1. CSI
MURAL PROJECT ON WASTE COLLECTION AREA
Arron Goh Swee Tien | Chin Cheong Soon | Chow Su Ling | Juergen Christian Martin | Kalvin Bong | Lim Peidi | Ng Pui Yan | Rudy Irawan
5. No Items Quantity Price (RM) Total (RM)
1 White Paint (1L) 3 30.00 90.00
2 Blue Paint (1L) 2 30.00 60.00
3 Yellow Paint (1L) 2 30.00 60.00
4 Red Paint (1L) 2 30.00 60.00
5 Green Paint (1L) 2 30.00 60.00
6 Black Paint (1L) 1 30.00 30.00
7 Paint Brush 8 2.00 16.00
8 Paint Roller 4 15.00 60.00
9 Masking Tape 5 3 15.00
10 Newspaper - - -
Total (RM) 451.00
Estimated Budget to Finish
Suggest for
sponsorship
to reduce
budget
6. Expenses for Mock Up
No Items Quantity Price (RM) Total (RM)
1 White Paint (1L) 1 25.00 25.00
2 Blue Paint (1L) 1 33.00 33.00
3 Yellow Paint (1L) 1 32.00 32.00
4 Red Paint (1L) 1 28.00 28.00
5 Green Paint (1L) 2 26.00 52.00
6 Black Paint 1 29.00 29.00
7 Paint Brush 2.5” 2 3.00 6.00
8 Paint Brush 1.5” 2 1.50 3.00
9 Paint Brush 1” 2 1.00 2.00
10 Thinner 1 3.00 3.00
11 Duct Tape 1 3.00 3.00
12 Brush and Marker 1 19.10 19.10
Total (RM) 235.10
7. Transportation from Taylor’s University to Sri Tioman 1
RM0.70 per km travelled
RM0.70 x 38km = RM26.60
Toll = RM2.10
Total = RM28.70
RM28.70 x 2 = RM57.40
8. Date Task Destination Number of Cars Total (RM)
31/3 First site visit Sri Tioman I 2 114.80
7/4 Painting of pegboard Sri Tioman I 1 57.40
8/4 Interview Sri Tioman I 1 57.40
25/4 Second site visit Sri Tioman I 1 57.40
20/5 Survey task Sri Tioman I 1 57.40
3/6 Mock up presentation Sri Tioman I 1 57.40
Total 401.80
Transportation from Taylor’s University to Sri Tioman 1
10. Timeline of Execution
Collection of
ideas from
interviews
Design and
research
Refinement
and feedback
Completion by
mock up
Week 10Week 1 - 4 Week 8 - 9Week 5 - 7
11. Timeline of Mock Up
Collection of
ideas from
residents
Design and
feedback
Participation of
residents
Completion
Week 10Week 1 - 3 Week 7 - 9Week 4 - 6
20. Collection of
Idea and Design
1. Participation from residents.
2. Choose a leader to keep progress on track.
3. Collection of idea from residents.
4. Submission of design.
22. Participation of
resident
1. Contribution of idea.
2. Submission and feedback of design.
3. Selection and agreement on chosen design.
4. Delegate task to participants.
24. Finish of
Mural Art
1. Drafting of design on wall.
2. Paint work.
3. Finishing and touch up.
25. END
CSI - MURAL PROJECT ON WASTE COLLECTION AREA
Arron Goh Swee Tien | Chin Cheong Soon | Chow Su Ling | Juergen Christian Martin | Kalvin Bong | Lim Peidi | Ng Pui Yan | Rudy Irawan