Milton Simpson
University of Salford
School of the Built Environment
BIM THEORY & PRACTICE
COURSEWORK 1
  2	
  
CONTENTS
1.1 Introduction
	
  
	
  
1.2 Strategy
1.3 Execution – Pre Contract
1.4 Post Contract
1.5 Delivery – MIDP
1.6 Mobilization
1.7 Production – BS1192
1.8 Common Data Environment - CDE (PIM)
1.9 Handover & Closeout - PIM
2.0 Project Information Model - PIM
2.1 Asset Information Model (AIM) - OPEX
2.2 Operations - COBie
  3	
  
BIM Theory and Practice – Semester 1
Module 2
1.1 INTRODUCTION
The Government Transport Authority has commissioned a scheme to build
a new link road (The Woodside Link) alongside the existing stretch of A1
that runs through Dunstable Bedfordshire.
The new stretch of road will start at the junction at Torn Turn (A505) and
finish at the Toddington Services. Work is due to complete in the spring of
2017. The link road will consist of three new junctions, two roundabouts, an
interchange with the M1, a bridge on the B579, Luton road and a further 4
bridges at various points along the A5-M1.
The feasibility of the new link has concluded that £38.3 million invested in
the new Woodside Link road is a strategic transport improvement that will
relieve traffic going through the town, thus increasing road safety and will
boost the local economy.
Infrastructure is a vital part of our long term economic plan to secure a better
future for the people of Bedfordshire, The A5-M1 Link road is a great example of
how we are delivering projects that will boost growth across the country.
RHon Patrick McLoughlin. (2015). Press release, boost for Bedfordshire economy as new A5-
M1 link road starts construction. Retrieved 14 October, 2015, from
http://www.gov.uk/government/news/
Figure 1: Layout of the new A5-M1Link Road (Source: Bedfordshire Council, 2015)
  4	
  
1.2 STRATEGY
The groundwork for BIM Level 2 procedures and workflows begin at an
early stage (before pre-contract). The level of consultation at this stage
between the BIM manager and employer has to be the most crucial stage
of the whole process. BIM’s ethos is to look at the project from beginning to
end and treat the process as a whole. This is where power of BIM comes
into it own, because its procedures play a crucial part in determining the
roles and responsibilities of all parties involved.
The first piece of the process is to make the employer aware of the PAS
and British Standards and guidelines that need to be followed to achieve
BIM Level 2. Below is a list of these documents.
PAS1192-2:2013 – Specification for information management for capital/delivery phase of
construction projects using Building Information Modeling.
PAS1192-3:2014 – Specification for information management for the operation phase of
assets using Building Information Modeling.
PAS1192-4:2014 - Collaborative production of information part4: Fulfilling employers
information exchange requirements using COBie – code of practice.
BS 1192-4:2014 – Collaborative production of information.
PAS1192-5:2015 – Specification for security-minded building information management,
digital built environments and smart asset management.
Construction Industry Council (CIC) – Building Information Model Protocol.
Digital Plan of Work (DPoW) – Working group representing a range of trade
organizations, suppliers and contractors.
Classification Systems Q2 – Specifications in Development.
The first document of the level 2 process is the PAS1192-2: 2013. This will
give us guidance on how to draft an Employers Information Requirement.
Below is a brief summery of what is the purpose of the EIR.
“The development of the EIR shall start either with the assessment of an existing
asset leading to the development of the employers need, or directly with the
employer’s need if no existing asset or asset information model (AIM) is to be
considered.”
Designing Buildings Wiki. (Last edited 20 Aug 2015). Employers information requirements for
BIM. Retrieved 16 October, 2015, from http://www.designingbuildings.co.uk/wiki/employer
%27s_ information_requirements_for_bim
If as stated above there are no previous schemes constructed without
Level 2, the BIM Manager and Employer work in close consultation to
develop the EIR. The PAS1192-2: 2013 specification will be the document
to optimize the requirements of the employer expectations of the project.
(This will form the basis of a BIM Execution Plan).
Once all parties have agreed the Employers Information Requirement. The
production of this document will run parallel with the requirements with
British standards BS6100-4 2008: Building and Civil Engineering. This
British standard is a statutory requirement along with the Technical
Approval of Highway Structures BD2/12, volume 1, section1, part 1.
  5	
  
Cont.
This document requires the scheme to meet the Technical Approval (TA);
a brief summery of these specifications is as follows:
“The TA procedures as described in the standard generally require the proposer
to submit an Approval In Principal (AIP) to the overseeing organization and to
receive endorsement of the AIP before proceeding with any design or assessment.
The completed design or assessment cannot be implemented until the overseeing
organization is in receipt of certified confirmation that the implementation
documents are accurate and fully in compliance with the requirements of the
AIP”.
Highways Agency Transport Guidance. (n.d.). Standards for highways online resources.
Retrieved 08 October 2015 from http://www.gov.uk/guidance/standards-for-highways-online-
resources.
Williams Lea. volume 1, section 1, dmrb | standards for highways. Retrieved from
http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf
Other requirements in the BD2/12 are:
1. The Technical Assessment dose or will not effect the terms of
contractual stipulations relating to all parties involved on the project,
with the exemptions of DBFO (Design, Build, Finance & Operate)
contracts are exempt from this.
2. The approval in principal for this scheme has to be defined in the
contract as only guides to construction or are sufficient enough to
proceed with tender invitations.
One clause in particular could prove to be sticking point from issuing an
EIR to next Level 2 document, the BIM Execution Plan (BEP). The
clause states under the Contractual Responsibilities and Procedures:
1.17 For some forms of procurement, Technical Assessment for the design would
typically be completed in detail before tenders for carrying out the construction
work required by the design are invited.
For other forms of procurement, where the design has not yet been completed
prior to inviting tenders the TA process would typically only be partially
completed during the tender period. Submission of a final detailed Approval In
Principal (AIP) would usually take place following award of contract.
Highways Agency Technical Approval of Highway Structures. (n.d.). BD2/12, Volume 1, Section
1, Part 1. Retrieved from Williams Lea. volume 1, section 1, dmrb | standards for highways.
Retrieved 08 October 2015 from http://www.standardsforhighways.co.uk
http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf
  6	
  
1.3 EXECUTION: Pre-Contract
Once the EIP conditions are collated, the invite to tender for the project
begins. All prospective bidders are required to be BIM compliant. This is
the mandatory requirement to undertake this project. Contractors will have
to supply a BIM Execution Plan (BEP). The BIM Execution Plan is a single
document split into 2 mini contracts: Pre Contract at tender stage and Post
Contract submitted by the successful bidder. The Pre BEP contract will
form part of the tender.
1.4 Post-Contract
Balfour Beatty was announced as the winning tender (Amey as the lead
Project Manager / Design consultants). At this point the Post-contract BEP
would be submitted as part of the contract and forms an integral part of the
project, so it is important that the contractor can demonstrate to the
employer that the plan of work is attainable. The building information model
protocol published by the Construction Industry Council will ensure that
BEP is central to the contract. The preface of this contract states:
The BEP shall list the agreed targets for responsibility, timely delivery, exchange,
reuse and final handover to the clients it will also list all of agreed elements as
outlined in the Employers Information Requirements (EIR). The brief, the
BS1192: 2007, PAS1192-2: 2013, the Construction Project Information Protocol
and the contract documents. The BEP is structured in accordance with PAS1192-
2: 2013.
CPIC, CPIx. (n.d.). BIM Execution Plan. Retrieved 14 October, 2015 from
http://www.cpic.org.uk/cpix /cpix-bim-execution-plan
A brief overview of a few content in the Post BEP Contract:
• Details of the Project Delivery Manager and Project Team
representatives and roles.
• The Contractors capacity and competence of their supply chains.
• Concise details of how the Information requirements of the
employer are met.
• Software applications to be agreed with all parties involved on the
project.
• The security safeguards of building information data during and
after completion of the project. Protection and prevention of
malicious breeches of systems set up by the main contractor &
stakeholder, from outside sources (Reference PAS1192-5 for
further guidance).
• A list of standards and procedures for the project.
• Roles and responsibilities or the team in ensuring the requirements
set out in the BIM Execution Plan.
  7	
  
1.5 Delivery – MIDP
On signing of the contract the next requirement is to set up the Master
Information Delivery Plan (MIDP). There are several pieces of information
that when combined make up the MIDP, the first of which is the
Construction Program or Project Plan submitted by the lead contractor.
The Construction Programme parameters will be linked to the MIDP.
The MIDP requires more information to become effective, this
information comes from an element that makes up the BIM Execution Plan:
the Supply Chain Capability Summery (SCCS). This document also
generates another document called the Responsibility Matrix (RM)also
known as ‘Projects roles tables’. The RM lists the responsibilities of each
discipline of production of information (documents or models) and the
relationship between all parties involved.
The final piece that makes up the MIDP is the Task Team Information
Delivery Plan (TIDP). The TIDP are documents containing information
deliverables and are submitted by the Task Team Managers directly into
the MIDP. The Information MIDP holds is fed back into the BIM Execution
Plan. All aspects of the CAPEX (construction) process is accounted for and
all procedures, systems, scheduling all lead back to the BIM Execution
Plan.
Below is a diagram designed by Mervyn Richards showing the flow of
Level 2 documentation.
  8	
  
Figure 2 (PAS1192-2, 2013, p.8) shows the relationship between documents used for Information Management
1.6 Mobilization
The next step is for the Project Delivery Team to review all the
documentation created (EIR, BEP and MIDP) and to begin to create the
framework to make them operational. Before the design stage begins the
team needs to:
1. Ensure that all relevant documents have been collated,
prepared and agreed by all parties.
2. Information Management systems are in place and are
capable of coping with the Information to be stored.
(Simulated test should take place to fix any problems at this
stage rather than at design / construction phase).
3. Establish if the Delivery Team has the skillset needed to
complete this project successfully. If there is a skills gap
further training and education will be provided.
4. Supply chain systems are ready and capable to deliver as
scheduled.
Once these issues have been addressed the move to the design phase
can begin. (*Note: a mobilization period agreed for this period by the
employer and contractor).
1.7 Production –BS1192
The standards set out in PAS1192-2 have given us scope to establishing
plan of work, procedures and information management. The BIM Manager
and Project Delivery Team will also work to British Standards: BS1192
(2007) a summary of the standard objectives states:
Establishes the methodology for managing the production, distribution and
quality of construction information, including that generated by CAD systems,
using a disciplined process for collaboration and a specified naming policy. It is
applicable to all parties involved in the presentation and use of information
throughout the design, construction, operation and deconstruction throughout the
project life cycle and the supply chain. The principles for information sharing and
common modeling are equally applicable to building and civil projects. This
standard is also a guide for developers of software applications to enable them to
support its implementation through the provision of configuration files or
application add-ons.
British Standards Institute (BSI) BS 1192-4:2014. Part 4: Fulfilling employer’s information
exchange requirements using COBie – Code of practice. 1192, (2007). Retrieved from
http://www.shop.bsigroup.com
  9	
  
This standard gives guidance and recommendations on how processes
can be carried out and addresses two key issues the first is the handling
and distribution of data, and the second is the naming convention of data.
These procedures are not compulsory but are widely adopted by the
construction industry.
Collaboration Management Process – BS1192
During the construction phase the Collaboration Management Process is a
procedure that enables teams involved with the design of models and
production of drawings to submit to a centralized depository in order to co-
ordinate designs as they develop. Each discipline still has control of their
work (work-in progress) before releasing to other teams to amend any
design flaws. Once all parties agree and approve a finished design, the
drawing or document will be published at agreed construction phases, and
archived. The employer as stipulated in the contract can access this
archive. Below is an illustration of this procedure.
In Figure 3 (PAS1192-3, 2013, p.16) the common data environment workflow extracted from PAS119-2
  10	
  
1.8 Common Data Environment – CDE (PIM)
The principals of a Common Data Environment have been discussed
within the construction industry since the year 2000. The software-as-a-
source applications as developed by companies like Hewlett Packard have
become available. The Common Data Environment is single source cloud
based application for information deposits collected, and manages data
through the project CAPEX period (conception, design and construction
phase) to the OPEX (handover and operation) stages.
The project team can deposit graphical and non-graphical content,
creating a single source of information and facilitates collaboration
between project team members. CDE’s key attribute is that it prevents
mistakes or duplication of work.
1.9 Handover & Closeout – (PIM)
At the end of the construction period the handover of the
infrastructure/asset from the contractor to the employer takes place. This is
done in stages, to ensure that any problems with the build need to be
rectified, this is known as ‘Defects Liability period’. There is also period of
handover known as a ‘soft landing’. A formal transfer of the Common Data
Environment (CDE) to the employer will also take place. Below is an
extract from PAS1192-2 in regards to this.
10.2.1 The effective transfer of structured information between the asset lifecycle
stages delivers significant value. To effectively enable this, formal handover
processes shall be documented in the EIR. The document shall define the
structure, process and content of information to be exchanged. This document
shall form the basis for the operational contract documentation. In addition,
appropriate surveys such as point cloud or LiDAR shall be provided to verify the
completeness of the as-constructed model.
British Standards Institute (BSI) & the Construction Industry Council (CIC): PAS1192-
3(2014). Specification for information management for the capital/delivery phase of
construction projects using Building Information Modeling. Retrieved from
http://shop.bsigroup.com
2.0 Project Information Model (PIM)
At this point I would like to discuss the main object of this Level 2
procedure: the infrastructure itself. This is the commissioned Link road. As
explained the different requirements needed to reach this stage: EIR, BEP,
MIDP and Mobilization, from this the Project Information Model is finalized.
The information delivery cycle has six objectives during the CAPEX stage:
Brief, Concept, Design, Definition, Build & Commission, Handover and
Closeout.
During the end of each stage data drops are made to the suppliers
information exchange in readiness of the next phase of the project. The
  11	
  
supply of information is also transferred to the Employer as stipulated in
the contract. Employer data drops only happen at stages: 1, 2, 3, 6 and 7.
2.1 Asset Information Model (AIM) - OPEX
There is a seventh stage: Operation this comes under the Asset
Information Model (AIM). This comes into effect on handover of the project
to the employer. This stage of the Level 2 process is governed by standard
ISO 55001 (this supersedes PAS 55), and PAS1192-3.
ISO 55001 (PAS 55): This standards set out a clear guide on how to
optimize management of assets. A 28-point specification whole-life
management system. and how to align the maintenance and operation of
the asset with the aims and strategy of the business. This can be adopted
for use on any form of infrastructure / asset.
PAS1192-3 2014: Standard covers the same areas of governance as ISO
55001 (PAS 55) to achieve the of the operation optimization of
infrastructure asset on handover:
2.2 Operations – COBie
Part of the operational function of level 2 BIM is the maintenance of an
asset throughout its lifespan. On completion of a project all documentation
associated is handed over form the contractor to the client. One crucial
document is the Construction Operation Building information exchange or
better known as COBie. The concept and development of this document
was created in the US where it has proven to be a valuable tool in
maintaining infrastructure. The format is a spreadsheet making it easy for
all parties to input, communicate and exchange information for the
duration of a project. COBie has been used successful as a go-to
operations manual.N
  12	
  
APENDIX
British Standards Institute. Construction Industry Council. Specification for information
management for the capital/delivery phase of construction projects using Building Information
Modeling. Retrieved from http://shop.bsigroup.com (BS 1192-4:2014, PAS1192-3 2014).
British Standards Institute. Construction Industry Council. Specification for information
management for the operational phase of assets using Building Information Modeling. Retrieved
form http://shop.bsigroup.com (PAS1192-3: 2014).
British Standards Institute. (2014). Part 4: Fulfilling employer’s information exchange
requirements using COBie – Code of practice. (BS 1192-4:2014). Retrieved from
http://www.shop.bsigroup.org
Central Bedfordshire Council. (2015). Layout of the woodland link road [Drawing]
Retrieved from http://www.centralbedfordshier.gov.uk/65489/
Construction Project Information Protocol. (n.d.). CPIx BIM Execution Plan. Retrieved 14
October, 2015. from http://www.cpic.org.uk/cpix /cpix-bim-execution-plan Committee.
Designing Buildings Wiki. (Last edited 20 Aug 2015). Employers information requirements for
BIM. Retrieved from http://www.designingbuildings.co.uk/ wiki/employer%27s_ information_
requirements_for_bim
Department for Transport. The Highways Agency. (2015). Transport Guidance. Standards for
highways online resources. Retrieved from http://www.gov.uk/guidance/standards-for-highways-
online-resources.
Department for Transport. The Highways Agency. Department Technical Approval of
Highway Structures BD2/12, Volume 1, Section 1, Part 1. Retrieved from Williams Lea. volume 1,
section 1, dmrb | standards for highways. Retrieved from
http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf
Nesbitt N, (2013). Technical Review of the use of COBie in Civil Engineering and Infrastructure
Handover. Strategy Paper for the Government Construction Client Group (BIM Industry Working
Group). Retrieved from http://bimtaskgroup.org
Richards, M. (2013). Relationships between documents used for Information Management
[Drawing]. In British Standards Institute (BSI) & the Construction Industry Council (CIC): 2013
Specification for information management for the capital/delivery phase of construction projects
using building information modeling, p. 8.
Richards, M. (2013). Common data environment extracted from PAS1192-2 [Drawing]. In
British Standards Institute (BSI) & the Construction Industry Council (CIC): 2013 Specification
for information management for the capital/delivery phase of construction projects using building
information modeling, p. 26.
Williams Lea. volume 1, section 1, dmrb | standards for highways. Retrieved from
http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf
  13	
  

More Related Content

What's hot

Applications of six sigma in Construction
Applications of six sigma in ConstructionApplications of six sigma in Construction
Applications of six sigma in Construction
Ankita Kolamkar
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
ashleyyeap
 
Software application assignment 2
Software application assignment 2Software application assignment 2
Software application assignment 2
Sow Wei Henn
 
Software report-complete-final
Software report-complete-finalSoftware report-complete-final
Software report-complete-final
Yong Sy
 

What's hot (20)

Change Management For Building Information Modelling (BIM)
Change Management For Building Information Modelling (BIM)Change Management For Building Information Modelling (BIM)
Change Management For Building Information Modelling (BIM)
 
Use of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real projectUse of BIM in planning and construction and implementation in real project
Use of BIM in planning and construction and implementation in real project
 
Applications of six sigma in Construction
Applications of six sigma in ConstructionApplications of six sigma in Construction
Applications of six sigma in Construction
 
BIM case study
BIM case studyBIM case study
BIM case study
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application Report
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
BIM - Operational readiness
BIM - Operational readinessBIM - Operational readiness
BIM - Operational readiness
 
Use of bim in project management
Use of bim in project managementUse of bim in project management
Use of bim in project management
 
022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)022 Construction Productivity (PART 1)
022 Construction Productivity (PART 1)
 
Implementing Building Information Modelling in Construction
Implementing Building Information Modelling in ConstructionImplementing Building Information Modelling in Construction
Implementing Building Information Modelling in Construction
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Bim
BimBim
Bim
 
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBETalk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
Talk on the Joint Contracts Tribunal and JCT 2016 Editions by Richard Saxon CBE
 
Software application assignment 2
Software application assignment 2Software application assignment 2
Software application assignment 2
 
Module 2 - Understanding BCA's Performance Requirements
Module 2 - Understanding BCA's Performance RequirementsModule 2 - Understanding BCA's Performance Requirements
Module 2 - Understanding BCA's Performance Requirements
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 
Synergis University 2014-BIM for Construction
Synergis University 2014-BIM for ConstructionSynergis University 2014-BIM for Construction
Synergis University 2014-BIM for Construction
 
Building information modeling & value to the AEC industry Part 1 v1
Building information modeling &  value to the AEC industry   Part 1 v1Building information modeling &  value to the AEC industry   Part 1 v1
Building information modeling & value to the AEC industry Part 1 v1
 
Software report-complete-final
Software report-complete-finalSoftware report-complete-final
Software report-complete-final
 
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
Malaysia's Architect Act 1967 & Architect Rules 1996 (amended 2010)
 

Viewers also liked

BIM Uses In Design
BIM Uses In DesignBIM Uses In Design
BIM Uses In Design
nevena_psu
 

Viewers also liked (8)

Adopting BIM - An Architect's Perspective (07 May 2014)
Adopting BIM - An Architect's Perspective (07 May 2014)Adopting BIM - An Architect's Perspective (07 May 2014)
Adopting BIM - An Architect's Perspective (07 May 2014)
 
5 things to know about Passivhaus
5 things to know about Passivhaus5 things to know about Passivhaus
5 things to know about Passivhaus
 
BIM & Sustainability
BIM & SustainabilityBIM & Sustainability
BIM & Sustainability
 
Bim interoperability analysis between revit and archicad for ifc exchange
Bim interoperability analysis between revit and archicad for ifc exchangeBim interoperability analysis between revit and archicad for ifc exchange
Bim interoperability analysis between revit and archicad for ifc exchange
 
RIBA Part 3 Course: BIM Overview + Application
RIBA Part 3 Course: BIM Overview + ApplicationRIBA Part 3 Course: BIM Overview + Application
RIBA Part 3 Course: BIM Overview + Application
 
BIM Uses In Design
BIM Uses In DesignBIM Uses In Design
BIM Uses In Design
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentation
 
The Top Skills That Can Get You Hired in 2017
The Top Skills That Can Get You Hired in 2017The Top Skills That Can Get You Hired in 2017
The Top Skills That Can Get You Hired in 2017
 

Similar to M Simpson coursework

Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
Bt Lee
 
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
CCT International
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
Association for Project Management
 

Similar to M Simpson coursework (20)

Employers Information Requirements (EIR) Explanatory Notes - P21+ and BIM
Employers Information Requirements (EIR) Explanatory Notes - P21+ and BIMEmployers Information Requirements (EIR) Explanatory Notes - P21+ and BIM
Employers Information Requirements (EIR) Explanatory Notes - P21+ and BIM
 
TMR and BIM
TMR and BIMTMR and BIM
TMR and BIM
 
BIM protocols: What are they? Do we need them? What should they contain?
BIM protocols: What are they? Do we need them? What should they contain?BIM protocols: What are they? Do we need them? What should they contain?
BIM protocols: What are they? Do we need them? What should they contain?
 
1217 loc tenders
1217 loc tenders1217 loc tenders
1217 loc tenders
 
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
 
Building information modelling - redefining the role of the project manager: ...
Building information modelling - redefining the role of the project manager: ...Building information modelling - redefining the role of the project manager: ...
Building information modelling - redefining the role of the project manager: ...
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 
BEP
BEPBEP
BEP
 
Pre and Post Contract BIM Execution Plans
Pre and Post Contract BIM Execution PlansPre and Post Contract BIM Execution Plans
Pre and Post Contract BIM Execution Plans
 
Mikael akkus module 3-employer's information rquirements
Mikael akkus  module 3-employer's information rquirementsMikael akkus  module 3-employer's information rquirements
Mikael akkus module 3-employer's information rquirements
 
BIM Toolkit Preview with Stephen Hamil
BIM Toolkit Preview with Stephen HamilBIM Toolkit Preview with Stephen Hamil
BIM Toolkit Preview with Stephen Hamil
 
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
Zuhair Haddad - 2nd Annual BIM Conference ME September 2013
 
Attachment Q - BIM Requirements (3).pdf
Attachment Q - BIM Requirements (3).pdfAttachment Q - BIM Requirements (3).pdf
Attachment Q - BIM Requirements (3).pdf
 
The NEW Role of the AIA's Digital Practice Documents
The NEW Role of the AIA's Digital Practice DocumentsThe NEW Role of the AIA's Digital Practice Documents
The NEW Role of the AIA's Digital Practice Documents
 
NEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinarNEC Contracts - Programmes under ECC and PSC webinar
NEC Contracts - Programmes under ECC and PSC webinar
 
Module-2 bim strategy case study structural project engineer-mikael akkus
Module-2 bim strategy case study  structural project engineer-mikael akkusModule-2 bim strategy case study  structural project engineer-mikael akkus
Module-2 bim strategy case study structural project engineer-mikael akkus
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
F1302033340
F1302033340F1302033340
F1302033340
 
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
 

Recently uploaded

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Recently uploaded (20)

This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)Jamworks pilot and AI at Jisc (20/03/2024)
Jamworks pilot and AI at Jisc (20/03/2024)
 
Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 

M Simpson coursework

  • 1. Milton Simpson University of Salford School of the Built Environment BIM THEORY & PRACTICE COURSEWORK 1
  • 2.   2   CONTENTS 1.1 Introduction     1.2 Strategy 1.3 Execution – Pre Contract 1.4 Post Contract 1.5 Delivery – MIDP 1.6 Mobilization 1.7 Production – BS1192 1.8 Common Data Environment - CDE (PIM) 1.9 Handover & Closeout - PIM 2.0 Project Information Model - PIM 2.1 Asset Information Model (AIM) - OPEX 2.2 Operations - COBie
  • 3.   3   BIM Theory and Practice – Semester 1 Module 2 1.1 INTRODUCTION The Government Transport Authority has commissioned a scheme to build a new link road (The Woodside Link) alongside the existing stretch of A1 that runs through Dunstable Bedfordshire. The new stretch of road will start at the junction at Torn Turn (A505) and finish at the Toddington Services. Work is due to complete in the spring of 2017. The link road will consist of three new junctions, two roundabouts, an interchange with the M1, a bridge on the B579, Luton road and a further 4 bridges at various points along the A5-M1. The feasibility of the new link has concluded that £38.3 million invested in the new Woodside Link road is a strategic transport improvement that will relieve traffic going through the town, thus increasing road safety and will boost the local economy. Infrastructure is a vital part of our long term economic plan to secure a better future for the people of Bedfordshire, The A5-M1 Link road is a great example of how we are delivering projects that will boost growth across the country. RHon Patrick McLoughlin. (2015). Press release, boost for Bedfordshire economy as new A5- M1 link road starts construction. Retrieved 14 October, 2015, from http://www.gov.uk/government/news/ Figure 1: Layout of the new A5-M1Link Road (Source: Bedfordshire Council, 2015)
  • 4.   4   1.2 STRATEGY The groundwork for BIM Level 2 procedures and workflows begin at an early stage (before pre-contract). The level of consultation at this stage between the BIM manager and employer has to be the most crucial stage of the whole process. BIM’s ethos is to look at the project from beginning to end and treat the process as a whole. This is where power of BIM comes into it own, because its procedures play a crucial part in determining the roles and responsibilities of all parties involved. The first piece of the process is to make the employer aware of the PAS and British Standards and guidelines that need to be followed to achieve BIM Level 2. Below is a list of these documents. PAS1192-2:2013 – Specification for information management for capital/delivery phase of construction projects using Building Information Modeling. PAS1192-3:2014 – Specification for information management for the operation phase of assets using Building Information Modeling. PAS1192-4:2014 - Collaborative production of information part4: Fulfilling employers information exchange requirements using COBie – code of practice. BS 1192-4:2014 – Collaborative production of information. PAS1192-5:2015 – Specification for security-minded building information management, digital built environments and smart asset management. Construction Industry Council (CIC) – Building Information Model Protocol. Digital Plan of Work (DPoW) – Working group representing a range of trade organizations, suppliers and contractors. Classification Systems Q2 – Specifications in Development. The first document of the level 2 process is the PAS1192-2: 2013. This will give us guidance on how to draft an Employers Information Requirement. Below is a brief summery of what is the purpose of the EIR. “The development of the EIR shall start either with the assessment of an existing asset leading to the development of the employers need, or directly with the employer’s need if no existing asset or asset information model (AIM) is to be considered.” Designing Buildings Wiki. (Last edited 20 Aug 2015). Employers information requirements for BIM. Retrieved 16 October, 2015, from http://www.designingbuildings.co.uk/wiki/employer %27s_ information_requirements_for_bim If as stated above there are no previous schemes constructed without Level 2, the BIM Manager and Employer work in close consultation to develop the EIR. The PAS1192-2: 2013 specification will be the document to optimize the requirements of the employer expectations of the project. (This will form the basis of a BIM Execution Plan). Once all parties have agreed the Employers Information Requirement. The production of this document will run parallel with the requirements with British standards BS6100-4 2008: Building and Civil Engineering. This British standard is a statutory requirement along with the Technical Approval of Highway Structures BD2/12, volume 1, section1, part 1.
  • 5.   5   Cont. This document requires the scheme to meet the Technical Approval (TA); a brief summery of these specifications is as follows: “The TA procedures as described in the standard generally require the proposer to submit an Approval In Principal (AIP) to the overseeing organization and to receive endorsement of the AIP before proceeding with any design or assessment. The completed design or assessment cannot be implemented until the overseeing organization is in receipt of certified confirmation that the implementation documents are accurate and fully in compliance with the requirements of the AIP”. Highways Agency Transport Guidance. (n.d.). Standards for highways online resources. Retrieved 08 October 2015 from http://www.gov.uk/guidance/standards-for-highways-online- resources. Williams Lea. volume 1, section 1, dmrb | standards for highways. Retrieved from http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf Other requirements in the BD2/12 are: 1. The Technical Assessment dose or will not effect the terms of contractual stipulations relating to all parties involved on the project, with the exemptions of DBFO (Design, Build, Finance & Operate) contracts are exempt from this. 2. The approval in principal for this scheme has to be defined in the contract as only guides to construction or are sufficient enough to proceed with tender invitations. One clause in particular could prove to be sticking point from issuing an EIR to next Level 2 document, the BIM Execution Plan (BEP). The clause states under the Contractual Responsibilities and Procedures: 1.17 For some forms of procurement, Technical Assessment for the design would typically be completed in detail before tenders for carrying out the construction work required by the design are invited. For other forms of procurement, where the design has not yet been completed prior to inviting tenders the TA process would typically only be partially completed during the tender period. Submission of a final detailed Approval In Principal (AIP) would usually take place following award of contract. Highways Agency Technical Approval of Highway Structures. (n.d.). BD2/12, Volume 1, Section 1, Part 1. Retrieved from Williams Lea. volume 1, section 1, dmrb | standards for highways. Retrieved 08 October 2015 from http://www.standardsforhighways.co.uk http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf
  • 6.   6   1.3 EXECUTION: Pre-Contract Once the EIP conditions are collated, the invite to tender for the project begins. All prospective bidders are required to be BIM compliant. This is the mandatory requirement to undertake this project. Contractors will have to supply a BIM Execution Plan (BEP). The BIM Execution Plan is a single document split into 2 mini contracts: Pre Contract at tender stage and Post Contract submitted by the successful bidder. The Pre BEP contract will form part of the tender. 1.4 Post-Contract Balfour Beatty was announced as the winning tender (Amey as the lead Project Manager / Design consultants). At this point the Post-contract BEP would be submitted as part of the contract and forms an integral part of the project, so it is important that the contractor can demonstrate to the employer that the plan of work is attainable. The building information model protocol published by the Construction Industry Council will ensure that BEP is central to the contract. The preface of this contract states: The BEP shall list the agreed targets for responsibility, timely delivery, exchange, reuse and final handover to the clients it will also list all of agreed elements as outlined in the Employers Information Requirements (EIR). The brief, the BS1192: 2007, PAS1192-2: 2013, the Construction Project Information Protocol and the contract documents. The BEP is structured in accordance with PAS1192- 2: 2013. CPIC, CPIx. (n.d.). BIM Execution Plan. Retrieved 14 October, 2015 from http://www.cpic.org.uk/cpix /cpix-bim-execution-plan A brief overview of a few content in the Post BEP Contract: • Details of the Project Delivery Manager and Project Team representatives and roles. • The Contractors capacity and competence of their supply chains. • Concise details of how the Information requirements of the employer are met. • Software applications to be agreed with all parties involved on the project. • The security safeguards of building information data during and after completion of the project. Protection and prevention of malicious breeches of systems set up by the main contractor & stakeholder, from outside sources (Reference PAS1192-5 for further guidance). • A list of standards and procedures for the project. • Roles and responsibilities or the team in ensuring the requirements set out in the BIM Execution Plan.
  • 7.   7   1.5 Delivery – MIDP On signing of the contract the next requirement is to set up the Master Information Delivery Plan (MIDP). There are several pieces of information that when combined make up the MIDP, the first of which is the Construction Program or Project Plan submitted by the lead contractor. The Construction Programme parameters will be linked to the MIDP. The MIDP requires more information to become effective, this information comes from an element that makes up the BIM Execution Plan: the Supply Chain Capability Summery (SCCS). This document also generates another document called the Responsibility Matrix (RM)also known as ‘Projects roles tables’. The RM lists the responsibilities of each discipline of production of information (documents or models) and the relationship between all parties involved. The final piece that makes up the MIDP is the Task Team Information Delivery Plan (TIDP). The TIDP are documents containing information deliverables and are submitted by the Task Team Managers directly into the MIDP. The Information MIDP holds is fed back into the BIM Execution Plan. All aspects of the CAPEX (construction) process is accounted for and all procedures, systems, scheduling all lead back to the BIM Execution Plan. Below is a diagram designed by Mervyn Richards showing the flow of Level 2 documentation.
  • 8.   8   Figure 2 (PAS1192-2, 2013, p.8) shows the relationship between documents used for Information Management 1.6 Mobilization The next step is for the Project Delivery Team to review all the documentation created (EIR, BEP and MIDP) and to begin to create the framework to make them operational. Before the design stage begins the team needs to: 1. Ensure that all relevant documents have been collated, prepared and agreed by all parties. 2. Information Management systems are in place and are capable of coping with the Information to be stored. (Simulated test should take place to fix any problems at this stage rather than at design / construction phase). 3. Establish if the Delivery Team has the skillset needed to complete this project successfully. If there is a skills gap further training and education will be provided. 4. Supply chain systems are ready and capable to deliver as scheduled. Once these issues have been addressed the move to the design phase can begin. (*Note: a mobilization period agreed for this period by the employer and contractor). 1.7 Production –BS1192 The standards set out in PAS1192-2 have given us scope to establishing plan of work, procedures and information management. The BIM Manager and Project Delivery Team will also work to British Standards: BS1192 (2007) a summary of the standard objectives states: Establishes the methodology for managing the production, distribution and quality of construction information, including that generated by CAD systems, using a disciplined process for collaboration and a specified naming policy. It is applicable to all parties involved in the presentation and use of information throughout the design, construction, operation and deconstruction throughout the project life cycle and the supply chain. The principles for information sharing and common modeling are equally applicable to building and civil projects. This standard is also a guide for developers of software applications to enable them to support its implementation through the provision of configuration files or application add-ons. British Standards Institute (BSI) BS 1192-4:2014. Part 4: Fulfilling employer’s information exchange requirements using COBie – Code of practice. 1192, (2007). Retrieved from http://www.shop.bsigroup.com
  • 9.   9   This standard gives guidance and recommendations on how processes can be carried out and addresses two key issues the first is the handling and distribution of data, and the second is the naming convention of data. These procedures are not compulsory but are widely adopted by the construction industry. Collaboration Management Process – BS1192 During the construction phase the Collaboration Management Process is a procedure that enables teams involved with the design of models and production of drawings to submit to a centralized depository in order to co- ordinate designs as they develop. Each discipline still has control of their work (work-in progress) before releasing to other teams to amend any design flaws. Once all parties agree and approve a finished design, the drawing or document will be published at agreed construction phases, and archived. The employer as stipulated in the contract can access this archive. Below is an illustration of this procedure. In Figure 3 (PAS1192-3, 2013, p.16) the common data environment workflow extracted from PAS119-2
  • 10.   10   1.8 Common Data Environment – CDE (PIM) The principals of a Common Data Environment have been discussed within the construction industry since the year 2000. The software-as-a- source applications as developed by companies like Hewlett Packard have become available. The Common Data Environment is single source cloud based application for information deposits collected, and manages data through the project CAPEX period (conception, design and construction phase) to the OPEX (handover and operation) stages. The project team can deposit graphical and non-graphical content, creating a single source of information and facilitates collaboration between project team members. CDE’s key attribute is that it prevents mistakes or duplication of work. 1.9 Handover & Closeout – (PIM) At the end of the construction period the handover of the infrastructure/asset from the contractor to the employer takes place. This is done in stages, to ensure that any problems with the build need to be rectified, this is known as ‘Defects Liability period’. There is also period of handover known as a ‘soft landing’. A formal transfer of the Common Data Environment (CDE) to the employer will also take place. Below is an extract from PAS1192-2 in regards to this. 10.2.1 The effective transfer of structured information between the asset lifecycle stages delivers significant value. To effectively enable this, formal handover processes shall be documented in the EIR. The document shall define the structure, process and content of information to be exchanged. This document shall form the basis for the operational contract documentation. In addition, appropriate surveys such as point cloud or LiDAR shall be provided to verify the completeness of the as-constructed model. British Standards Institute (BSI) & the Construction Industry Council (CIC): PAS1192- 3(2014). Specification for information management for the capital/delivery phase of construction projects using Building Information Modeling. Retrieved from http://shop.bsigroup.com 2.0 Project Information Model (PIM) At this point I would like to discuss the main object of this Level 2 procedure: the infrastructure itself. This is the commissioned Link road. As explained the different requirements needed to reach this stage: EIR, BEP, MIDP and Mobilization, from this the Project Information Model is finalized. The information delivery cycle has six objectives during the CAPEX stage: Brief, Concept, Design, Definition, Build & Commission, Handover and Closeout. During the end of each stage data drops are made to the suppliers information exchange in readiness of the next phase of the project. The
  • 11.   11   supply of information is also transferred to the Employer as stipulated in the contract. Employer data drops only happen at stages: 1, 2, 3, 6 and 7. 2.1 Asset Information Model (AIM) - OPEX There is a seventh stage: Operation this comes under the Asset Information Model (AIM). This comes into effect on handover of the project to the employer. This stage of the Level 2 process is governed by standard ISO 55001 (this supersedes PAS 55), and PAS1192-3. ISO 55001 (PAS 55): This standards set out a clear guide on how to optimize management of assets. A 28-point specification whole-life management system. and how to align the maintenance and operation of the asset with the aims and strategy of the business. This can be adopted for use on any form of infrastructure / asset. PAS1192-3 2014: Standard covers the same areas of governance as ISO 55001 (PAS 55) to achieve the of the operation optimization of infrastructure asset on handover: 2.2 Operations – COBie Part of the operational function of level 2 BIM is the maintenance of an asset throughout its lifespan. On completion of a project all documentation associated is handed over form the contractor to the client. One crucial document is the Construction Operation Building information exchange or better known as COBie. The concept and development of this document was created in the US where it has proven to be a valuable tool in maintaining infrastructure. The format is a spreadsheet making it easy for all parties to input, communicate and exchange information for the duration of a project. COBie has been used successful as a go-to operations manual.N
  • 12.   12   APENDIX British Standards Institute. Construction Industry Council. Specification for information management for the capital/delivery phase of construction projects using Building Information Modeling. Retrieved from http://shop.bsigroup.com (BS 1192-4:2014, PAS1192-3 2014). British Standards Institute. Construction Industry Council. Specification for information management for the operational phase of assets using Building Information Modeling. Retrieved form http://shop.bsigroup.com (PAS1192-3: 2014). British Standards Institute. (2014). Part 4: Fulfilling employer’s information exchange requirements using COBie – Code of practice. (BS 1192-4:2014). Retrieved from http://www.shop.bsigroup.org Central Bedfordshire Council. (2015). Layout of the woodland link road [Drawing] Retrieved from http://www.centralbedfordshier.gov.uk/65489/ Construction Project Information Protocol. (n.d.). CPIx BIM Execution Plan. Retrieved 14 October, 2015. from http://www.cpic.org.uk/cpix /cpix-bim-execution-plan Committee. Designing Buildings Wiki. (Last edited 20 Aug 2015). Employers information requirements for BIM. Retrieved from http://www.designingbuildings.co.uk/ wiki/employer%27s_ information_ requirements_for_bim Department for Transport. The Highways Agency. (2015). Transport Guidance. Standards for highways online resources. Retrieved from http://www.gov.uk/guidance/standards-for-highways- online-resources. Department for Transport. The Highways Agency. Department Technical Approval of Highway Structures BD2/12, Volume 1, Section 1, Part 1. Retrieved from Williams Lea. volume 1, section 1, dmrb | standards for highways. Retrieved from http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf Nesbitt N, (2013). Technical Review of the use of COBie in Civil Engineering and Infrastructure Handover. Strategy Paper for the Government Construction Client Group (BIM Industry Working Group). Retrieved from http://bimtaskgroup.org Richards, M. (2013). Relationships between documents used for Information Management [Drawing]. In British Standards Institute (BSI) & the Construction Industry Council (CIC): 2013 Specification for information management for the capital/delivery phase of construction projects using building information modeling, p. 8. Richards, M. (2013). Common data environment extracted from PAS1192-2 [Drawing]. In British Standards Institute (BSI) & the Construction Industry Council (CIC): 2013 Specification for information management for the capital/delivery phase of construction projects using building information modeling, p. 26. Williams Lea. volume 1, section 1, dmrb | standards for highways. Retrieved from http://www.standardsforhighways.co.uk/ha/standards/dmrb/vol0/ section1/bd212-548kb-pdf