CONSTRUCTION DELAY ANALYSIS, SIMPLIFIED…
Presented By: Michael A. Pink
www.construxsolutions.com 2
ABOUT THE PRESENTER: MICHAEL PINK
 Founder of Construx Solutions, LLC
 Inventor of SmartPM: Data Capture, Storage and Analysis Technology
 15 Years of Advisory Experience in Commercial Construction Industry
 Specialization in Project Controls, Risk Management, Dispute Avoidance
 Advisory Board Member for the School of Building Construction at Georgia Tech
 Certified Planning and Scheduling Professional (PSP)
 Certified Cost Engineer (CCE)
www.construxsolutions.com 3
COURSE OBJECTIVES
 Why is Delay Analysis Common in Construction?
 Important Steps to Developing a Delay Analysis
 Summarizing the Baseline Schedule
 The As Planned versus As-Built Schedule
 Identifying and Tracking the As-Built Critical Path
 A Simplified Analysis for a Trade Contractor
www.construxsolutions.com 4
WHY IS DELAY ANALYSIS NECESSARY IN CONSTRUCTION?
 Most Project Bids and Baseline Schedules are “Best Case” Scenarios
 Project Master Schedules are typically complex, with a lot of moving parts
 Schedules and Budgets are generally impacted for multiple overlapping reasons
 Lack of strong controls in Scheduling, Work Flow and Data Management
 Construction is Expensive and there is a lot of money at stake.
 A majority of Budget overruns are caused by Delay/Impacts issues
Crossed With
Crossed With
Crossed With
Crossed With
Crossed With
www.construxsolutions.com 5
ENGINEERS &
ARCHITECTS
OWNERS
CONSTRUCTION
MANAGERS
CONTRACTORS OTHER
• Poor Design
• Incomplete Design
• Slow Response Time
• Excessive Changes
• Delayed Approvals/
Permits
• Prolonged Planning
• Delayed Payment
• Poor Planning/
Scheduling
• Poor Contract
Management
• Coordination Issues
• Unachievable
Schedule
• Poor Data
Management
• Mismanagement of
Resources
• Unachievable Bid
• Poor Productivity/
Performance
• Mismanagement of
resources
• Labor Shortages
• Default
• Unanticipated
Weather
• Changing Market
Conditions
• Unforeseen
Conditions
• Force majeure
WHAT IMPACTS THE SCHEDULE IN CONSTRUCTION?
www.construxsolutions.com 6
Steps in Performing a Delay Analysis (on a master schedule)
 Locate and Summarize the “Baseline” Master Schedule (Level 2).
 Gain an understanding of the Planned Critical Path of the Master Plan.
 Gain an understanding of the intended trade flow throughout the project (the order of
construction by area, crew and trades).
 Generate an As Built Schedule (in the same ordering/level as the As Planned).
 Compare the As-Planned Schedule to the As-Built Schedule (Level 2) .
 Perform a holistic review to pinpoint delayed areas/issues; Try to find a theme.
 Review contemporaneous information to determine the Historical (or “As-Built”) Critical Path.
 Choose a methodology to highlight / prove “Critical Path” delay.
 Measure Critical Path Delay to the Project over time.
 Determine Causation for Critical Delay identified.
www.construxsolutions.com 7
SUMMARIZING THE BASELINE MASTER SCHEDULE
QUESTION:
Why is this Necessary?
ANSWERS:
• A summary of the Master Schedule makes it more simple to
digest the planned work flow of the entire job (ie. Logic).
• Comparisons at a Summary Level makes it easier and quicker to
pinpoint delays
• A summary is much easier to explain than a full CPM Schedule
www.construxsolutions.com 8
STEPS TO SUMMARIZING THE BASELINE MASTER SCHEDULE
 Review the Schedule and figure out the “Trade Flow” of the Project.
 Create a baseline summary that essentially divides the project by
area/location, and has a line item for each trade (Level 2). This will
become the basis for ANALYSIS. NOTE: “Areas” can be levels, site
locations, structures, etc. It depends on the project and the schedule.
 Distinguish the Planned Critical Path in the Baseline Summary.
 Prepare a Level 1 summary of that schedule for graphical purposes.
This will become the basis for DISCUSSION.
 Study the Summary Schedule to understand the flow/logic of crews/
trades/resources
www.construxsolutions.com 9
SUMMARIZING THE BASELINE SCHEDULE – LEVEL 2
www.construxsolutions.com 10
SUMMARIZING THE BASELINE SCHEDULE – LEVEL 2
www.construxsolutions.com 11
SUMMARIZING THE BASELINE SCHEDULE – LEVEL 2
www.construxsolutions.com 12
SUMMARIZING THE BASELINE SCHEDULE (AGAIN) – LEVEL 1
NOTE: The Level 1 schedule needs to fit on ONE (1) page, whereas the Level 2 Schedule
can be spread out across multiple pages.
www.construxsolutions.com 13
QUESTIONS?
www.construxsolutions.com 14
THE AS PLANNED VS. AS BUILT ANALYSIS
 Find the latest contemporaneous schedule update.
 Summarize “as-built” data points in latest schedule update to mirror
the Level 2 Baseline Summary. Compare.
NOTE: If no schedule update exists, use other sources to determine start and finish
dates for summary level activities (ie. payment applications, photo’s, dailies, etc.)
NOTE: Seek start dates and “substantial completion” dates for each activity.
 Begin to analyze duration variances in each area, measure delay
from completion of one trade to the next and try to determine if there
appears to be a theme. (See example on next slide).
 Overlap Areas, and see if a particular trade is impacting workflow
and driving delays
 Begin to highlight delay issues for future analysis
www.construxsolutions.com 15
LEVEL 2 COMPARISON EXAMPLE – BUILDING F
59 cd delay
81 cd delay
(net 22 cd)
160 cd delay
(net 79 cd)
288 cd delay
(net 128 cd)
www.construxsolutions.com 16
QUESTIONS?
www.construxsolutions.com 17
WHAT IS THE CRITICAL PATH AND WHY IS IT RELEVANT?
• It is the longest “String” or “Path” of activities that logically
connects the start date of the project to the end of the project.
• It is the one and only path on a project that has no float or slack
and will results in a delay to the end date of the project if delayed.
• It is relevant because only a critical path activity can delay the
project a certain point in time.
• Determining the “Historic” Critical path, is the most important step
in building a Delay Analysis / Claim.
• Once Historical Critical Path is identified, one can assess
responsibility for delay and then entitlement.
www.construxsolutions.com 18
What is Compensable, Concurrent and Non Compensable Delay?
Once delay is identified, it is typically categorized into the following:
‒ Excusable Compensable – The Contractor was delayed and had no part in
causing the delay (“Out of the its Control’); Granted time and money for
extended GC’s, acceleration and/or impact costs.
‒ Excusable Non Compensable (“Concurrent”) – The Contractor was equally
involved/responsible for a delay, along with another party (ie. owner, engineer,
etc); Granted time, but no money for extended GC’s, acceleration, and/or other
impact costs.
‒ Non Excusable Non Compensable – The Contractor was solely responsible the
delay for a particular period of time; Granted no time and no money.
NOTE: On Projects where multiple delays are identified, each will need to be classified with the above
categories to ultimately prepare a delay claim.
www.construxsolutions.com 19
How do we determine the Historical Critical Path?
• Start with reviewing the Contemporaneous Schedule Updates.
• Try to determine if the schedule updates were used to “manage” versus used
to “check the box”; Try these indicators:
‒ See if the project critical path was clearly delayed over time and the end date stayed the same for a long time. This
indicates the schedule is likely not usable to document CP.
‒ A lot of logic changes and shortened durations of activities. This indicates the schedule is likely unusable.
‒ If trades started getting stacked towards the end of the project and the end date stays the same. This indicates the
schedule is unusable for documenting historical CP.
‒ HINT: Create a Database of Schedule Updates with the following fields: Schedule Title, Data Date, No. of Activities,
Project Completion Date, Go Forward Critical Path
• If the schedule updates seem legit, document the critical path and delay
through a “Windows Analysis”.
• If the updates do not seem legit, one will need to either review meeting
minutes, letters of delay, or calculate in an as planned versus as-built scenario.
www.construxsolutions.com 20
WHAT IS A WINDOWS ANALYSIS?
 A Technique that measures delay while documenting the historical critical
path through different periods (or windows) of time.
 It essentially allows users to easily decipher what was deemed critical from
one period to the next, as the schedule is updated.
 If properly utilized, it will document shifts in the critical path, from planned to
actual.
 The more periods reviewed, the better. But lets not get crazy. Monthly
windows are best.
 If properly performed it will be easier to digest, and more difficult to argue.
 Windows Analysis should be analyzed in a Level 2 Summary, explained in a
Level 1 Summary.
www.construxsolutions.com 21
WINDOWS ANALYSIS EXAMPLE
www.construxsolutions.com 22
WINDOW 1 UPDATE
1/1
1/1
www.construxsolutions.com 23
WINDOW 1 – SUMMARY OF DELAY
www.construxsolutions.com 24
WINDOW 2 UPDATE
1/1
1/1
www.construxsolutions.com 25
WINDOW 2 – SUMMARY OF DELAY
www.construxsolutions.com 26
OTHER WAYS TO DETERMINE THE HISTORICAL CRITICAL PATH
• As Planned vs. As built Calculation Method
• Determine Variances by comparing Late Dates to Actual Dates
• Chart it out
• Compare
• Review of Meeting Minutes, Emails, Progress Reports to highlight
what appear to be “delaying issues”
• Read Correspondence
• Document Issues
• Highlight time frame
www.construxsolutions.com 27
EXAMPLE: AS PLANNED V AS BUILT CALCULATION METHOD
0
50
100
150
200
250
300
350
8/10/2010 11/18/2010 2/26/2011 6/6/2011 9/14/2011 12/23/2011 4/1/2012
Core Area 1 Core Area 2 Core Area 3
DaysofDelay
Critical Path equals
Highest Line
Concurrent Delay
www.construxsolutions.com 28
QUESTIONS?
www.construxsolutions.com 29
THE SIMPLIFIED METHOD
• As Planned Versus As Built Method Works Best.
• Step 1: Document the Agreed to Baseline (in Excel)
• Step 2: Document every day worked on which activity using daily
reports (in Excel).
• Step 3: Analyze variances, disruption, delay and even manpower
• Step 4: Determine Causation for budget overruns and delay
• NOTE: The project critical path and the trade contractors critical
path can be different. The trade contractor needs to determine both
for “offense” and “defense”.
• NOTE: If the trade contractors opts not to submit daily reports, this
analysis will become a lot harder.
www.construxsolutions.com 30
SETTING UP THE AS PLANNED SCHEDULE INTO A VISUAL DATABASE
www.construxsolutions.com 31
ADDING DAILY REPORT DATA INTO A VISUAL DATABASE
www.construxsolutions.com 32
CONVERTING DAILY REPORT DATA INTO PERFORMANCE METRICS
www.construxsolutions.com 33
PRESENTED BY: MICHAEL PINK
Contact Info:
C: 404 277 4387
O: 404 329 3000
mpink@construxsolutions.com
Feel free to contact me directly if
you have any additional questions
Sign up for our upcoming courses:
— CPM Scheduling
— Data Management and Performance Analysis
— Delay Analysis in Construction
— Construction Claims Review/Prep
Follow us on LinkedIn for more info.

More Related Content

What's hot

Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean ConstructionVedzen Consultants
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)Amr Morsy
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisPlanning Engineer Est.
 

What's hot (20)

Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean Construction
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays Analysis
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 

Similar to Construction Delay Analysis, Simplified

As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2David Greig
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryMichael Pink
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
Planning_and_scheduling.pptx
Planning_and_scheduling.pptxPlanning_and_scheduling.pptx
Planning_and_scheduling.pptxKAhmedRehman
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides SlideTeam
 
Analyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionAnalyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionMichael Pink
 
Pm0015 quantitative methods in project management
Pm0015   quantitative methods in project managementPm0015   quantitative methods in project management
Pm0015 quantitative methods in project managementsmumbahelp
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Trade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docxTrade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docxturveycharlyn
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9VancityInstitute
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 
A Fresh Take on Project Forensics
A Fresh Take on Project ForensicsA Fresh Take on Project Forensics
A Fresh Take on Project ForensicsAcumen
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptxPigPug1
 

Similar to Construction Delay Analysis, Simplified (20)

As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
Planning_and_scheduling.pptx
Planning_and_scheduling.pptxPlanning_and_scheduling.pptx
Planning_and_scheduling.pptx
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides
 
Analyzing data, performance and impacts in construction
Analyzing data, performance and impacts in constructionAnalyzing data, performance and impacts in construction
Analyzing data, performance and impacts in construction
 
Pm0015 quantitative methods in project management
Pm0015   quantitative methods in project managementPm0015   quantitative methods in project management
Pm0015 quantitative methods in project management
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Trade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docxTrade-off Analysis in a Project EnvironmentWhen we try .docx
Trade-off Analysis in a Project EnvironmentWhen we try .docx
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9
 
ch13.ppt
ch13.pptch13.ppt
ch13.ppt
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
A Fresh Take on Project Forensics
A Fresh Take on Project ForensicsA Fresh Take on Project Forensics
A Fresh Take on Project Forensics
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptx
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 

Recently uploaded

Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...amitlee9823
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAroojKhan71
 
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night StandCall Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...
Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...
Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...amitlee9823
 
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...amitlee9823
 
Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Accredited-Transport-Cooperatives-Jan-2021-Web.pdf
Accredited-Transport-Cooperatives-Jan-2021-Web.pdfAccredited-Transport-Cooperatives-Jan-2021-Web.pdf
Accredited-Transport-Cooperatives-Jan-2021-Web.pdfadriantubila
 
Probability Grade 10 Third Quarter Lessons
Probability Grade 10 Third Quarter LessonsProbability Grade 10 Third Quarter Lessons
Probability Grade 10 Third Quarter LessonsJoseMangaJr1
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFxolyaivanovalion
 
Capstone Project on IBM Data Analytics Program
Capstone Project on IBM Data Analytics ProgramCapstone Project on IBM Data Analytics Program
Capstone Project on IBM Data Analytics ProgramMoniSankarHazra
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfMarinCaroMartnezBerg
 
Discover Why Less is More in B2B Research
Discover Why Less is More in B2B ResearchDiscover Why Less is More in B2B Research
Discover Why Less is More in B2B Researchmichael115558
 
Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...only4webmaster01
 
BDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort ServiceBDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort ServiceDelhi Call girls
 
Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...amitlee9823
 
Generative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusGenerative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusTimothy Spann
 
5CL-ADBA,5cladba, Chinese supplier, safety is guaranteed
5CL-ADBA,5cladba, Chinese supplier, safety is guaranteed5CL-ADBA,5cladba, Chinese supplier, safety is guaranteed
5CL-ADBA,5cladba, Chinese supplier, safety is guaranteedamy56318795
 
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Delhi Call girls
 

Recently uploaded (20)

Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Jalahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
 
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al BarshaAl Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
Al Barsha Escorts $#$ O565212860 $#$ Escort Service In Al Barsha
 
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night StandCall Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Doddaballapur Road ☎ 7737669865 🥵 Book Your One night Stand
 
Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...
Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...
Mg Road Call Girls Service: 🍓 7737669865 🍓 High Profile Model Escorts | Banga...
 
Abortion pills in Doha Qatar (+966572737505 ! Get Cytotec
Abortion pills in Doha Qatar (+966572737505 ! Get CytotecAbortion pills in Doha Qatar (+966572737505 ! Get Cytotec
Abortion pills in Doha Qatar (+966572737505 ! Get Cytotec
 
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men  🔝malwa🔝   Escorts Ser...
➥🔝 7737669865 🔝▻ malwa Call-girls in Women Seeking Men 🔝malwa🔝 Escorts Ser...
 
Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Surabaya ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
CHEAP Call Girls in Saket (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Saket (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICECHEAP Call Girls in Saket (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
CHEAP Call Girls in Saket (-DELHI )🔝 9953056974🔝(=)/CALL GIRLS SERVICE
 
Accredited-Transport-Cooperatives-Jan-2021-Web.pdf
Accredited-Transport-Cooperatives-Jan-2021-Web.pdfAccredited-Transport-Cooperatives-Jan-2021-Web.pdf
Accredited-Transport-Cooperatives-Jan-2021-Web.pdf
 
Probability Grade 10 Third Quarter Lessons
Probability Grade 10 Third Quarter LessonsProbability Grade 10 Third Quarter Lessons
Probability Grade 10 Third Quarter Lessons
 
Halmar dropshipping via API with DroFx
Halmar  dropshipping  via API with DroFxHalmar  dropshipping  via API with DroFx
Halmar dropshipping via API with DroFx
 
Capstone Project on IBM Data Analytics Program
Capstone Project on IBM Data Analytics ProgramCapstone Project on IBM Data Analytics Program
Capstone Project on IBM Data Analytics Program
 
FESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdfFESE Capital Markets Fact Sheet 2024 Q1.pdf
FESE Capital Markets Fact Sheet 2024 Q1.pdf
 
Discover Why Less is More in B2B Research
Discover Why Less is More in B2B ResearchDiscover Why Less is More in B2B Research
Discover Why Less is More in B2B Research
 
Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...
Call Girls Indiranagar Just Call 👗 9155563397 👗 Top Class Call Girl Service B...
 
BDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort ServiceBDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort Service
BDSM⚡Call Girls in Mandawali Delhi >༒8448380779 Escort Service
 
Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
Call Girls Hsr Layout Just Call 👗 7737669865 👗 Top Class Call Girl Service Ba...
 
Generative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and MilvusGenerative AI on Enterprise Cloud with NiFi and Milvus
Generative AI on Enterprise Cloud with NiFi and Milvus
 
5CL-ADBA,5cladba, Chinese supplier, safety is guaranteed
5CL-ADBA,5cladba, Chinese supplier, safety is guaranteed5CL-ADBA,5cladba, Chinese supplier, safety is guaranteed
5CL-ADBA,5cladba, Chinese supplier, safety is guaranteed
 
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
Call Girls in Sarai Kale Khan Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escorts S...
 

Construction Delay Analysis, Simplified

  • 1. CONSTRUCTION DELAY ANALYSIS, SIMPLIFIED… Presented By: Michael A. Pink
  • 2. www.construxsolutions.com 2 ABOUT THE PRESENTER: MICHAEL PINK  Founder of Construx Solutions, LLC  Inventor of SmartPM: Data Capture, Storage and Analysis Technology  15 Years of Advisory Experience in Commercial Construction Industry  Specialization in Project Controls, Risk Management, Dispute Avoidance  Advisory Board Member for the School of Building Construction at Georgia Tech  Certified Planning and Scheduling Professional (PSP)  Certified Cost Engineer (CCE)
  • 3. www.construxsolutions.com 3 COURSE OBJECTIVES  Why is Delay Analysis Common in Construction?  Important Steps to Developing a Delay Analysis  Summarizing the Baseline Schedule  The As Planned versus As-Built Schedule  Identifying and Tracking the As-Built Critical Path  A Simplified Analysis for a Trade Contractor
  • 4. www.construxsolutions.com 4 WHY IS DELAY ANALYSIS NECESSARY IN CONSTRUCTION?  Most Project Bids and Baseline Schedules are “Best Case” Scenarios  Project Master Schedules are typically complex, with a lot of moving parts  Schedules and Budgets are generally impacted for multiple overlapping reasons  Lack of strong controls in Scheduling, Work Flow and Data Management  Construction is Expensive and there is a lot of money at stake.  A majority of Budget overruns are caused by Delay/Impacts issues Crossed With Crossed With Crossed With Crossed With Crossed With
  • 5. www.construxsolutions.com 5 ENGINEERS & ARCHITECTS OWNERS CONSTRUCTION MANAGERS CONTRACTORS OTHER • Poor Design • Incomplete Design • Slow Response Time • Excessive Changes • Delayed Approvals/ Permits • Prolonged Planning • Delayed Payment • Poor Planning/ Scheduling • Poor Contract Management • Coordination Issues • Unachievable Schedule • Poor Data Management • Mismanagement of Resources • Unachievable Bid • Poor Productivity/ Performance • Mismanagement of resources • Labor Shortages • Default • Unanticipated Weather • Changing Market Conditions • Unforeseen Conditions • Force majeure WHAT IMPACTS THE SCHEDULE IN CONSTRUCTION?
  • 6. www.construxsolutions.com 6 Steps in Performing a Delay Analysis (on a master schedule)  Locate and Summarize the “Baseline” Master Schedule (Level 2).  Gain an understanding of the Planned Critical Path of the Master Plan.  Gain an understanding of the intended trade flow throughout the project (the order of construction by area, crew and trades).  Generate an As Built Schedule (in the same ordering/level as the As Planned).  Compare the As-Planned Schedule to the As-Built Schedule (Level 2) .  Perform a holistic review to pinpoint delayed areas/issues; Try to find a theme.  Review contemporaneous information to determine the Historical (or “As-Built”) Critical Path.  Choose a methodology to highlight / prove “Critical Path” delay.  Measure Critical Path Delay to the Project over time.  Determine Causation for Critical Delay identified.
  • 7. www.construxsolutions.com 7 SUMMARIZING THE BASELINE MASTER SCHEDULE QUESTION: Why is this Necessary? ANSWERS: • A summary of the Master Schedule makes it more simple to digest the planned work flow of the entire job (ie. Logic). • Comparisons at a Summary Level makes it easier and quicker to pinpoint delays • A summary is much easier to explain than a full CPM Schedule
  • 8. www.construxsolutions.com 8 STEPS TO SUMMARIZING THE BASELINE MASTER SCHEDULE  Review the Schedule and figure out the “Trade Flow” of the Project.  Create a baseline summary that essentially divides the project by area/location, and has a line item for each trade (Level 2). This will become the basis for ANALYSIS. NOTE: “Areas” can be levels, site locations, structures, etc. It depends on the project and the schedule.  Distinguish the Planned Critical Path in the Baseline Summary.  Prepare a Level 1 summary of that schedule for graphical purposes. This will become the basis for DISCUSSION.  Study the Summary Schedule to understand the flow/logic of crews/ trades/resources
  • 9. www.construxsolutions.com 9 SUMMARIZING THE BASELINE SCHEDULE – LEVEL 2
  • 10. www.construxsolutions.com 10 SUMMARIZING THE BASELINE SCHEDULE – LEVEL 2
  • 11. www.construxsolutions.com 11 SUMMARIZING THE BASELINE SCHEDULE – LEVEL 2
  • 12. www.construxsolutions.com 12 SUMMARIZING THE BASELINE SCHEDULE (AGAIN) – LEVEL 1 NOTE: The Level 1 schedule needs to fit on ONE (1) page, whereas the Level 2 Schedule can be spread out across multiple pages.
  • 14. www.construxsolutions.com 14 THE AS PLANNED VS. AS BUILT ANALYSIS  Find the latest contemporaneous schedule update.  Summarize “as-built” data points in latest schedule update to mirror the Level 2 Baseline Summary. Compare. NOTE: If no schedule update exists, use other sources to determine start and finish dates for summary level activities (ie. payment applications, photo’s, dailies, etc.) NOTE: Seek start dates and “substantial completion” dates for each activity.  Begin to analyze duration variances in each area, measure delay from completion of one trade to the next and try to determine if there appears to be a theme. (See example on next slide).  Overlap Areas, and see if a particular trade is impacting workflow and driving delays  Begin to highlight delay issues for future analysis
  • 15. www.construxsolutions.com 15 LEVEL 2 COMPARISON EXAMPLE – BUILDING F 59 cd delay 81 cd delay (net 22 cd) 160 cd delay (net 79 cd) 288 cd delay (net 128 cd)
  • 17. www.construxsolutions.com 17 WHAT IS THE CRITICAL PATH AND WHY IS IT RELEVANT? • It is the longest “String” or “Path” of activities that logically connects the start date of the project to the end of the project. • It is the one and only path on a project that has no float or slack and will results in a delay to the end date of the project if delayed. • It is relevant because only a critical path activity can delay the project a certain point in time. • Determining the “Historic” Critical path, is the most important step in building a Delay Analysis / Claim. • Once Historical Critical Path is identified, one can assess responsibility for delay and then entitlement.
  • 18. www.construxsolutions.com 18 What is Compensable, Concurrent and Non Compensable Delay? Once delay is identified, it is typically categorized into the following: ‒ Excusable Compensable – The Contractor was delayed and had no part in causing the delay (“Out of the its Control’); Granted time and money for extended GC’s, acceleration and/or impact costs. ‒ Excusable Non Compensable (“Concurrent”) – The Contractor was equally involved/responsible for a delay, along with another party (ie. owner, engineer, etc); Granted time, but no money for extended GC’s, acceleration, and/or other impact costs. ‒ Non Excusable Non Compensable – The Contractor was solely responsible the delay for a particular period of time; Granted no time and no money. NOTE: On Projects where multiple delays are identified, each will need to be classified with the above categories to ultimately prepare a delay claim.
  • 19. www.construxsolutions.com 19 How do we determine the Historical Critical Path? • Start with reviewing the Contemporaneous Schedule Updates. • Try to determine if the schedule updates were used to “manage” versus used to “check the box”; Try these indicators: ‒ See if the project critical path was clearly delayed over time and the end date stayed the same for a long time. This indicates the schedule is likely not usable to document CP. ‒ A lot of logic changes and shortened durations of activities. This indicates the schedule is likely unusable. ‒ If trades started getting stacked towards the end of the project and the end date stays the same. This indicates the schedule is unusable for documenting historical CP. ‒ HINT: Create a Database of Schedule Updates with the following fields: Schedule Title, Data Date, No. of Activities, Project Completion Date, Go Forward Critical Path • If the schedule updates seem legit, document the critical path and delay through a “Windows Analysis”. • If the updates do not seem legit, one will need to either review meeting minutes, letters of delay, or calculate in an as planned versus as-built scenario.
  • 20. www.construxsolutions.com 20 WHAT IS A WINDOWS ANALYSIS?  A Technique that measures delay while documenting the historical critical path through different periods (or windows) of time.  It essentially allows users to easily decipher what was deemed critical from one period to the next, as the schedule is updated.  If properly utilized, it will document shifts in the critical path, from planned to actual.  The more periods reviewed, the better. But lets not get crazy. Monthly windows are best.  If properly performed it will be easier to digest, and more difficult to argue.  Windows Analysis should be analyzed in a Level 2 Summary, explained in a Level 1 Summary.
  • 26. www.construxsolutions.com 26 OTHER WAYS TO DETERMINE THE HISTORICAL CRITICAL PATH • As Planned vs. As built Calculation Method • Determine Variances by comparing Late Dates to Actual Dates • Chart it out • Compare • Review of Meeting Minutes, Emails, Progress Reports to highlight what appear to be “delaying issues” • Read Correspondence • Document Issues • Highlight time frame
  • 27. www.construxsolutions.com 27 EXAMPLE: AS PLANNED V AS BUILT CALCULATION METHOD 0 50 100 150 200 250 300 350 8/10/2010 11/18/2010 2/26/2011 6/6/2011 9/14/2011 12/23/2011 4/1/2012 Core Area 1 Core Area 2 Core Area 3 DaysofDelay Critical Path equals Highest Line Concurrent Delay
  • 29. www.construxsolutions.com 29 THE SIMPLIFIED METHOD • As Planned Versus As Built Method Works Best. • Step 1: Document the Agreed to Baseline (in Excel) • Step 2: Document every day worked on which activity using daily reports (in Excel). • Step 3: Analyze variances, disruption, delay and even manpower • Step 4: Determine Causation for budget overruns and delay • NOTE: The project critical path and the trade contractors critical path can be different. The trade contractor needs to determine both for “offense” and “defense”. • NOTE: If the trade contractors opts not to submit daily reports, this analysis will become a lot harder.
  • 30. www.construxsolutions.com 30 SETTING UP THE AS PLANNED SCHEDULE INTO A VISUAL DATABASE
  • 31. www.construxsolutions.com 31 ADDING DAILY REPORT DATA INTO A VISUAL DATABASE
  • 32. www.construxsolutions.com 32 CONVERTING DAILY REPORT DATA INTO PERFORMANCE METRICS
  • 33. www.construxsolutions.com 33 PRESENTED BY: MICHAEL PINK Contact Info: C: 404 277 4387 O: 404 329 3000 mpink@construxsolutions.com Feel free to contact me directly if you have any additional questions Sign up for our upcoming courses: — CPM Scheduling — Data Management and Performance Analysis — Delay Analysis in Construction — Construction Claims Review/Prep Follow us on LinkedIn for more info.