CASE STUDY ON CHUNNEL TUNNEL PROJECT
Team 5
Overview:
• Designed to create spur in Economic Development
• Improve the trade relations with alternate high speed transportation
• One of the largest privately funded construction Project between two countries
• 51.5 Km long double rail tunnel.
• Project was initially estimated at 5.5 Billion dollars on completion the cost increased
to 14.9 Billion dollars
Chunnel Tunnel Group/French
Manche (BOT basis)
Transmanche Link
(TML) (Construction)
French and
British Govts.,
Scope Management
Inception
• Lack of defined
scope
• Scope defined in
Lump sum basis
• Difficulty in
Resource
planning
• Formation of
IGC
Development
• Enormous scope
• Measures to
prevent the
scope creep was
not put in place
• Project
Planning, cost
estimation,
Funding was
affected due to
scope change
Implementation
• IGC had major
control over
scope
• Frequent
change in scope
• Door and A/c
System
contributed to
major scope
changes
Closeout
• Even when the
tunnel was
deemed to
complete, there
were
discrepancies
over scope of
some works.
Rating :
2
2
2 22
Time Management
Inception
• Hasty Bidding
and concept
development
• Not enough time
provided to
complete
detailed design
studies
Development
• Change in
requirement by
IGC caused delay
• Approval of
drawings
mandated from
both
governments
• Very good
tracking with
hefty status
report
Implementation
• Faster Tunneling
• Rail and car
systems were
delivered late
• Alteration of
passenger door
sizes caused
delay for 9
months.
Closeout
• Cascading effects
of previous
phases
• 19 month delay
• Project
management
team could not
be held
responsible
Rating :
3
3
3 2
2
Cost Management
Inception
• Estimated cost
of USD 5.5 bn.
• Initial Cost
Estimates were
not detailed
out.
• Financing
arranged via
equity and
capital market
Development
• USD 2.25 Bn
claim against
Eutotunnel by
contractor was
not anticipated
• Use of
sophesticted
equipment not
anticipated
Implementation
• Unnecessary
use of costly
technologies in
some cases like
grouting.
• Wrong
selection of
TBM.
Closeout
• Efforts were
driven towards
settlemnt of
claims rather
than analysing
on sources of
cost overrun.
Rating :
2
1
2
1
2
Quality Management
Inception
• Difference in
standards ->
Higher
standard
• Latest laser
and computer
technology
proposed to
bore the
tunnel.
Development
• Good PAC was
framed.
• No margin for
errors
• Formation of
IGC
Implementation
• Stringent
requirements
from IGC
• Very high
accuracy
maintained.
Closeout
• Quality
parameters
achieved
were above
industry
average.
Rating :
5
4
5
5
5
Human Resources Management
Inception
• Team work
envisaged
• Good structure
with proper
responsibilities
formed.
Development
• Every British
team member
had French
counter part
Implementation
• Managed
15,000 workers
in good
manner
• Workers from
different
cultures were
engaged with
high level of
efficiency
Closeout
• Most of the
persons were
demotivated
due to non
settlement of
claims.
• Win-win
situation was
lost
Rating :
3
3
3 2
3
Communications Management
Inception
• Difference in
languages of
two countries
Development
• Limited
communication
between two
teams since
both of them
were trying to
meet in
middle.
• This lead to
difference of
opinion at later
stages
Implementation
• Delay in
communication
regarding
specification
change.
Closeout
• Negotiations
not proper at
Closeout since
bankers did not
settle for
claims.
Rating :
2
3
3 1
2
Risk Management
Inception
• Technical risk only
considered
• Process and
approval risk were
not envisaged
• Both governments
denied to provide
financial
guarantee.
• Social cost benefit
analysis not done.
Development
• Over management
of risk – advanced
techniques
considered
• Contingencies and
margins were
barest mimimum.
• Contractors forced
to consider best
situation.
• Risk assessment
plan was not
made.
Implementation
• Fast tracking of
design and
construction
processes done
without risk
analysis.
• New unproven
technology
increased risk
• Banks were
involved for
minimising the
risk, however IGC
was controlling.
Closeout
• Courts ruled in
favour of
contractor.
Rating :
2
2
2
2
2
Procurement Management
Inception
• Rigorous time
constraints
caused hasty
procurement
plan/contracts.
• Procurement of
rolling stock and
associated major
equipment
finalised on cost
plus percentage
fee basis
Development
• Procurement
delayed since
scope/
specification was
changing.
Implementation
• Fixed price
contracts with
several
contractors
• Differences in
goals since many
contractors were
having equity.
Closeout
• Cascading effect
of
implementation
created 17
months delay.
• Non settlement
of extra claims
Rating :
2
2
2
2
3
Integration Management
Inception
• Various
international
agencies took part
for
conceptualisation.
• Mistrust among
agencies since
both govts didn’t
provide guarantee
but placed
requirements.
Development
• 46 contractors
were deployed for
design
• 7 Lakh
shareholders, 220
Lending banks
were involved for
financing.
Implementation
• Huge resources,
huge scope of
work were
managed in best
of industry
standards.
• Logistical and
communication
challenges.
Close out
• Teams not
integrated due to
poor
communication.
• Each party tried to
focus on their own
interests.
• International
chamber of
commerce
engaged for
dispute resolution
Rating :
3
2
3 2
3
Project
Management Area
Inception
Phase
Developme
nt Phase
Implementa
tion Phase
Closeout
Phase
Average
Scope Mgt 2 2 2 2 2
Time Mgt 3 3 2 2 3
Cost Mgt 1 2 2 1 2
Quality Mgt 4 5 5 5 5
HRM 3 3 3 2 3
Communications
Mgt
3 3 2 1 2
Risk Mgt 2 2 2 2 2
Procurement Mgt 2 2 3 2 2
Integration Mgt 2 3 3 2 3
Rating Scale - Summary
Rating Scale : 5-Excellent, 4- Very Good, 3- Good, 2- Poor, 1- Very Poor
Key Dates
Year Key Developments
1802 Albert Mathieu put forward a cross channel proposal
1875 Channel Tunnel Company Ltd began preliminary trials
1882
Experimental work on both sides of the Channel started but soon idea was
abandoned citing national defense security.
1975 A UK–France government backed scheme that started in 1974 was cancelled
1984
British & French govt. agreed to common safety, environmental & security
concern, prior opening up the project to bidder
1985 British & French govt. asked for proposals.
1986
Project awarded to Eurotunnel on BOOT basis with 55 year concession
period with initial cost of US$ 5.5 billion.
June 1988 In France, first tunneling was started
December
1988
Tunneling operation was started in UK
May 1994
Tunnel was formally inaugurated & started functioning. Project was
completed with cost & time over run.
Major Area of Strength Managing this Project
QUALITY
MANAGEMENT
• Quality management was implemented successfully.
• Technical expertise .
TEAM WORK
• Excellent team work between two groups.
• Construction of tunnel completed 3 months ahead of schedule.
• Project office support was excellent.
SAFETY
MANAGEMENT
• Accidents below industry average.
• 15000 workmen, numerous engineers, handled precisely.
Major Opportunities for improvement from Management P.O.V
SCOPE
MANAGEMENT
• Detailed Functional requirement & Technical specification
• Consideration of Scope contingency
CONTRACT
MANAGEMENT
• Applicability of Single Contract to both group.
• Coverage of risk exposures
COMMUNICATION
MANAGEMENT
• Communication protocol preparation
• Protocol for escalating unresolved / pending issue
• Tracking & monitoring
Major Opportunities for improvement from Management P.O.V (cont.)
RISK
MANAGEMENT
• Project process & approval risk was overlooked.
• Not prepared to handle the degree of IGC supervision & change
management controls.
• Contingencies for known & unknown risk & a strategy for handling
change management missing.
COST
MANAGEMENT
• Use a standardized change-control management to eliminate cost
considerations issues imposed by out-of-control-change management
control processes.
• Specification and validation of functional and technical requirements at
front.
• Replacement of material, equipment with alternate option of same
specification.
STAKEHOLDER
MANAGEMENT
• Project Stakeholder management plan was not prepared in detailed and
also not followed throughout project life cycle. By implementing this,
variance in cost, schedule and extra claims could have been minimized.
Major Project Management Lessons learned
Review past engineering studies & take
them in consideration
Technical as well functional aspects of
project management should be given
equal importance
Detailed risk analysis required in
inception stage & needs to be tracked,
monitored during PLC of project
Major Project Management Lessons learned
Maintaining communication throughout the
life of project yields better operational
project results.
In large international construction projects of
the involving countries, Govt. support &
communication channels should be roped in.
Whole hearted effort to be made right from
the inception of project in order to avoid
adverse situation at the end
Conclusion:
• Time Over run – 19 months delay
• Cost Over run – USD 9.4 Bn
• Trail of unhappy investors and stakeholders
• Key learnings
• Modern Engineering Marvel
• Undoubted Public benefit
Summary chunnel tunnel project management

More Related Content

What's hot

The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementMilind_jagtap_
 
Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost managementSagar Rana
 
Project Management Report
Project Management ReportProject Management Report
Project Management ReportSANKET SENAPATI
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,Indiaoyepuneeta
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016teohwooisin
 
Bechtel project planning example
Bechtel project planning exampleBechtel project planning example
Bechtel project planning exampleasfandiyar
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planningJeanette C. Patindol
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementNarendra Bhandava
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)Anand Subramaniam
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideasAhmad Hamid
 
Paseo caribe case study analysis
Paseo caribe case study analysis Paseo caribe case study analysis
Paseo caribe case study analysis Yamna Rashid
 
Project, Program and Portfolio Comparison
Project, Program and Portfolio ComparisonProject, Program and Portfolio Comparison
Project, Program and Portfolio ComparisonRicardo Viana Vargas
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea linkAnkita Pal
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1Ho Yen Liang
 

What's hot (20)

The Chunnel Project - Quality Management
The Chunnel Project - Quality ManagementThe Chunnel Project - Quality Management
The Chunnel Project - Quality Management
 
Channel tunnel
Channel tunnelChannel tunnel
Channel tunnel
 
Chunnel project project cost management
Chunnel  project project cost managementChunnel  project project cost management
Chunnel project project cost management
 
An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
 
Bandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,IndiaBandra worli sea link,Mumbai,Maharashtra,India
Bandra worli sea link,Mumbai,Maharashtra,India
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 
Bechtel project planning example
Bechtel project planning exampleBechtel project planning example
Bechtel project planning example
 
5. project activity and risk planning
5. project activity and risk planning5. project activity and risk planning
5. project activity and risk planning
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Project Management Office (PMO)
Project Management Office (PMO)Project Management Office (PMO)
Project Management Office (PMO)
 
PMP selected topics and ideas
PMP selected topics and ideasPMP selected topics and ideas
PMP selected topics and ideas
 
Paseo caribe case study analysis
Paseo caribe case study analysis Paseo caribe case study analysis
Paseo caribe case study analysis
 
Epc contractor
Epc contractorEpc contractor
Epc contractor
 
Project, Program and Portfolio Comparison
Project, Program and Portfolio ComparisonProject, Program and Portfolio Comparison
Project, Program and Portfolio Comparison
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Bandra - Worli sea link
Bandra - Worli sea linkBandra - Worli sea link
Bandra - Worli sea link
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 

Viewers also liked

Channel Tunnel
Channel TunnelChannel Tunnel
Channel TunnelTim Howell
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...peter747
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine mohammadsalikali
 
ulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndromeulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndromeHome~^^
 
E1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk AnalysisE1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk AnalysisS Giancola
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/FailurePeter Salmon
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineeringAdil Shaikh
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project managementStriking Group Pty Ltd
 
Opera sydney case study analysis
Opera sydney case study analysisOpera sydney case study analysis
Opera sydney case study analysisKhaled Eid
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentLengkengs
 
Seven modern wonders of the world
Seven modern wonders of the worldSeven modern wonders of the world
Seven modern wonders of the worldvvelasco
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnelspartha sharma
 

Viewers also liked (20)

Channel Tunnel
Channel TunnelChannel Tunnel
Channel Tunnel
 
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...Project management final report ENG3004 Griffith University Guri Dam & Chunne...
Project management final report ENG3004 Griffith University Guri Dam & Chunne...
 
Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine Tunnel making methods and tunnel boring machine
Tunnel making methods and tunnel boring machine
 
Channel tunnel
Channel  tunnelChannel  tunnel
Channel tunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
Eurotunnel
EurotunnelEurotunnel
Eurotunnel
 
tunneling & its effects
tunneling & its effectstunneling & its effects
tunneling & its effects
 
ulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndromeulnar Entrapment Neuropathy and double crush syndrome
ulnar Entrapment Neuropathy and double crush syndrome
 
E1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk AnalysisE1 - Panama Canal Risk Analysis
E1 - Panama Canal Risk Analysis
 
Embedding quality assurance within procurement
Embedding quality assurance within procurementEmbedding quality assurance within procurement
Embedding quality assurance within procurement
 
CJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint PresentationCJM Construction Consulting PowerPoint Presentation
CJM Construction Consulting PowerPoint Presentation
 
Project Success/Failure
Project Success/FailureProject Success/Failure
Project Success/Failure
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Study of tunnel engineering
Study of tunnel engineeringStudy of tunnel engineering
Study of tunnel engineering
 
10 things to improve project management
10 things to improve project management10 things to improve project management
10 things to improve project management
 
Tunnelling
TunnellingTunnelling
Tunnelling
 
Opera sydney case study analysis
Opera sydney case study analysisOpera sydney case study analysis
Opera sydney case study analysis
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
 
Seven modern wonders of the world
Seven modern wonders of the worldSeven modern wonders of the world
Seven modern wonders of the world
 
Excavation of Tunnels
Excavation of TunnelsExcavation of Tunnels
Excavation of Tunnels
 

Similar to Summary chunnel tunnel project management

PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTNiruban Projoth
 
How to setup and lead a successfully PMO
How to setup and lead a successfully PMOHow to setup and lead a successfully PMO
How to setup and lead a successfully PMOPMOfficers PMOAcademy
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdfAmarDeo7
 
Course Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsCourse Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsFragoso Josue Muhae
 
Project management case study.pptx
Project management case study.pptxProject management case study.pptx
Project management case study.pptxDrRRajalakshmi
 
Project management
Project managementProject management
Project managementtwilight89
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
HISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptxHISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptxAaleenKttk
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project managementprakashnachnani
 

Similar to Summary chunnel tunnel project management (20)

PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Warrington Western Link, Robert Holloway
Warrington Western Link, Robert HollowayWarrington Western Link, Robert Holloway
Warrington Western Link, Robert Holloway
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
BASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENTBASICS OF PROJECT MANAGEMENT
BASICS OF PROJECT MANAGEMENT
 
57086 01 introduction
57086 01 introduction57086 01 introduction
57086 01 introduction
 
slides
slidesslides
slides
 
How to setup and lead a successfully PMO
How to setup and lead a successfully PMOHow to setup and lead a successfully PMO
How to setup and lead a successfully PMO
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Managing Project Transitions
Managing Project TransitionsManaging Project Transitions
Managing Project Transitions
 
projectmanagement-123765482.pdf
projectmanagement-123765482.pdfprojectmanagement-123765482.pdf
projectmanagement-123765482.pdf
 
Course Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering ProjectsCourse Assignment: Financing and Initiating Major Engineering Projects
Course Assignment: Financing and Initiating Major Engineering Projects
 
London 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingencyLondon 2012 Olympics, Managing and controlling contingency
London 2012 Olympics, Managing and controlling contingency
 
Stephanus Roux_Senior Project Manager
Stephanus Roux_Senior Project ManagerStephanus Roux_Senior Project Manager
Stephanus Roux_Senior Project Manager
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
Project management case study.pptx
Project management case study.pptxProject management case study.pptx
Project management case study.pptx
 
Project management
Project managementProject management
Project management
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
HISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptxHISTORY OF PROJECT MANAGEMENT & (1).pptx
HISTORY OF PROJECT MANAGEMENT & (1).pptx
 
Introduction to international project management
Introduction to international project managementIntroduction to international project management
Introduction to international project management
 

Recently uploaded

Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysistanmayarora45
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Ram V Chary
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhiguptaswati8536
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 

Recently uploaded (15)

Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 

Summary chunnel tunnel project management

  • 1. CASE STUDY ON CHUNNEL TUNNEL PROJECT Team 5
  • 2. Overview: • Designed to create spur in Economic Development • Improve the trade relations with alternate high speed transportation • One of the largest privately funded construction Project between two countries • 51.5 Km long double rail tunnel. • Project was initially estimated at 5.5 Billion dollars on completion the cost increased to 14.9 Billion dollars Chunnel Tunnel Group/French Manche (BOT basis) Transmanche Link (TML) (Construction) French and British Govts.,
  • 3. Scope Management Inception • Lack of defined scope • Scope defined in Lump sum basis • Difficulty in Resource planning • Formation of IGC Development • Enormous scope • Measures to prevent the scope creep was not put in place • Project Planning, cost estimation, Funding was affected due to scope change Implementation • IGC had major control over scope • Frequent change in scope • Door and A/c System contributed to major scope changes Closeout • Even when the tunnel was deemed to complete, there were discrepancies over scope of some works. Rating : 2 2 2 22
  • 4. Time Management Inception • Hasty Bidding and concept development • Not enough time provided to complete detailed design studies Development • Change in requirement by IGC caused delay • Approval of drawings mandated from both governments • Very good tracking with hefty status report Implementation • Faster Tunneling • Rail and car systems were delivered late • Alteration of passenger door sizes caused delay for 9 months. Closeout • Cascading effects of previous phases • 19 month delay • Project management team could not be held responsible Rating : 3 3 3 2 2
  • 5. Cost Management Inception • Estimated cost of USD 5.5 bn. • Initial Cost Estimates were not detailed out. • Financing arranged via equity and capital market Development • USD 2.25 Bn claim against Eutotunnel by contractor was not anticipated • Use of sophesticted equipment not anticipated Implementation • Unnecessary use of costly technologies in some cases like grouting. • Wrong selection of TBM. Closeout • Efforts were driven towards settlemnt of claims rather than analysing on sources of cost overrun. Rating : 2 1 2 1 2
  • 6. Quality Management Inception • Difference in standards -> Higher standard • Latest laser and computer technology proposed to bore the tunnel. Development • Good PAC was framed. • No margin for errors • Formation of IGC Implementation • Stringent requirements from IGC • Very high accuracy maintained. Closeout • Quality parameters achieved were above industry average. Rating : 5 4 5 5 5
  • 7. Human Resources Management Inception • Team work envisaged • Good structure with proper responsibilities formed. Development • Every British team member had French counter part Implementation • Managed 15,000 workers in good manner • Workers from different cultures were engaged with high level of efficiency Closeout • Most of the persons were demotivated due to non settlement of claims. • Win-win situation was lost Rating : 3 3 3 2 3
  • 8. Communications Management Inception • Difference in languages of two countries Development • Limited communication between two teams since both of them were trying to meet in middle. • This lead to difference of opinion at later stages Implementation • Delay in communication regarding specification change. Closeout • Negotiations not proper at Closeout since bankers did not settle for claims. Rating : 2 3 3 1 2
  • 9. Risk Management Inception • Technical risk only considered • Process and approval risk were not envisaged • Both governments denied to provide financial guarantee. • Social cost benefit analysis not done. Development • Over management of risk – advanced techniques considered • Contingencies and margins were barest mimimum. • Contractors forced to consider best situation. • Risk assessment plan was not made. Implementation • Fast tracking of design and construction processes done without risk analysis. • New unproven technology increased risk • Banks were involved for minimising the risk, however IGC was controlling. Closeout • Courts ruled in favour of contractor. Rating : 2 2 2 2 2
  • 10. Procurement Management Inception • Rigorous time constraints caused hasty procurement plan/contracts. • Procurement of rolling stock and associated major equipment finalised on cost plus percentage fee basis Development • Procurement delayed since scope/ specification was changing. Implementation • Fixed price contracts with several contractors • Differences in goals since many contractors were having equity. Closeout • Cascading effect of implementation created 17 months delay. • Non settlement of extra claims Rating : 2 2 2 2 3
  • 11. Integration Management Inception • Various international agencies took part for conceptualisation. • Mistrust among agencies since both govts didn’t provide guarantee but placed requirements. Development • 46 contractors were deployed for design • 7 Lakh shareholders, 220 Lending banks were involved for financing. Implementation • Huge resources, huge scope of work were managed in best of industry standards. • Logistical and communication challenges. Close out • Teams not integrated due to poor communication. • Each party tried to focus on their own interests. • International chamber of commerce engaged for dispute resolution Rating : 3 2 3 2 3
  • 12. Project Management Area Inception Phase Developme nt Phase Implementa tion Phase Closeout Phase Average Scope Mgt 2 2 2 2 2 Time Mgt 3 3 2 2 3 Cost Mgt 1 2 2 1 2 Quality Mgt 4 5 5 5 5 HRM 3 3 3 2 3 Communications Mgt 3 3 2 1 2 Risk Mgt 2 2 2 2 2 Procurement Mgt 2 2 3 2 2 Integration Mgt 2 3 3 2 3 Rating Scale - Summary Rating Scale : 5-Excellent, 4- Very Good, 3- Good, 2- Poor, 1- Very Poor
  • 13. Key Dates Year Key Developments 1802 Albert Mathieu put forward a cross channel proposal 1875 Channel Tunnel Company Ltd began preliminary trials 1882 Experimental work on both sides of the Channel started but soon idea was abandoned citing national defense security. 1975 A UK–France government backed scheme that started in 1974 was cancelled 1984 British & French govt. agreed to common safety, environmental & security concern, prior opening up the project to bidder 1985 British & French govt. asked for proposals. 1986 Project awarded to Eurotunnel on BOOT basis with 55 year concession period with initial cost of US$ 5.5 billion. June 1988 In France, first tunneling was started December 1988 Tunneling operation was started in UK May 1994 Tunnel was formally inaugurated & started functioning. Project was completed with cost & time over run.
  • 14. Major Area of Strength Managing this Project QUALITY MANAGEMENT • Quality management was implemented successfully. • Technical expertise . TEAM WORK • Excellent team work between two groups. • Construction of tunnel completed 3 months ahead of schedule. • Project office support was excellent. SAFETY MANAGEMENT • Accidents below industry average. • 15000 workmen, numerous engineers, handled precisely.
  • 15. Major Opportunities for improvement from Management P.O.V SCOPE MANAGEMENT • Detailed Functional requirement & Technical specification • Consideration of Scope contingency CONTRACT MANAGEMENT • Applicability of Single Contract to both group. • Coverage of risk exposures COMMUNICATION MANAGEMENT • Communication protocol preparation • Protocol for escalating unresolved / pending issue • Tracking & monitoring
  • 16. Major Opportunities for improvement from Management P.O.V (cont.) RISK MANAGEMENT • Project process & approval risk was overlooked. • Not prepared to handle the degree of IGC supervision & change management controls. • Contingencies for known & unknown risk & a strategy for handling change management missing. COST MANAGEMENT • Use a standardized change-control management to eliminate cost considerations issues imposed by out-of-control-change management control processes. • Specification and validation of functional and technical requirements at front. • Replacement of material, equipment with alternate option of same specification. STAKEHOLDER MANAGEMENT • Project Stakeholder management plan was not prepared in detailed and also not followed throughout project life cycle. By implementing this, variance in cost, schedule and extra claims could have been minimized.
  • 17. Major Project Management Lessons learned Review past engineering studies & take them in consideration Technical as well functional aspects of project management should be given equal importance Detailed risk analysis required in inception stage & needs to be tracked, monitored during PLC of project
  • 18. Major Project Management Lessons learned Maintaining communication throughout the life of project yields better operational project results. In large international construction projects of the involving countries, Govt. support & communication channels should be roped in. Whole hearted effort to be made right from the inception of project in order to avoid adverse situation at the end
  • 19. Conclusion: • Time Over run – 19 months delay • Cost Over run – USD 9.4 Bn • Trail of unhappy investors and stakeholders • Key learnings • Modern Engineering Marvel • Undoubted Public benefit