Financial planning for
Construction projects
Mohamed Abdalla
Hassan Hamed
MSc,MBA,PMP,PQP
I am more than glad
to be your speaker for
the next 45 minutes
 MOHAMED ABDALLA
 Projects Manager, Public Speaker
 MSC,MBA, PMP,PQP
 +971508143450
 pm@ace.ae
Introduction
Name:
Job Title & role
PM Knowledge
Interests
Introduction
• The construction industry is one of the most
important sectors in United Arab Emirates, 660
billion dirham, the value of construction
projects in the UAE in 2013, So it is essential to
know the ingredients for success of
construction projects in UAE. While
construction project is unique, projects differ
in objectives, size, budget, timeline and
complexity, but we may find some common
features such as changes and risks concerns.
.
Agenda
 What is a Financial plan ? Funding gaps ?
 Why Funding gaps occur ?
 How to cover the funding gaps in construction
projects ?
 What are the alternative solutions ?
Challenges in Construction
Challenges
Changes Financial
Funding gaps
Client
Consultant
Contractor
Gaps are good or bad
Gaps are good or bad
RISK ISSUE
• What is a ‘Financial plan'
A reliable financial plan is an indispensable
management tool for any company
• One of the most time and cost consuming
tasks in compiling a cash-flow plan is the
compilation of the cost-flow. This is achieved
by spreading the field costs of each project
over its duration.
Funding gaps
• What is a 'Funding Gap'
The amount of money needed to fund the
ongoing project activities that is not currently
provided by cash, equity or debt.
• Funding gaps can be covered !!!!
• Cash-flow forecasting is a dynamic process.
Funding gaps
When F.G occurred
Cash In
Cash our
20,000$
35,000$
Cash-flow forecasting is a dynamic process.
Who will cover the gaps ?
Gaps
Funding gaps
F.G
• One of the largest companies in the United Arab Emirates,
specialized in multi-investment, has submitted a tender for the
implementation of a project for which you have been assigned
to study the tender documents and decide whether the
company will submit a tender in the project or not. The
following information is available in the project activities and
cost
Example
Project
Funding gaps
• Make a funding plan throughout the project duration.
Determine the (MBR ) Minimum Budget Required to
funding the project . (How much is enough?)
• The most sensitive activities (Critical activities).
• Funding gaps .
• Financial Decisions to cover the funding gaps.
Project Schedule
3 7 7 10
8 4 12 12 3 15
12 21
8 12
15 9 24
11 4 15
0 3 3 8 24 33 33 37
0 3 3 6 5 11 24 9 33 37 4 37
8 11
11 3 14 14 10
14 10 24
3 9 9 14
3 6 9 9 5 14
K
D H
I
E
F
J
L
B
C
G
A
MBR (how much is enough?)
)
.Activity
A 100 100 100 A
B 100 100 100 100 B
C 100 100 100 100 100 C
D 100 100 100 100 100 100 D
G 100 100 100 G
E 100 100 100 100 E
F 100 100 100 F
H 100 100 100 100 100 H
J 100 100 100 100 100 100 100 100 100 J
I 100 100 100 100 100 100 100 100 100 100 I
K 100 100 100 100 100 100 100 100 100 K
L 100 100 100 100 L
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37
Early
Monthly
100
100
100
300
300
300
300
300
400
400
300
200
200
200
200
200
200
200
200
200
200
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
Early
Accum.
100
200
300
600
900
1,200
1,500
1,800
2,200
2,600
2,900
3,100
3,300
3,500
3,700
3,900
4,100
4,300
4,500
4,700
4,900
5,000
5,100
5,200
5,300
5,400
5,500
5,600
5,700
5,800
5,900
6,000
6,100
6,200
6,300
6,400
6,500
Milestone
w3
w9
w14
w24
w33
w37
Time Schedule (Early Dates)
Lead & Lag
.Activity
A 100 100 100 A
B 100 100 100 100 B
C 100 100 100 100 100 C
D 100 100 100 100 100 100 D
G 100 100 100 G
E 100 100 100 100 E
F 100 100 100 F
H 100 100 100 100 100 H
J 100 100 100 100 100 100 100 100 100 J
I 100 100 100 100 100 100 100 100 100 100 I
K 100 100 100 100 100 100 100 100 100 K
L 100 100 100 100 L
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37
Late
Monthly
100
100
100
100
100
100
200
200
300
300
300
400
400
400
300
200
200
200
200
200
200
200
200
200
100
100
100
100
100
100
100
100
100
100
100
100
100
Late
Accum.
100
200
300
400
500
600
800
1,000
1,300
1,600
1,900
2,300
2,700
3,100
3,400
3,600
3,800
4,000
4,200
4,400
4,600
4,800
5,000
5,200
5,300
5,400
5,500
5,600
5,700
5,800
5,900
6,000
6,100
6,200
6,300
6,400
6,500
Milestone
w3
w9
w14
w24
w33
w37
Time Schedule (Late Dates)
Milestone Mile. 01 (w3) Mile. 02 (w9) Mile. 03 (w14) Mile. 04 (w24) Mile. 05 (w33) Mile. 06 (w37)
C accum. (ES) 300 2,200 3,500 5,200 6,100 6,500
C accum. (LS) 300 1,300 3,100 5,200 6,100 6,500
300 900
1,400
2,400
3,300
3,700
2,200
3,500
300
1,300
3,100
5,200
6,100
6,500
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37
MBR Early Accum. Late Accum.
FG 02
FG 03
FG 01
FG 04
FG 05
Funding gaps throughout the entire
project life cycle
‫المشروع‬ ‫عمر‬ ‫خالل‬ ‫التمويليه‬ ‫الفجوات‬ 5
No Time Internal MBR L.SSC Fund Gap
1 0-3 300 300 0 Nil
2 4-9 900 1,300 (400) F.G .01
3 10-14 1,400 3,100 (1,700) F.G. 02
4 15-24 2,400 5,200 (2,800) F.G. 03
5 25-33 3,300 6,100 (2,800) F.G. 04
6 34-37 3,700 6,500 (2,800) F.G. 05
Decisions to Covering funding gaps
Decisions to Covering funding gaps
1. MBR from the commencement of
the project to cover any funding gaps
and invest the balance amount in the
bank with interest.
2. Advance Payment 20% + MBR
No
Time
Internal
MBR L.SSC Fund Gap
1 0-3 3,700 300 3,400 Nil
2 4-9 0 1,300 2,400 Nil
3 10-14 0 3,100 600 Nil
4 15-24 0 5,200 (1,500) F.G. 01
5 25-33 0 6,100 (2,400) F.G. 02
6 34-37 0 6,500 (2,800) F.G. 03
No
Time
Internal
Advance
payment2
0%
MBR L.SSC Fund Gap
1 0-3 1,300 300 300 1,300 Nil
2 4-9 900 1,300 900 Nil
3 10-14 1,400 3,100 (400) F.G. 01
4 15-24 2,400 5,200 (1,500) F.G. 02
5 25-33 3,300 6,100 (1,500) F.G. 03
6 34-37 3,700 6,500 (1,500) F.G. 04
3..Borrow from bank with interest 5%
Conclusion
Solutions to cover FG
1.
MBR
2.
Advance
payment 25%
+
MBR
3.
Using
Subcontractors
4.
Borrow from
bank with
interest 5%
Questions
Contacts
• For more details, please call at +971508143450 or
• send an email at pm@ace.ae
THANK YOU FOR ATTENDING THE
PRESENTATION
A wealth of presentations and reports
will be available at The BIG 5 – Dubai
are available at www.big5.ae

More Related Content

Similar to Big 5 dubai 2017 ppt template project management talks

BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_Presentation
Vijay Pandey
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
Kinshook Chaturvedi
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
SIBANJAN MISHRA
 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
Mohammed Feroze
 

Similar to Big 5 dubai 2017 ppt template project management talks (20)

BeingTheBest_PMI_Presentation
BeingTheBest_PMI_PresentationBeingTheBest_PMI_Presentation
BeingTheBest_PMI_Presentation
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Looking for venture capital on iron ore project
Looking for venture capital on iron ore projectLooking for venture capital on iron ore project
Looking for venture capital on iron ore project
 
Work Pricing in construction projects by K C Iyer
Work Pricing in construction projects by K C IyerWork Pricing in construction projects by K C Iyer
Work Pricing in construction projects by K C Iyer
 
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip LewWhen Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
 
The CECL Workshop Series Part II: Vintage Analysis
The CECL Workshop Series Part II: Vintage AnalysisThe CECL Workshop Series Part II: Vintage Analysis
The CECL Workshop Series Part II: Vintage Analysis
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
 
M2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptxM2Lesson7IntroductiontoFinancialModeling.pptx
M2Lesson7IntroductiontoFinancialModeling.pptx
 
Scheduling by Primavera - Training
Scheduling by Primavera - TrainingScheduling by Primavera - Training
Scheduling by Primavera - Training
 
Where did it go wrong?
Where did it go wrong?Where did it go wrong?
Where did it go wrong?
 
Introducing financial analysis
Introducing financial analysisIntroducing financial analysis
Introducing financial analysis
 
TeamSixBP
TeamSixBPTeamSixBP
TeamSixBP
 
Business Plan - Term Project
Business Plan - Term ProjectBusiness Plan - Term Project
Business Plan - Term Project
 
CGCC May 5 budget committee
CGCC May 5 budget committee CGCC May 5 budget committee
CGCC May 5 budget committee
 
Investor Presentation - November 2014
Investor Presentation - November 2014Investor Presentation - November 2014
Investor Presentation - November 2014
 
Project management
Project managementProject management
Project management
 
PresentationIIP
PresentationIIPPresentationIIP
PresentationIIP
 
A Leading Manufacturer of Architectural Glass and Windows Serving the Global...
 A Leading Manufacturer of Architectural Glass and Windows Serving the Global... A Leading Manufacturer of Architectural Glass and Windows Serving the Global...
A Leading Manufacturer of Architectural Glass and Windows Serving the Global...
 
Business Proposal PowerPoint Presentation Slides
Business Proposal PowerPoint Presentation SlidesBusiness Proposal PowerPoint Presentation Slides
Business Proposal PowerPoint Presentation Slides
 
Q1 2013 presentation final v001 v2g6k8
Q1 2013 presentation final v001 v2g6k8Q1 2013 presentation final v001 v2g6k8
Q1 2013 presentation final v001 v2g6k8
 

Recently uploaded

UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 

Recently uploaded (20)

(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 

Big 5 dubai 2017 ppt template project management talks

  • 1. Financial planning for Construction projects Mohamed Abdalla Hassan Hamed MSc,MBA,PMP,PQP
  • 2. I am more than glad to be your speaker for the next 45 minutes
  • 3.  MOHAMED ABDALLA  Projects Manager, Public Speaker  MSC,MBA, PMP,PQP  +971508143450  pm@ace.ae
  • 4. Introduction Name: Job Title & role PM Knowledge Interests
  • 5. Introduction • The construction industry is one of the most important sectors in United Arab Emirates, 660 billion dirham, the value of construction projects in the UAE in 2013, So it is essential to know the ingredients for success of construction projects in UAE. While construction project is unique, projects differ in objectives, size, budget, timeline and complexity, but we may find some common features such as changes and risks concerns.
  • 6. .
  • 7. Agenda  What is a Financial plan ? Funding gaps ?  Why Funding gaps occur ?  How to cover the funding gaps in construction projects ?  What are the alternative solutions ?
  • 8. Challenges in Construction Challenges Changes Financial Funding gaps Client Consultant Contractor
  • 9. Gaps are good or bad
  • 10. Gaps are good or bad RISK ISSUE
  • 11. • What is a ‘Financial plan' A reliable financial plan is an indispensable management tool for any company • One of the most time and cost consuming tasks in compiling a cash-flow plan is the compilation of the cost-flow. This is achieved by spreading the field costs of each project over its duration. Funding gaps
  • 12. • What is a 'Funding Gap' The amount of money needed to fund the ongoing project activities that is not currently provided by cash, equity or debt. • Funding gaps can be covered !!!! • Cash-flow forecasting is a dynamic process. Funding gaps
  • 13. When F.G occurred Cash In Cash our 20,000$ 35,000$ Cash-flow forecasting is a dynamic process.
  • 14. Who will cover the gaps ? Gaps
  • 16. • One of the largest companies in the United Arab Emirates, specialized in multi-investment, has submitted a tender for the implementation of a project for which you have been assigned to study the tender documents and decide whether the company will submit a tender in the project or not. The following information is available in the project activities and cost Example
  • 18. Funding gaps • Make a funding plan throughout the project duration. Determine the (MBR ) Minimum Budget Required to funding the project . (How much is enough?) • The most sensitive activities (Critical activities). • Funding gaps . • Financial Decisions to cover the funding gaps.
  • 19. Project Schedule 3 7 7 10 8 4 12 12 3 15 12 21 8 12 15 9 24 11 4 15 0 3 3 8 24 33 33 37 0 3 3 6 5 11 24 9 33 37 4 37 8 11 11 3 14 14 10 14 10 24 3 9 9 14 3 6 9 9 5 14 K D H I E F J L B C G A
  • 20. MBR (how much is enough?) )
  • 21. .Activity A 100 100 100 A B 100 100 100 100 B C 100 100 100 100 100 C D 100 100 100 100 100 100 D G 100 100 100 G E 100 100 100 100 E F 100 100 100 F H 100 100 100 100 100 H J 100 100 100 100 100 100 100 100 100 J I 100 100 100 100 100 100 100 100 100 100 I K 100 100 100 100 100 100 100 100 100 K L 100 100 100 100 L 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Early Monthly 100 100 100 300 300 300 300 300 400 400 300 200 200 200 200 200 200 200 200 200 200 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 Early Accum. 100 200 300 600 900 1,200 1,500 1,800 2,200 2,600 2,900 3,100 3,300 3,500 3,700 3,900 4,100 4,300 4,500 4,700 4,900 5,000 5,100 5,200 5,300 5,400 5,500 5,600 5,700 5,800 5,900 6,000 6,100 6,200 6,300 6,400 6,500 Milestone w3 w9 w14 w24 w33 w37 Time Schedule (Early Dates)
  • 23. .Activity A 100 100 100 A B 100 100 100 100 B C 100 100 100 100 100 C D 100 100 100 100 100 100 D G 100 100 100 G E 100 100 100 100 E F 100 100 100 F H 100 100 100 100 100 H J 100 100 100 100 100 100 100 100 100 J I 100 100 100 100 100 100 100 100 100 100 I K 100 100 100 100 100 100 100 100 100 K L 100 100 100 100 L 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Late Monthly 100 100 100 100 100 100 200 200 300 300 300 400 400 400 300 200 200 200 200 200 200 200 200 200 100 100 100 100 100 100 100 100 100 100 100 100 100 Late Accum. 100 200 300 400 500 600 800 1,000 1,300 1,600 1,900 2,300 2,700 3,100 3,400 3,600 3,800 4,000 4,200 4,400 4,600 4,800 5,000 5,200 5,300 5,400 5,500 5,600 5,700 5,800 5,900 6,000 6,100 6,200 6,300 6,400 6,500 Milestone w3 w9 w14 w24 w33 w37 Time Schedule (Late Dates)
  • 24. Milestone Mile. 01 (w3) Mile. 02 (w9) Mile. 03 (w14) Mile. 04 (w24) Mile. 05 (w33) Mile. 06 (w37) C accum. (ES) 300 2,200 3,500 5,200 6,100 6,500 C accum. (LS) 300 1,300 3,100 5,200 6,100 6,500 300 900 1,400 2,400 3,300 3,700 2,200 3,500 300 1,300 3,100 5,200 6,100 6,500 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 MBR Early Accum. Late Accum. FG 02 FG 03 FG 01 FG 04 FG 05
  • 25. Funding gaps throughout the entire project life cycle ‫المشروع‬ ‫عمر‬ ‫خالل‬ ‫التمويليه‬ ‫الفجوات‬ 5 No Time Internal MBR L.SSC Fund Gap 1 0-3 300 300 0 Nil 2 4-9 900 1,300 (400) F.G .01 3 10-14 1,400 3,100 (1,700) F.G. 02 4 15-24 2,400 5,200 (2,800) F.G. 03 5 25-33 3,300 6,100 (2,800) F.G. 04 6 34-37 3,700 6,500 (2,800) F.G. 05
  • 26. Decisions to Covering funding gaps Decisions to Covering funding gaps 1. MBR from the commencement of the project to cover any funding gaps and invest the balance amount in the bank with interest. 2. Advance Payment 20% + MBR No Time Internal MBR L.SSC Fund Gap 1 0-3 3,700 300 3,400 Nil 2 4-9 0 1,300 2,400 Nil 3 10-14 0 3,100 600 Nil 4 15-24 0 5,200 (1,500) F.G. 01 5 25-33 0 6,100 (2,400) F.G. 02 6 34-37 0 6,500 (2,800) F.G. 03 No Time Internal Advance payment2 0% MBR L.SSC Fund Gap 1 0-3 1,300 300 300 1,300 Nil 2 4-9 900 1,300 900 Nil 3 10-14 1,400 3,100 (400) F.G. 01 4 15-24 2,400 5,200 (1,500) F.G. 02 5 25-33 3,300 6,100 (1,500) F.G. 03 6 34-37 3,700 6,500 (1,500) F.G. 04 3..Borrow from bank with interest 5%
  • 27. Conclusion Solutions to cover FG 1. MBR 2. Advance payment 25% + MBR 3. Using Subcontractors 4. Borrow from bank with interest 5%