DESIGN CONSIDERATION
OF COLUMN
ACCORDINGTO ACI CODE
According to ACI Code 2.2,
๏ถ a structural element with a ratio of height-to-least
lateral dimension >3
COLUMN:
๏ถ support vertical loads transfer these loads to
the footings.
๏ถ usually support compressive loads with or without
bending
Types of Columns:divided into three types according to
reinforcement.
Tied Columns
๏ถ The longitudinal reinforcement bars are tied together with
separate smaller diameter ties spaced at some interval along the
column height.
๏ถ These ties help to hold the longitudinal reinforcement bars in
place during construction and ensure stability of these bars
against local buckling.
๏ถ The cross sections of such columns are usually square,
rectangular, or circular in shape.
๏ถ A minimum of four bars is used in rectangular and circular
cross sections.
Spirally-Reinforced Columns :
๏ถ The longitudinal bars are arranged in a circle
surrounded by a closely spaced continuous
spiral.
๏ถ These columns are usually circular or square in
shape.
๏ถ A minimum of six bars is used for longitudinal
reinforcement.
Composite Columns:
๏ถ A column made of structural steel shapes or pipes surrounded
by or filled by concrete with or without longitudinal
reinforcement.
FAILURE OF TIED AND SPIRAL COLUMN:
๏ถ Axial loading on tied and spirally reinforced columns having
the same cross-sectional areas of concrete and steel
reinforcement behave in the same manner up to the ultimate
load.
๏ถ At that load tied columns fail suddenly due to excessive
cracking in the concrete section followed by buckling of the
longitudinal reinforcement between ties within the failure
region.
๏ถ For spirally reinforced columns, when ultimate load is reached,
the concrete shell covering the spiral starts to peel off. Only
then, the spiral comes to action by providing a confining force
to the concrete core, thus enabling the column to sustain large
deformations before final collapse occurs.
ACI Code Requirements forColumns:
ForTiesColumn:
๏ถ No. 3 ties for longitudinal reinforcement no. 10 bars or less,
no. 4 ties for no. 11 bars or larger and bundled bars.
๏ถ Tie spacing shall not exceed 16 diameter of longitudinal
bars, 48 diameters of tie bars, nor the least dimension of
column.
๏ถ Every corner bar and alternate bars shall have lateral tie
provide the angle shall not exceed 135 degree.
๏ถ No longitudinal bar shall be spacing more
than 6 inches without a lateral tie.
Forspiral Columns:
๏ถ At least six longitudinal bars must be used
within spiral ties.
๏ถ Spirals may not have diameters less than 3/8 in.
๏ถ The clear spacing between spirals may not be
less than 1 in. or greater than 3 in.
Design Considerations:
MaximumandMinimumReinforcementRatios
ACI Code 10.9.1 specifies that a minimum reinforcement
ratio of 1 % is to be used in tied or spirally reinforced
columns.This minimum reinforcement is needed to
safeguard against any bending, reduce the effect of
shrinkage and creep and enhance ductility of columns.
MinimumNumberofReinforcingBars:
ACI Code 10.9.2 specifies a minimum of four bars
within rectangular or circular sections; or one bar in
each corner of the cross section for other shapes and
a minimum of six bars in spirally reinforced columns
Clear Distance between Reinforcing Bars:
ACI Code 7.6.3 and 7.6.4 specify that for tied or
spirally reinforced columns, clear distance between
bars, is not to be less than the larger of 1.50 times
bar diameter or 4 cm
Concrete Protection Cover:
ACI Code 7.7.1 specifies that for reinforced columns,
the clear concrete cover is not to be taken less than 4
cm for columns not exposed to weather or in contact
with ground. It is essential for protecting the
reinforcement from corrosion or fire hazards.
Minimum Cross Sectional Dimensions:
With the 1971 Code, For practical considerations,
column dimensions are taken as multiples of 5 cm.
Lateral Reinforcement:
Ties are effective in restraining the longitudinal bars from
buckling out through the surface of the column, holding
the reinforcement cage together during the construction
process, confining the concrete core and when columns are
subjected to horizontal forces, they serve as shear
reinforcement. Spirals, on the other hand, serve in addition
to these benefits in compensating for the strength loss due
to spalling of the outside concrete shell at ultimate column
strength.
Ties:
According to ACI Code 7.10.5.1, for longitudinal bars 32
mm or smaller, lateral ties 10 mm in diameter are used. In
our country and in some neighboring countries, ties 8 mm
in diameter are used in column construction.

More Related Content

What's hot

Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920INTEZAAR ALAM
ย 
Civil structural engineering - Flat slab design
Civil structural engineering -  Flat slab designCivil structural engineering -  Flat slab design
Civil structural engineering - Flat slab designSatish Narayan
ย 
Design of slender columns as per IS 456-2000
Design of slender columns as per IS 456-2000Design of slender columns as per IS 456-2000
Design of slender columns as per IS 456-2000PraveenKumar Shanmugam
ย 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete DesignPriodeep Chowdhury
ย 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)ahsanrabbani
ย 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000VVIETCIVIL
ย 
ONE WAY SLAB DESIGN
ONE WAY SLAB DESIGNONE WAY SLAB DESIGN
ONE WAY SLAB DESIGNMd.Asif Rahman
ย 
Design of tension members
Design of tension membersDesign of tension members
Design of tension membersSabna Thilakan
ย 
Design of columns axial load as per IS 456-2000
Design of columns  axial load as per IS 456-2000Design of columns  axial load as per IS 456-2000
Design of columns axial load as per IS 456-2000PraveenKumar Shanmugam
ย 
Column base plates_prof_thomas_murray
Column base plates_prof_thomas_murrayColumn base plates_prof_thomas_murray
Column base plates_prof_thomas_murrayAlberto Rosado
ย 
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Hossam Shafiq II
ย 
Design of short columns using helical reinforcement
Design of short columns using helical reinforcementDesign of short columns using helical reinforcement
Design of short columns using helical reinforcementshivam gautam
ย 
Combined footings
Combined footingsCombined footings
Combined footingsseemavgiri
ย 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc buildinghlksd
ย 
Seismic Analysis
Seismic AnalysisSeismic Analysis
Seismic AnalysisKrishnagnr
ย 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beamsIr. David Puen
ย 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000PraveenKumar Shanmugam
ย 
Slab Design-(BNBC & ACI)
Slab Design-(BNBC & ACI)Slab Design-(BNBC & ACI)
Slab Design-(BNBC & ACI)Priodeep Chowdhury
ย 

What's hot (20)

Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920
ย 
Civil structural engineering - Flat slab design
Civil structural engineering -  Flat slab designCivil structural engineering -  Flat slab design
Civil structural engineering - Flat slab design
ย 
Beam design
Beam designBeam design
Beam design
ย 
Design of slender columns as per IS 456-2000
Design of slender columns as per IS 456-2000Design of slender columns as per IS 456-2000
Design of slender columns as per IS 456-2000
ย 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
ย 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
ย 
Reinforced column design
Reinforced column design Reinforced column design
Reinforced column design
ย 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000
ย 
ONE WAY SLAB DESIGN
ONE WAY SLAB DESIGNONE WAY SLAB DESIGN
ONE WAY SLAB DESIGN
ย 
Design of tension members
Design of tension membersDesign of tension members
Design of tension members
ย 
Design of columns axial load as per IS 456-2000
Design of columns  axial load as per IS 456-2000Design of columns  axial load as per IS 456-2000
Design of columns axial load as per IS 456-2000
ย 
Column base plates_prof_thomas_murray
Column base plates_prof_thomas_murrayColumn base plates_prof_thomas_murray
Column base plates_prof_thomas_murray
ย 
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
ย 
Design of short columns using helical reinforcement
Design of short columns using helical reinforcementDesign of short columns using helical reinforcement
Design of short columns using helical reinforcement
ย 
Combined footings
Combined footingsCombined footings
Combined footings
ย 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc building
ย 
Seismic Analysis
Seismic AnalysisSeismic Analysis
Seismic Analysis
ย 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beams
ย 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
ย 
Slab Design-(BNBC & ACI)
Slab Design-(BNBC & ACI)Slab Design-(BNBC & ACI)
Slab Design-(BNBC & ACI)
ย 

Similar to Design of column according ACI codes

Introduction to design of rcc column
Introduction to design of rcc columnIntroduction to design of rcc column
Introduction to design of rcc columnPHURTSHERINGSHERPA
ย 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailingBinay Shrestha
ย 
BEAM.pptx
BEAM.pptxBEAM.pptx
BEAM.pptxRishi Nath
ย 
Lecture note on column design
Lecture note on column designLecture note on column design
Lecture note on column designNiyogakiza Philemon
ย 
2 column
2 column2 column
2 columnP Ramana
ย 
Details of REINFORCEMENT Summary
Details of REINFORCEMENT SummaryDetails of REINFORCEMENT Summary
Details of REINFORCEMENT SummaryMuhammad Yousif Nazar
ย 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)swatapriya
ย 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)swatapriya
ย 
Building project rc column
Building project rc columnBuilding project rc column
Building project rc columnsathananthankartheep
ย 
RCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptxRCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptxHaswanthKollu
ย 
Columns rajeevan sir
Columns rajeevan sirColumns rajeevan sir
Columns rajeevan sirSHAMJITH KM
ย 
Introduction of columns
Introduction of columns Introduction of columns
Introduction of columns QutbuddinNoyan
ย 
Jsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsns
JsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsnsJsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsns
JsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsnsHiteshVasava8
ย 
Seismic Behavior of Beam Column Joint
Seismic Behavior of Beam Column JointSeismic Behavior of Beam Column Joint
Seismic Behavior of Beam Column JointShoaib Wani
ย 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.Puneet Chhonker
ย 

Similar to Design of column according ACI codes (20)

Introduction to design of rcc column
Introduction to design of rcc columnIntroduction to design of rcc column
Introduction to design of rcc column
ย 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
ย 
Beams and columns
Beams and columns Beams and columns
Beams and columns
ย 
BEAM.pptx
BEAM.pptxBEAM.pptx
BEAM.pptx
ย 
Lecture note on column design
Lecture note on column designLecture note on column design
Lecture note on column design
ย 
Reinforced concrete column
Reinforced concrete columnReinforced concrete column
Reinforced concrete column
ย 
2 column
2 column2 column
2 column
ย 
Details of REINFORCEMENT Summary
Details of REINFORCEMENT SummaryDetails of REINFORCEMENT Summary
Details of REINFORCEMENT Summary
ย 
Presentation123
Presentation123Presentation123
Presentation123
ย 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)
ย 
Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)Column detailing, Session 14-15 (DUET)
Column detailing, Session 14-15 (DUET)
ย 
Building project rc column
Building project rc columnBuilding project rc column
Building project rc column
ย 
RCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptxRCC column_Shortly Axially Loaded column.pptx
RCC column_Shortly Axially Loaded column.pptx
ย 
Columns rajeevan sir
Columns rajeevan sirColumns rajeevan sir
Columns rajeevan sir
ย 
Introduction of columns
Introduction of columns Introduction of columns
Introduction of columns
ย 
Jsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsns
JsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsnsJsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsns
Jsjdjsjsjjeksksksksmsmmsmsmsmsmsmksksmmsnsns
ย 
Seismic Behavior of Beam Column Joint
Seismic Behavior of Beam Column JointSeismic Behavior of Beam Column Joint
Seismic Behavior of Beam Column Joint
ย 
Reinfocing details of column
Reinfocing details of columnReinfocing details of column
Reinfocing details of column
ย 
Column
ColumnColumn
Column
ย 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
ย 

Recently uploaded

Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
ย 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
ย 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .DerechoLaboralIndivi
ย 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
ย 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
ย 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
ย 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7Call Girls in Nagpur High Profile Call Girls
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
ย 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
ย 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
ย 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdfSuman Jyoti
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 

Recently uploaded (20)

Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
ย 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
ย 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
ย 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
ย 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
ย 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
ย 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
ย 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
ย 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
ย 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
ย 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
ย 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
ย 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
ย 

Design of column according ACI codes

  • 2. According to ACI Code 2.2, ๏ถ a structural element with a ratio of height-to-least lateral dimension >3 COLUMN: ๏ถ support vertical loads transfer these loads to the footings. ๏ถ usually support compressive loads with or without bending
  • 3. Types of Columns:divided into three types according to reinforcement. Tied Columns ๏ถ The longitudinal reinforcement bars are tied together with separate smaller diameter ties spaced at some interval along the column height. ๏ถ These ties help to hold the longitudinal reinforcement bars in place during construction and ensure stability of these bars against local buckling.
  • 4. ๏ถ The cross sections of such columns are usually square, rectangular, or circular in shape. ๏ถ A minimum of four bars is used in rectangular and circular cross sections.
  • 5. Spirally-Reinforced Columns : ๏ถ The longitudinal bars are arranged in a circle surrounded by a closely spaced continuous spiral. ๏ถ These columns are usually circular or square in shape. ๏ถ A minimum of six bars is used for longitudinal reinforcement.
  • 6. Composite Columns: ๏ถ A column made of structural steel shapes or pipes surrounded by or filled by concrete with or without longitudinal reinforcement.
  • 7. FAILURE OF TIED AND SPIRAL COLUMN: ๏ถ Axial loading on tied and spirally reinforced columns having the same cross-sectional areas of concrete and steel reinforcement behave in the same manner up to the ultimate load. ๏ถ At that load tied columns fail suddenly due to excessive cracking in the concrete section followed by buckling of the longitudinal reinforcement between ties within the failure region.
  • 8. ๏ถ For spirally reinforced columns, when ultimate load is reached, the concrete shell covering the spiral starts to peel off. Only then, the spiral comes to action by providing a confining force to the concrete core, thus enabling the column to sustain large deformations before final collapse occurs.
  • 9. ACI Code Requirements forColumns: ForTiesColumn: ๏ถ No. 3 ties for longitudinal reinforcement no. 10 bars or less, no. 4 ties for no. 11 bars or larger and bundled bars. ๏ถ Tie spacing shall not exceed 16 diameter of longitudinal bars, 48 diameters of tie bars, nor the least dimension of column. ๏ถ Every corner bar and alternate bars shall have lateral tie provide the angle shall not exceed 135 degree.
  • 10. ๏ถ No longitudinal bar shall be spacing more than 6 inches without a lateral tie. Forspiral Columns: ๏ถ At least six longitudinal bars must be used within spiral ties. ๏ถ Spirals may not have diameters less than 3/8 in. ๏ถ The clear spacing between spirals may not be less than 1 in. or greater than 3 in.
  • 11. Design Considerations: MaximumandMinimumReinforcementRatios ACI Code 10.9.1 specifies that a minimum reinforcement ratio of 1 % is to be used in tied or spirally reinforced columns.This minimum reinforcement is needed to safeguard against any bending, reduce the effect of shrinkage and creep and enhance ductility of columns.
  • 12. MinimumNumberofReinforcingBars: ACI Code 10.9.2 specifies a minimum of four bars within rectangular or circular sections; or one bar in each corner of the cross section for other shapes and a minimum of six bars in spirally reinforced columns
  • 13. Clear Distance between Reinforcing Bars: ACI Code 7.6.3 and 7.6.4 specify that for tied or spirally reinforced columns, clear distance between bars, is not to be less than the larger of 1.50 times bar diameter or 4 cm
  • 14. Concrete Protection Cover: ACI Code 7.7.1 specifies that for reinforced columns, the clear concrete cover is not to be taken less than 4 cm for columns not exposed to weather or in contact with ground. It is essential for protecting the reinforcement from corrosion or fire hazards.
  • 15. Minimum Cross Sectional Dimensions: With the 1971 Code, For practical considerations, column dimensions are taken as multiples of 5 cm.
  • 16. Lateral Reinforcement: Ties are effective in restraining the longitudinal bars from buckling out through the surface of the column, holding the reinforcement cage together during the construction process, confining the concrete core and when columns are subjected to horizontal forces, they serve as shear reinforcement. Spirals, on the other hand, serve in addition to these benefits in compensating for the strength loss due to spalling of the outside concrete shell at ultimate column strength.
  • 17. Ties: According to ACI Code 7.10.5.1, for longitudinal bars 32 mm or smaller, lateral ties 10 mm in diameter are used. In our country and in some neighboring countries, ties 8 mm in diameter are used in column construction.