Nordic PPP Forum 2008
Stockholm, 28th - 29th October 2008
Presentation by:
Ir. P.J.A. Peekel, Project Manager
2
PPP Procurement Process
Public Infrastructure Planning Process
DBFM Infrastructure Projects
3
PPP Procurement Process
• Introduced for public sector contracts in EU Directive
2004/18/EC;
• Entered into force in April 2004; EU member states were required
to formally adopt the Directive before 1st January 2006;
• In the Netherlands first applied, prior to formal adoption, to
Second Coentunnel Project (start September 2005);
• Complements the Open and Restricted Procedures (which
require detailed specifications and award criteria to be drawn up
in advance);
• Intended to be a preferred alternative over the Negotiated
Procedure;
Introduction Competitive Dialogue Procedure
4
PPP Procurement Process
• Contracting authorities are permitted to use this procedure:
• Where the nature of the works or services that they are procuring or
the risks related to them are such that prior overall pricing is not
feasible; and/or
• In case of a services contract (e.g. most PPP contracts) where the
specifications cannot be drawn up with sufficient precision to allow
pricing prior to the request for tenders; and/or
• Where there is a need for the contracting authority to discuss all
aspects of the proposed contract with candidates;
• Negotiated Procedure remains for truly exceptional
circumstances;
Application of Competitive Dialogue
5
PPP Procurement Process
• Typical steps in the process:
1. Prequalification Phase (economic/financial standing, technical
and/or professional ability);
2. Plan of Approach Phase (short-listing to 3 bidders);
3. Consultation Phase (discuss contract, requirements, etc);
4. Dialogue Phase (develop solutions; prepare Dialogue Products
e.g. Management Plan, Document Management System,
Performance Monitoring System, project planning, risk allocation,
etc; Resolve commercial and prizing issues;
5. Freeze documents and call for Final Tenders; Receive bids;
6. Clarifications, followed by appointing Preferred Bidder;
Structure of Competitive Dialogue
6
PPP Procurement Process
• After submitting final tenders,
• Authority may only request clarification and fine-tuning or confirm
commitments contained in the tender;
• No negotiation on price or other substantial changes in scope
can be agreed after appointing Preferred Bidder;
• Preferred Bidder must the candidate with Most Economically
Advantageous Tender (MEAT);
• MEAT is determined on the basis of the prior award criteria laid
down in the Tender Guidelines;
• Quality requirements are translated to MEAT criteria;
• Tenders allow focus on quality and price;
Key characteristics of Competitive Dialogue
7
PPP Procurement Process
• Quality worked into price: (1) List Risks and (2) Wishes
• List Risks:
• Predefined key risks of critical importance to Project;
• Risk allocation choice determines for each risk the bid price mark-
ups and the bid ceiling price adjustments:
• Wishes:
• Solutions the Client desires but not necessarily requires;
• Each wish has a bid mark-up value;
Competition on highest quality/price ratio
Ceiling unchangedPart price mark-up onlyShare risk with Client
Ceiling decreasedFull price mark-upLeave full risk for Client
Ceiling increasedNo price mark-upTake full risk
Ceiling unchangedPart price mark-up onlyShare risk with Client
Ceiling decreasedFull price mark-upLeave full risk for Client
Ceiling increasedNo price mark-upTake full risk
Mark-up pro rataWish partially fulfilled
Full price mark-upWish not fulfilled
No price mark-upWish fully fulfilled
Mark-up pro rataWish partially fulfilled
Full price mark-upWish not fulfilled
No price mark-upWish fully fulfilled
8
PPP Procurement Process
• MEAT = Lowest [Bid Price + Mark-upRisks + Mark-upWishes]
• Strategy is typically: To create distinctive / unique solutions that:
-Minimize consequences of risks and enables you to take the risks;
-Maximize the fulfillment of wishes at minimum cost;
• This typically requires widening the boundaries of the
specifications during the Consultation Phase;
Consortium tender strategies under Competitive Dialogue
Plan of Approach
Phase
Consultation Phase Dialogue Phase
ProcurementProcess
9
PPP Procurement Process
• A tender procedure which can be used in case of complex
projects where solutions and specifications and estimated price
cannot be defined up front;
• A procedure which therefore allows development of
requirements and solutions during the procurement process in
a dialogue with the candidates, while maintaining competition;
• Consortium tender strategies tend to focus on the creation of
alternatives that add most value for the best possible price.
This often calls for flexibility in specifications and relaxation of
tightly defined solution constraints.
Competitive Dialogue summarized
10
Infrastructure Planning Process
• Well structured and highly regulated process to determine
optimal routing of line infrastructure (railway, road);
• Takes due account of:
• Desired functional requirements; What problem to be solved;
• Advantages and disadvantages of all possible solutions;
• Technical, economical and environmental impact factors;
• Requirements and wishes of project and public stakeholders;
• Objective decision making process which includes public
consultation (interaction with public stakeholders);
Characteristics of public Infrastructure Planning Process
11
Infrastructure Planning Process
• Structure is typically similar for railway and road projects;
• Significant similarity of process structures between different EU
countries;
• Time frames:
• Rail project Sweden (e.g. Citybanan Stockholm): 4-5 years
• Road project in The Netherlands (typical): 5-6 years
• Longer periods for complex projects are not uncommon;
Structure and timeframe
12
Infrastructure Planning Process
Similarity Swedish and Dutch Planning Processes
Final Route Decree
Järnvägsplanen
Plan Study Phase part 2 (Draft Route Decree phase);
Work out in detail the preferred route; Update
EIA; Establish land acquisitions; Establish costs and
planning;
Tillåtlighetsprövning
"Standpunt"; Decision by Minister of Transport for
preferred route;
Järnvägsutredning +
MiljöKonsekvens
Beskrivning (MKB)
Plan Study Phase part 1 ("Trajectnota/MER Fase");
Study selected route options and carry out
Environmental Impact Assessments (EIA);
Förstudien
Exploration Phase ("Verkenningsfase"); Define
problems and explore feasible options that could
solve them;
Planeringsprocess
(Banverket) Sweden
Route Decree Process The Netherlands
√ Såmrad
√ Såmrad
√ Såmrad
√ Inspraak
√ Inspraak
√ Inspraak
13
Infrastructure Planning Process
• Starting with many potential alternative options;
• Ending up with a well defined single alternative;
• Very limited (if any) degrees of freedom remain for a design
process in the tender of the project or in project execution;
• Selected detailed solution is often also described in
agreements with public authorities;
• Details by which solution is fixed are often more stringent than
the law calls for;
Converging to a single solution
Feasibility Alternatives /
EIA
Detail selected
route / EIA
Route Decree
PlanningProcess
14
Infrastructure Planning Process
• A well structured and highly regulated process, bound by
formalized decision making and significant public stakeholder
involvement;
• Aims to develop a single best alternative out of many options
that may be available at the start of the process;
• Tends to rigorously tie down that ultimate single solution in a
detailed Route Decree and by means of one or more
stakeholder agreements;
Characteristics summarized
15
Combining Processes
• Sequential approach of processes;
• Fully interwoven processes;
• Semi-interwoven processes;
Infrastructure Planning and Procurement
16
The sequential approach
• Procurement Process begins after Planning Process has been
completed:
• Final design (selected and well defined alternative);
• Route Decree (formal governmental decision);
• Public stakeholder agreements signed;
• Tends to limit variety in solutions and in risk allocations offered;
• Results in competition on price only rather than quality + price;
Planning Process à Procurement Process
Feasibility Alternatives /
EIA
Detail selected route /
EIA
Route
Decree
Plan of
Approach Phase
Consultation
Phase
Dialogue Phase
Possibilities offered in Consultation Phase
are often severely limited by prescribed
details in Route Decree and by constraining
clauses in Stakeholder Agreements.
Solutions (possibly with
considerable added value to
the Client) cannot be
accommodated
Sub-Optimum
Solution awarded
PlanningProcess
ProcurementProcess
17
Fully interwoven processes
• Tender starts after Feasibility Stage (i.e. after Förstudien);
• Tender solutions are injected in Planning Process;
• Preferred Bidder solution = Route Decree solution;
• Dutch infra project where being applied: A2 Maastricht project;
Start tender very early in Planning Process
Feasibility Alternatives
/ EIA
Work out in detail
selected route / EIA
Route Decree
Plan of
Approach
Consultation
Phase
Dialogue
Phase
MEAT solution awarded
(conditionally to Route Decree)
A
B
C
A’
B’
C’
A”’
A’
B’
C’
D (public)
Tender
Solutions
Preferred Bidder Solution (MEAT) > Route Decree Solution
A’’
B’’
C’’
PlanningProcessProcurementProcess
18
Semi-interwoven processes
• Tender starts after “Standpunt” (i.e Tillåtlighetsprövning);
• Tenders are variations to publicly preferred solution;
• Preferred Bidder solution = Route Decree solution;
• Dutch infra project where applied: Second Coentunnel project;
Start tender about halfway in Planning Process
Feasibility Alternatives /
EIA
Work out in detail
selected route / EIA
Route Decree
Plan of
Approach
Consultation
Phase
Dialogue
Phase
BAFO
A’
B’
C’
A’’
B’’
C’’
A
B
C
PlanningProcessProcurementProcess
19
Interweaving of processes
Key to success
• Concurrent timing of decisions in both processes;
• Integrity of each process individually must be maintained;
• Exchange of information between processes must take account of
public transparency and procurement confidentiality requirements;
Example of major
“decision knot”:
• Decision to
conditionally award
“Voorlopige Gunning”
AND (at the same time)
• “Standpunt”
Tillåtlighetsprövning
20
Transaction time and costs
• Competitive Dialogues tend to be long and can be costly;
• When interweaving, tender process increases in duration, but
intensity of effort varies in time;
• When interweaving, the necessity to adhere to a tendering
timescale will reduce public decision making delays;
• When fully interwoven, design cost compensation given by
tendering authority should consider that some of the public
activity (i.e. working out alternatives) is done by the bidders;
• Semi-Interweaving doesn’t automatically mean that more
attractive solutions are possible, because sometimes public
agreements turn out to have completely restrained all degrees of
freedom;
Competitive Dialogue and Interweaving
21
Dutch experience
• Total value: EUR 630 mln;
• Contract type: DBfM (small F!);
• Infrastructure + urban area development;
• Tender started Q4 2006; 5>3 bidders;
• 3 bidder plans > public hearings;
• Planned Contract Close: August 2009;
Fully interwoven: A2 Maastricht
22
Dutch experience
• Total value: EUR 600 mln;
• Contract type: DBFMO;
• 6 + 24 yrs concession;
• Maintenance from Contract Close;
• Infrastructure (tunnel + roads);
• Very innovative bidder solutions;
• Costly procedure: both Base Case
and Alternatives were progressed;
• Innovative solutions could ultimately
not be accommodated (too many
constraints build into Public
Agreements);
Semi-interwoven: 2nd Coentunnel
23
Interweaving described
• Jointly developed between Ministry of Transport and
representatives from the Private Sector;
• General principles; Do’s and Don’t; Advantages and
disadvantages of various interweaving models;
• It’s a Guideline > project specific fine-tuning is possible;
Manual available (in Dutch)
Translation:
“Guideline concerning the
interweaving of Route
Decree / EIA procedure and
tendering procedure for
infrastructure projects”
24
Lessons for Nordic Region
• Adopt Competitive Dialogue Procedure for DBFM tenders;
• When Route Decree Planning Procedure is interwoven with DBFM
tender procedure, the possibility exists that due to competition very
innovative solutions are developed with significant added value to
Client and the public at large;
• Do not restrict innovative alternatives by converging in the Route
Decree Planning Procedure to a single and narrowly defined
preferred alternative;
• Do not constraint (more than absolutely necessary) the degrees of
freedom for alternatives in Public Stakeholder Agreements;
• When still in Route Decree Planning Procedure, the Client and the
Preferred Bidder should work in Partnership (Alliance); And
continue working like that throughout project execution!!
For PPP infrastructure projects (roads, rail, incl. light rail)
25
Interweaving
of
PPP Procurement
and
Public Infrastructure Planning
Processes
For more information:
Paul J.A. Peekel
+31 30 240 7896
paul.peekel@strukton.com
DBFM Infrastructure Projects
Nordic PPP Forum 2008

More Related Content

What's hot

What's hot (20)

Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Construction Bidding Step-by-Step
Construction Bidding Step-by-StepConstruction Bidding Step-by-Step
Construction Bidding Step-by-Step
 
Tendering
TenderingTendering
Tendering
 
Tpt's tendering process at a glance
Tpt's tendering process at a glanceTpt's tendering process at a glance
Tpt's tendering process at a glance
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Successful Tender
Successful TenderSuccessful Tender
Successful Tender
 
Bid and Tender Process Training Presentation
Bid and Tender Process Training PresentationBid and Tender Process Training Presentation
Bid and Tender Process Training Presentation
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
PM_Project LifeCycle
PM_Project LifeCyclePM_Project LifeCycle
PM_Project LifeCycle
 
Types of tenders & stages for successful tendering
Types of tenders & stages for successful tenderingTypes of tenders & stages for successful tendering
Types of tenders & stages for successful tendering
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Tender processing
Tender processingTender processing
Tender processing
 
EVALUATION OF BID & AWARDING OF WORK
EVALUATION OF BID & AWARDING OF WORKEVALUATION OF BID & AWARDING OF WORK
EVALUATION OF BID & AWARDING OF WORK
 
3 tender stage
3 tender stage3 tender stage
3 tender stage
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
 
Tender
TenderTender
Tender
 

Similar to 14102008 - Nordic Ppp Forum Presentation Pja Peekel Final

Suggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation ConstructionSuggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation Constructionartba
 
Toronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project PresentationToronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project PresentationAhmed Mahmoud
 
Practical Issues of Public Tenders- A Consultant's Perspective
Practical Issues of Public Tenders- A Consultant's PerspectivePractical Issues of Public Tenders- A Consultant's Perspective
Practical Issues of Public Tenders- A Consultant's PerspectiveS.S.Afemikhe Consulting
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptxDoctorOkelloBen
 
Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavarubanthevaraja pavaruban
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectivessombat nirund
 
Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010Elaine Creamer
 
introduction to public private partnership
introduction to public private partnershipintroduction to public private partnership
introduction to public private partnershipHayJirenyaa
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
 
Construction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptxConstruction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptxIsmailFakhro1
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmDNVGLEnergy
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slidesDoreen Yeo
 
Archiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_finalArchiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_finalArchiver
 
Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx2ke21cv405
 

Similar to 14102008 - Nordic Ppp Forum Presentation Pja Peekel Final (20)

Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
Presentation, SIGMA workshop on tendering of PPP projects and contract signat...
 
Suggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation ConstructionSuggested Best Practices for Design-Build in Transportation Construction
Suggested Best Practices for Design-Build in Transportation Construction
 
Toronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project PresentationToronto Pearson Airport - Terminal Expansion Project Presentation
Toronto Pearson Airport - Terminal Expansion Project Presentation
 
Practical Issues of Public Tenders- A Consultant's Perspective
Practical Issues of Public Tenders- A Consultant's PerspectivePractical Issues of Public Tenders- A Consultant's Perspective
Practical Issues of Public Tenders- A Consultant's Perspective
 
2. Project Procurement Process.pptx
2. Project Procurement Process.pptx2. Project Procurement Process.pptx
2. Project Procurement Process.pptx
 
Mesurement presentation pavaruban
Mesurement presentation pavarubanMesurement presentation pavaruban
Mesurement presentation pavaruban
 
CompTIA Project+ Objectives
CompTIA Project+ ObjectivesCompTIA Project+ Objectives
CompTIA Project+ Objectives
 
Hands-on guidance roundtables and open discussions (parallel sessions)
Hands-on guidance roundtables and open discussions (parallel sessions)Hands-on guidance roundtables and open discussions (parallel sessions)
Hands-on guidance roundtables and open discussions (parallel sessions)
 
Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
 
introduction to public private partnership
introduction to public private partnershipintroduction to public private partnership
introduction to public private partnership
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
Construction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptxConstruction Contract Relationships Presentation.pptx
Construction Contract Relationships Presentation.pptx
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 
Archiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_finalArchiver omc stansted_tendering_procedure_and_requirements_final
Archiver omc stansted_tendering_procedure_and_requirements_final
 
Tender & its process.pptx
Tender & its process.pptxTender & its process.pptx
Tender & its process.pptx
 

Recently uploaded

What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 

Recently uploaded (20)

What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 

14102008 - Nordic Ppp Forum Presentation Pja Peekel Final

  • 1. 1 Nordic PPP Forum 2008 Stockholm, 28th - 29th October 2008 Presentation by: Ir. P.J.A. Peekel, Project Manager
  • 2. 2 PPP Procurement Process Public Infrastructure Planning Process DBFM Infrastructure Projects
  • 3. 3 PPP Procurement Process • Introduced for public sector contracts in EU Directive 2004/18/EC; • Entered into force in April 2004; EU member states were required to formally adopt the Directive before 1st January 2006; • In the Netherlands first applied, prior to formal adoption, to Second Coentunnel Project (start September 2005); • Complements the Open and Restricted Procedures (which require detailed specifications and award criteria to be drawn up in advance); • Intended to be a preferred alternative over the Negotiated Procedure; Introduction Competitive Dialogue Procedure
  • 4. 4 PPP Procurement Process • Contracting authorities are permitted to use this procedure: • Where the nature of the works or services that they are procuring or the risks related to them are such that prior overall pricing is not feasible; and/or • In case of a services contract (e.g. most PPP contracts) where the specifications cannot be drawn up with sufficient precision to allow pricing prior to the request for tenders; and/or • Where there is a need for the contracting authority to discuss all aspects of the proposed contract with candidates; • Negotiated Procedure remains for truly exceptional circumstances; Application of Competitive Dialogue
  • 5. 5 PPP Procurement Process • Typical steps in the process: 1. Prequalification Phase (economic/financial standing, technical and/or professional ability); 2. Plan of Approach Phase (short-listing to 3 bidders); 3. Consultation Phase (discuss contract, requirements, etc); 4. Dialogue Phase (develop solutions; prepare Dialogue Products e.g. Management Plan, Document Management System, Performance Monitoring System, project planning, risk allocation, etc; Resolve commercial and prizing issues; 5. Freeze documents and call for Final Tenders; Receive bids; 6. Clarifications, followed by appointing Preferred Bidder; Structure of Competitive Dialogue
  • 6. 6 PPP Procurement Process • After submitting final tenders, • Authority may only request clarification and fine-tuning or confirm commitments contained in the tender; • No negotiation on price or other substantial changes in scope can be agreed after appointing Preferred Bidder; • Preferred Bidder must the candidate with Most Economically Advantageous Tender (MEAT); • MEAT is determined on the basis of the prior award criteria laid down in the Tender Guidelines; • Quality requirements are translated to MEAT criteria; • Tenders allow focus on quality and price; Key characteristics of Competitive Dialogue
  • 7. 7 PPP Procurement Process • Quality worked into price: (1) List Risks and (2) Wishes • List Risks: • Predefined key risks of critical importance to Project; • Risk allocation choice determines for each risk the bid price mark- ups and the bid ceiling price adjustments: • Wishes: • Solutions the Client desires but not necessarily requires; • Each wish has a bid mark-up value; Competition on highest quality/price ratio Ceiling unchangedPart price mark-up onlyShare risk with Client Ceiling decreasedFull price mark-upLeave full risk for Client Ceiling increasedNo price mark-upTake full risk Ceiling unchangedPart price mark-up onlyShare risk with Client Ceiling decreasedFull price mark-upLeave full risk for Client Ceiling increasedNo price mark-upTake full risk Mark-up pro rataWish partially fulfilled Full price mark-upWish not fulfilled No price mark-upWish fully fulfilled Mark-up pro rataWish partially fulfilled Full price mark-upWish not fulfilled No price mark-upWish fully fulfilled
  • 8. 8 PPP Procurement Process • MEAT = Lowest [Bid Price + Mark-upRisks + Mark-upWishes] • Strategy is typically: To create distinctive / unique solutions that: -Minimize consequences of risks and enables you to take the risks; -Maximize the fulfillment of wishes at minimum cost; • This typically requires widening the boundaries of the specifications during the Consultation Phase; Consortium tender strategies under Competitive Dialogue Plan of Approach Phase Consultation Phase Dialogue Phase ProcurementProcess
  • 9. 9 PPP Procurement Process • A tender procedure which can be used in case of complex projects where solutions and specifications and estimated price cannot be defined up front; • A procedure which therefore allows development of requirements and solutions during the procurement process in a dialogue with the candidates, while maintaining competition; • Consortium tender strategies tend to focus on the creation of alternatives that add most value for the best possible price. This often calls for flexibility in specifications and relaxation of tightly defined solution constraints. Competitive Dialogue summarized
  • 10. 10 Infrastructure Planning Process • Well structured and highly regulated process to determine optimal routing of line infrastructure (railway, road); • Takes due account of: • Desired functional requirements; What problem to be solved; • Advantages and disadvantages of all possible solutions; • Technical, economical and environmental impact factors; • Requirements and wishes of project and public stakeholders; • Objective decision making process which includes public consultation (interaction with public stakeholders); Characteristics of public Infrastructure Planning Process
  • 11. 11 Infrastructure Planning Process • Structure is typically similar for railway and road projects; • Significant similarity of process structures between different EU countries; • Time frames: • Rail project Sweden (e.g. Citybanan Stockholm): 4-5 years • Road project in The Netherlands (typical): 5-6 years • Longer periods for complex projects are not uncommon; Structure and timeframe
  • 12. 12 Infrastructure Planning Process Similarity Swedish and Dutch Planning Processes Final Route Decree Järnvägsplanen Plan Study Phase part 2 (Draft Route Decree phase); Work out in detail the preferred route; Update EIA; Establish land acquisitions; Establish costs and planning; Tillåtlighetsprövning "Standpunt"; Decision by Minister of Transport for preferred route; Järnvägsutredning + MiljöKonsekvens Beskrivning (MKB) Plan Study Phase part 1 ("Trajectnota/MER Fase"); Study selected route options and carry out Environmental Impact Assessments (EIA); Förstudien Exploration Phase ("Verkenningsfase"); Define problems and explore feasible options that could solve them; Planeringsprocess (Banverket) Sweden Route Decree Process The Netherlands √ Såmrad √ Såmrad √ Såmrad √ Inspraak √ Inspraak √ Inspraak
  • 13. 13 Infrastructure Planning Process • Starting with many potential alternative options; • Ending up with a well defined single alternative; • Very limited (if any) degrees of freedom remain for a design process in the tender of the project or in project execution; • Selected detailed solution is often also described in agreements with public authorities; • Details by which solution is fixed are often more stringent than the law calls for; Converging to a single solution Feasibility Alternatives / EIA Detail selected route / EIA Route Decree PlanningProcess
  • 14. 14 Infrastructure Planning Process • A well structured and highly regulated process, bound by formalized decision making and significant public stakeholder involvement; • Aims to develop a single best alternative out of many options that may be available at the start of the process; • Tends to rigorously tie down that ultimate single solution in a detailed Route Decree and by means of one or more stakeholder agreements; Characteristics summarized
  • 15. 15 Combining Processes • Sequential approach of processes; • Fully interwoven processes; • Semi-interwoven processes; Infrastructure Planning and Procurement
  • 16. 16 The sequential approach • Procurement Process begins after Planning Process has been completed: • Final design (selected and well defined alternative); • Route Decree (formal governmental decision); • Public stakeholder agreements signed; • Tends to limit variety in solutions and in risk allocations offered; • Results in competition on price only rather than quality + price; Planning Process à Procurement Process Feasibility Alternatives / EIA Detail selected route / EIA Route Decree Plan of Approach Phase Consultation Phase Dialogue Phase Possibilities offered in Consultation Phase are often severely limited by prescribed details in Route Decree and by constraining clauses in Stakeholder Agreements. Solutions (possibly with considerable added value to the Client) cannot be accommodated Sub-Optimum Solution awarded PlanningProcess ProcurementProcess
  • 17. 17 Fully interwoven processes • Tender starts after Feasibility Stage (i.e. after Förstudien); • Tender solutions are injected in Planning Process; • Preferred Bidder solution = Route Decree solution; • Dutch infra project where being applied: A2 Maastricht project; Start tender very early in Planning Process Feasibility Alternatives / EIA Work out in detail selected route / EIA Route Decree Plan of Approach Consultation Phase Dialogue Phase MEAT solution awarded (conditionally to Route Decree) A B C A’ B’ C’ A”’ A’ B’ C’ D (public) Tender Solutions Preferred Bidder Solution (MEAT) > Route Decree Solution A’’ B’’ C’’ PlanningProcessProcurementProcess
  • 18. 18 Semi-interwoven processes • Tender starts after “Standpunt” (i.e Tillåtlighetsprövning); • Tenders are variations to publicly preferred solution; • Preferred Bidder solution = Route Decree solution; • Dutch infra project where applied: Second Coentunnel project; Start tender about halfway in Planning Process Feasibility Alternatives / EIA Work out in detail selected route / EIA Route Decree Plan of Approach Consultation Phase Dialogue Phase BAFO A’ B’ C’ A’’ B’’ C’’ A B C PlanningProcessProcurementProcess
  • 19. 19 Interweaving of processes Key to success • Concurrent timing of decisions in both processes; • Integrity of each process individually must be maintained; • Exchange of information between processes must take account of public transparency and procurement confidentiality requirements; Example of major “decision knot”: • Decision to conditionally award “Voorlopige Gunning” AND (at the same time) • “Standpunt” Tillåtlighetsprövning
  • 20. 20 Transaction time and costs • Competitive Dialogues tend to be long and can be costly; • When interweaving, tender process increases in duration, but intensity of effort varies in time; • When interweaving, the necessity to adhere to a tendering timescale will reduce public decision making delays; • When fully interwoven, design cost compensation given by tendering authority should consider that some of the public activity (i.e. working out alternatives) is done by the bidders; • Semi-Interweaving doesn’t automatically mean that more attractive solutions are possible, because sometimes public agreements turn out to have completely restrained all degrees of freedom; Competitive Dialogue and Interweaving
  • 21. 21 Dutch experience • Total value: EUR 630 mln; • Contract type: DBfM (small F!); • Infrastructure + urban area development; • Tender started Q4 2006; 5>3 bidders; • 3 bidder plans > public hearings; • Planned Contract Close: August 2009; Fully interwoven: A2 Maastricht
  • 22. 22 Dutch experience • Total value: EUR 600 mln; • Contract type: DBFMO; • 6 + 24 yrs concession; • Maintenance from Contract Close; • Infrastructure (tunnel + roads); • Very innovative bidder solutions; • Costly procedure: both Base Case and Alternatives were progressed; • Innovative solutions could ultimately not be accommodated (too many constraints build into Public Agreements); Semi-interwoven: 2nd Coentunnel
  • 23. 23 Interweaving described • Jointly developed between Ministry of Transport and representatives from the Private Sector; • General principles; Do’s and Don’t; Advantages and disadvantages of various interweaving models; • It’s a Guideline > project specific fine-tuning is possible; Manual available (in Dutch) Translation: “Guideline concerning the interweaving of Route Decree / EIA procedure and tendering procedure for infrastructure projects”
  • 24. 24 Lessons for Nordic Region • Adopt Competitive Dialogue Procedure for DBFM tenders; • When Route Decree Planning Procedure is interwoven with DBFM tender procedure, the possibility exists that due to competition very innovative solutions are developed with significant added value to Client and the public at large; • Do not restrict innovative alternatives by converging in the Route Decree Planning Procedure to a single and narrowly defined preferred alternative; • Do not constraint (more than absolutely necessary) the degrees of freedom for alternatives in Public Stakeholder Agreements; • When still in Route Decree Planning Procedure, the Client and the Preferred Bidder should work in Partnership (Alliance); And continue working like that throughout project execution!! For PPP infrastructure projects (roads, rail, incl. light rail)
  • 25. 25 Interweaving of PPP Procurement and Public Infrastructure Planning Processes For more information: Paul J.A. Peekel +31 30 240 7896 paul.peekel@strukton.com DBFM Infrastructure Projects Nordic PPP Forum 2008