02Trigonometric leveling  02
Trigonometric leveling 02
 
Levelling
LevellingLevelling
Levelling
 
3.compass surveying
3.compass surveying3.compass surveying
3.compass surveying
 
Engineering survey
Engineering surveyEngineering survey
Engineering survey
 
Levelling
LevellingLevelling
Levelling
 
traversing survey principles.docx
traversing survey principles.docxtraversing survey principles.docx
traversing survey principles.docx
 
Traverse Survey Part 1/2
Traverse Survey Part 1/2Traverse Survey Part 1/2
Traverse Survey Part 1/2
 
Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...Surveying presentation and its objectives in detail including principles,hist...
Surveying presentation and its objectives in detail including principles,hist...
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Control surveying
Control surveyingControl surveying
Control surveying
 
Theodolite survey
Theodolite surveyTheodolite survey
Theodolite survey
 
Method Of Chaining On Sloping Ground
Method Of Chaining On Sloping GroundMethod Of Chaining On Sloping Ground
Method Of Chaining On Sloping Ground
 
Linear Measurements
Linear MeasurementsLinear Measurements
Linear Measurements
 
Levelling
LevellingLevelling
Levelling
 
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTSSURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
SURVEYING-LEVELING-MODERN SURVEYING INSTRUMENTS
 
Levelling
LevellingLevelling
Levelling
 

Similar to Surveying and Leveling

Theodolite_surveying.ppt
Theodolite_surveying.pptTheodolite_surveying.ppt
Theodolite_surveying.pptsivaganesan23
 
Unit No 2 Theodolite Surveying and Traversing.pptx
Unit No 2  Theodolite Surveying and Traversing.pptxUnit No 2  Theodolite Surveying and Traversing.pptx
Unit No 2 Theodolite Surveying and Traversing.pptxADCET, Ashta
 
Mass diagram and its characeristics .ppt
Mass diagram and its characeristics .pptMass diagram and its characeristics .ppt
Mass diagram and its characeristics .pptNITINSURESH30
 
Introduction About Theodolite Instrument Theoretical part
Introduction About Theodolite Instrument Theoretical part Introduction About Theodolite Instrument Theoretical part
Introduction About Theodolite Instrument Theoretical part Bahzad5
 
Surveying and leveling-2
Surveying and leveling-2Surveying and leveling-2
Surveying and leveling-2Gulfam Akram
 
fdocuments.in_angular-measurement-2014.ppt
fdocuments.in_angular-measurement-2014.pptfdocuments.in_angular-measurement-2014.ppt
fdocuments.in_angular-measurement-2014.pptDivyaPriya700213
 
Theodolite ppt in 7
Theodolite ppt in 7Theodolite ppt in 7
Theodolite ppt in 7Arun Kama
 
Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Enoch Wong
 
Surveying practical work book
Surveying practical work bookSurveying practical work book
Surveying practical work bookTalha Hussain
 
Site surveying report ii
Site surveying   report iiSite surveying   report ii
Site surveying report ii마 이환
 
Theodolite & measurment
Theodolite  & measurmentTheodolite  & measurment
Theodolite & measurmentMahendra meena
 
Theodolite and measurement of angles
Theodolite and measurement of anglesTheodolite and measurement of angles
Theodolite and measurement of anglesRajendra Prasad
 
Surveying short question answers
Surveying short question answersSurveying short question answers
Surveying short question answersSaurabh Pare
 

Similar to Surveying and Leveling (20)

UNIT-4B.pdf
UNIT-4B.pdfUNIT-4B.pdf
UNIT-4B.pdf
 
Theodolite_surveying.ppt
Theodolite_surveying.pptTheodolite_surveying.ppt
Theodolite_surveying.ppt
 
Theodolite lecture 1 1
Theodolite lecture 1 1Theodolite lecture 1 1
Theodolite lecture 1 1
 
Unit No 2 Theodolite Surveying and Traversing.pptx
Unit No 2  Theodolite Surveying and Traversing.pptxUnit No 2  Theodolite Surveying and Traversing.pptx
Unit No 2 Theodolite Surveying and Traversing.pptx
 
Theodolite survey
Theodolite surveyTheodolite survey
Theodolite survey
 
Mass diagram and its characeristics .ppt
Mass diagram and its characeristics .pptMass diagram and its characeristics .ppt
Mass diagram and its characeristics .ppt
 
THEODOLITE.ppsx
THEODOLITE.ppsxTHEODOLITE.ppsx
THEODOLITE.ppsx
 
Introduction About Theodolite Instrument Theoretical part
Introduction About Theodolite Instrument Theoretical part Introduction About Theodolite Instrument Theoretical part
Introduction About Theodolite Instrument Theoretical part
 
ADS .pptx
ADS .pptxADS .pptx
ADS .pptx
 
Surveying and leveling-2
Surveying and leveling-2Surveying and leveling-2
Surveying and leveling-2
 
Surveying Lab II Manual
Surveying Lab II ManualSurveying Lab II Manual
Surveying Lab II Manual
 
fdocuments.in_angular-measurement-2014.ppt
fdocuments.in_angular-measurement-2014.pptfdocuments.in_angular-measurement-2014.ppt
fdocuments.in_angular-measurement-2014.ppt
 
Theodolite ppt in 7
Theodolite ppt in 7Theodolite ppt in 7
Theodolite ppt in 7
 
Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)Fieldwork 2 (Traversing)
Fieldwork 2 (Traversing)
 
Surveying practical work book
Surveying practical work bookSurveying practical work book
Surveying practical work book
 
Site surveying report ii
Site surveying   report iiSite surveying   report ii
Site surveying report ii
 
Theodolite & measurment
Theodolite  & measurmentTheodolite  & measurment
Theodolite & measurment
 
Theodolite and measurement of angles
Theodolite and measurement of anglesTheodolite and measurement of angles
Theodolite and measurement of angles
 
Surveying short question answers
Surveying short question answersSurveying short question answers
Surveying short question answers
 
Theodolite
TheodoliteTheodolite
Theodolite
 

More from Latif Hyder Wadho

Internal Control Internal Checking Internal Auditing - Auditing By LATiFHRW
Internal Control  Internal Checking Internal Auditing - Auditing By LATiFHRWInternal Control  Internal Checking Internal Auditing - Auditing By LATiFHRW
Internal Control Internal Checking Internal Auditing - Auditing By LATiFHRWLatif Hyder Wadho
 
Supply and Demand - Modern Economics LATiFHRW
Supply and Demand - Modern Economics LATiFHRWSupply and Demand - Modern Economics LATiFHRW
Supply and Demand - Modern Economics LATiFHRWLatif Hyder Wadho
 
SPSC CCE 2013 Pcs past papers
SPSC  CCE 2013 Pcs past papersSPSC  CCE 2013 Pcs past papers
SPSC CCE 2013 Pcs past papersLatif Hyder Wadho
 
SPSC CCE 2013 Pcs screening test
SPSC CCE 2013 Pcs screening testSPSC CCE 2013 Pcs screening test
SPSC CCE 2013 Pcs screening testLatif Hyder Wadho
 
Why is english as a global language
Why is english as a global languageWhy is english as a global language
Why is english as a global languageLatif Hyder Wadho
 
Introduction to Geo technical Engineering 2
 Introduction to Geo technical Engineering 2 Introduction to Geo technical Engineering 2
Introduction to Geo technical Engineering 2Latif Hyder Wadho
 
Introdction to Geo technical Engineering
Introdction to Geo technical EngineeringIntrodction to Geo technical Engineering
Introdction to Geo technical EngineeringLatif Hyder Wadho
 
Sub surface exploration part 2
Sub surface exploration part 2Sub surface exploration part 2
Sub surface exploration part 2Latif Hyder Wadho
 
Problems on piles and deep footing
Problems on piles and deep footingProblems on piles and deep footing
Problems on piles and deep footingLatif Hyder Wadho
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of pilesLatif Hyder Wadho
 
Subsurface exploration (part-3)
Subsurface exploration (part-3)Subsurface exploration (part-3)
Subsurface exploration (part-3)Latif Hyder Wadho
 
Sub surface exploration (part-1)
Sub surface exploration (part-1)Sub surface exploration (part-1)
Sub surface exploration (part-1)Latif Hyder Wadho
 
Introduction to Foundation Engineering
Introduction to Foundation EngineeringIntroduction to Foundation Engineering
Introduction to Foundation EngineeringLatif Hyder Wadho
 

More from Latif Hyder Wadho (20)

Internal Control Internal Checking Internal Auditing - Auditing By LATiFHRW
Internal Control  Internal Checking Internal Auditing - Auditing By LATiFHRWInternal Control  Internal Checking Internal Auditing - Auditing By LATiFHRW
Internal Control Internal Checking Internal Auditing - Auditing By LATiFHRW
 
Supply and Demand - Modern Economics LATiFHRW
Supply and Demand - Modern Economics LATiFHRWSupply and Demand - Modern Economics LATiFHRW
Supply and Demand - Modern Economics LATiFHRW
 
Energy crisis in Pakistan
Energy crisis in PakistanEnergy crisis in Pakistan
Energy crisis in Pakistan
 
SPSC PCS Syllabus cce 2018
SPSC PCS Syllabus cce 2018SPSC PCS Syllabus cce 2018
SPSC PCS Syllabus cce 2018
 
SPSC CCE 2013 Pcs past papers
SPSC  CCE 2013 Pcs past papersSPSC  CCE 2013 Pcs past papers
SPSC CCE 2013 Pcs past papers
 
SPSC CCE 2013 Pcs screening test
SPSC CCE 2013 Pcs screening testSPSC CCE 2013 Pcs screening test
SPSC CCE 2013 Pcs screening test
 
Engineering drawing
Engineering drawingEngineering drawing
Engineering drawing
 
Why is english as a global language
Why is english as a global languageWhy is english as a global language
Why is english as a global language
 
Bricks
BricksBricks
Bricks
 
Introduction to Geo technical Engineering 2
 Introduction to Geo technical Engineering 2 Introduction to Geo technical Engineering 2
Introduction to Geo technical Engineering 2
 
Introdction to Geo technical Engineering
Introdction to Geo technical EngineeringIntrodction to Geo technical Engineering
Introdction to Geo technical Engineering
 
Sub surface exploration part 2
Sub surface exploration part 2Sub surface exploration part 2
Sub surface exploration part 2
 
Problems on piles and deep footing
Problems on piles and deep footingProblems on piles and deep footing
Problems on piles and deep footing
 
Load carrying capacity of piles
Load carrying capacity of pilesLoad carrying capacity of piles
Load carrying capacity of piles
 
Settlement of piles
Settlement of pilesSettlement of piles
Settlement of piles
 
Plate load test
Plate load testPlate load test
Plate load test
 
Subsurface exploration (part-3)
Subsurface exploration (part-3)Subsurface exploration (part-3)
Subsurface exploration (part-3)
 
Sub surface exploration (part-1)
Sub surface exploration (part-1)Sub surface exploration (part-1)
Sub surface exploration (part-1)
 
Introduction to Foundation Engineering
Introduction to Foundation EngineeringIntroduction to Foundation Engineering
Introduction to Foundation Engineering
 
Review of soil mechanics
Review of soil mechanicsReview of soil mechanics
Review of soil mechanics
 

Recently uploaded

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 

Recently uploaded (20)

Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 

Surveying and Leveling

  • 2. Theory Max. Marks 100 Sessional Marks 20 – Attendance 10 – Test(s) 05 – Assignments 05 • Mid Semester Exam: 20 • Final Semester Exam: 60 • Practical Max. Marks 50 – Attendance 05 – Lab Evaluation Work 15 – Semester Lab Exam: 30 (Test + Viva) Final Semester Examination will be of 3-hours duration for 3 CHs course and each question paper will contain 5 questions without any choice. Lecture No:01 Dt:7th Jan 2014
  • 3.  Theodolite Traversing  General, Types & Use of Theodolite.  Adjustment of Transit Theodolite.  Measurements of Bearings, Horizontal & Vertical.  Traversing with Theodolite.  Principles & Methods of Theodolite Traversing.  Traverse computations, close error & its adjustments.  Tachometric surveying  System of tachometry, Principles & field procedures of tachometry.  Use of tachometry for Traversing.  Curves  Field Astronomy  Introduction of Geographical & Astronomical terms.  Determination of True Meridian, Latitude & Longitude & Time for astronomical observations.  Hydrographic Surveying  Photographic Surveying, Principles of Aerial & Terrestrial Photogrammetry, Arial surveying.  Trigonometric Surveying  Tunnel Surveying Lecture No:01 Dt:7th Jan 2014
  • 4. 1. Introduction to Surveying by: Jmes.M.Anderson 2. Surveying Vol (II + III) by: BC Punmia, 9th Edition 3. Surveying by: R.Agore, 4th Edition, Khanna publisher India. 4. Surveying & Levelling by: T.P Kanetkar & S.V Kulkarni Lecture No:01 Dt:7th Jan 2014
  • 5. So far we have been measuring horizontal angles by using a Compass with respect to meridian, which is less accurate and also it is not possible to measure vertical angles with a Compass. So when the objects are at a considerable distance or situated at a considerable elevation or depression ,it becomes necessary to measure horizontal and vertical angles more precisely. So these measurements are taken by an instrument known as a Theodolite. Lecture No:01 Dt:7th Jan 2014
  • 6. THEODOLITE SURVEYING The system of surveying in which the angles are measured with the help of a theodolite, is called Theodolite surveying. Lecture No:01 Dt:7th Jan 2014
  • 7.  Theodolite is the most accurate instrument used for measurement of horizontal and vertical angles.  It consist of a telescope by means of which distant object can be sighted.  Telescope has two different motions one in the horizontal plane and the other in the vertical plane.  Theodolites are primarly classified as  Transit and  Non-Transit. Lecture No:01 Dt:7th Jan 2014
  • 9. THEODOLITE USED FOR: The Theodolite is a most accurate surveying instrument mainly used for :  Measuring horizontal and vertical angles.  Locating points on a line.  Prolonging survey lines.  Finding difference of level.  Setting out grades  Ranging curves  Tacheometric Survey Lecture No:01 Dt:7th Jan 2014
  • 11. Theodolite Traversing Lecture No:01 Dt:7th Jan 2014
  • 12. CLASSIFICATION OF THEODOLITES Theodolites may be classified as ; A. i) Transit Theodolite. ii) Non Transit Theodolite. B. i) Vernier Theodolites. ii) Micrometer Theodolites. Lecture No:01 Dt:7th Jan 2014
  • 13. A. Transit Theodolite: A theodolite is called a transit theodolite when its telescope can be transited i.e revolved through a complete revolution about its horizontal axis in the vertical plane, whereas in a- Non-Transit type, the telescope cannot be transited. They are inferior in utility and have now become obsolete. CLASSIFICATION OF THEODOLITES Lecture No:01 Dt:7th Jan 2014
  • 14. B. Vernier Theodolite: For reading the graduated circle if verniers are used ,the theodolite is called as a Vernier Theodolite. Whereas, if a micrometer is provided to read the graduated circle the same is called as a Micrometer Theodolite. Vernier type theodolites are commonly used. CLASSIFICATION OF THEODOLITES Lecture No:01 Dt:7th Jan 2014
  • 15. SIZE OF THEODOLITE A theodolite is designated by diameter of the graduated circle on the lower plate. The common sizes are 8cm to 12 cm while 14 cm to 25 cm instrument are used for triangulation work. Greater accuracy is achieved with larger theodolites as they have bigger graduated circle with larger divisions hence used where the survey works require high degree of accuracy. Lecture No:01 Dt:7th Jan 2014
  • 16. DESCRIPTION OF A TRANSIT VERNIER THEODOLITE A Transit vernier theodolite essentially consist of the following : 1. Levelling Head. 6. T- Frame. 2. Lower Circular Plate. 7. Plumb –bob. 3. Upper Plate. 8. Tripod Stand. 4. Telescope. 5. Vernier Scale. Lecture No:01 Dt:7th Jan 2014
  • 17. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. 1.Centering: Centering means setting the theodolite exactly over an instrument- station so that its vertical axis lies immediately above the station- mark. It can be done by means of plumb bob suspended from a small hook attached to the vertical axis of the theodolite. The centre shifting arrangement if provided with the instrument helps in easy and rapid performance of the centering. Lecture No:01 Dt:7th Jan 2014
  • 18. 2. Transiting : Transiting is also known as plunging or reversing. It is the process of turning the telescope about its horizontal axis through 1800 in the vertical plane thus bringing it upside down and making it point , exactly in opposite direction. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:01 Dt:7th Jan 2014
  • 19. 3. Swinging the telescope It means turning the telescope about its vertical axis in the horizontal plane. A swing is called right or left according as the telescope is rotated clockwise or counter clockwise. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:02 Dt:8th Jan 2014
  • 20. 4. Face Left If the vertical circle of the instrument is on the left side of the observer while taking a reading ,the position is called the face left and the observation taken on the horizontal or vertical circle in this position, is known as the face left observation TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:02 Dt: 8th Jan 2014
  • 21. 5. Face Right If the vertical circle of the instrument is on the right side of the observer while taking a reading ,the position is called the face right and The observation taken on the horizontal or vertical circle in this position, is known as the face right observation. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:01 Dt:7th Jan 2014
  • 22. 6. Changing Face It is the operation of bringing the vertical circle to the right of the observer, if originally it is to the left , and vice – versa. It is done in two steps; Firstly revolve the telescope through 1800 in a vertical plane and then rotate it through 1800 in the horizontal plane i.e first transit the telescope and then swing it through 1800. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:01 Dt:7th Jan 2014
  • 23. 7. Line of Collimation LINE OF COLLIMATION DIAPHRAGM TELESCOPE It is also known as the line of sight .It is an imaginary line joining the intersection of the cross- hairs of the diaphragm to the optical centre of the object- glass and its continuation. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:02 Dt:8th Jan 2014
  • 24. 8. Axis of the telescope AXIS OF THE TELESCOPE TELESCOPE It is also known an imaginary line joining the optical centre of the object- glass to the centre of eye piece. OBJECT GLASS . TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:02 Dt:8th Jan 2014
  • 25. 9. Axis of the Level Tube It is also called the bubble line. It is a straight line tangential to the longitudinal curve of the level tube at the centre of the tube. It is horizontal when the bubble is in the centre. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:02 Dt:8th Jan 2014
  • 26. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:02 Dt:8th Jan 2014
  • 27. 10. Vertical Axis It is the axis about which the telescope can be rotated in the horizontal plane. 11. Horizontal Axis It is the axis about which the telescope can be rotated in the vertical plane. It is also called the trunnion axis. TERMS USED IN MANIPULATING A TRANSIT VERNIER THEODOLITE. Lecture No:02 Dt:8th Jan 2014
  • 28. The horizontal angle which the line makes with some reference direction or meridian is called bearing of a line. There are two types; 1. Whole Circle Bearing (WCB) 2. Quadrantal/Reduced Bearing (RB) 1. WCB: In WCB, the angle measured clockwise from North to wards the line. 2. RB: The angle measured clockwise or anticlockwise from North or South towards the line. Rule for conversion WCB into RB In first quadrant RB = WCB In 2nd quadrant RB = 180-WCB In 3rd quadrant RB = WCB-180 In 4th quadrant RB = 360-WCB Bearings Lecture No:02 Dt:8th Jan 2014
  • 29. Convert the following WCB to quadrant bearing by using rules of RB. 1. 680 32’ 2. 1320 12’ 3. 2360 37’ 4. 3340 52’ Home work Lecture No:02 Dt:8th Jan 2014
  • 30. It is series of connected lines. There are two types of traverse; 1. Open traverse 2. Close traverse 1. Open traverse: In open traverse the last point does not meet with the starting point. 2. Close traverse: In close traverse the last point meet with the starting point. Traverse Lecture No:02 Dt:8th Jan 2014
  • 31. Sum of interior angles should be equal to (2n-4) x90 Problem No:01: The following are the interior angles of a closed traverse ABCDE < A = 960 53’ 15” < B = 750 03’ 17” < C = 1590 05’ 15” < D = 1280 33’ 43” < E = 800 25’ 30” Bearing of a line AB is 2870 54’ 10”, calculate the bearing of the remaining sides of a traverse. Check of Traverse Lecture No:02 Dt:8th Jan 2014