 Agile Planning

    Artem Marchenko
    AgilDays.ru, December 9, 2009


               © 2003–2009 Artem Marchenko and Mountain Goat Software®




Artem Marchenko - background




               © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                 1
24.11.2009




What’s a good plan?
•   A good plan is one that supports reliable
    decision-making
•   Will go from
    •   We’ll be done in the third quarter
    •   We’ll be done in August
    •   We’ll be done August 18th




                          © 2003–2009 Artem Marchenko and Mountain Goat Software®




What makes planning agile?
      Is more focused on
    planning than the plan

               Encourages change

                      Results in plans that
                      are easily changed
                                 Is spread throughout
                                      the project
                          © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                            2
24.11.2009




Starting assumptions
•   We have a product backlog (prioritized feature
    list)
•   Items on the product backlog (user stories is my
    preference) have been estimated in story points
    or ideal days
•   We have a team with a known velocity
    •   We’ll relax this assumption shortly




                          © 2003–2009 Artem Marchenko and Mountain Goat Software®




An example with velocity=14
                                         Story A            Story F
 Sprint 1                               Sprints 3-4
                                                      5                   5
                                         Story B            Story G

                                                      8                   1
                                         Story C            Story H
 Sprint 2
                                                      3                 13
                                         Story D            Story I

                                                      5                   5
                                         Story E             Story J

                                                       1                  8
                          © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                            3
24.11.2009




Release and sprint planning

  Release Plan
   Sprint    Sprint   Sprint       Sprints 4–7
     1         2        3




                                         Task A       8 hours
                                         Task B      16 hours
                                         Task C       5 hours
                                         Task D       8 hours


                         © 2003–2009 Artem Marchenko and Mountain Goat Software®




            Agenda

            • Sprint planning
            • Estimating velocity
            • Release planning
               • Contracting on fixed-date
                 & fixed-scope projects




                         © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                           4
24.11.2009




                      © 2003–2009 Artem Marchenko and Mountain Goat Software®




Two approaches
•   Velocity-driven sprint planning
•   Commitment-driven sprint planning




                      © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                        5
24.11.2009




Velocity-driven sprint planning
•   “We finished 15 story points last time, let’s plan
    on 15 story points this time.”
•   Very unreliable in what will be accomplished
    during an iteration
    •   Velocity is mostly useful over the long term




                           © 2003–2009 Artem Marchenko and Mountain Goat Software®




Commitment-driven sprint planning
• Discuss the highest priority item on the product
    backlog
• Decompose it into tasks
• Estimate each task
• Ask ourselves, “Can we commit to this?”
    • If yes, see if we can add another backlog item
    • If not, remove this item but see if we can add another
        smaller one. Possibly by splitting the original story



                           © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                             6
24.11.2009




It looks something like this
As a user, I want ...        • Code the abc class (8 hours)
                             • Code the user interface (4)
                             • Write test fixtures (4)      26
                             • Code the xyz class (6)
                    2        • Update performance tests (4)


         Team can commit, so they continue...

As a user, I want ...
                             • Prototype the UI (8 hours)
                             • Demo UI to 3 outside users (3)
                             • Code new UI (12)            26
                             • Update documentation (3)
                    3
                         © 2003–2009 Artem Marchenko and Mountain Goat Software®




                    1


                                                2
                  time


                                               time


                         © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                           7
24.11.2009




                     © 2003–2009 Artem Marchenko and Mountain Goat Software®




How to estimate velocity
1
    Use historical values

           2
               Don’t, until you’ve run
                  a sprint or two
                        3
                                      Forecast it


                     © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                       8
24.11.2009




Forecasting velocity
•   Just like commitment-driven sprint planning
    •   Estimate available hours for the sprint
    •   Repeat until full:
        •   Pick a story, break into tasks, estimate each task




                              © 2003–2009 Artem Marchenko and Mountain Goat Software®




An example
•   Estimating available hours

             Person           Hours per Day            Hours per Sprint

             Sergey                  4-6                       40-60

             Kimmo                   5-7                       50-70

             Jarmo                   2-3                       20-30

                         Total                               110-160

                              © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                                9
24.11.2009




An example
                At 110-160 available hours per
              sprint, what is the team’s velocity?

    Code the ...    12
                                                                     Code the UI         8
     Do the...      8
                              As a frequent flyer, I
                                                                   Write test fixture    6
          48
Document the...     8
                                    want to...          3                  31
                                                                   Code middle tier     12
    Test the...     8
                                                                      Write tests        5
 Analyze the...     4         As a user, I want to...   5
 Document ...       8        As a vacation planner,
                                   I want to...         5                  50
                                                                          ...           50
                              As a frequent flyer, I
          20
        ...         20              want to...          2


                                    © 2003–2009 Artem Marchenko and Mountain Goat Software®




Put a range around it
•     You’re unlikely to have precisely forecasted the
      exact velocity the team will average
•     So, put a range around your velocity estimate:
                   Known team, domain,                      +5%
                       technology                           −10%
                                                            +10%
                                                            −25%
                      Unknown team,                         +25%
                    domain, technology                      −50%
     †Numbers  based on PMI advice on progressive
     accuracy of estimates.       © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                                     10
24.11.2009




Expressing velocity as a range

                        1.10       20                200 ÷ 20 = 10
   Estimated velocity
         = 18
                        .75        14               200 ÷ 14 = 15

   Adjustments                Total of
 from prior page           estimates on
    or intuition             product
                             backlog

         “Right now, before we start this project,
           our best estimate is that it will take
              between 10 and 15 sprints.”
                          © 2003–2009 Artem Marchenko and Mountain Goat Software®




                          © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                           11
24.11.2009




Create a range from historical
data
                                           Mean (Best 3) = 37
                                           Mean (Last 8) = 33
                                           Mean (Worst 3) = 28




          Sprints
                © 2003–2009 Artem Marchenko and Mountain Goat Software®




Predicting where we finish


          At our slowest velocity we’ll finish here
          (5×28)

          At our long-term average we’ll finish here
          (5×33)
          At our best velocity we’ll finish here (5×37)




                © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                 12
24.11.2009




Planning on contracted projects
    Fixed-date projects
                                      Fixed-scope projects

    A caveat
•   There are times you need to do this
    • So let’s look at some good techniques
•   Better though is try for a collaborative
    relationship with your customer
    • “You’ll have this team for each sprint, can
       direct them at the start of each, and stop
       when you have enough”
                            © 2003–2009 Artem Marchenko and Mountain Goat Software®




Fixed-date planning
          How much can I get by <date>?
1. Determine how many sprints you have
2. Estimate velocity as a range
3. Multiply low velocity × number of sprints
    • Count off that many points
      • These are “Will Have” items
4. Multiply high velocity × number of sprints
    • Count off that many more points
      • These are “Might Have items”


                            © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                             13
24.11.2009




Fixed-date planning: an example
   Desired
               30 June
release date
                                             Will have
Today’s Date 1 January

 Number of                          6×15
           6 (monthly)                          Might
  sprints
                                                have
   Low                              6×20
               15
  velocity
   High
               20                       Won’t have
  velocity

                    © 2003–2009 Artem Marchenko and Mountain Goat Software®




Fixed-date contracting
                       If you write a contract
                       for just the will haves:
                       • You won’t likely win the contract
  Will have            • But you’ll probably make money if
                         you do

6×15                   If you write a contract that
       Might           includes the might haves:
       have            • You will likely win the contract
6×20                   • But probably not make money on it

 Won’t have              It’s a risk issue
                         Where do you want to be?
                    © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                     14
24.11.2009




Fixed-scope planning
         When will all of this be done?
1. Sum all the backlog items the customer needs
2. Estimate velocity as a range
3. Divide total story points by high velocity
  • This is the shortest number of sprints it could
    take
4. Divide total story points by low velocity
  • This is the “most” sprints it could take

                      © 2003–2009 Artem Marchenko and Mountain Goat Software®




Fixed-scope planning: an example
     Total story points desired                    120
            Low velocity                            15
           High velocity                            20

120÷20=



120÷15=


                      © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                       15
24.11.2009




Fixed-scope contracting
    If you write a contract
    for the short duration:

    • You’ll likely win the contract
    • But may not make any money

                                If you write a contract
                                for the long duration:
                                 • You probably won’t win the contract
                                 • But will make money if you


                    It’s a risk issue

                    Where do you want to be?
                                © 2003–2009 Artem Marchenko and Mountain Goat Software®




Ranges
•   Notice in both cases we had a range
•   For a fixed date project, use a scope range:
    •   “By that date you’ll have all of these features and
        some of these.”
•   For a fixed-scope project, use a date range:
    •   “It will take us between 5 and 8 sprints to deliver all
        of those features.”



                                © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                                 16
24.11.2009




Artem Marchenko contact info


        artem.marchenko@gmail.com
     http://AgileSoftwareDevelopment.com
         http://twitter.com/AgileArtem




                © 2003–2009 Artem Marchenko and Mountain Goat Software®




                                                                                 17

More Related Content

Similar to Agile Planning (6)

Agile Planning
Agile PlanningAgile Planning
Agile Planning
 
Scrum Out Of The Nutshell
Scrum Out Of The NutshellScrum Out Of The Nutshell
Scrum Out Of The Nutshell
 
Scrum Out Of The Nutshell V3
Scrum Out Of The Nutshell V3Scrum Out Of The Nutshell V3
Scrum Out Of The Nutshell V3
 
Becoming Indie
Becoming IndieBecoming Indie
Becoming Indie
 
Getting Agile with Scrum
Getting Agile with ScrumGetting Agile with Scrum
Getting Agile with Scrum
 
Zh Tw Introduction To Cloud Computing
Zh Tw Introduction To Cloud ComputingZh Tw Introduction To Cloud Computing
Zh Tw Introduction To Cloud Computing
 

More from Nikita Filippov

Project Manager - Глупая идея
Project Manager - Глупая идеяProject Manager - Глупая идея
Project Manager - Глупая идея
Nikita Filippov
 
Lego симуляция © Alex Krivitsky
Lego симуляция © Alex KrivitskyLego симуляция © Alex Krivitsky
Lego симуляция © Alex Krivitsky
Nikita Filippov
 

More from Nikita Filippov (20)

Project Manager - Глупая идея
Project Manager - Глупая идеяProject Manager - Глупая идея
Project Manager - Глупая идея
 
6 scrum master
6 scrum master6 scrum master
6 scrum master
 
7 retro
7 retro7 retro
7 retro
 
5 risk
5 risk5 risk
5 risk
 
3 story mapping
3 story mapping3 story mapping
3 story mapping
 
2 bmg
2 bmg2 bmg
2 bmg
 
Lego симуляция © Alex Krivitsky
Lego симуляция © Alex KrivitskyLego симуляция © Alex Krivitsky
Lego симуляция © Alex Krivitsky
 
4 woz
4 woz4 woz
4 woz
 
Simple steps to makes great products
Simple steps to makes great productsSimple steps to makes great products
Simple steps to makes great products
 
Vietnam
VietnamVietnam
Vietnam
 
Story mapping
Story mapping Story mapping
Story mapping
 
Vision Crafting
Vision Crafting Vision Crafting
Vision Crafting
 
Lean startup
Lean startupLean startup
Lean startup
 
Customer Development
Customer Development Customer Development
Customer Development
 
Scrum в Заказной разработке
Scrum в Заказной разработкеScrum в Заказной разработке
Scrum в Заказной разработке
 
Innovation games for Agileee
Innovation games for AgileeeInnovation games for Agileee
Innovation games for Agileee
 
Who is Scrum Master Today?
Who is Scrum Master Today?Who is Scrum Master Today?
Who is Scrum Master Today?
 
Распределенный SCRUM - to be or not to be collocated collocated
Распределенный SCRUM - to be or not to be collocated collocatedРаспределенный SCRUM - to be or not to be collocated collocated
Распределенный SCRUM - to be or not to be collocated collocated
 
Командный старт
Командный стартКомандный старт
Командный старт
 
Rugby, Scrum и командная работа
Rugby, Scrum и командная работаRugby, Scrum и командная работа
Rugby, Scrum и командная работа
 

Recently uploaded

Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 

Recently uploaded (20)

Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)Introduction to Multilingual Retrieval Augmented Generation (RAG)
Introduction to Multilingual Retrieval Augmented Generation (RAG)
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot ModelMcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Mcleodganj Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf[BuildWithAI] Introduction to Gemini.pdf
[BuildWithAI] Introduction to Gemini.pdf
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
WSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering DevelopersWSO2's API Vision: Unifying Control, Empowering Developers
WSO2's API Vision: Unifying Control, Empowering Developers
 
Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..Understanding the FAA Part 107 License ..
Understanding the FAA Part 107 License ..
 
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
Navigating the Deluge_ Dubai Floods and the Resilience of Dubai International...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 

Agile Planning

  • 1. 24.11.2009 Agile Planning Artem Marchenko AgilDays.ru, December 9, 2009 © 2003–2009 Artem Marchenko and Mountain Goat Software® Artem Marchenko - background © 2003–2009 Artem Marchenko and Mountain Goat Software® 1
  • 2. 24.11.2009 What’s a good plan? • A good plan is one that supports reliable decision-making • Will go from • We’ll be done in the third quarter • We’ll be done in August • We’ll be done August 18th © 2003–2009 Artem Marchenko and Mountain Goat Software® What makes planning agile? Is more focused on planning than the plan Encourages change Results in plans that are easily changed Is spread throughout the project © 2003–2009 Artem Marchenko and Mountain Goat Software® 2
  • 3. 24.11.2009 Starting assumptions • We have a product backlog (prioritized feature list) • Items on the product backlog (user stories is my preference) have been estimated in story points or ideal days • We have a team with a known velocity • We’ll relax this assumption shortly © 2003–2009 Artem Marchenko and Mountain Goat Software® An example with velocity=14 Story A Story F Sprint 1 Sprints 3-4 5 5 Story B Story G 8 1 Story C Story H Sprint 2 3 13 Story D Story I 5 5 Story E Story J 1 8 © 2003–2009 Artem Marchenko and Mountain Goat Software® 3
  • 4. 24.11.2009 Release and sprint planning Release Plan Sprint Sprint Sprint Sprints 4–7 1 2 3 Task A 8 hours Task B 16 hours Task C 5 hours Task D 8 hours © 2003–2009 Artem Marchenko and Mountain Goat Software® Agenda • Sprint planning • Estimating velocity • Release planning • Contracting on fixed-date & fixed-scope projects © 2003–2009 Artem Marchenko and Mountain Goat Software® 4
  • 5. 24.11.2009 © 2003–2009 Artem Marchenko and Mountain Goat Software® Two approaches • Velocity-driven sprint planning • Commitment-driven sprint planning © 2003–2009 Artem Marchenko and Mountain Goat Software® 5
  • 6. 24.11.2009 Velocity-driven sprint planning • “We finished 15 story points last time, let’s plan on 15 story points this time.” • Very unreliable in what will be accomplished during an iteration • Velocity is mostly useful over the long term © 2003–2009 Artem Marchenko and Mountain Goat Software® Commitment-driven sprint planning • Discuss the highest priority item on the product backlog • Decompose it into tasks • Estimate each task • Ask ourselves, “Can we commit to this?” • If yes, see if we can add another backlog item • If not, remove this item but see if we can add another smaller one. Possibly by splitting the original story © 2003–2009 Artem Marchenko and Mountain Goat Software® 6
  • 7. 24.11.2009 It looks something like this As a user, I want ... • Code the abc class (8 hours) • Code the user interface (4) • Write test fixtures (4) 26 • Code the xyz class (6) 2 • Update performance tests (4) Team can commit, so they continue... As a user, I want ... • Prototype the UI (8 hours) • Demo UI to 3 outside users (3) • Code new UI (12) 26 • Update documentation (3) 3 © 2003–2009 Artem Marchenko and Mountain Goat Software® 1 2 time time © 2003–2009 Artem Marchenko and Mountain Goat Software® 7
  • 8. 24.11.2009 © 2003–2009 Artem Marchenko and Mountain Goat Software® How to estimate velocity 1 Use historical values 2 Don’t, until you’ve run a sprint or two 3 Forecast it © 2003–2009 Artem Marchenko and Mountain Goat Software® 8
  • 9. 24.11.2009 Forecasting velocity • Just like commitment-driven sprint planning • Estimate available hours for the sprint • Repeat until full: • Pick a story, break into tasks, estimate each task © 2003–2009 Artem Marchenko and Mountain Goat Software® An example • Estimating available hours Person Hours per Day Hours per Sprint Sergey 4-6 40-60 Kimmo 5-7 50-70 Jarmo 2-3 20-30 Total 110-160 © 2003–2009 Artem Marchenko and Mountain Goat Software® 9
  • 10. 24.11.2009 An example At 110-160 available hours per sprint, what is the team’s velocity? Code the ... 12 Code the UI 8 Do the... 8 As a frequent flyer, I Write test fixture 6 48 Document the... 8 want to... 3 31 Code middle tier 12 Test the... 8 Write tests 5 Analyze the... 4 As a user, I want to... 5 Document ... 8 As a vacation planner, I want to... 5 50 ... 50 As a frequent flyer, I 20 ... 20 want to... 2 © 2003–2009 Artem Marchenko and Mountain Goat Software® Put a range around it • You’re unlikely to have precisely forecasted the exact velocity the team will average • So, put a range around your velocity estimate: Known team, domain, +5% technology −10% +10% −25% Unknown team, +25% domain, technology −50% †Numbers based on PMI advice on progressive accuracy of estimates. © 2003–2009 Artem Marchenko and Mountain Goat Software® 10
  • 11. 24.11.2009 Expressing velocity as a range 1.10 20 200 ÷ 20 = 10 Estimated velocity = 18 .75 14 200 ÷ 14 = 15 Adjustments Total of from prior page estimates on or intuition product backlog “Right now, before we start this project, our best estimate is that it will take between 10 and 15 sprints.” © 2003–2009 Artem Marchenko and Mountain Goat Software® © 2003–2009 Artem Marchenko and Mountain Goat Software® 11
  • 12. 24.11.2009 Create a range from historical data Mean (Best 3) = 37 Mean (Last 8) = 33 Mean (Worst 3) = 28 Sprints © 2003–2009 Artem Marchenko and Mountain Goat Software® Predicting where we finish At our slowest velocity we’ll finish here (5×28) At our long-term average we’ll finish here (5×33) At our best velocity we’ll finish here (5×37) © 2003–2009 Artem Marchenko and Mountain Goat Software® 12
  • 13. 24.11.2009 Planning on contracted projects Fixed-date projects Fixed-scope projects A caveat • There are times you need to do this • So let’s look at some good techniques • Better though is try for a collaborative relationship with your customer • “You’ll have this team for each sprint, can direct them at the start of each, and stop when you have enough” © 2003–2009 Artem Marchenko and Mountain Goat Software® Fixed-date planning How much can I get by <date>? 1. Determine how many sprints you have 2. Estimate velocity as a range 3. Multiply low velocity × number of sprints • Count off that many points • These are “Will Have” items 4. Multiply high velocity × number of sprints • Count off that many more points • These are “Might Have items” © 2003–2009 Artem Marchenko and Mountain Goat Software® 13
  • 14. 24.11.2009 Fixed-date planning: an example Desired 30 June release date Will have Today’s Date 1 January Number of 6×15 6 (monthly) Might sprints have Low 6×20 15 velocity High 20 Won’t have velocity © 2003–2009 Artem Marchenko and Mountain Goat Software® Fixed-date contracting If you write a contract for just the will haves: • You won’t likely win the contract Will have • But you’ll probably make money if you do 6×15 If you write a contract that Might includes the might haves: have • You will likely win the contract 6×20 • But probably not make money on it Won’t have It’s a risk issue Where do you want to be? © 2003–2009 Artem Marchenko and Mountain Goat Software® 14
  • 15. 24.11.2009 Fixed-scope planning When will all of this be done? 1. Sum all the backlog items the customer needs 2. Estimate velocity as a range 3. Divide total story points by high velocity • This is the shortest number of sprints it could take 4. Divide total story points by low velocity • This is the “most” sprints it could take © 2003–2009 Artem Marchenko and Mountain Goat Software® Fixed-scope planning: an example Total story points desired 120 Low velocity 15 High velocity 20 120÷20= 120÷15= © 2003–2009 Artem Marchenko and Mountain Goat Software® 15
  • 16. 24.11.2009 Fixed-scope contracting If you write a contract for the short duration: • You’ll likely win the contract • But may not make any money If you write a contract for the long duration: • You probably won’t win the contract • But will make money if you It’s a risk issue Where do you want to be? © 2003–2009 Artem Marchenko and Mountain Goat Software® Ranges • Notice in both cases we had a range • For a fixed date project, use a scope range: • “By that date you’ll have all of these features and some of these.” • For a fixed-scope project, use a date range: • “It will take us between 5 and 8 sprints to deliver all of those features.” © 2003–2009 Artem Marchenko and Mountain Goat Software® 16
  • 17. 24.11.2009 Artem Marchenko contact info artem.marchenko@gmail.com http://AgileSoftwareDevelopment.com http://twitter.com/AgileArtem © 2003–2009 Artem Marchenko and Mountain Goat Software® 17