CHAPTER 1
ABOUT PWD
1.1 Introduction
The Public Works Department has a glorious history in the development of the state since pre
independence. The department is mainly entrusted with construction and maintenance of Roads,
Bridges and Govt. buildings. The department also acts as Technical Advisor to the State Government.
Initially, Irrigation, Public Health engineering were units of PWD. Subsequently these units were
given separate entities to handle increased scope of work in the respective field. Since the inception
of the Department, it has strived through its continuous quest for excellence and putting milestones in
the feat of Engineering. It is this time that the Department is treading into a new era of information
technology to keep pace with the modernization. The Public Works Department being the oldest
engineering department of the State, has its well woven network even below tensile level which
enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state
1.2 About Public Works Department
The Public Works Department has a glorious history in the development of the state since pre
independence. The department is mainly entrusted with construction and maintenance of Roads,
Bridges and Govt. buildings. The department also acts as Technical Advisor to the State Government
in these matters.
Total road length being maintained by the department is more than 87500 KM the Department also
maintains State buildings all over Rajasthan & outside. The current annual budget allocation to the
department for construction & maintenance activities is over Rs 1000 Crores.
The Public Works Department being the oldest engineering department of the State, has its well
woven network even below tensile level which enables the P.W.D. to ensure the execution of a
variety of jobs/tasks any where in the state.
2
Initially, Irrigation, Public Health engineering were units of PWD. Subsequently these units were
given separate entities to handle increased scope of work in the respective field. Since the inception
of the Department, it has strived through its continuous quest for excellence and putting milestones in
the feat of Engineering. It is this time that the Department is treading into a new era of information
technology to keep pace with the modernization. The Public Works Department being the oldest
engineering department of the State, has its well woven network even below tensile level which
enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state.
1.3 Agencies
1. Relief works in the event of Natural calamities like famine, flood, earthquakes et al.
2. D.R.D.A. Works like Employment Assurance Scheme (EAS) etc.
3. Assessments of rent of private premises requisitioned for housing Govt. offices.
4. Design, construction, maintenance and repairs of runway relating to the State Government.
5. Development and maintenance of Public Parks and Gardens in important Public Buildings.
6. Up keeping of Govt. Rest House and Circuit Houses.
3
7. To permit construction of approaches on both sides of roads to private individual, other
institutions, factories, Petrol Pumps etc.
8. To evacuate the encroachment coming along the road sides. To evacuate the encroachment
coming along the road sides.
9. Issue of certificates periodically to Cinema Houses about stability of structures/ arrangement
related to electrical fittings conforming to Cinema Regulation Act.
10. Plantation of trees along both sides of the road.
4
CHAPTER 2
INTRODUCTION
2.1 Introduction
Drainage is the process of interception and removal of water from over, and under the vicinity of the
road surface. Drainage can be surface (where water is conveyed on the road surface and drainage
channels), or subsurface (water flows underneath the pavement structure).
Surface and subsurface drainage of roads critically affects their structural integrity, life and safety to
users, and is thus important during highway design and construction. Road designs therefore have to
provide efficient means for removal of this water; hence the need for road drainage designs.
Drainage facilities are required to protect the road against damage from surface and sub surface
water. Traffic safety is also important as poor drainage can result in dangerous conditions like
hydroplaning. Poor drainage can also compromise the structural integrity and life of a pavement.
Drainage systems combine various natural and man made facilities e.g. ditches, pipes, culverts, curbs
to convey this water safely.
5
2.2 Aims ofdocument
The purpose of this document is to provide guidance for road authorities and other relevant bodies in
respect of road drainage. The document is not intended to be a comprehensive design manual for
drainage for all new roads but concentrates on the design, rehabilitation and maintenance of drainage
systems on regional and local roads. Some of the matters covered will also have applicability for
national roads particularly national secondary roads). The document suggests some basic method
sand approaches for drainage design and references other documents for the design of major new
schemes and where more rigorous drainage analysis is required.
2.3 Importance ofdrainage
It is essential that adequate provision is made for road drainage to ensure that a road pavement
performs satisfactorily. The main functions of a road drainage system are:
1. To prevent flooding of the road and ponding on the road surface
2. To protect the bearing capacity of the pavement and the sub grade material
3. To avoid the erosion of side slopes
The type of road drainage which is selected for a particular road will depend on such factors as to
whether it is a rural or an urban road, or if it is in cut or fill and also on ground water conditions.
Open drains are used to carry away surface water and can also pick up some subsoil water (depending
on depth).
5
The survey indicated that existing road drainage systems use a mix of open drains, pipes and french
drains depending on road circumstances. The maintenance of these systems is variable and in general
most counties indicate reservations about the adequacy of current maintenance arrangements. The
separate forms of drainage systems in common use are considered briefly in this review of current
practice.
2.4 Open Drains
Open drains are the most common form of road drainage on rural national and non national roads.
Maintenance practice from the data available indicates various levelsof attention to the open drain
system. Opening of drainage inlets and/or total removal of road margin, to ensure rapid removal of
6
road surface water, appears to be common practice. However, frequency of inlet opening is perceived
to be inadequate in many circumstances.
Open drains have the advantage of being easily inspected for blockages and are also effective at
draining the road sub grade provided the drain flows to an adequate outfall. Open drains are
generally, but not always, within the road limits. In circumstances where open drains are on private
property the Authority’s powers under the Roads Act should be exercised to ensure that drain age is
not interfered with. The review suggests that drains outside the road limits may
not be receiving adequate attention.
2.5 French Drains
French drains are used extensively on sections of the national network and to a limited extent on non-
national roads. The drains generally include pipe work in conjunction with stone media. Maintenance
levels are low and this may affect the long term performance. In most instances maintenance is
carried out as problems manifest themselves, with few counties having an annual maintenance
programme.
2.6 Piped Drainage
Piped drainage systems are essential in urban areas and are also used in rural areas where space is
limited. Piped systems can be sealed or open-jointed. The normal practice is to use sealed systems in
urban areas and open-jointed systems in rural areas. Piped systems with gullies require regular
maintenance and while in many instances these systems are cleaned annually the data received
suggests that the frequency of maintenance is generally considered inadequate6
7
Chapter 3
Road
3.1 Introduction
A road is a thoroughfare, route, or way on land between two places, which has been paved or
otherwise improved to allow travel by some conveyance, including a horse, cart, or motor vehicle.
Roads consist of one, or sometimes two, roadways (carriageways) each with one or more lanes and
also any associated sidewalks (British English: pavement) and road verges. Roads that are available
for use by the public may be referred to as public roads or highways.
3.2 Type of Road:
FREEWAYS:
Freeways have strict classification rules.
1. Multi-Lane, divided road
2. No cross traffic.
3. No stop lights (except for ramp meters).
4. No stop signs.
5. No parking.
6. No stopping (except for toll booths, freeway access metering)
7. Highest speed limits. (relative to region)
8. Some have minimum speed limits.
8
9. Limited access
3.3 MAJAOR HIGHWAYS:
Purposely built as a major throughway.
• Higher speeds. Speed limits should be near or equal to Interstate or Freeway speed limits in
the same area. (typically within 10-20 Kmph)
• Multiple lanes in each direction.
• Separated directions of travel.
• Turning traffic is typically limited to specified turn lanes or freeway style ramps to minimize
obstructions to thru traffic.
• Partially limited access with few minor streets intersecting with this road. Intersections are
most often with primary roads or other highways.
9
3.4 MINOR HIGHWAYS:
Minor Highways vary widely from large multi-lane roads with stoplights and higher speed limits, to
small residential streets with stops signs.
Some minor highways may zigzag thru an area with many turns on local streets.
A Minor Highway thru the main street of a small town often retains focus on local access with
pedestrian traffic and on street parking.
A side street is a street that intersects a main street and ends there. It is generally of little importance
to through traffic. Being the last mile of the road system, it generally carries little traffic. Common
characteristics of a side street include low speed limits (usually not more than 30 mph or 50 km/h),
curbside parking, and few or no painted line markings to display lanes. Intersections in urban or
suburban areas are usually marked by stop signs, or occasionally yield signs in some suburban areas
when intersecting other side streets. In rural areas, some intersections are uncontrolled.
Most side streets are lined with residences. Occasionally, a place of worship or a school may be
located on a side street, but in a residential area, it is rare to find any commercial development (this is
often prohibited by local zoning laws, unless directly adjacent to a major street).
10
CHAPTER 4
DRAINAGE
4.1 Introduction
Drainage is the natural or artificial removal of surface and sub-surface water from an area. Many
agricultural soils need drainage to improve production or to manage water supplies.
The civil engineer is responsible for drainage in construction projects. They set out from the plans all
the roads, street gutters, drainage, culverts and sewers involved in construction operations. During the
construction process he/she will set out all the necessary levels for each of the previously mentioned
factors.
Civil engineers and construction managers work alongside architects and supervisors, planners,
quantity surveyors, the general workforce, as well as subcontractors. Typically, most jurisdictions
have some body of drainage law to govern to what degree a landowner can alter the drainage from his
parcel.
4.2 Types of drainage
There are basically three types of drainage applied to highways that ;
1. Subsurface drainage
2. Surface drainage
3. Cross drainage
4.2.1 SUBSURFACE DRAINAGE
Subsurface drainage is concerned with the interception and removal of water from within the
pavement. Some of the sources of subsurface water include; infiltration through surface cracks,
capillary rise from lower layers, seepage from the sides of the pavement to mention but a few.
Application of side slopes on the road surface, installing of drainage beds in the pavement and use of
transverse drains are some of the measures of effecting subsurface drainage.
11
When groundwater cannot be effectively removed or intercepted by surface drainage, subsurface
drainage techniques are required. As discussed in previous sections of this workbook, if water is not
removed from sub grade or pavement structures it may create instability, reduce load bearing
capacity, increase the danger of frost action and create a safety hazard by freezing of the traveled
surface.
Field investigations carried out during the route reconnaissance and design stages may not always
reveal sub drainage problems. These less obvious problems can be effectively dealt with during
construction. Field investigations should be carried out during the wet season and may include soil
and/or geologic studies, borings or trenches to locate groundwater, inspections of natural and cut
slopes in the local area, and measurement of discharge when possible. Sites with potential slope
stability problems should be more thoroughly evaluated. When groundwater tables approach the
ground surface, such as in low, swampy areas, the gradeline should be placed high enough to keep
water from being drawn up into the fill by capillary action. Whenever possible, well graded granular
materials, such as coarse sand, should be used for fill construction. For a detailed discussion of
grading requirements for filter materials the reader is referred to the Earth Manual published by the
U.S. Department of the Interior (1974).
Three types of sub drainage systems are commonly used:
(1) Pipe underdrains. This system consists of perforated pipe placed at the bottom of a narrow
trench and backfilled with a filter material such as coarse sand. It is generally used along the toes of
cut or fill slopes. The trench should be below the groundwater surface and dug into a lower, more
inpervious soil layer to intercept groundwater. The drains may be made of metal, concrete, clay,
asbestos-cement, or bituminous fiber and should be 15 centimeters (6 inches) in diameter or larger.
(2) Drilled drains. This system consists of perforated metal pipes placed in holes drilled into cut or
fill slopes after construction.
(3) French drains. This system consists of trenches backfilled with porous material, such as very
coarse sand or gravel. This type of drain is apt to become clogged with fines and is not
recommended.
12
A major difficulty in selecting a drainage system is the lack of adequate performance data for various
drainage methods. A good knowledge of seasonal groundwater fluctuations, variation in lateral and
vertical permeability, and the ratio of vertical to lateral permeability are critical. Long term
monitoring of drainage performance is important in determining appropriate prescriptions for future
installations. For example, perforated drains are commonly prescribed but often will not function
properly as a result of clogging of pores with fines or from geochemical reactions leading to the
formation of precipitates. Several methods may be used to prevent plugging depending on soil
characteristics and material availability. The first is to enclose the perforated pipe with geotextile
fabric. Second, surround the pipe with an open graded aggregate material, which in turn is
surrounded by a fabric. The use of fabric eliminates the need for an inverted filter consisting of
various sized gravel and sand layers. Third, if fabric is not available, surround the pipe with a graded
aggregate filter. Although the cost of installing such a drainage system is high, it may effectively
reduce final road costs by decreasing the depth of base rock needed, thereby reducing subgrade
widths and associated costs for clearing, excavating, and maintenance.
4.2.2 SURFACE DRAINAGE
Surface drainage deals with arrangements for quickly and effectively leading away the water that
collects on the surface of the pavement, shoulders, slopes of embankments, cuts and the land
adjoining the highway. Reducing the erosive power of water can achieved by reducing its velocity. If, for
practical reasons, water velocity cannot be reduced, surfaces must be hardened or protected as much as
possible to minimize erosion from high velocity flows. Road surface drainage attempts to remove the surface
water before it accelerates to erosive velocities and/or infiltrates into the road prism destroying soil strength by
increasing pore water pressures. This is especially true for unpaved, gravel, or dirt roads.
The main source of surface water in most places is precipitation in form of rain. When precipitation
falls on an area, some of the water infiltrates in to the ground while a considerable amount remains on
top of the surface as surface run off.
Dip locations are determined at the time the grade line is established on the ground or during vertical
alignment design. The total length of the two vertical curves comprising the dip should be sufficient
to allow the design vehicle to pass safely over them at the design speed. The minimum vertical
distance between the crest and sag of the curves should be at least 30 cm (1 ft). It is important that the
dip be constructed at a 30 degree or greater angle downgrade and that the dips have an adverse slope
13
on the downroad side. The downroad side of the dip should slope gently downward from the toe of
the road cut to the shoulder of the fill. The discharge point of the dip should be armored with rock or
equipped with a down-drain to prevent erosion of the fill. Equipment operators performing routine
maintenance should be aware of the presence and function of the dips so that they are not
inadvertently destroyed.
MEASURES ADOPTED FOR SURFACE DRAINAGE
1. The proper cross slope should be provided for both to pavement and shoulders
2. The subgrade should be sufficiently above the highest level of ground water table or the
natural ground level
3. Side drainage should have to be provided at edges of right-of-way where the road is in
embankment and the edge of the roadway in cutting
4. On hill roads, water may flow towards the road depending on the slope and rainfall
5. Catch water drains should be provided to intercept the flow down.
COLLECTION OF SURFACE WATER
The water collected is lead into natural channels or artificial channels so that it does not interfere with
the proper functioning of any part of the highway.
Surface drainage must be provided to drain the precipitation away from the pavement structure.
4.2.2.1 CLASSIFICATIONOF SIDE DRAINAGE
There are different types of road side drainage, classified according to the type of construction, which
is as follows;
Trapezoidal surface drainage
A trapezoidal ditch is the most efficient hydraulically and should be used for ditches carrying a large
amount of water. The flat bottom spreads out the flow and helps reduce erosion problems. They are more
14
difficult to construct, but the Soil and Water Conservation District and Natural Conservation Service can
provide assistance.
V-shaped lined surface drainage
A V–shaped ditch is easy to construct, especially with a grader. However, the bottom of the V is prone to
erosion and can be difficult to maintain.
Urban surface drainage
A U–shaped ditch is more efficient hydraulically and a good shape for erosion control. It can be built with
an excavating machine and is easy to maintain. However, most U–shaped ditches in New York State are
too steep on the road side of the ditch. Two ways to solve the problem are to cuff the break of the ditch
and the shoulder with a grader or the excavator bucket, or curl the bucket back during the final pass to
make a rounded shape.
15
4.2.3 CROSS DRAINAGE
When stream have to cross a roadway or when water from a side drainage have to be diverted to
water course across the roadway, then a cross drainage work such as culvert or small bridge is
provided.
On less important roads, in order to reduce the construction cost of drainage structures, sometimes
submersible bridges or course way are constructed. During the flood the water will flow over the
road. Cross drains are often needed to intercept the longitudinal, or down-road, flow of water in order to
reduce and/or minimize surface erosion. In time, traffic will cause ruts to form, channeling surface water
longitudinally down the road.
REQUIREMENT OF HIGHWAY DRAINAGE SYSTEM
1. The surface water from the carriage way and shoulder should effectively be drained off
without allowing it to percolate to sub grade
2. The surface water from the adjoining land should be prevented from entering the roadway.
3. The surface drainage should have sufficient capacity and longitudinal slope to carry away
all the surface water collected.
16
4. Flow of surface water across the road and shoulders and along slopes should not cause
formation of erosion.
17
CHAPTER 5
CULVERTS
5.1 Introduction
Reducing the erosive power of water can achieved by reducing its velocity. If, for practical reasons,
water velocity cannot be reduced, surfaces must be hardened or protected as much as possible to
minimize erosion from high velocity flows. Road surface drainage attempts to remove the surface
water before it accelerates to erosive velocities and/or infiltrates into the road prism destroying soil
strength by increasing pore water pressures. This is especially true for unpaved, gravel, or dirt roads.
A culvert helps move water under a road or driveway to a stream, lake, or detention basin. While
culverts can, and have been, defined in many ways (such as any span under 20 feet), for drainage, a
culvert is usually prefabricated and comes in standard sizes. In addition, a culvert is allowed to have
the ends completely submerged.
The first item we need to understand is the amount of flow a culvert will need to carry. Then we can
look at the materials, installation, inspection, and maintenance.
Water moves across the road surface laterally or longitudinally. Lateral drainage is achieved by
crowning or by in- or out- sloping of road surfaces (Figure 79). Longitudinal water movement is
intercepted by dips or cross drains. These drainage features become important on steep grades or on
unpaved roads where ruts may channel water longitudinally on the road surface.
• Hydrological analysis
• Hydraulic analysis
Runoff
The first step in determining the size of a culvert (or other drainage structure, including ditches) is
calculating the runoff or flow coming to a culvert. Several methods exist for determining the amount
of flow. TR–55; the Soil Conservation Service’s Graphical method; the Bureau of Public Roads; the
Rational method; and other methods are used to determine the amount of runoff. The Rational
method, used for small watersheds, is useful to explain the concepts of runoff.
18
Runoff at a specific site is controlled by many factors including the intensity of precipitation, the area
of the watershed, and the proportion of rainfall which gets to the culvert.
Fig 5.1 Precipitation and runoff (hydrograph)
5.2 Hydrological analysis
This deals mainly with precipitation and runoff in the area of interest. When rainfall, which is the
main source of water, falls onto an area some of the water infiltrates into the soil while the remaining
portion either evaporates or runs off.
The portion that remains as runoff is the one of major importance in the design of surface drainage
facilities.
5.3 Determination of runoff
Runoff at a particular point is determined with respect to a given catchment area and depends on a
number of factors such; type and condition of the soil in the catchment, kind and extent of vegetation
or cultivation, length and steepness of the slopes and the developments on the area among others.
The following formula known as the rational formula is used for calculation of runoff water for
highway drainage.
Q= 0.028CIA
19
Where:
Q = maximum runoff in m3 per sec
C = a constant depending upon the nature of the surface
I = the critical intensity of storm in mm per hour occurring
during the time of concentration.
A = the catchment area in km2
5.4 Hydraulic Design
Once the design runoff Q is determined, the next is the hydraulic design of drains. The side drainage
and other structures are designed based on the principles of flow through open channels.
If Q is the quantity of surface water (m3/sec) to be removed by a side drainage and V is allowable
velocity of flow (m/s) on the side drainage, the area of cross section A of the channel (m2) is found
from the relation below:
Q=A.V
The velocity of unlined channel must be high enough to prevent silting and it should not be too high
as to cause erosion. The allowable velocity should be greater than one (1m/sec) for lined channel.
The slope S of the longitudinal drain of known or assumed cross section and depth of flow ,may
determined by using Manning’s formula for the design value of velocity of flow V, roughness
coefficient n and hydraulic radius R.
Manning’s Formula
V=1/n*R2/3*S1/2
Where:
V=Average velocity m/sec
20
n=Manning’s roughness coefficient
R=Hydraulic radius
S=Longitudinal slope of channel.
Manning’s Roughness coefficient
N= 0.02 for unlined ordinary ditches
=0.05 to 0.1 for unlined ditches with heavy vegetation
=0.013 for rough rubble
=0.04 for stone riprap
=0.015 for pipe culverts
Hydraulic Radius = Cross sectional area
Wetted perimeter
5.5 Time of concentration (t c)
Time of concentration is that time required for water to travel all the way from catchments area to
the designed element.
The time taken by water to flow along the longitudinal drain is determined from the length of the
longitudinal drain L the nearest cross drainage or a water course and allowable velocity of the flow V
in the drain.
T = V/L
The total time for inlet flow and flow along the drain is taken as time of concentration or the design
value of rain fall duration.
T c = T1+ T2
21
Where,
T1 = overland flow time in minutes
T2 = channel flow time in minute
T1 = [(0.885x L3)/H] 0.385
Where,
L = the length of overland flow in km from critical point the mouth of the drain.
H = total fall of level from the critical point to the mouth of the drain in meters.
Note:
From the rainfall intensity –duration- frequency curves the rainfall I is found in mm/sec.
Corresponding to duration T and frequency of return period.
The required depth of flow in the drain is calculated for convenient bottom width and side slope of
drain. The actual depth of the open channel drain may be increased slightly to give a free body. The
hydraulic mean radius of flow R is determined.
The required longitudinal slope S of the drain is calculated using Manning formula adopting suitable
value of roughness coefficient.
22
23
CHAPTER 6
ABOUT THE MATERIAL
6.1 Introduction
Culvert pipes come in many materials, shapes, and sizes. Each material has its own characteristics
and advantages. The four most common materials are corrugated metal pipe (CMP), plastic, concrete,
and smooth steel. The pipes are generally thought of in two broad categories which correspond to the
way they carry loads, rigid and flexible.
Flexible pipe (CMP and plastic) gains strength by transferring some of the load into the surrounding
soil. Imagine what would happen if you drove a fully loaded truck over a flexible pipe. It would
crush. It gains strength from the surrounding soil when it flexes.
Flexible pipes must be backfilled properly and have a minimum amount of cover or the loads do not
build up in the soil and the pipe will fail. They are generally less expensive to place than rigid pipes
but do not last as long. Coatings may increase their lifespan. Failure to bed the pipe carefully will
shorten the life of the pipe and may cause premature failure.
Rigid pipes (concrete, heavy steel, and masonry) are strong enough by themselves to carry all loads.
The transferring of loads is of secondary benefit. They generally last longer than flexible pipes but
are much more expensive to place. Cranes and larger equipment are usually needed to set them.
6.2 Corrugatedmetal pipe
Sometimes referred to as CMP (corrugated metal pipe), metal pipe is the most common type of
material used in culverts. The versatility of the pipe and the wide range of shapes and sizes available
make it a very useful product.
The base metal can be steel or aluminum. Coatings can be added to increase lifespan, reduce
corrosion, and improve hydraulics (flow capacity). Steel is the most common metal used, but is
usually galvanized for corrosion protection. The steel may be mixed or coated with an aluminum
alloy which is more durable than galvanizing alone and does not increase the price significantly. Or,
the pipe can be made of all aluminum. Care should be taken when installing an aluminum pipe,
because it is easily damaged. Asphalt and concrete coatings are sometimes added for durability,
improved flow characteristics, and resistance to wear from stream bed materials.
24
Metal pipes are manufactured in a variety of shapes as shown. Listed beside each are some of the
reasons for using the different shapes. ROUND Easy and inexpensive to manufacture. Has a high
flow capacity. Sizes up to 12 inches in diameter.
6.3 Plastic
Plastic pipe, usually made of high density polyethylene (HDPE), is the fastest growing pipe in terms
of use. It is easy to construct due to its light weight and is easy to maneuver and cut. It can be used in
a variety of applications including lining existing pipes. It can be lined with a smooth section of
plastic to increase flow capacity and improve strength. Plastic pipe is flammable and can be burned.
The pipes are limited in size to about six feet and are uneconomical for many applications if more
than four feet in diameter. New processes may provide more pipe types and sizes in the future. Plastic
pipes only come in a round shape currently, up to 6 feet in diameter for smooth pipes, and 2 feet for
corrugated pipes.
Figure 7.1 - Pipe shapes (metal)
6.4 Concrete
Concrete pipe comes in a variety of shapes and sizes. It can be pre–cast or cast–in–place and
primarily used in deep fills or urban areas where construction costs are high. It is more expensive
than plastic or metal pipe but is very durable and has a long life. Cranes and other heavy equipment
are usually needed to place the pipe.
Concrete pipes come in several shapes, but the most common are round and elliptical. Elliptical pipe
may be vertical or horizontal in alignment. Concrete box culverts are some of the most common
bridge and large culvert types built.
6.5 Heavy steel
Solid steel pipe, sometimes made from old boilers, tank cars, or pipelines can be economical when
available locally. It is usually very durable. However, the durability of the pipe is usually unknown
25
and the pipe can deteriorate quickly. The major problem, with steel culverts, however, is the joints.
They need to be well built or failure at the joint can allow infiltration of fines and settlement at the
surface. Steel pipes are usually round and come in limited sizes.
26
6.5 Durability
Concrete pipe is the most durable with an expected life of 75 to 100 years. It is expensive to install,
but in deep fills and urban areas (villages and cities) it is usually justified by comparing the cost of
replacement to the amount of time between replacement.
Solid steel is usually the next most durable. However, if you buy a used pipe, the lifespan may be
very short.
Plastic and corrugated metal are about the same in durability. Steel pipe is better able to handle bed
loads and debris but is very susceptible to corrosion due to low pH water (acidic) which is found in
the Southern Tier and parts of the Adirondacks. Other areas may have high alkalinity in the soil. In
those areas, plastic pipe or lining of pipes may be necessary to keep pipe from corroding early. Plastic
and corrugated metal pipes have a 25 to 50 year life if designed and built properly. Also, bed load can
cause premature failure. Lining of existing pipes, or adding liners during construction may be useful.
6.6 SIZE AND CAPACITY
How large of a pipe is needed? Several factors need to be considered. First let’s discuss the factors.
Then we will bring all of the results together below.
The flow capacity of a pipe is determined by several factors including the:
• Area and shape of the opening of the pipe
• Allowable head or amount of backwater
• Kind of inlet
• Culvert length and slope
• Material used (roughness of the pipe)
• Other factors including constrictions of flow due to debris, tailwater, or channel alignment
6.6.1 Area and shape of opening
By far the most critical factor for determining capacity is the area of the opening of the pipe. The
amount of flow that can go through a culvert is directly proportional to the area of the opening.
27
Doubling the area doubles the capacity of the pipe. An 18–inch diameter pipe has more than twice the
capacity of a 12–inch diameter pipe because the area is more than twice as large.
(18–inch diameter pipe area = 254 in
2
vs. 12–inch diameter pipe area = 113 in
2
).
6.6.2 Allowable head or depth of water at the inlet
The allowable head is the maximum depth of flow before either the road is overtopped by the water
backed up at the culvert, or damage to the road or adjacent property is likely to occur. The
overtopping does not have to be at the pipe. In many cases, the flow crosses the road downhill from
the culvert due to natural alignments or planned changes in the roadway. Damage could be a washout
of the roadway due to overflow or inundation of a building that is built lower than the roadway
elevation.
The greater the allowable depth, the more flow can be pushed through the pipe. Increases in the cover
over a pipe (and therefore increases in allowable depth) can greatly increase the allowable flow in the
pipe. Care must be taken to use existing allowable heads or increases in the height of the roadway.
Lowering the pipe to get more cover does not work. The pipe will probably fill in with sediment and
the area of the opening will be diminished, reducing the flow capacity by far more than the increase due
to extra head.
28
CHAPTER 7
MATERIALS, SHAPES, and SIZES
Culvert pipes come in many materials, shapes, and sizes. Each material has its own characteristics
and advantages. The four most common materials are corrugated metal pipe (CMP), plastic, concrete,
and smooth steel. The pipes are generally thought of in two broad categories which correspond to the
way they carry loads, rigid and flexible.
Flexible pipe (CMP and plastic) gains strength by transferring some of the load into the surrounding
soil. Imagine what would happen if you drove a fully loaded truck over a flexible pipe. It would
crush. It gains strength from the surrounding soil when it flexes.
Flexible pipes must be backfilled properly and have a minimum amount of cover or the loads do not
build up in the soil and the pipe will fail. They are generally less expensive to place than rigid pipes
but do not last as long. Coatings may increase their lifespan. Failure to bed the pipe carefully will
shorten the life of the pipe and may cause premature failure.
Rigid pipes (concrete, heavy steel, and masonry) are strong enough by themselves to carry all loads.
The transferring of loads is of secondary benefit. They generally last longer than flexible pipes but
are much more expensive to place. Cranes and larger equipment are usually needed to set them.
7.1 Corrugatedmetal pipe
Sometimes referred to as CMP (corrugated metal pipe), metal pipe is the most common type of
material used in culverts. The versatility of the pipe and the wide range of shapes and sizes available
make it a very useful product.
The base metal can be steel or aluminum. Coatings can be added to increase lifespan, reduce
corrosion, and improve hydraulics (flow capacity). Steel is the most common metal used, but is
usually galvanized for corrosion protection. The steel may be mixed or coated with an aluminum
alloy which is more durable than galvanizing alone and does not increase the price significantly. Or,
the pipe can be made of all aluminum. Care should be taken when installing an aluminum pipe,
because it is easily damaged. Asphalt and concrete coatings are sometimes added for durability,
improved flow characteristics, and resistance to wear from stream bed materials.
29
7.2 Plastic
Plastic pipe, usually made of high density polyethylene (HDPE), is the fastest growing pipe in terms of
use. It is easy to construct due to its light weight and is easy to maneuver and cut. It can be used in a
variety of applications including lining existing pipes. It can be lined with a smooth section of plastic to
increase flow capacity and improve strength. Plastic pipe is flammable and can be burned. The pipes are
limited in size to about six feet and are uneconomical for many applications if more than four feet in
diameter. New processes may provide more pipe types and sizes in the future. Plastic pipes only come in
a round shape currently, up to 6 feet in diameter for smooth pipes, and 2 feet for corrugated pipes.
Figure 7.1 - Pipe shapes (plastic)
Figure 7.2 - Pipe shapes (metal)
30
7.3 Concrete
Concrete pipe comes in a variety of shapes and sizes. It can be pre–cast or cast–in–place and
primarily used in deep fills or urban areas where construction costs are high. It is more expensive
than plastic or metal pipe but is very durable and has a long life. Cranes and other heavy equipment
are usually needed to place the pipe.
Concrete pipes come in several shapes, but the most common are round and elliptical. Elliptical pipe
may be vertical or horizontal in alignment. Concrete box culverts are some of the most common
bridge and large culvert types built.
7.4 Heavy steel
Solid steel pipe, sometimes made from old boilers, tank cars, or pipelines can be economical when
available locally. It is usually very durable. However, the durability of the pipe is usually unknown
and the pipe can deteriorate quickly. The major problem, with steel culverts, however, is the joints.
They need to be well built or failure at the joint can allow infiltration of fines and settlement at the
surface. Steel pipes are usually round and come in limited sizes.
Figure 28 - Pipe shapes (steel)
31
7.5 Durability
Concrete pipe is the most durable with an expected life of 75 to 100 years. It is expensive to install,
but in deep fills and urban areas (villages and cities) it is usually justified by comparing the cost of
replacement to the amount of time between replacements.
Solid steel is usually the next most durable. However, if you buy a used pipe, the lifespan may be
very short.
Plastic and corrugated metal are about the same in durability. Steel pipe is better able to handle bed
loads and debris but is very susceptible to corrosion due to low pH water (acidic) which is found in
the Southern Tier and parts of the Adirondacks. Other areas may have high alkalinity in the soil. In
those areas, plastic pipe or lining of pipes may be necessary to keep pipe from corroding early. Plastic
and corrugated metal pipes have a 25 to 50 year life if designed and built properly. Also, bed load can
cause premature failure. Lining of existing pipes, or adding liners during construction may be useful.
32
7.6 SIZE AND CAPACITY
How large of a pipe is needed? Several factors need to be considered. First let’s discuss the factors.
Then we will bring all of the results together below.
The flow capacity of a pipe is determined by several factors including the:
1. Area and shape of the opening of the pipe
2. Allowable head or amount of backwater
3. Kind of inlet
4. Culvert length and slope
5. Material used (roughness of the pipe)
7.6.1 Area and shape of opening
By far the most critical factor for determining capacity is the area of the opening of the pipe. The
amount of flow that can go through a culvert is directly proportional to the area of the opening.
Doubling the area doubles the capacity of the pipe. An 18–inch diameter pipe has more than twice the
capacity of a 12–inch diameter pipe because the area is more than twice as large.
(18–inch diameter pipe area = 254 in
2
vs. 12–inch diameter pipe area = 113 in
2
).
Figure 7.4 - Factors determining flow capacity of a pipe
7.6.2 Allowable head or depth of waterat the inlet
The allowable head is the maximum depth of flow before either the road is overtopped by the water
backed up at the culvert, or damage to the road or adjacent property is likely to occur. The overtopping
does not have to be at the pipe. In many cases, the flow crosses the road downhill from the culvert due to
33
natural alignments or planned changes in the roadway. Damage could be a washout of the roadway due to
overflow or inundation of a building that is built lower than the roadway elevation.
The greater the allowable depth, the more flow can be pushed through the pipe. Increases in the cover
over a pipe (and therefore increases in allowable depth) can greatly increase the allowable flow in the
pipe. Care must be taken to use existing allowable heads or increases in the height of the roadway.
Lowering the pipe to get more cover does not work. The pipe will probably fill in with sediment and
the area of the opening will be diminished, reducing the flow capacity by far more than the increase
due to extra head.
Figure 7.5 - Shape of openings
34
7.6.3 Kind of inlet
The most common inlet (and outlet) type is the projecting pipe. Small increases in the capacity can be
gained by using the mitered or headwall inlet. Also, use of special ends on both the upstream and
downstream side can reduce scour, improve appearance, and make maintenance easier. The extra
capacity in a culvert due to use of inlets is anywhere from no increase to 10 percent increase in the
flow capacity.
Most commonly, inlets are placed to improve characteristics other than flow. Mitering the pipe to fit
the slope makes the slope safer for errant vehicles and is easier to maintain. However, the ends are
susceptible to failure if the ends are not anchored properly. A set of #8 rebars placed on a one–foot
grid over the opening allows the highway department to eliminate the use of guiderail. The bars help
keep debris out of the pipe. Care must be taken to leave an opening below the grate to allow the
majority of the flow through the pipe or plugging can occur and damage the pipe.
Special ends can be purchased to attach to the ends of most round pipes. The price can be very high
for larger pipes, but the ends protect against scour, have good appearances, and can be protected by a
rebar grate in the same way a metered end is protected. In addition, if there is a need to extend the
pipe in the future, the end can be removed, a new section of pipe added to the first section, and the
end replaced.
Figure 7.6 - Inlet (outlet) designs (projecting, mitered, and headwall)
35
Headwalls are usually used with high flows, major alignment changes near the openings which cause
heavy scour, and deeper pipes which warrant more expensive protection. The headwalls can be made
on concrete, precast concrete and masonry, gabion baskets, plastic, and timber. Concrete is more
expensive, but fits the opening better and reduces the chances of piping. Gabion baskets are fairly
labor intensive, but can be shaped to fit the pipe. Masonry and precast concrete do not fit the pipe and
usually some grout or concrete must be placed around the opening to get a good fit. Timber and other
items (tires, sandbags) are not as effective due to shorter life spans and uncertainty about durability.
7.6.4 Culvert length and slope
For most small culverts (60 feet or less) the capacity of the pipe is not affected by the slope. The
opening of the pipe will control the amount of water that can get into the pipe. Increasing the slope
will increase the velocity of the flow but the capacity will NOT increase.
For culverts of more than 60 feet, the slope and length do make a difference but usually only at very
flat slopes (1 percent or less [3 inches per 20–foot section of pipe]). In fact, increasing the slope
beyond 2 percent (5 inches per section of pipe) can actually cause problems due to increases in
velocity of the water leaving the pipe.
7.4.5 Materialused
Concrete, steel, and smooth plastic may have slightly more capacity than corrugated pipes. However,
this is only true for pipes that are fairly long and flat. In most cases, the selection of the material to be
used is a function of cost, availability, ease of construction, maintenance, and longevity. In many
cases, the smoother pipes are used at flat slopes because they are less likely to fill with sediment and
plug. However, use of smooth pipes on steep slopes can actually cause erosion and other problems.
Figure 7.6 - Corrugated pipe special end section
36
CHAPTER 8
SLOPES AND EROSION CONTROL
8.1 HOW TO STOP EROSION
Stopping erosion is difficult. Keeping erosion from occurring in the first place is usually more successful.
Many of the maintenance activities performed on roads and streets would be unnecessary if erosion was
controlled. As an example, stopping erosion from occurring at the top of a hill will reduce the ditching at
the bottom of the hill. Approximately 30 tons of material can be eroded from a mile of ditches before you
can see the damage! To remove and replace 30 tons of material is a lot of work.
Also, you need to be concerned about erosion during construction and maintenance work. The work can
cause additional erosion.
8.2 TYPES OF EROSION
Three types of erosion are common: surface, rill, and galley. Different soils erode differently. For most
highway materials you can be sure of two things. One, unprotected materials will erode and cause
sedimentation. Two, the flatter the slope the fewer erosion problems occur.
• Surface Surface or sheet erosion occurs when rainfall dislodges soil on the surface of
material, and the water plus soil flows in sheets. The washing of shoulders is often started
by this process.
• Rill Rill erosion occurs when the velocity of the flow is great enough to dislodge soil in
addition to that dislodged by rainfall. Rill erosion is typified by the narrow little channels
that form in banks and slopes that are not protected from erosion.
• Gully Gully erosion occurs when rill erosion combines and concentrates the flow of runoff
into gullies. Washouts between pavement and shoulders are usually gully erosion.
37
8.3 SEDIMENTATION
All of the material removed by erosion is deposited at some location downstream from the erosion.
This process of sedimentation usually occurs where a change in the speed of the flow occurs. Filling
of culverts, ditches, streambeds, and even lakes is a result of sedimentation. Stopping erosion will
eliminate or reduce many of the problems associated with poor drainage.
8.4 SLOPES
Even very flat ground erodes. The reason you do not notice the erosion is that sedimentation occurs at
the same location as the erosion. Steep terrain erodes very quickly. You need to reduce erosion
problems. In addition, for slopes you have to be concerned about three factors: stability, safety, and
maintenance.
Figure 9.2 - Slopes
38
8.4.1 Stability
Most highway materials are stable at slopes of 1:2 or flatter. Slopes steeper than 1:2 are more prone
to erosion and washouts. If saturated, the entire slope may fail.
8.4.2 Safety
Slopes along the edge of roads, including ditches and banks, need to be kept fairly flat to allow errant
vehicles a safe place to drive. Slopes of 1:3 or flatter are considered safe. If the slope is less than 3 feet
high a 1:2 slope is acceptable. More information on roadside safety can be found in the Cornell Local
Roads Program’s manual.
8.4.3 Maintenance
Mowing slopes is the most common maintenance technique. If slopes are 1:2 or flatter, the mowing crews
can easily mow the slope. Minor repairs may be needed to fix small washouts and erosion.
8.4.4 Options
If a slope is too steep, several items need to be examined to repair the problem:
• Stabilize Unstable slopes can be stabilized by use of geotextiles or other earth
reinforcement materials. If you have a high steep slope that is showing signs of distress,
GET HELP.
• Retaining walls Use of gabions, concrete, and block retaining walls may be needed on very
steep slopes or to help stabilize the toe of an existing slope. If a slope is so steep the
erosion mitigations listed below will not work, a retaining wall may be needed. GET HELP
to determine the best course of action.
• Signing Slopes steeper than 1:3 (1:2 for 3 or fewer feet in height) need to be protected. As a
minimum, signs should be used to delineate the slope and warn motorists of the hazard. See
Chapter 17B New York Code of Rules and Regulations (NYCRR) for future information.
39
• Guiderail Guiderail should be used on steep slopes. It needs to be installed and used
correctly as part of an overall plan to upgrade the roads. The NYSDOT publication,
Guiderail III, has valuable information about the use of guiderail to protect slopes.
40
CHAPTER 9
CONCLUSION
After this research many problems were discovered such as potholes, corrugations, water lodging,
ruts ,erosion on the edge of the road as the result of inspection, practical checking of the whole road
and all areas surrounding the road. In order to maintain the life span and purpose of the road as
designing Road side drainage of adequate size and capacity, the discharge and all dimensions
produced can be used for the construction as it designed.Terefore we conclude our major project by
researching and knowing the major problems and thus understanding it.
41
Chapter 10
Learning and outcome
1. Learning how to work in professional environment.
2. Learning the technology
3. Punctuality,time evaluation,priority deciding
4. Helped in developing knowledege about the technology
5. Overcoming hurdles and meeting hurdles
6. Implementation of theoritical knowledge in practical.
7. I built my knowledge about tha drain construction and also able to make road side drains.

More Related Content

What's hot (20)

Sewer Appurtenances
Sewer AppurtenancesSewer Appurtenances
Sewer Appurtenances
 
Service Reservoirs 111001110634-phpapp02
Service Reservoirs 111001110634-phpapp02Service Reservoirs 111001110634-phpapp02
Service Reservoirs 111001110634-phpapp02
 
Hydraulic design of sewer
Hydraulic design of sewerHydraulic design of sewer
Hydraulic design of sewer
 
Spillways
SpillwaysSpillways
Spillways
 
Drainage design
Drainage designDrainage design
Drainage design
 
L 5and l-6 sewer design
L 5and l-6 sewer designL 5and l-6 sewer design
L 5and l-6 sewer design
 
presentation : cross drainage work
presentation : cross drainage workpresentation : cross drainage work
presentation : cross drainage work
 
Diversion Headworks
Diversion HeadworksDiversion Headworks
Diversion Headworks
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 
Sewer appurtenances
Sewer appurtenancesSewer appurtenances
Sewer appurtenances
 
Stilling basin
Stilling basinStilling basin
Stilling basin
 
Highway drainage
Highway drainageHighway drainage
Highway drainage
 
Storm drainage design
Storm drainage designStorm drainage design
Storm drainage design
 
Cross section of the canal, balancing depth and canal fsl
Cross section of the canal, balancing depth  and canal fslCross section of the canal, balancing depth  and canal fsl
Cross section of the canal, balancing depth and canal fsl
 
Earthen Dam
Earthen DamEarthen Dam
Earthen Dam
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
 
Spillway
Spillway Spillway
Spillway
 
Modes of failure earth dams
Modes of failure   earth damsModes of failure   earth dams
Modes of failure earth dams
 
Weirs on Permeable Foundations
Weirs on Permeable FoundationsWeirs on Permeable Foundations
Weirs on Permeable Foundations
 
river training work
river training workriver training work
river training work
 

Viewers also liked

Monthly cheklist inspection
Monthly cheklist inspectionMonthly cheklist inspection
Monthly cheklist inspectionVeton Sopjani
 
Self Inspection Checklist
Self Inspection ChecklistSelf Inspection Checklist
Self Inspection ChecklistKris Schade
 
Reasons for road failure
Reasons for road failureReasons for road failure
Reasons for road failureENGR HUMI Kakar
 
F3 Subsoil drainage and installation
F3 Subsoil drainage and installationF3 Subsoil drainage and installation
F3 Subsoil drainage and installationtoverwater
 
New techniques of erosion controls on hill roads[ a v shinde]
New techniques of erosion controls on hill roads[ a v shinde]New techniques of erosion controls on hill roads[ a v shinde]
New techniques of erosion controls on hill roads[ a v shinde]santosh212121
 
Validation of water
Validation of waterValidation of water
Validation of wateranilak123
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply systemceutics1315
 
The road to failure
The road to failureThe road to failure
The road to failureTarek Fahim
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failureNabaraj Poudel
 
DESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEMDESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEMNamitha M R
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a BuildingAroh Thombre
 
Plumbing in Architecture
Plumbing in ArchitecturePlumbing in Architecture
Plumbing in ArchitectureSneha Nagarajan
 
drainage class 9
drainage class 9drainage class 9
drainage class 9deepak190
 
Drainage system
Drainage systemDrainage system
Drainage systemNikhil Jp
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbingLiguidliguid
 

Viewers also liked (20)

Drainage
DrainageDrainage
Drainage
 
Monthly cheklist inspection
Monthly cheklist inspectionMonthly cheklist inspection
Monthly cheklist inspection
 
Self Inspection Checklist
Self Inspection ChecklistSelf Inspection Checklist
Self Inspection Checklist
 
Reasons for road failure
Reasons for road failureReasons for road failure
Reasons for road failure
 
F3 Subsoil drainage and installation
F3 Subsoil drainage and installationF3 Subsoil drainage and installation
F3 Subsoil drainage and installation
 
New techniques of erosion controls on hill roads[ a v shinde]
New techniques of erosion controls on hill roads[ a v shinde]New techniques of erosion controls on hill roads[ a v shinde]
New techniques of erosion controls on hill roads[ a v shinde]
 
Drainage
DrainageDrainage
Drainage
 
Validation of water
Validation of waterValidation of water
Validation of water
 
Validation of water supply system
Validation of water supply systemValidation of water supply system
Validation of water supply system
 
The road to failure
The road to failureThe road to failure
The road to failure
 
Flexible pavement failure
Flexible pavement failureFlexible pavement failure
Flexible pavement failure
 
DESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEMDESIGN OF SUBSURFACE DRAINAGE SYSTEM
DESIGN OF SUBSURFACE DRAINAGE SYSTEM
 
Retaining Walls
Retaining WallsRetaining Walls
Retaining Walls
 
Drainage System For a Building
Drainage System For a BuildingDrainage System For a Building
Drainage System For a Building
 
Plumbing in Architecture
Plumbing in ArchitecturePlumbing in Architecture
Plumbing in Architecture
 
House Drainage System
House Drainage SystemHouse Drainage System
House Drainage System
 
drainage class 9
drainage class 9drainage class 9
drainage class 9
 
Water distribution system
Water distribution systemWater distribution system
Water distribution system
 
Drainage system
Drainage systemDrainage system
Drainage system
 
Presentation plumbing
Presentation plumbingPresentation plumbing
Presentation plumbing
 

Similar to Water drainage

CTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxCTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxAnandBaratePatil
 
Synopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMSynopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMAbhinay Saraswat
 
Erosion control-handbook-for-local-roads by us dept of highway
Erosion control-handbook-for-local-roads by us dept of highwayErosion control-handbook-for-local-roads by us dept of highway
Erosion control-handbook-for-local-roads by us dept of highwayBhim Upadhyaya
 
INVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATE
INVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATEINVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATE
INVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATEIAEME Publication
 
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...SaurabhPawar76
 
Design manual-for-small-bridges
Design manual-for-small-bridgesDesign manual-for-small-bridges
Design manual-for-small-bridgesindranaths
 
IRJET- Evaluating Cost-Effective Railway Level Crossing Protection Systems
IRJET- Evaluating Cost-Effective Railway Level Crossing Protection SystemsIRJET- Evaluating Cost-Effective Railway Level Crossing Protection Systems
IRJET- Evaluating Cost-Effective Railway Level Crossing Protection SystemsIRJET Journal
 
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.pptQcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.pptanjali_02
 
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.pptQcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.pptnamita9553
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
IRJET- Evaluating Traffic Congestion and its Remedial Measures
IRJET-  	  Evaluating Traffic Congestion and its Remedial MeasuresIRJET-  	  Evaluating Traffic Congestion and its Remedial Measures
IRJET- Evaluating Traffic Congestion and its Remedial MeasuresIRJET Journal
 
Description of Lusaka sanitation-network
Description of Lusaka sanitation-network Description of Lusaka sanitation-network
Description of Lusaka sanitation-network Mwaba Kapema
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa Nisenson
 

Similar to Water drainage (20)

AN M.ENG PRESENTATION ON ROAD NETWORK
AN M.ENG PRESENTATION ON ROAD NETWORKAN M.ENG PRESENTATION ON ROAD NETWORK
AN M.ENG PRESENTATION ON ROAD NETWORK
 
CTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptxCTA110 Anand Barate-Patil seminar.pptx
CTA110 Anand Barate-Patil seminar.pptx
 
Synopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEMSynopsis ON ROAD DRAINAGE SYSTEM
Synopsis ON ROAD DRAINAGE SYSTEM
 
Erosion control-handbook-for-local-roads by us dept of highway
Erosion control-handbook-for-local-roads by us dept of highwayErosion control-handbook-for-local-roads by us dept of highway
Erosion control-handbook-for-local-roads by us dept of highway
 
MPW Drainage Manual.pdf
MPW Drainage Manual.pdfMPW Drainage Manual.pdf
MPW Drainage Manual.pdf
 
INVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATE
INVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATEINVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATE
INVESTIGATING SURFACE DRAINAGE PROBLEM OF ROADS IN KHARTOUM STATE
 
E sewage
E  sewageE  sewage
E sewage
 
TE PPT.pptx
TE PPT.pptxTE PPT.pptx
TE PPT.pptx
 
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
W.A.R.(waterabsorbingroad): New technique for road construction using permeab...
 
7 Types of Infrastructure.docx
7 Types of Infrastructure.docx7 Types of Infrastructure.docx
7 Types of Infrastructure.docx
 
Design manual-for-small-bridges
Design manual-for-small-bridgesDesign manual-for-small-bridges
Design manual-for-small-bridges
 
IRJET- Evaluating Cost-Effective Railway Level Crossing Protection Systems
IRJET- Evaluating Cost-Effective Railway Level Crossing Protection SystemsIRJET- Evaluating Cost-Effective Railway Level Crossing Protection Systems
IRJET- Evaluating Cost-Effective Railway Level Crossing Protection Systems
 
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.pptQcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
 
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.pptQcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
Qcl 14 v3_[pareto diagram]_[banasthali university]_[anjali}.ppt
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
IRJET- Evaluating Traffic Congestion and its Remedial Measures
IRJET-  	  Evaluating Traffic Congestion and its Remedial MeasuresIRJET-  	  Evaluating Traffic Congestion and its Remedial Measures
IRJET- Evaluating Traffic Congestion and its Remedial Measures
 
kochi Metro
kochi Metrokochi Metro
kochi Metro
 
Highway civil
Highway civilHighway civil
Highway civil
 
Description of Lusaka sanitation-network
Description of Lusaka sanitation-network Description of Lusaka sanitation-network
Description of Lusaka sanitation-network
 
Lisa stormcon presentation number one ieca
Lisa stormcon presentation number one iecaLisa stormcon presentation number one ieca
Lisa stormcon presentation number one ieca
 

Recently uploaded

Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 

Recently uploaded (20)

Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 

Water drainage

  • 1. 1 CHAPTER 1 ABOUT PWD 1.1 Introduction The Public Works Department has a glorious history in the development of the state since pre independence. The department is mainly entrusted with construction and maintenance of Roads, Bridges and Govt. buildings. The department also acts as Technical Advisor to the State Government. Initially, Irrigation, Public Health engineering were units of PWD. Subsequently these units were given separate entities to handle increased scope of work in the respective field. Since the inception of the Department, it has strived through its continuous quest for excellence and putting milestones in the feat of Engineering. It is this time that the Department is treading into a new era of information technology to keep pace with the modernization. The Public Works Department being the oldest engineering department of the State, has its well woven network even below tensile level which enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state 1.2 About Public Works Department The Public Works Department has a glorious history in the development of the state since pre independence. The department is mainly entrusted with construction and maintenance of Roads, Bridges and Govt. buildings. The department also acts as Technical Advisor to the State Government in these matters. Total road length being maintained by the department is more than 87500 KM the Department also maintains State buildings all over Rajasthan & outside. The current annual budget allocation to the department for construction & maintenance activities is over Rs 1000 Crores. The Public Works Department being the oldest engineering department of the State, has its well woven network even below tensile level which enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state.
  • 2. 2 Initially, Irrigation, Public Health engineering were units of PWD. Subsequently these units were given separate entities to handle increased scope of work in the respective field. Since the inception of the Department, it has strived through its continuous quest for excellence and putting milestones in the feat of Engineering. It is this time that the Department is treading into a new era of information technology to keep pace with the modernization. The Public Works Department being the oldest engineering department of the State, has its well woven network even below tensile level which enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state. 1.3 Agencies 1. Relief works in the event of Natural calamities like famine, flood, earthquakes et al. 2. D.R.D.A. Works like Employment Assurance Scheme (EAS) etc. 3. Assessments of rent of private premises requisitioned for housing Govt. offices. 4. Design, construction, maintenance and repairs of runway relating to the State Government. 5. Development and maintenance of Public Parks and Gardens in important Public Buildings. 6. Up keeping of Govt. Rest House and Circuit Houses.
  • 3. 3 7. To permit construction of approaches on both sides of roads to private individual, other institutions, factories, Petrol Pumps etc. 8. To evacuate the encroachment coming along the road sides. To evacuate the encroachment coming along the road sides. 9. Issue of certificates periodically to Cinema Houses about stability of structures/ arrangement related to electrical fittings conforming to Cinema Regulation Act. 10. Plantation of trees along both sides of the road.
  • 4. 4 CHAPTER 2 INTRODUCTION 2.1 Introduction Drainage is the process of interception and removal of water from over, and under the vicinity of the road surface. Drainage can be surface (where water is conveyed on the road surface and drainage channels), or subsurface (water flows underneath the pavement structure). Surface and subsurface drainage of roads critically affects their structural integrity, life and safety to users, and is thus important during highway design and construction. Road designs therefore have to provide efficient means for removal of this water; hence the need for road drainage designs. Drainage facilities are required to protect the road against damage from surface and sub surface water. Traffic safety is also important as poor drainage can result in dangerous conditions like hydroplaning. Poor drainage can also compromise the structural integrity and life of a pavement. Drainage systems combine various natural and man made facilities e.g. ditches, pipes, culverts, curbs to convey this water safely.
  • 5. 5 2.2 Aims ofdocument The purpose of this document is to provide guidance for road authorities and other relevant bodies in respect of road drainage. The document is not intended to be a comprehensive design manual for drainage for all new roads but concentrates on the design, rehabilitation and maintenance of drainage systems on regional and local roads. Some of the matters covered will also have applicability for national roads particularly national secondary roads). The document suggests some basic method sand approaches for drainage design and references other documents for the design of major new schemes and where more rigorous drainage analysis is required. 2.3 Importance ofdrainage It is essential that adequate provision is made for road drainage to ensure that a road pavement performs satisfactorily. The main functions of a road drainage system are: 1. To prevent flooding of the road and ponding on the road surface 2. To protect the bearing capacity of the pavement and the sub grade material 3. To avoid the erosion of side slopes The type of road drainage which is selected for a particular road will depend on such factors as to whether it is a rural or an urban road, or if it is in cut or fill and also on ground water conditions. Open drains are used to carry away surface water and can also pick up some subsoil water (depending on depth). 5 The survey indicated that existing road drainage systems use a mix of open drains, pipes and french drains depending on road circumstances. The maintenance of these systems is variable and in general most counties indicate reservations about the adequacy of current maintenance arrangements. The separate forms of drainage systems in common use are considered briefly in this review of current practice. 2.4 Open Drains Open drains are the most common form of road drainage on rural national and non national roads. Maintenance practice from the data available indicates various levelsof attention to the open drain system. Opening of drainage inlets and/or total removal of road margin, to ensure rapid removal of
  • 6. 6 road surface water, appears to be common practice. However, frequency of inlet opening is perceived to be inadequate in many circumstances. Open drains have the advantage of being easily inspected for blockages and are also effective at draining the road sub grade provided the drain flows to an adequate outfall. Open drains are generally, but not always, within the road limits. In circumstances where open drains are on private property the Authority’s powers under the Roads Act should be exercised to ensure that drain age is not interfered with. The review suggests that drains outside the road limits may not be receiving adequate attention. 2.5 French Drains French drains are used extensively on sections of the national network and to a limited extent on non- national roads. The drains generally include pipe work in conjunction with stone media. Maintenance levels are low and this may affect the long term performance. In most instances maintenance is carried out as problems manifest themselves, with few counties having an annual maintenance programme. 2.6 Piped Drainage Piped drainage systems are essential in urban areas and are also used in rural areas where space is limited. Piped systems can be sealed or open-jointed. The normal practice is to use sealed systems in urban areas and open-jointed systems in rural areas. Piped systems with gullies require regular maintenance and while in many instances these systems are cleaned annually the data received suggests that the frequency of maintenance is generally considered inadequate6
  • 7. 7 Chapter 3 Road 3.1 Introduction A road is a thoroughfare, route, or way on land between two places, which has been paved or otherwise improved to allow travel by some conveyance, including a horse, cart, or motor vehicle. Roads consist of one, or sometimes two, roadways (carriageways) each with one or more lanes and also any associated sidewalks (British English: pavement) and road verges. Roads that are available for use by the public may be referred to as public roads or highways. 3.2 Type of Road: FREEWAYS: Freeways have strict classification rules. 1. Multi-Lane, divided road 2. No cross traffic. 3. No stop lights (except for ramp meters). 4. No stop signs. 5. No parking. 6. No stopping (except for toll booths, freeway access metering) 7. Highest speed limits. (relative to region) 8. Some have minimum speed limits.
  • 8. 8 9. Limited access 3.3 MAJAOR HIGHWAYS: Purposely built as a major throughway. • Higher speeds. Speed limits should be near or equal to Interstate or Freeway speed limits in the same area. (typically within 10-20 Kmph) • Multiple lanes in each direction. • Separated directions of travel. • Turning traffic is typically limited to specified turn lanes or freeway style ramps to minimize obstructions to thru traffic. • Partially limited access with few minor streets intersecting with this road. Intersections are most often with primary roads or other highways.
  • 9. 9 3.4 MINOR HIGHWAYS: Minor Highways vary widely from large multi-lane roads with stoplights and higher speed limits, to small residential streets with stops signs. Some minor highways may zigzag thru an area with many turns on local streets. A Minor Highway thru the main street of a small town often retains focus on local access with pedestrian traffic and on street parking. A side street is a street that intersects a main street and ends there. It is generally of little importance to through traffic. Being the last mile of the road system, it generally carries little traffic. Common characteristics of a side street include low speed limits (usually not more than 30 mph or 50 km/h), curbside parking, and few or no painted line markings to display lanes. Intersections in urban or suburban areas are usually marked by stop signs, or occasionally yield signs in some suburban areas when intersecting other side streets. In rural areas, some intersections are uncontrolled. Most side streets are lined with residences. Occasionally, a place of worship or a school may be located on a side street, but in a residential area, it is rare to find any commercial development (this is often prohibited by local zoning laws, unless directly adjacent to a major street).
  • 10. 10 CHAPTER 4 DRAINAGE 4.1 Introduction Drainage is the natural or artificial removal of surface and sub-surface water from an area. Many agricultural soils need drainage to improve production or to manage water supplies. The civil engineer is responsible for drainage in construction projects. They set out from the plans all the roads, street gutters, drainage, culverts and sewers involved in construction operations. During the construction process he/she will set out all the necessary levels for each of the previously mentioned factors. Civil engineers and construction managers work alongside architects and supervisors, planners, quantity surveyors, the general workforce, as well as subcontractors. Typically, most jurisdictions have some body of drainage law to govern to what degree a landowner can alter the drainage from his parcel. 4.2 Types of drainage There are basically three types of drainage applied to highways that ; 1. Subsurface drainage 2. Surface drainage 3. Cross drainage 4.2.1 SUBSURFACE DRAINAGE Subsurface drainage is concerned with the interception and removal of water from within the pavement. Some of the sources of subsurface water include; infiltration through surface cracks, capillary rise from lower layers, seepage from the sides of the pavement to mention but a few. Application of side slopes on the road surface, installing of drainage beds in the pavement and use of transverse drains are some of the measures of effecting subsurface drainage.
  • 11. 11 When groundwater cannot be effectively removed or intercepted by surface drainage, subsurface drainage techniques are required. As discussed in previous sections of this workbook, if water is not removed from sub grade or pavement structures it may create instability, reduce load bearing capacity, increase the danger of frost action and create a safety hazard by freezing of the traveled surface. Field investigations carried out during the route reconnaissance and design stages may not always reveal sub drainage problems. These less obvious problems can be effectively dealt with during construction. Field investigations should be carried out during the wet season and may include soil and/or geologic studies, borings or trenches to locate groundwater, inspections of natural and cut slopes in the local area, and measurement of discharge when possible. Sites with potential slope stability problems should be more thoroughly evaluated. When groundwater tables approach the ground surface, such as in low, swampy areas, the gradeline should be placed high enough to keep water from being drawn up into the fill by capillary action. Whenever possible, well graded granular materials, such as coarse sand, should be used for fill construction. For a detailed discussion of grading requirements for filter materials the reader is referred to the Earth Manual published by the U.S. Department of the Interior (1974). Three types of sub drainage systems are commonly used: (1) Pipe underdrains. This system consists of perforated pipe placed at the bottom of a narrow trench and backfilled with a filter material such as coarse sand. It is generally used along the toes of cut or fill slopes. The trench should be below the groundwater surface and dug into a lower, more inpervious soil layer to intercept groundwater. The drains may be made of metal, concrete, clay, asbestos-cement, or bituminous fiber and should be 15 centimeters (6 inches) in diameter or larger. (2) Drilled drains. This system consists of perforated metal pipes placed in holes drilled into cut or fill slopes after construction. (3) French drains. This system consists of trenches backfilled with porous material, such as very coarse sand or gravel. This type of drain is apt to become clogged with fines and is not recommended.
  • 12. 12 A major difficulty in selecting a drainage system is the lack of adequate performance data for various drainage methods. A good knowledge of seasonal groundwater fluctuations, variation in lateral and vertical permeability, and the ratio of vertical to lateral permeability are critical. Long term monitoring of drainage performance is important in determining appropriate prescriptions for future installations. For example, perforated drains are commonly prescribed but often will not function properly as a result of clogging of pores with fines or from geochemical reactions leading to the formation of precipitates. Several methods may be used to prevent plugging depending on soil characteristics and material availability. The first is to enclose the perforated pipe with geotextile fabric. Second, surround the pipe with an open graded aggregate material, which in turn is surrounded by a fabric. The use of fabric eliminates the need for an inverted filter consisting of various sized gravel and sand layers. Third, if fabric is not available, surround the pipe with a graded aggregate filter. Although the cost of installing such a drainage system is high, it may effectively reduce final road costs by decreasing the depth of base rock needed, thereby reducing subgrade widths and associated costs for clearing, excavating, and maintenance. 4.2.2 SURFACE DRAINAGE Surface drainage deals with arrangements for quickly and effectively leading away the water that collects on the surface of the pavement, shoulders, slopes of embankments, cuts and the land adjoining the highway. Reducing the erosive power of water can achieved by reducing its velocity. If, for practical reasons, water velocity cannot be reduced, surfaces must be hardened or protected as much as possible to minimize erosion from high velocity flows. Road surface drainage attempts to remove the surface water before it accelerates to erosive velocities and/or infiltrates into the road prism destroying soil strength by increasing pore water pressures. This is especially true for unpaved, gravel, or dirt roads. The main source of surface water in most places is precipitation in form of rain. When precipitation falls on an area, some of the water infiltrates in to the ground while a considerable amount remains on top of the surface as surface run off. Dip locations are determined at the time the grade line is established on the ground or during vertical alignment design. The total length of the two vertical curves comprising the dip should be sufficient to allow the design vehicle to pass safely over them at the design speed. The minimum vertical distance between the crest and sag of the curves should be at least 30 cm (1 ft). It is important that the dip be constructed at a 30 degree or greater angle downgrade and that the dips have an adverse slope
  • 13. 13 on the downroad side. The downroad side of the dip should slope gently downward from the toe of the road cut to the shoulder of the fill. The discharge point of the dip should be armored with rock or equipped with a down-drain to prevent erosion of the fill. Equipment operators performing routine maintenance should be aware of the presence and function of the dips so that they are not inadvertently destroyed. MEASURES ADOPTED FOR SURFACE DRAINAGE 1. The proper cross slope should be provided for both to pavement and shoulders 2. The subgrade should be sufficiently above the highest level of ground water table or the natural ground level 3. Side drainage should have to be provided at edges of right-of-way where the road is in embankment and the edge of the roadway in cutting 4. On hill roads, water may flow towards the road depending on the slope and rainfall 5. Catch water drains should be provided to intercept the flow down. COLLECTION OF SURFACE WATER The water collected is lead into natural channels or artificial channels so that it does not interfere with the proper functioning of any part of the highway. Surface drainage must be provided to drain the precipitation away from the pavement structure. 4.2.2.1 CLASSIFICATIONOF SIDE DRAINAGE There are different types of road side drainage, classified according to the type of construction, which is as follows; Trapezoidal surface drainage A trapezoidal ditch is the most efficient hydraulically and should be used for ditches carrying a large amount of water. The flat bottom spreads out the flow and helps reduce erosion problems. They are more
  • 14. 14 difficult to construct, but the Soil and Water Conservation District and Natural Conservation Service can provide assistance. V-shaped lined surface drainage A V–shaped ditch is easy to construct, especially with a grader. However, the bottom of the V is prone to erosion and can be difficult to maintain. Urban surface drainage A U–shaped ditch is more efficient hydraulically and a good shape for erosion control. It can be built with an excavating machine and is easy to maintain. However, most U–shaped ditches in New York State are too steep on the road side of the ditch. Two ways to solve the problem are to cuff the break of the ditch and the shoulder with a grader or the excavator bucket, or curl the bucket back during the final pass to make a rounded shape.
  • 15. 15 4.2.3 CROSS DRAINAGE When stream have to cross a roadway or when water from a side drainage have to be diverted to water course across the roadway, then a cross drainage work such as culvert or small bridge is provided. On less important roads, in order to reduce the construction cost of drainage structures, sometimes submersible bridges or course way are constructed. During the flood the water will flow over the road. Cross drains are often needed to intercept the longitudinal, or down-road, flow of water in order to reduce and/or minimize surface erosion. In time, traffic will cause ruts to form, channeling surface water longitudinally down the road. REQUIREMENT OF HIGHWAY DRAINAGE SYSTEM 1. The surface water from the carriage way and shoulder should effectively be drained off without allowing it to percolate to sub grade 2. The surface water from the adjoining land should be prevented from entering the roadway. 3. The surface drainage should have sufficient capacity and longitudinal slope to carry away all the surface water collected.
  • 16. 16 4. Flow of surface water across the road and shoulders and along slopes should not cause formation of erosion.
  • 17. 17 CHAPTER 5 CULVERTS 5.1 Introduction Reducing the erosive power of water can achieved by reducing its velocity. If, for practical reasons, water velocity cannot be reduced, surfaces must be hardened or protected as much as possible to minimize erosion from high velocity flows. Road surface drainage attempts to remove the surface water before it accelerates to erosive velocities and/or infiltrates into the road prism destroying soil strength by increasing pore water pressures. This is especially true for unpaved, gravel, or dirt roads. A culvert helps move water under a road or driveway to a stream, lake, or detention basin. While culverts can, and have been, defined in many ways (such as any span under 20 feet), for drainage, a culvert is usually prefabricated and comes in standard sizes. In addition, a culvert is allowed to have the ends completely submerged. The first item we need to understand is the amount of flow a culvert will need to carry. Then we can look at the materials, installation, inspection, and maintenance. Water moves across the road surface laterally or longitudinally. Lateral drainage is achieved by crowning or by in- or out- sloping of road surfaces (Figure 79). Longitudinal water movement is intercepted by dips or cross drains. These drainage features become important on steep grades or on unpaved roads where ruts may channel water longitudinally on the road surface. • Hydrological analysis • Hydraulic analysis Runoff The first step in determining the size of a culvert (or other drainage structure, including ditches) is calculating the runoff or flow coming to a culvert. Several methods exist for determining the amount of flow. TR–55; the Soil Conservation Service’s Graphical method; the Bureau of Public Roads; the Rational method; and other methods are used to determine the amount of runoff. The Rational method, used for small watersheds, is useful to explain the concepts of runoff.
  • 18. 18 Runoff at a specific site is controlled by many factors including the intensity of precipitation, the area of the watershed, and the proportion of rainfall which gets to the culvert. Fig 5.1 Precipitation and runoff (hydrograph) 5.2 Hydrological analysis This deals mainly with precipitation and runoff in the area of interest. When rainfall, which is the main source of water, falls onto an area some of the water infiltrates into the soil while the remaining portion either evaporates or runs off. The portion that remains as runoff is the one of major importance in the design of surface drainage facilities. 5.3 Determination of runoff Runoff at a particular point is determined with respect to a given catchment area and depends on a number of factors such; type and condition of the soil in the catchment, kind and extent of vegetation or cultivation, length and steepness of the slopes and the developments on the area among others. The following formula known as the rational formula is used for calculation of runoff water for highway drainage. Q= 0.028CIA
  • 19. 19 Where: Q = maximum runoff in m3 per sec C = a constant depending upon the nature of the surface I = the critical intensity of storm in mm per hour occurring during the time of concentration. A = the catchment area in km2 5.4 Hydraulic Design Once the design runoff Q is determined, the next is the hydraulic design of drains. The side drainage and other structures are designed based on the principles of flow through open channels. If Q is the quantity of surface water (m3/sec) to be removed by a side drainage and V is allowable velocity of flow (m/s) on the side drainage, the area of cross section A of the channel (m2) is found from the relation below: Q=A.V The velocity of unlined channel must be high enough to prevent silting and it should not be too high as to cause erosion. The allowable velocity should be greater than one (1m/sec) for lined channel. The slope S of the longitudinal drain of known or assumed cross section and depth of flow ,may determined by using Manning’s formula for the design value of velocity of flow V, roughness coefficient n and hydraulic radius R. Manning’s Formula V=1/n*R2/3*S1/2 Where: V=Average velocity m/sec
  • 20. 20 n=Manning’s roughness coefficient R=Hydraulic radius S=Longitudinal slope of channel. Manning’s Roughness coefficient N= 0.02 for unlined ordinary ditches =0.05 to 0.1 for unlined ditches with heavy vegetation =0.013 for rough rubble =0.04 for stone riprap =0.015 for pipe culverts Hydraulic Radius = Cross sectional area Wetted perimeter 5.5 Time of concentration (t c) Time of concentration is that time required for water to travel all the way from catchments area to the designed element. The time taken by water to flow along the longitudinal drain is determined from the length of the longitudinal drain L the nearest cross drainage or a water course and allowable velocity of the flow V in the drain. T = V/L The total time for inlet flow and flow along the drain is taken as time of concentration or the design value of rain fall duration. T c = T1+ T2
  • 21. 21 Where, T1 = overland flow time in minutes T2 = channel flow time in minute T1 = [(0.885x L3)/H] 0.385 Where, L = the length of overland flow in km from critical point the mouth of the drain. H = total fall of level from the critical point to the mouth of the drain in meters. Note: From the rainfall intensity –duration- frequency curves the rainfall I is found in mm/sec. Corresponding to duration T and frequency of return period. The required depth of flow in the drain is calculated for convenient bottom width and side slope of drain. The actual depth of the open channel drain may be increased slightly to give a free body. The hydraulic mean radius of flow R is determined. The required longitudinal slope S of the drain is calculated using Manning formula adopting suitable value of roughness coefficient.
  • 22. 22
  • 23. 23 CHAPTER 6 ABOUT THE MATERIAL 6.1 Introduction Culvert pipes come in many materials, shapes, and sizes. Each material has its own characteristics and advantages. The four most common materials are corrugated metal pipe (CMP), plastic, concrete, and smooth steel. The pipes are generally thought of in two broad categories which correspond to the way they carry loads, rigid and flexible. Flexible pipe (CMP and plastic) gains strength by transferring some of the load into the surrounding soil. Imagine what would happen if you drove a fully loaded truck over a flexible pipe. It would crush. It gains strength from the surrounding soil when it flexes. Flexible pipes must be backfilled properly and have a minimum amount of cover or the loads do not build up in the soil and the pipe will fail. They are generally less expensive to place than rigid pipes but do not last as long. Coatings may increase their lifespan. Failure to bed the pipe carefully will shorten the life of the pipe and may cause premature failure. Rigid pipes (concrete, heavy steel, and masonry) are strong enough by themselves to carry all loads. The transferring of loads is of secondary benefit. They generally last longer than flexible pipes but are much more expensive to place. Cranes and larger equipment are usually needed to set them. 6.2 Corrugatedmetal pipe Sometimes referred to as CMP (corrugated metal pipe), metal pipe is the most common type of material used in culverts. The versatility of the pipe and the wide range of shapes and sizes available make it a very useful product. The base metal can be steel or aluminum. Coatings can be added to increase lifespan, reduce corrosion, and improve hydraulics (flow capacity). Steel is the most common metal used, but is usually galvanized for corrosion protection. The steel may be mixed or coated with an aluminum alloy which is more durable than galvanizing alone and does not increase the price significantly. Or, the pipe can be made of all aluminum. Care should be taken when installing an aluminum pipe, because it is easily damaged. Asphalt and concrete coatings are sometimes added for durability, improved flow characteristics, and resistance to wear from stream bed materials.
  • 24. 24 Metal pipes are manufactured in a variety of shapes as shown. Listed beside each are some of the reasons for using the different shapes. ROUND Easy and inexpensive to manufacture. Has a high flow capacity. Sizes up to 12 inches in diameter. 6.3 Plastic Plastic pipe, usually made of high density polyethylene (HDPE), is the fastest growing pipe in terms of use. It is easy to construct due to its light weight and is easy to maneuver and cut. It can be used in a variety of applications including lining existing pipes. It can be lined with a smooth section of plastic to increase flow capacity and improve strength. Plastic pipe is flammable and can be burned. The pipes are limited in size to about six feet and are uneconomical for many applications if more than four feet in diameter. New processes may provide more pipe types and sizes in the future. Plastic pipes only come in a round shape currently, up to 6 feet in diameter for smooth pipes, and 2 feet for corrugated pipes. Figure 7.1 - Pipe shapes (metal) 6.4 Concrete Concrete pipe comes in a variety of shapes and sizes. It can be pre–cast or cast–in–place and primarily used in deep fills or urban areas where construction costs are high. It is more expensive than plastic or metal pipe but is very durable and has a long life. Cranes and other heavy equipment are usually needed to place the pipe. Concrete pipes come in several shapes, but the most common are round and elliptical. Elliptical pipe may be vertical or horizontal in alignment. Concrete box culverts are some of the most common bridge and large culvert types built. 6.5 Heavy steel Solid steel pipe, sometimes made from old boilers, tank cars, or pipelines can be economical when available locally. It is usually very durable. However, the durability of the pipe is usually unknown
  • 25. 25 and the pipe can deteriorate quickly. The major problem, with steel culverts, however, is the joints. They need to be well built or failure at the joint can allow infiltration of fines and settlement at the surface. Steel pipes are usually round and come in limited sizes.
  • 26. 26 6.5 Durability Concrete pipe is the most durable with an expected life of 75 to 100 years. It is expensive to install, but in deep fills and urban areas (villages and cities) it is usually justified by comparing the cost of replacement to the amount of time between replacement. Solid steel is usually the next most durable. However, if you buy a used pipe, the lifespan may be very short. Plastic and corrugated metal are about the same in durability. Steel pipe is better able to handle bed loads and debris but is very susceptible to corrosion due to low pH water (acidic) which is found in the Southern Tier and parts of the Adirondacks. Other areas may have high alkalinity in the soil. In those areas, plastic pipe or lining of pipes may be necessary to keep pipe from corroding early. Plastic and corrugated metal pipes have a 25 to 50 year life if designed and built properly. Also, bed load can cause premature failure. Lining of existing pipes, or adding liners during construction may be useful. 6.6 SIZE AND CAPACITY How large of a pipe is needed? Several factors need to be considered. First let’s discuss the factors. Then we will bring all of the results together below. The flow capacity of a pipe is determined by several factors including the: • Area and shape of the opening of the pipe • Allowable head or amount of backwater • Kind of inlet • Culvert length and slope • Material used (roughness of the pipe) • Other factors including constrictions of flow due to debris, tailwater, or channel alignment 6.6.1 Area and shape of opening By far the most critical factor for determining capacity is the area of the opening of the pipe. The amount of flow that can go through a culvert is directly proportional to the area of the opening.
  • 27. 27 Doubling the area doubles the capacity of the pipe. An 18–inch diameter pipe has more than twice the capacity of a 12–inch diameter pipe because the area is more than twice as large. (18–inch diameter pipe area = 254 in 2 vs. 12–inch diameter pipe area = 113 in 2 ). 6.6.2 Allowable head or depth of water at the inlet The allowable head is the maximum depth of flow before either the road is overtopped by the water backed up at the culvert, or damage to the road or adjacent property is likely to occur. The overtopping does not have to be at the pipe. In many cases, the flow crosses the road downhill from the culvert due to natural alignments or planned changes in the roadway. Damage could be a washout of the roadway due to overflow or inundation of a building that is built lower than the roadway elevation. The greater the allowable depth, the more flow can be pushed through the pipe. Increases in the cover over a pipe (and therefore increases in allowable depth) can greatly increase the allowable flow in the pipe. Care must be taken to use existing allowable heads or increases in the height of the roadway. Lowering the pipe to get more cover does not work. The pipe will probably fill in with sediment and the area of the opening will be diminished, reducing the flow capacity by far more than the increase due to extra head.
  • 28. 28 CHAPTER 7 MATERIALS, SHAPES, and SIZES Culvert pipes come in many materials, shapes, and sizes. Each material has its own characteristics and advantages. The four most common materials are corrugated metal pipe (CMP), plastic, concrete, and smooth steel. The pipes are generally thought of in two broad categories which correspond to the way they carry loads, rigid and flexible. Flexible pipe (CMP and plastic) gains strength by transferring some of the load into the surrounding soil. Imagine what would happen if you drove a fully loaded truck over a flexible pipe. It would crush. It gains strength from the surrounding soil when it flexes. Flexible pipes must be backfilled properly and have a minimum amount of cover or the loads do not build up in the soil and the pipe will fail. They are generally less expensive to place than rigid pipes but do not last as long. Coatings may increase their lifespan. Failure to bed the pipe carefully will shorten the life of the pipe and may cause premature failure. Rigid pipes (concrete, heavy steel, and masonry) are strong enough by themselves to carry all loads. The transferring of loads is of secondary benefit. They generally last longer than flexible pipes but are much more expensive to place. Cranes and larger equipment are usually needed to set them. 7.1 Corrugatedmetal pipe Sometimes referred to as CMP (corrugated metal pipe), metal pipe is the most common type of material used in culverts. The versatility of the pipe and the wide range of shapes and sizes available make it a very useful product. The base metal can be steel or aluminum. Coatings can be added to increase lifespan, reduce corrosion, and improve hydraulics (flow capacity). Steel is the most common metal used, but is usually galvanized for corrosion protection. The steel may be mixed or coated with an aluminum alloy which is more durable than galvanizing alone and does not increase the price significantly. Or, the pipe can be made of all aluminum. Care should be taken when installing an aluminum pipe, because it is easily damaged. Asphalt and concrete coatings are sometimes added for durability, improved flow characteristics, and resistance to wear from stream bed materials.
  • 29. 29 7.2 Plastic Plastic pipe, usually made of high density polyethylene (HDPE), is the fastest growing pipe in terms of use. It is easy to construct due to its light weight and is easy to maneuver and cut. It can be used in a variety of applications including lining existing pipes. It can be lined with a smooth section of plastic to increase flow capacity and improve strength. Plastic pipe is flammable and can be burned. The pipes are limited in size to about six feet and are uneconomical for many applications if more than four feet in diameter. New processes may provide more pipe types and sizes in the future. Plastic pipes only come in a round shape currently, up to 6 feet in diameter for smooth pipes, and 2 feet for corrugated pipes. Figure 7.1 - Pipe shapes (plastic) Figure 7.2 - Pipe shapes (metal)
  • 30. 30 7.3 Concrete Concrete pipe comes in a variety of shapes and sizes. It can be pre–cast or cast–in–place and primarily used in deep fills or urban areas where construction costs are high. It is more expensive than plastic or metal pipe but is very durable and has a long life. Cranes and other heavy equipment are usually needed to place the pipe. Concrete pipes come in several shapes, but the most common are round and elliptical. Elliptical pipe may be vertical or horizontal in alignment. Concrete box culverts are some of the most common bridge and large culvert types built. 7.4 Heavy steel Solid steel pipe, sometimes made from old boilers, tank cars, or pipelines can be economical when available locally. It is usually very durable. However, the durability of the pipe is usually unknown and the pipe can deteriorate quickly. The major problem, with steel culverts, however, is the joints. They need to be well built or failure at the joint can allow infiltration of fines and settlement at the surface. Steel pipes are usually round and come in limited sizes. Figure 28 - Pipe shapes (steel)
  • 31. 31 7.5 Durability Concrete pipe is the most durable with an expected life of 75 to 100 years. It is expensive to install, but in deep fills and urban areas (villages and cities) it is usually justified by comparing the cost of replacement to the amount of time between replacements. Solid steel is usually the next most durable. However, if you buy a used pipe, the lifespan may be very short. Plastic and corrugated metal are about the same in durability. Steel pipe is better able to handle bed loads and debris but is very susceptible to corrosion due to low pH water (acidic) which is found in the Southern Tier and parts of the Adirondacks. Other areas may have high alkalinity in the soil. In those areas, plastic pipe or lining of pipes may be necessary to keep pipe from corroding early. Plastic and corrugated metal pipes have a 25 to 50 year life if designed and built properly. Also, bed load can cause premature failure. Lining of existing pipes, or adding liners during construction may be useful.
  • 32. 32 7.6 SIZE AND CAPACITY How large of a pipe is needed? Several factors need to be considered. First let’s discuss the factors. Then we will bring all of the results together below. The flow capacity of a pipe is determined by several factors including the: 1. Area and shape of the opening of the pipe 2. Allowable head or amount of backwater 3. Kind of inlet 4. Culvert length and slope 5. Material used (roughness of the pipe) 7.6.1 Area and shape of opening By far the most critical factor for determining capacity is the area of the opening of the pipe. The amount of flow that can go through a culvert is directly proportional to the area of the opening. Doubling the area doubles the capacity of the pipe. An 18–inch diameter pipe has more than twice the capacity of a 12–inch diameter pipe because the area is more than twice as large. (18–inch diameter pipe area = 254 in 2 vs. 12–inch diameter pipe area = 113 in 2 ). Figure 7.4 - Factors determining flow capacity of a pipe 7.6.2 Allowable head or depth of waterat the inlet The allowable head is the maximum depth of flow before either the road is overtopped by the water backed up at the culvert, or damage to the road or adjacent property is likely to occur. The overtopping does not have to be at the pipe. In many cases, the flow crosses the road downhill from the culvert due to
  • 33. 33 natural alignments or planned changes in the roadway. Damage could be a washout of the roadway due to overflow or inundation of a building that is built lower than the roadway elevation. The greater the allowable depth, the more flow can be pushed through the pipe. Increases in the cover over a pipe (and therefore increases in allowable depth) can greatly increase the allowable flow in the pipe. Care must be taken to use existing allowable heads or increases in the height of the roadway. Lowering the pipe to get more cover does not work. The pipe will probably fill in with sediment and the area of the opening will be diminished, reducing the flow capacity by far more than the increase due to extra head. Figure 7.5 - Shape of openings
  • 34. 34 7.6.3 Kind of inlet The most common inlet (and outlet) type is the projecting pipe. Small increases in the capacity can be gained by using the mitered or headwall inlet. Also, use of special ends on both the upstream and downstream side can reduce scour, improve appearance, and make maintenance easier. The extra capacity in a culvert due to use of inlets is anywhere from no increase to 10 percent increase in the flow capacity. Most commonly, inlets are placed to improve characteristics other than flow. Mitering the pipe to fit the slope makes the slope safer for errant vehicles and is easier to maintain. However, the ends are susceptible to failure if the ends are not anchored properly. A set of #8 rebars placed on a one–foot grid over the opening allows the highway department to eliminate the use of guiderail. The bars help keep debris out of the pipe. Care must be taken to leave an opening below the grate to allow the majority of the flow through the pipe or plugging can occur and damage the pipe. Special ends can be purchased to attach to the ends of most round pipes. The price can be very high for larger pipes, but the ends protect against scour, have good appearances, and can be protected by a rebar grate in the same way a metered end is protected. In addition, if there is a need to extend the pipe in the future, the end can be removed, a new section of pipe added to the first section, and the end replaced. Figure 7.6 - Inlet (outlet) designs (projecting, mitered, and headwall)
  • 35. 35 Headwalls are usually used with high flows, major alignment changes near the openings which cause heavy scour, and deeper pipes which warrant more expensive protection. The headwalls can be made on concrete, precast concrete and masonry, gabion baskets, plastic, and timber. Concrete is more expensive, but fits the opening better and reduces the chances of piping. Gabion baskets are fairly labor intensive, but can be shaped to fit the pipe. Masonry and precast concrete do not fit the pipe and usually some grout or concrete must be placed around the opening to get a good fit. Timber and other items (tires, sandbags) are not as effective due to shorter life spans and uncertainty about durability. 7.6.4 Culvert length and slope For most small culverts (60 feet or less) the capacity of the pipe is not affected by the slope. The opening of the pipe will control the amount of water that can get into the pipe. Increasing the slope will increase the velocity of the flow but the capacity will NOT increase. For culverts of more than 60 feet, the slope and length do make a difference but usually only at very flat slopes (1 percent or less [3 inches per 20–foot section of pipe]). In fact, increasing the slope beyond 2 percent (5 inches per section of pipe) can actually cause problems due to increases in velocity of the water leaving the pipe. 7.4.5 Materialused Concrete, steel, and smooth plastic may have slightly more capacity than corrugated pipes. However, this is only true for pipes that are fairly long and flat. In most cases, the selection of the material to be used is a function of cost, availability, ease of construction, maintenance, and longevity. In many cases, the smoother pipes are used at flat slopes because they are less likely to fill with sediment and plug. However, use of smooth pipes on steep slopes can actually cause erosion and other problems. Figure 7.6 - Corrugated pipe special end section
  • 36. 36 CHAPTER 8 SLOPES AND EROSION CONTROL 8.1 HOW TO STOP EROSION Stopping erosion is difficult. Keeping erosion from occurring in the first place is usually more successful. Many of the maintenance activities performed on roads and streets would be unnecessary if erosion was controlled. As an example, stopping erosion from occurring at the top of a hill will reduce the ditching at the bottom of the hill. Approximately 30 tons of material can be eroded from a mile of ditches before you can see the damage! To remove and replace 30 tons of material is a lot of work. Also, you need to be concerned about erosion during construction and maintenance work. The work can cause additional erosion. 8.2 TYPES OF EROSION Three types of erosion are common: surface, rill, and galley. Different soils erode differently. For most highway materials you can be sure of two things. One, unprotected materials will erode and cause sedimentation. Two, the flatter the slope the fewer erosion problems occur. • Surface Surface or sheet erosion occurs when rainfall dislodges soil on the surface of material, and the water plus soil flows in sheets. The washing of shoulders is often started by this process. • Rill Rill erosion occurs when the velocity of the flow is great enough to dislodge soil in addition to that dislodged by rainfall. Rill erosion is typified by the narrow little channels that form in banks and slopes that are not protected from erosion. • Gully Gully erosion occurs when rill erosion combines and concentrates the flow of runoff into gullies. Washouts between pavement and shoulders are usually gully erosion.
  • 37. 37 8.3 SEDIMENTATION All of the material removed by erosion is deposited at some location downstream from the erosion. This process of sedimentation usually occurs where a change in the speed of the flow occurs. Filling of culverts, ditches, streambeds, and even lakes is a result of sedimentation. Stopping erosion will eliminate or reduce many of the problems associated with poor drainage. 8.4 SLOPES Even very flat ground erodes. The reason you do not notice the erosion is that sedimentation occurs at the same location as the erosion. Steep terrain erodes very quickly. You need to reduce erosion problems. In addition, for slopes you have to be concerned about three factors: stability, safety, and maintenance. Figure 9.2 - Slopes
  • 38. 38 8.4.1 Stability Most highway materials are stable at slopes of 1:2 or flatter. Slopes steeper than 1:2 are more prone to erosion and washouts. If saturated, the entire slope may fail. 8.4.2 Safety Slopes along the edge of roads, including ditches and banks, need to be kept fairly flat to allow errant vehicles a safe place to drive. Slopes of 1:3 or flatter are considered safe. If the slope is less than 3 feet high a 1:2 slope is acceptable. More information on roadside safety can be found in the Cornell Local Roads Program’s manual. 8.4.3 Maintenance Mowing slopes is the most common maintenance technique. If slopes are 1:2 or flatter, the mowing crews can easily mow the slope. Minor repairs may be needed to fix small washouts and erosion. 8.4.4 Options If a slope is too steep, several items need to be examined to repair the problem: • Stabilize Unstable slopes can be stabilized by use of geotextiles or other earth reinforcement materials. If you have a high steep slope that is showing signs of distress, GET HELP. • Retaining walls Use of gabions, concrete, and block retaining walls may be needed on very steep slopes or to help stabilize the toe of an existing slope. If a slope is so steep the erosion mitigations listed below will not work, a retaining wall may be needed. GET HELP to determine the best course of action. • Signing Slopes steeper than 1:3 (1:2 for 3 or fewer feet in height) need to be protected. As a minimum, signs should be used to delineate the slope and warn motorists of the hazard. See Chapter 17B New York Code of Rules and Regulations (NYCRR) for future information.
  • 39. 39 • Guiderail Guiderail should be used on steep slopes. It needs to be installed and used correctly as part of an overall plan to upgrade the roads. The NYSDOT publication, Guiderail III, has valuable information about the use of guiderail to protect slopes.
  • 40. 40 CHAPTER 9 CONCLUSION After this research many problems were discovered such as potholes, corrugations, water lodging, ruts ,erosion on the edge of the road as the result of inspection, practical checking of the whole road and all areas surrounding the road. In order to maintain the life span and purpose of the road as designing Road side drainage of adequate size and capacity, the discharge and all dimensions produced can be used for the construction as it designed.Terefore we conclude our major project by researching and knowing the major problems and thus understanding it.
  • 41. 41 Chapter 10 Learning and outcome 1. Learning how to work in professional environment. 2. Learning the technology 3. Punctuality,time evaluation,priority deciding 4. Helped in developing knowledege about the technology 5. Overcoming hurdles and meeting hurdles 6. Implementation of theoritical knowledge in practical. 7. I built my knowledge about tha drain construction and also able to make road side drains.