SlideShare a Scribd company logo
1 of 40
Download to read offline
Introduction to Planning & Scheduling
Project Controls Expo, 9/10 Nov – London UK
About the Author
Anil Godhawale,
Anil Godhawale is Director of ProjCon Consultants and Founder of 
ProjectControlsOnline.com. Anil has over 14 years of international field and home office 
experience in Project Planning & Scheduling, Cost Engineering, EVA, Risk and Delay Claims 
Analysis with project values ranging from $10M to $1.5B. Anil has a strong Project 
Controls background &  has worked in all phases of projects  in various sectors that 
includes Petroleum & Chemicals, LNG regasification & liquefaction facilities, CCU’s
(Carbon Capture Units), Power Projects and Pipelines.
Anil is also very active with industry professional associations as fellow at ACostE, UK and 
member of AACEi, USA since last decade. He also contributed to CIOB, UK as member of 
TDWG to develop guidelines for accreditation in Time Management. Anil also holds 
distinguished Project Controls Certifications CCE & PSP from AACEI, USA and is a 
registered member (IEng) of Engineering Council UK. Find out more about Anil and his 
contribution to industry by visiting www.linkedin.com/in/godhawale
Question...
What is the difference between planning and scheduling?
What is Planning...
Making decisions with the objective of influencing the 
future:
What tasks will be performed?
How tasks will be performed?
Who will perform the tasks?
What is Scheduling....
Determination of timing of events in the Project:
When tasks will be performed
In what sequence the tasks will be performed?
Reflection of plan
Food for thought..
If PLANNING is an Art form based on Experience and 
knowledge then, SCHEDULING is a Systematic exercise 
in using applied Logic.
Plan
Schedule
Kick
Off
Plan
List
Activities
Check
Scope
Estimated
Duration
Logic
Sequence
Resultant
Schedule
Check with
Project Criteria
Resource
Load
Sanity
Check
Adjust/Modify
Get Buy‐in
Project
Review
Modify and
Issue
What
How
Who When
Why
Project Controls Principles
Planning
Level of Detail Essential for Planning
Sufficient to communicate the method of work execution.
Do not duplicate level of detail contained in supporting 
documents.
Expanded level of detail in potential problem areas.
Planning ‐ Top down or bottom up?
Top‐down is the most logical way of thinking about a project and is 
usually the best approach to new endeavours. It provides an early 
high‐level plan, including initial costs and timings, which can be used 
in the project's definition and benefit case.
Bottom‐up planning makes sense where we already have a good 
example of a successful similar project plan to base the new project 
on. A majority of projects will be similar to something that has been 
done before and it makes sense to use that as a starting point 
(assuming it was of good quality). As well as saving time in the
planning process, this allows us to learn lessons from the previous 
experiences. In particular, estimates can often be extrapolated from 
the previous projects.
Components/Elements of Plan
Scope of Work ..................... Work Breakdown Structure
Method of Execution ......….  Project Execution Plan
Project Budget ..................... Usage of Resources
Time Objectives ................... Project Milestones
Requirements for building a Plan
Scope Definition
Execution strategy
Identifying / Defining the activities & milestones necessary
Be Creative
Be Flexible
Level of  detail
Discipline integration
Questions the Scheduler Asks
What tasks will be performed? (Scope)
How will the tasks be performed? (Execution Plan)
What is the sequence in which the tasks will be performed?  
(Execution Plan & Resources)
Who will perform the tasks?  (Resources & Execution Plan)
Where is the equipment list, is there any exotic material used? 
(Scope & Execution Plan)
How many s/c’s do we plan to use? (Execution Plan & Resources)
What Permits are required and who is responsible for them? 
(Scope & Execution Plan)
Where is the Project to be executed?  (Scope, Execution Plan & 
Resources)
Planning Term: WBS
A WBS (Work Breakdown Structure) is the top down 
logical structuring of project work that defines and 
displays all of the work to be performed in 
accomplishing the project objectives.
A WBS (Work Breakdown Structure) is the top down 
logical structuring of project work that defines and 
displays all of the work to be performed in 
accomplishing the project objectives.
Importance of WBS
Avoids omission of key project activities through a systematic planning 
process.
Removes the complexity of the project by dividing it into manageable units.
Provides a framework for...
Defining specific tasks within a project from which schedules can be 
developed
Linking activities with resources
Facilitating communication
Integrating  project plans (schedule, resources, cost)
Key Terms : Network Diagram
Network Diagram : 
A graphic display of schedule activities and predecessors 
which aid project planning by showing the logical 
relationships of activities, one to another. It forces the 
user to define and plan the work in detail from start to  
finish. Permits early identification of potential  
problems. Reveals how much the responsible supervisor 
understands about the project and discloses how much 
the scheduler understands about the process.
Network Diagram. Contd..
Project Controls Principles
Scheduling
Depicts the Scope of work 
Improves the probability for the project team to meet its goals.
Establishes overall schedule parameters.
Aids in determining staffing requirements.
Resource loading basis.
Identifies long lead items.
Act as Communication tool
Identifies Phases of Project i.e., E, P, C
Importance of Schedule
Scheduling Terms
Activity : 
The Basic element into which a project is subdivided for scheduling a 
network.
‐ Has a definable start and finish 
‐ Consumes time (Exclusion is milestones and hammocks)
‐ Is assignable
‐ Consumes resources
‐ Is measurable
‐ Is defined by a Work Package for Engineering
‐ Is a Physical Task for Construction 
Scheduling Terms
Work Package : 
A group or number of Engineering Deliverables that will enable 
Procurement or Construction to accomplish a meaningful task.
i.e.   All of the Data Sheets & Specifications required for a 
Purchase Order.
i.e.   All of the Drawings & Details necessary to Locate, Excavate, 
Form and Pour a Foundation
Scheduling Terms
Milestone : 
Is a GOAL to be achieved.
Can be either a Start or Finish Achievement
Is a single point in Time
Has no duration
Has no resources 
Has a specific and unique Definition
It is either YES or NO 
Scheduling Terms
Predecessor & Successor: 
Predecessor : 
An activity that must occur before another activity.  
A predecessor activity controls the start or finish date of its successor 
(s).  An activity can have multiple predecessors, each with a different 
relationship to it.
Successor : 
An activity that must occur after the start or finish of predecessor 
activity.   
An activity can have multiple successors, each with a different 
relationship to it.
Scheduling Terms
Relationships  (Logic): 
There are four types of Relationships:
Finish to Start ‐ FS ‐ A relationship in which the predecessor activity 
must Finish before its successor activity can Start.
Start to Start ‐ SS  ‐ A relationship in which the Start of the  
predecessor activity controls the Start of a successor activity.
Finish to Finish ‐ FF  ‐ A relationship in which the Finish of a successor 
activity depends on the Finish of its predecessor activity.
Start to Finish ‐ SF  ‐ A relationship in which the Start of the 
predecessor activity controls the Finish of a successor activity
Scheduling Terms
Lag : 
An offset or delay from an activity to its successor.  Lag can be positive 
or negative.
Total Float:
The amount of time the start or finish of an activity can be delayed 
without affecting the project finish date. Please note TF can also drive 
toward an intermediate milestone, not just project completion so if 
there is a delay in intermediate milestone, it does not mean project is 
delayed.
Free Float:
The amount of time than that the early start/finish of an activity can be 
delayed without delaying the early start/finish of a successor activity.
Scheduling Terms
Critical Path: 
‐ One or more continuous chains of zero or negative float activities running 
from the start event to the finish event in the schedule. This does not mean 
project can never be ahead of schedule and show positive TF.
‐The sequence of activities that must be completed on schedule for the entire 
project to be completed on schedule. Theoretically, this is the longest duration 
path through the work‐plan. If an activity on the critical path is delayed by one 
day, then entire project will be delayed by one day (unless another activity on 
the critical path can be accelerated by one day). Please note critical path may 
not be the longest path, if the schedule contains more than one or two start 
constraints. In such scenario, least float can be considered. 
‐ Any activity on the critical path is called a Critical Activity.
Common Scheduling failures
1. Lack of buy‐in by all project team members
2. Lack of PLANNING
3. Poorly defined activities
4. Inappropriate scheduling detail
5. Inadequate or inappropriate logic ties
6. Poor duration estimating
7. Lack of information
8. Failure to disseminate the proper information to all parties
9. Lack of Sufficient Funding
10. Lack of adequate consideration of resources, and work conditions
Milestone Summary Schedule – Level 1
Project Intermediate Schedules – Level 2 
Details – Level 3/4
Hierarchy of Schedules
Level 1 ‐ Milestone Summary Schedule
Level 1 is the first schedule produced to give a overall picture in 
summarized format. 
Independently produced; not electronic roll up
Comprises a select mix of activities and WBS levels
Used to depict overall plan for execution of the Project and  highlight 
significant or critical events
Level 2 ‐ Intermediate Schedule
Engineering
Summarized by Discipline
Depicts overall timeframes
Procurement
Highlights ‘long lead’ items
Critical items
‘Bulk’ procurement
Construction/Installation/Cutover 
Summarized by discipline  grouped by area
Depicts overall timeframes
Level 3 ‐ EPC Schedule
ENGINEERING ‐ Sorts by: WBS
Discipline / Craft
Facility/Area/Work and/or Grouped by Systems
Depicts Facility/Area Relationships and Time frames
Depicts system requirements 
PROCUREMENT 
Identifies Demands by Facility/Area or Systems
Identifies Major Equipment Delivery by Tag number 
CONSTRUCTION/ STARTUP
Facility/Area and/or Grouped by Systems
Depicts Area Relationships and Time frames 
Level 4 – Working Schedules
ENGINEERING –
Broken down by discipline and work activity (Drawing, Spec., Data Sheet, etc). 
PROCUREMENT –
Identifies Equipment & bulk releases along with Vendor drawing deliverables 
by purchase order.
CONSTRUCTION –
Depicts Construction by Work Package/Area/Facility/ Craft/Crew. Establishes 
Construction Sequence
CPM (Critical Path Method) Scheduling
Definition of CPM :
The calculation of the earliest and latest start and finish dates of activities 
based on their durations and relationships to other activities.
CPM Calculation
Early dates indicate the earliest start and finish dates when an activity can be 
performed if all preceding activities have been completed (Forward Pass). 
Late start and finish dates are the latest dates an activity can be performed 
without delaying the project (Backward Pass).
A computer is suited to handle the numerous calculations of a forward pass and 
backward pass.
Overview of Total Float
Total Float identifies the extent to which any activity can be delayed 
without negatively impacting downstream deadlines.  Please note float 
could be positive as well. 
Negative Float : Amount of time that the start or finish of any activity 
exceeds the time allowed.
NOTE: Total Float is determined during Critical Path Analysis (CPA) and 
it is not a “product” of CPA.
Float Types
Total Float :  Amount of time an activity can exceed its early finish date 
without affecting the project end date or other imposed dates.
Free Float : Amount of time by which an activity can delay its early start 
or early finish date without affecting the early start or early finish date 
of any successor.
Float Responsibility
Float is owned by the Project ‐ According to FIDIC conditions of contract, the 
contractor develop the contract schedule but there is a liberty to the client to 
accept or reject it and ask the contractor to amend accordingly.
Once the Baseline Schedule is accepted by the Owner, then it becomes 
contractually binding on both parties.
The float on any activity is not there exclusively for the people on that activity 
to use.  It is to be shared by all activities along the same path … before and 
after.
Said differently, Float on an activity does not confer any right to delay an 
activity – to dip into the float.
Disadvantages of displaying total float
End user may delay start of activity thinking there is slack time
May cause false sense of security
Once used as an activity ‐‐ it’s gone … for all parties
Assumes CPM is complete with correct logic
Disadvantages of NOT 
displaying total float
End user may work on low priority items
Too much emphasis on non‐critical activities
May consume resources on non‐critical activities
Precludes line supervisor’s opportunity to efficiently manage the work
Questions & Additional info
Thanks for attending this session on Planning & 
Scheduling. 
If you like this presentation and wish to attend our full 
classroom course, please visit www.ProjCon.co.uk . 
You can also find all our modules in elearning (video) 
format at www.ProjectControlsOnline.com

More Related Content

Viewers also liked

Viewers also liked (6)

Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
Project Controls Expo 18th Nov 2014 - "Cost Estimate Risk Analysis: For Capit...
 
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
Project Controls Expo, 18th Nov 2014 - "Schedule Risk Analysis for Complex Pr...
 
Project Controls Expo 09/10 Nov London 2011 - An introduction to project cont...
Project Controls Expo 09/10 Nov London 2011 - An introduction to project cont...Project Controls Expo 09/10 Nov London 2011 - An introduction to project cont...
Project Controls Expo 09/10 Nov London 2011 - An introduction to project cont...
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 

Similar to Project Controls Expo, 9/10 Nov, London UK - Introduction to Planning & Scheduling By Anil Godhawale

Green Building Design, Engineering and Commissioning
Green Building Design, Engineering and CommissioningGreen Building Design, Engineering and Commissioning
Green Building Design, Engineering and Commissioning
Kevin Sullivan
 
Updated CV 29th August 2016 Costa Tsemtsidis
Updated CV 29th August 2016 Costa TsemtsidisUpdated CV 29th August 2016 Costa Tsemtsidis
Updated CV 29th August 2016 Costa Tsemtsidis
Costa Tsemtsidis
 
KHALED CV
KHALED CVKHALED CV
KHALED CV
Khaled El-Gohary
 
Neutral Services Resume
Neutral Services ResumeNeutral Services Resume
Neutral Services Resume
Ron Leaders
 
Bryan Butler Resume B
Bryan Butler Resume BBryan Butler Resume B
Bryan Butler Resume B
Bryan Butler
 
Bryan Butler Resume A1
Bryan Butler Resume A1Bryan Butler Resume A1
Bryan Butler Resume A1
Bryan Butler
 

Similar to Project Controls Expo, 9/10 Nov, London UK - Introduction to Planning & Scheduling By Anil Godhawale (20)

TVD Workshop - Boise
TVD Workshop - BoiseTVD Workshop - Boise
TVD Workshop - Boise
 
Green Building Design, Engineering and Commissioning
Green Building Design, Engineering and CommissioningGreen Building Design, Engineering and Commissioning
Green Building Design, Engineering and Commissioning
 
Accomplishments - 2015
Accomplishments - 2015Accomplishments - 2015
Accomplishments - 2015
 
Article for CCI Newspaper
Article for CCI NewspaperArticle for CCI Newspaper
Article for CCI Newspaper
 
Roadmap for CCS Demonstration and Deployment for the People's Republic of China
Roadmap for CCS Demonstration and Deployment for the People's Republic of ChinaRoadmap for CCS Demonstration and Deployment for the People's Republic of China
Roadmap for CCS Demonstration and Deployment for the People's Republic of China
 
Updated CV 29th August 2016 Costa Tsemtsidis
Updated CV 29th August 2016 Costa TsemtsidisUpdated CV 29th August 2016 Costa Tsemtsidis
Updated CV 29th August 2016 Costa Tsemtsidis
 
EVI Profile 2011
EVI Profile 2011EVI Profile 2011
EVI Profile 2011
 
KHALED CV
KHALED CVKHALED CV
KHALED CV
 
Neutral Services Resume
Neutral Services ResumeNeutral Services Resume
Neutral Services Resume
 
Cbh the domo_co.pptx
Cbh the domo_co.pptxCbh the domo_co.pptx
Cbh the domo_co.pptx
 
FS CV 2016
FS CV 2016FS CV 2016
FS CV 2016
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
 
Lean new product and process development
Lean new product and process developmentLean new product and process development
Lean new product and process development
 
CPC_PROFILE_COMPLETE
CPC_PROFILE_COMPLETECPC_PROFILE_COMPLETE
CPC_PROFILE_COMPLETE
 
Bryan Butler Resume B
Bryan Butler Resume BBryan Butler Resume B
Bryan Butler Resume B
 
Bryan Butler Resume A1
Bryan Butler Resume A1Bryan Butler Resume A1
Bryan Butler Resume A1
 
Sustainability Seminar Series By Scott Boutwell Oct08
Sustainability Seminar Series By Scott Boutwell Oct08Sustainability Seminar Series By Scott Boutwell Oct08
Sustainability Seminar Series By Scott Boutwell Oct08
 
Project Controls Expo 09/10 Nov London 2011 - "Schedule Maturity" By Terry Ho...
Project Controls Expo 09/10 Nov London 2011 - "Schedule Maturity" By Terry Ho...Project Controls Expo 09/10 Nov London 2011 - "Schedule Maturity" By Terry Ho...
Project Controls Expo 09/10 Nov London 2011 - "Schedule Maturity" By Terry Ho...
 
Paolo CV Jan 2016
Paolo CV Jan 2016Paolo CV Jan 2016
Paolo CV Jan 2016
 
Lean Construction - Approach Capable of Dealing with Complexity and Uncertainty
Lean Construction - Approach Capable of Dealing with Complexity and UncertaintyLean Construction - Approach Capable of Dealing with Complexity and Uncertainty
Lean Construction - Approach Capable of Dealing with Complexity and Uncertainty
 

More from Project Controls Expo

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Project Controls Expo, 9/10 Nov, London UK - Introduction to Planning & Scheduling By Anil Godhawale