SlideShare a Scribd company logo
1 of 89
Download to read offline
Copyright @ 2011. All rights reserved
Delay Claims and Analysis Based on FIDIC
Forms of Contract
Project Controls Expo – 13th Oct 2015
Emirates Stadium, London
Copyright @ 2011. All rights reserved
About the Speaker
Ewen Maclean, Eur Ing MEng (Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
Director, Berkeley Research Group
Ewen is an experienced expert in the field of programming; delay and disruption; and associated
prolongation costs in relation to construction and engineering projects. In particular, he has worked for
both international consultants and contractors and has first-hand experience of assisting and representing
clients in litigation, arbitration, mediation and adjudication, both for the claimant and respondent. He has
prepared numerous expert witness reports; drafted standard forms of contract and lectured on various
commercial and contractual subjects within the construction industry. Ewen has also acted in commercial
negotiations and settlements, resolving potential disputes as well as providing advice on contract
procurement.
Ewen is well versed in many of the standard forms of construction contract including the NEC, JCT, ICE,
FIDIC, GC Works Conditions as well as bespoke forms of contracts including PFI contracts and has worked on
contracts that span, inter alia, major building, civil engineering, oil and gas, energy, mechanical and
electrical, pharmaceutical, infrastructure including highways and rail as well as fit-out works.
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Structure
1. What Do We Mean by Delay and Disruption?
2. Definitions in Delay and Disruption Analysis
3. Delay Analysis and its Methodologies
4. FIDIC Claims and Extension of Time Provisions
5. Scenario - Delay Analysis In Action
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
1. What Do We Mean By Delay and
Disruption?
 Delay
 Delay to completion which is a delay which will cause a
contract completion date not to be met.
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Delay and its consequences
 Contractor liable to employer for liquidated damages
 Contractor incurs cost of maintaining resources and site establishment for longer
 Employer may suffer from loss of revenue & negative publicity
 Delay to completion
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
What Do We Mean By Delay and Disruption?
 Disruption
 Delay to progress which is a delay which will merely cause
delay to the Contractor’s progress without causing a contract
completion date not to be met.
 Disruption (as distinct from delay) is disturbance, hindrance or
interruption to a Contractor’s normal working methods,
resulting in lower efficiency. If caused by the Employer, it may
give rise to a right to compensation either under the contract or
as a breach of contract.
(SCL Delay and Disruption Protocol at page 9)
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Delay and its Consequences
 Disturbance of regular progress of the work
 Non-critical delay
 Additional costs associated with local disturbance to progress
 Delay to progress
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Types of Delay and Purpose of Extension of
Time Clause
 Types of delay
 Employer default / responsibility
 Contractor default / responsibility
 “Neutral” cause
 Purpose of EOT clause:
 Risk allocation
 Common EOT clause: any cause for which E responsible
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Employer’s cause
Delay
= EoT and money
Employer Delay
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Contractor’s cause
Delay
= No EoT and no money
Contractor Delay
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Concurrency
 Both events must be effective causes of delay to critical path
EoT but, no prolongation money
Employer’s cause
Contractor’s cause
Delay
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
2. Definitions in Delay and Disruption
Analysis
 Prospective v retrospective analysis of delay
 The Critical Path
 Float
 Causation
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Prospective vs. Retrospective Delay
 Prospective:
 Refer to the future and seek to determine the likely impact of
actual progress or a particular event(s) on project completion
 During currency of project
 Per SCL Protocol
 Contract requirement (e.g. NEC)
 Avoid disputes
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Prospective vs. Retrospective Delay
 Retrospective:
 Refer to the historic and usually seek to determine the actual
impact of events upon progress and completion
 During currency of project (after the event)
 Claim preparation
 Dispute resolution (expert analysis)
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Critical Path
 The critical path is the path or sequence of activities, which
represents the longest total time required to complete the project.
 A delay in any activity on the critical path causes a delay in the
completion of the project.
 There may also be more than one critical path depending upon
the logical dependencies between activities.
 Additionally, the critical path is not fixed for any particular project,
but may change as activities are either delayed or able to
progress ahead of programme.
emaclean@brg-expert.com
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Float
‘The time available for an activity in addition to its duration’
(BS4335)
Or
The period by which a task can be delayed without affecting
other tasks or the project end date.
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Types of Float
 ‘Free float - the period by which a task can be delayed or
extended without affecting any other tasks, or the completion of
the project.
 Total float - the period by which a task can be delayed or
extended without delaying the completion of the project.
 Terminal Float: the float between the planned completion date
and the date for completion in the contract
 Who owns the float?
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Causation
 Part of legal requirement to demonstrate that event was causal of
the delay or loss (cause and effect)
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Delay Analysis
 Components
 Programme
 Events
 Progress Records/As-built
 Contract requirements
 Other supporting evidence
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Programme
 The objectives of a programme:
 to determine the earliest date upon which completion can be
achieved;
 to show the interrelationship of activities
 to show the rationale of the sequence of site operations;
 to identify the time constraints imposed by labour, plant and
materials.
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Programme as basis of delay analysis
 Complete and reliable
 Accurate and reasonable activity durations
 Logical relationships between activities
 Plant and equipment delivery dates
 Milestone dates
 Includes all work to be carried out by sub-contractors
 Includes all public holidays
 Includes all employer constraints
 Makes appropriate allowances for seasonal weather conditions
 Compliant with conditions of contract/specification
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Master/Baseline Programme
 Allows comparison of what would have happened with what
actually happened
 Needs to:
 Meet contract requirements
 Be a workable management tool
 Be current
 Be shared
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Progress records
 Allow comparison of what would have happened with what
actually happened
 Need to:
 Meet contract requirements
 Be expressed by reference to a programme
 Be quantitative
 Be accurate
 Be regularly kept
 Be public
 Be consistent
 Record context
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Records
 Minimum requirements:
 Meet contract
requirements
 Start and finish
 Degree of completion
 Labour resources
 Plant resources
 Key procurement activities
 Consider:
 Marked up drawings
 Photographs
 Videos
 More sophisticated
techniques
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
3. Delay Analysis and its Methodologies
 Common Methods of Delay Analysis
 As-planned vs As-built
 Impacted as-planned
 Collapsed as-built
 Time impact analysis
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Parameters
 Relevant conditions of contract
 Nature of causative events
 Value of the dispute
 Time available
 Records available
 Programme information available
 Programmer’s skill level
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
A. As-planned vs As-built
 Essentials
 Good base programme (ideally agreed at start)
 Programme as closely as possible reflects project logic
 As-built information to establish as-built comparison
 May be chosen where issues are simple and liability is clear
 No CPA required
 Steps
 Determine baseline programme
 Determine as-built programme and plot against planned
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
A. As-planned vs As-built
As-built
Claim
As-planned
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
A. As-planned vs As-built
 ‘As-planned’ vs ‘As-built’
 Only retrospective
 No cause and effect
 Takes no account of concurrency
 Assumes fault lies with others
 Unreliable in dispute resolution
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
B. Impacted ‘As-planned’
 Essentials
 Good base programme (ideally agreed at start)
 Programme reflects project logic
 Likely choice where programme not updated and limited/no
as-built information available
 Steps
 Impact all events on planned programme
 Can be done in steps of time intervals - cross checked with
key as-built milestones
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
B. Impacted ‘As-planned’ - illustrated
Claim
Baseline
EOT eventAs-built
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
B. Impacted ‘As-planned’
 Impacted ‘As-planned’
 Prospective/Retrospective
 Limited cause and effect
 Takes no account of:
 Progress
 Resources
 Changing logic
 Unreliable in dispute resolution
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
 Essentials
 Detailed as-built records
 Detailed understanding of construction logic
 Access to site team
 Basis for measuring and identifying the extent of delays
 Steps
 Reconstruct As-built programme & determine Logic
 Identify delay periods & responsibility for delays
 Carry out delay analysis
 Explain approach and results
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
 Identify Employer Delays
Contract
period
As-built
Project Completion
Actual Completion
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
 Zero the Employer Delays
Contract
period
As-built
Actual Completion ‘but for’
Employer Delays
Actual
Completion
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
 Entitlement
Contract period
As-built
Contractor
culpable delays
Contractor EoT
entitlement
Actual
Completion
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
C. Collapsed ‘As-built’
 Collapsed ‘As-built’
 Retrospective (limited Prospective)
 Factually based
 If done properly:
 Demonstrates cause and effect
 Takes account of concurrency
 Relatively quick
 Reliable in dispute resolution
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
 Essentials
 Good base programme (ideally agreed at start)
 Programme reflects project logic
 Reliable and consistent progress data, in sufficient detail and
at small enough intervals to make the analysis meaningful
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
 Steps
 Verify base programme and correct for errors
 Identify delay events and periods
 Input progress up to start of first window period or first delay
 Reschedule and check completion
 Impact delay and record any logic changes to deal with
mitigation
 Reschedule and check completion and record any further delay
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
 Master Programme
Activity 1
Activity 2
Activity 3
Project completion
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
D. Time Impact Analysis - illustrated
 Step 2, Enter progress & record effect
Activity 1
Activity 2
Activity 3
Project completionTime Now
Delay to
Project completion
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
D. Time Impact Analysis - illustrated
 Step 3, Analyse the delaying event
Activity 1
Activity 2
Activity 3
Project completionTime Now
Delaying Event
Delay to
Project completion
Period
of EoT
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
D. Time Impact Analysis
 Time Impact analysis
 Prospective/Retrospective
 Cause and Effect
 Takes account of Progress/Resource/Logic
 Reliable in Dispute Resolution
 Preferred method of SCL Protocol
 Complicated (and therefore slow)
 Difficult to communicate (Skanska v Egger [2004])
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
FIDIC Claims and Extensions of Time
Claims Under the Yellow Book
Clause EoT Costs Profit
1.9 (Errors in the Employer's Requirements) ✓ ✓ ✓
2.1 (Right of Access to the Site) ✓ ✓ ✓
4.7 (Setting Out) ✓ ✓ ✓
4.12 (Unforeseeable Physical Conditions) ✓ ✓
4.24 (Fossils) ✓ ✓
7.4 (Testing) ✓ ✓ ✓
8.4 (a) (Extension of Time for Completion) - Variations ✓
8.4 (c) (Extension of Time for Completion) - Exceptionally Adverse Climatic Conditions ✓
8.4 (d) (Extension of Time for Completion) - Unforeseeable shortages caused by Epidemic or Government Actions ✓
8.4 (e) (Extension of Time for Completion) - Delay, Impediment by Employer or his Agents or Contractors ✓
8.9 (Consequences of Suspension) ✓ ✓
10.2 (Taking Over of Parts of the Works) ✓ ✓
10.3 (Interference with Tests on Completion) ✓ ✓ ✓
12.2 (Delayed Tests) ✓ ✓
12.4 (Failure to Pass Tests after Completion) ✓ ✓
13.7 (Adjustment for Changes in Legislation) ✓ ✓
16.1 (Contractor's Entitlement to Suspend Work) ✓ ✓ ✓
17.4 (Consequences of the Employer's Risks) ✓ ✓ ✓
18.1 (General Requirements for Insurances) ✓ ✓
19.4 (Consequences of Force Majeure) ✓ ✓
For the Silver Book, see Sub-Clauses 2.1, 4.24, 7.4, 8.4, 8.9, 10.3, 12.2, 12.4, 13.7, 16.1, 17.4, 18.1 and 19.4.
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Contractor’s obligations (Yellow Book)
 to commence the design and execution of the Works as soon
as reasonably practicable after the Commencement Date &
 to proceed with the Works with due expedition and without
delay – Sub-clause 8.1
 to complete within the Time for Completion – Sub-clauses 8.2
 to submit a programme and revised programmes: Sub-clause
8.3
 NB Clause 9 for other FIDIC Gold Book
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Entitlement to an extension of time – Sub-clause 8.4 (Yellow Book)
“The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s
Claims], to an extension of the Time for Completion if and to the extent that
completion… is or will be delayed by any of the following causes:”
 Delay must be due to a cause listed in Sub-clause 8.4
 A Variation, Sub-clause, adverse climatic conditions, unforeseeable
shortages; and an Employer default
 Contractor must give notice pursuant to Sub-clause 20.1
 “is or will be delayed” indicates that an entitlement can arise prior to the
effects of the delay having ceased
 Once awarded, the EOT cannot be decreased
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Employer’s right to delay damages – Sub-clause 8.7 (Yellow Book)
 Right under Sub-clause 8.7
 At rate and to the maximum stated in the Appendix to Tender
 Subject to requirements to sub-clause 2.5 – notice to the Contractor
“If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion],
the Contractor shall, subject to Sub-Clause 2.5 [Employer's Claims], pay
delay damages to the Employer for this default. These delay damages shall
be the sum stated in the Appendix to Tender, which shall be paid for every
day which shall elapse between the relevant Time for Completion and the
date stated in the Taking Over Certificate. However, the total amount due
under this Sub-Clause shall not exceed the maximum amount of delay
damages (if any) stated in the Appendix to Tender.”
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Claims, Disputes and Arbitration
 Sub-clause 20.1 Contractor’s Claims (Yellow Book - Notices)
“If the Contractor considers himself to be entitled to any extension of the Time
for Completion and/or any additional payment, under any Clause of these
Conditions or otherwise in connection with the Contract, the Contractor shall
give notice to the Engineer, describing the event or circumstance giving rise to
the claim. The notice shall be given as soon as practicable, and not later than 28
days after the Contractor became aware, or should have become aware, of the
event or circumstance.”
“If the Contractor fails to give notice of a claim within such period of 28 days, the
Time for Completion shall not be extended, the Contractor shall not be entitled to
additional payment, and the Employer shall be discharged from all liability in
connection with the claim…”
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Sub-clause 20.1 Contractor’s Claims (Yellow Book – Contemporary
Records)
“The Contractor shall keep such contemporary records as may be necessary to
substantiate any claim, either on the Site or at another location acceptable to the
Engineer. Without admitting the Employer's liability, the Engineer may, after
receiving any notice under this Sub-Clause, monitor the record-keeping and/or
instruct the Contractor to keep further contemporary records. The Contractor
shall permit the Engineer to inspect all these records, and shall (if instructed)
submit copies to the Engineer.”
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Sub-clause 20.1 (Yellow Book - Details and particulars )
“Within 42 days after the Contractor became aware (or should have become
aware) of the event or circumstance giving rise to the claim, or within such other
period as may be proposed by the Contractor and approved by the Engineer, the
Contractor shall send to the Engineer a fully detailed claim which includes full
supporting particulars of (the basis of the claim and of the extension of time
and/or additional payment claimed. If the event or circumstance giving rise to the
claim has a continuing effect:
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Sub-clause 20.1 (Yellow Book - Details and particulars )
“If the event or circumstance giving rise to the claim has a continuing effect:
(a) this fully detailed claim shall be considered as interim;
(b) the Contractor shall send further interim claims at monthly intervals,
giving the accumulated delay and/or amount claimed, and such further
particulars as the Engineer may reasonably require; and
(c) the Contractor shall send a final claim within 28 days after the end of the
effects resulting from the event or circumstance, or within such other period
as may be proposed by the Contractor and approved by the Engineer.
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Sub-clause 20.1 (Yellow Book- Engineer’s Response )
“Within 42 days after receiving a claim or any further particulars supporting a
previous claim, or within such other period as may be proposed by the Engineer
and approved by the Contractor, the Engineer shall respond with approval, or
with disapproval and detailed comments. He may also request any necessary
further particulars, but shall nevertheless give his response on the principles of
the claim within such time.”
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Sub-clause 20.1 (Yellow Book- Engineer’s Response )
“Each Payment Certificate shall include such amounts for any claim as have been reasonably
substantiated as due under the relevant provision of the Contract. Unless and until the particulars
supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to
payment for such part of the claim as he has been able to substantiate. The Engineer shall proceed in
accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) the extension (if any) of the
Time for Completion (before or after its expiry) in accordance with Sub-Clause 8.4 [Extension of Time
for Completion], and/or (ii) the additional payment (if any) to which the Contractor is entitled under the
Contract.
The requirements of this Sub-Clause are in addition to those of any other Sub-Clause which may apply
to a claim. If the Contractor fails to comply with this or another Sub-clause in relation to any claim, any
extension of time and/or additional payment shall take account of the extent (if any) to which the failure
has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the
second paragraph of this Sub-Clause.”
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
 Sub-clause 2.5 (Employer’s Claims) (Yellow Book)
“If the Employer considers himself to be entitled to any payment under any Clause of these
Conditions or otherwise in connection with the Contract, and/or to any extension of the
Defects Notification Period, the Employer or the Engineer shall give notice and particulars
to the Contractor…
The notice shall be given as soon as practicable after the Employer became aware of the
event or circumstances giving rise to the claim... A notice relating to any extension of the
Defects Notification Period shall be given before the expiry of such period. The particulars
shall specify the Clause or other basis of the claim, and shall include substantiation of the
amount and/or extension to which the Employer considers himself to be entitled in
connection with the Contract. The Engineer shall then proceed in accordance with Sub-
Clause 3.5 [Determinations] to agree or determine (i) the amount (if any) which the
Employer is entitled to be paid by the Contractor, and/or (ii) the extension (if any) of the
Defects Notification Period in accordance with Sub-Clause 11.3 [Extension of Defects
Notification Period].”
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
4. FIDIC Claims and Extensions of Time
13 Oct 15: Contractor became or should have become aware of the event
Oct
24 Nov 15: Contractor provides fully detailed claim
Nov
10 Nov 15: Contractor gives Notice to the Engineer
2016
≤ 28 days
Dec
05 Jan 16: Engineer’s Response
≤ 42 days
≤ 42 days
2015
Jan
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
5. Scenario
 Delay Analysis In Action!
emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
As-Planned versus As-Built
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
As-Planned versus As-Built
with Events
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Contractor’s Global Claim
Employer late clearing site
Fire Change in Law
Design Issues
Strike
19 weeks 1 day
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
Employer blames
whole delay on riot
caused by Contractor
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
Employer claims fire is a
Contractor responsibility
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
3 (Change in Law) 1 week Employer 100 weeks 0 weeks
Employer notes
change in law not
critical
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
3 (Change in Law) 1 week Employer 100 weeks 0 weeks
4 (Strike) 1 day Force Majeure 100 weeks 0 weeks
Employer says 1 day
delay not significant
and can be mitigated
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Employer’s Impacted
As-Planned Response
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1 (Riot) 4 weeks Contractor 100 weeks 0 weeks
2 (Fire) 5 weeks Contractor 100 weeks 0 weeks
3 (Change in Law) 1 week Employer 100 weeks 0 weeks
4 (Strike) 1 day Force Majeure 100 weeks 0 weeks
5 (Subcontractor) 10 weeks Contractor 100 weeks 0 weeks
Employer only notes
subcontractor delay
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
Consultant believes concurrent
and claims EOT but no money
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
Consultant believes strike is a
Force Majeure event
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks
Consultant acknowledges
change in law not critical
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks
2 (Fire) 5 weeks Contractor 110 weeks 1 day 0 weeks
Consultant acknowledges fire
as a Contractor responsibility
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Hired Consultant
Collapsed As-built View
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks
4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day
3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks
2 (Fire) 5 weeks Contractor 110 weeks 1 day 0 weeks
1 (Late Clear & Riot) 4 weeks Employer 114 weeks 1 day 4 weeks
Consultant claims late
clearance of site
dominant cause of delay
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
Riot is not critical after
impact of late clearance
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
Fire considered to be a
Contractor responsibility
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
Change in Law
not critical
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 week Force Majeure Mitigation Mitigation
Force Majeure shown
as 1 week effect
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
Force Majeure shown
as 1 day effect after
mitigation
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
5 (Design & Subcon) 10 weeks Contractor 104 weeks 1 day 0 weeks
Design is critical delay &
subcontractor delay not critical.
However, design can be attributed
to Employer if required
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120
Infrastructure
Substructure
Superstructure
Mechanical
Commissioning
Enabling Works
Electrical
Expert Opinion: Time
Impact Analysis
Event Delay Responsibility Time for Completion EoT
Commencement - - 100 weeks -
1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks
1b (Riot) 1 week Contractor 104 weeks 0 weeks
2 (Fire) 5 weeks Contractor 104 weeks 0 weeks
3 (Change in Law) 1 week Employer 104 weeks 0 weeks
4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day
5 (Design & Subcon) 10 weeks Contractor 104 weeks 1 day 0 weeks
Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb
O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Summary of Extension of Time Claims
1. Contractor’s claim: 19 weeks and 1 day
2. Employer’s Response: 00 weeks
3. Hired Consultant’s View: 14 weeks 1 day
4. Expert Opinion: 04 weeks 1 day
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Why the Difference?
1. The Contractor’s claim was global and did not consider progress,
concurrency, culpable delay or criticality.
2. The Employer’s Response was one sided and did not consider
progress, concurrency, valid claims and actual criticality.
3. Hired Consultant’s view did not fully adjust for progress,
concurrency or actual criticality.
4. Expert Opinion considered progress, concurrency, liability and
criticality.
emaclean@brg-expert.com
Copyright @ 2011. All rights reserved
Delay Analysis Conclusions
 Meet contract requirements
 Focus upon what has to be established
 Review the available records
 Select the method accordingly
 Record at each stage
 Do it properly
 Do it accurately!
emaclean@brg-expert.com

More Related Content

What's hot

VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoignitetribes
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draftignitetribes
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Fakhar-un -Nisa
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 

What's hot (20)

VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Claims
ClaimsClaims
Claims
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)Claims 20.1 (Flow chart)
Claims 20.1 (Flow chart)
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Construction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & ResponsibilitiesConstruction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & Responsibilities
 

Similar to Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract

EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Indonesia
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16Cong Danh Tran
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Project Controls Expo
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
C10 project management
C10 project managementC10 project management
C10 project managementhakimizaki
 
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo
 
ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract
ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract
ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract Sean Durrant
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013Weero Koster
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...mtingle
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec domsBabasab Patil
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 

Similar to Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract (20)

EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: D...
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
CV _Eng_Tran Cong Danh_Project Engineer_15-Oct-16
 
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
Session M2 - Scream If You Want To Go Faster - The contractual, legal, financ...
 
C10 project management
C10 project managementC10 project management
C10 project management
 
C10 project management
C10 project managementC10 project management
C10 project management
 
2014-2015
2014-20152014-2015
2014-2015
 
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
Project Controls Expo, 18th Nov 2014 - "The Computer Age and Estimating – Don...
 
ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract
ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract
ECTS Signalling Project Manager Job Ref 1302 20 - Overseas Contract
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Wind power epc o&m april 2013
Wind power epc o&m  april 2013Wind power epc o&m  april 2013
Wind power epc o&m april 2013
 
Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...Managing Technical & Project Risks on Small Renewable Energy Projects (...
Managing Technical & Project Risks on Small Renewable Energy Projects (...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
PROJECT_STEPS
PROJECT_STEPSPROJECT_STEPS
PROJECT_STEPS
 
Project management @ bec doms
Project management @ bec domsProject management @ bec doms
Project management @ bec doms
 
Contract Management
Contract ManagementContract Management
Contract Management
 
ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)
 
ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)ACH 216 Lecture 09 (Issues During Project)
ACH 216 Lecture 09 (Issues During Project)
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 

More from Project Controls Expo

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureProject Controls Expo
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Project Controls Expo
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Project Controls Expo
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Project Controls Expo
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Project Controls Expo
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...Project Controls Expo
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Project Controls Expo
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Project Controls Expo
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...Project Controls Expo
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Project Controls Expo
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...Project Controls Expo
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Project Controls Expo
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Project Controls Expo
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Project Controls Expo
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Project Controls Expo
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...Project Controls Expo
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...Project Controls Expo
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Project Controls Expo
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Project Controls Expo
 

More from Project Controls Expo (20)

National Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and futureNational Grids Project Controls Journey – past, present and future
National Grids Project Controls Journey – past, present and future
 
Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...Case study in Company Project Controls Transformation By Rod Whiting - Region...
Case study in Company Project Controls Transformation By Rod Whiting - Region...
 
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
Balancing burdens of proof in dispute avoidance and resolution by "Ari Isaacs...
 
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
Managing Changes on a Capital Programme by "Iain Cameron - Technical Director...
 
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
Navigating BIM waters by "Natacha Redon - Associate / BIM Lead for Identity C...
 
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
NEC4: Evolution of the ECC by "Ben Walker - NEC4 Contract Drafter, CEO for CE...
 
Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...Managing the risk of change by "Simon White - Risk Management Consultant for ...
Managing the risk of change by "Simon White - Risk Management Consultant for ...
 
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
Economic Value Chains - costing the impact of risk by "Colin Sandall - Senior...
 
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
What makes a good plan, and how do you know you’ve got one? by "Paul Kidston ...
 
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
Next Generation Planning for Mega Projects by "Dr. Dan Patterson - CEO and Fo...
 
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...
 
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...Governance: An Enabler? by "	 Ian Beaumont - Delivery Partner Programme Direc...
Governance: An Enabler? by " Ian Beaumont - Delivery Partner Programme Direc...
 
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...Governance and the art of decision making on Crossrail by "Walter Macharg - H...
Governance and the art of decision making on Crossrail by "Walter Macharg - H...
 
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
Tideway - Transforming the Thames by "Niall Faris - Project Controls Leader f...
 
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
Adding Value through the Lower Thames Crossing project by "Iain Minns - Partn...
 
Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...Governance and Assurance for Nationally Significant Infrastructure Projects b...
Governance and Assurance for Nationally Significant Infrastructure Projects b...
 
A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...A review of whether interdependency exists in effective Project Control Metho...
A review of whether interdependency exists in effective Project Control Metho...
 
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...A Source of Project Cost Integration by "David Hurren - Technical Director fo...
A Source of Project Cost Integration by "David Hurren - Technical Director fo...
 
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
Programmatic Controls Approach to; Fast track Disaster Recovery by "Saurabh B...
 
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
Enterprise Scheduling and Risk Management at Los Angeles Metro by "Julie Owen...
 

Recently uploaded

Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEMCharmi13
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRRsarwankumar4524
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxAsifArshad8
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.KathleenAnnCordero2
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Escort Service
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRachelAnnTenibroAmaz
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxRoquia Salam
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptxogubuikealex
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comsaastr
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...Henrik Hanke
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this periodSaraIsabelJimenez
 
Internship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SEInternship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SESaleh Ibne Omar
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...漢銘 謝
 
proposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeegerproposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeegerkumenegertelayegrama
 
Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸mathanramanathan2005
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationNathan Young
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxaryanv1753
 
CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...
CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...
CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...university
 

Recently uploaded (19)

Quality by design.. ppt for RA (1ST SEM
Quality by design.. ppt for  RA (1ST SEMQuality by design.. ppt for  RA (1ST SEM
Quality by design.. ppt for RA (1ST SEM
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
 
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular PlasticsDutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
Dutch Power - 26 maart 2024 - Henk Kras - Circular Plastics
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
 
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
PAG-UNLAD NG EKONOMIYA na dapat isaalang alang sa pag-aaral.
 
Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170Call Girls In Aerocity 🤳 Call Us +919599264170
Call Girls In Aerocity 🤳 Call Us +919599264170
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptx
 
Chizaram's Women Tech Makers Deck. .pptx
Chizaram's Women Tech Makers Deck.  .pptxChizaram's Women Tech Makers Deck.  .pptx
Chizaram's Women Tech Makers Deck. .pptx
 
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.comSaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
SaaStr Workshop Wednesday w/ Kyle Norton, Owner.com
 
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
DGT @ CTAC 2024 Valencia: Most crucial invest to digitalisation_Sven Zoelle_v...
 
Early Modern Spain. All about this period
Early Modern Spain. All about this periodEarly Modern Spain. All about this period
Early Modern Spain. All about this period
 
Internship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SEInternship Presentation | PPT | CSE | SE
Internship Presentation | PPT | CSE | SE
 
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
THE COUNTRY WHO SOLVED THE WORLD_HOW CHINA LAUNCHED THE CIVILIZATION REVOLUTI...
 
proposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeegerproposal kumeneger edited.docx A kumeeger
proposal kumeneger edited.docx A kumeeger
 
Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸Mathan flower ppt.pptx slide orchids ✨🌸
Mathan flower ppt.pptx slide orchids ✨🌸
 
The Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism PresentationThe Ten Facts About People With Autism Presentation
The Ten Facts About People With Autism Presentation
 
Event 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptxEvent 4 Introduction to Open Source.pptx
Event 4 Introduction to Open Source.pptx
 
CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...
CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...
CHROMATOGRAPHY and its types with procedure,diagrams,flow charts,advantages a...
 

Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract

  • 1. Copyright @ 2011. All rights reserved Delay Claims and Analysis Based on FIDIC Forms of Contract Project Controls Expo – 13th Oct 2015 Emirates Stadium, London
  • 2. Copyright @ 2011. All rights reserved About the Speaker Ewen Maclean, Eur Ing MEng (Hons) MSc (Const. Law & Arb) CEng FICE FCIArb Director, Berkeley Research Group Ewen is an experienced expert in the field of programming; delay and disruption; and associated prolongation costs in relation to construction and engineering projects. In particular, he has worked for both international consultants and contractors and has first-hand experience of assisting and representing clients in litigation, arbitration, mediation and adjudication, both for the claimant and respondent. He has prepared numerous expert witness reports; drafted standard forms of contract and lectured on various commercial and contractual subjects within the construction industry. Ewen has also acted in commercial negotiations and settlements, resolving potential disputes as well as providing advice on contract procurement. Ewen is well versed in many of the standard forms of construction contract including the NEC, JCT, ICE, FIDIC, GC Works Conditions as well as bespoke forms of contracts including PFI contracts and has worked on contracts that span, inter alia, major building, civil engineering, oil and gas, energy, mechanical and electrical, pharmaceutical, infrastructure including highways and rail as well as fit-out works. emaclean@brg-expert.com
  • 3. Copyright @ 2011. All rights reserved Structure 1. What Do We Mean by Delay and Disruption? 2. Definitions in Delay and Disruption Analysis 3. Delay Analysis and its Methodologies 4. FIDIC Claims and Extension of Time Provisions 5. Scenario - Delay Analysis In Action emaclean@brg-expert.com
  • 4. Copyright @ 2011. All rights reserved 1. What Do We Mean By Delay and Disruption?  Delay  Delay to completion which is a delay which will cause a contract completion date not to be met. emaclean@brg-expert.com
  • 5. Copyright @ 2011. All rights reserved Delay and its consequences  Contractor liable to employer for liquidated damages  Contractor incurs cost of maintaining resources and site establishment for longer  Employer may suffer from loss of revenue & negative publicity  Delay to completion emaclean@brg-expert.com
  • 6. Copyright @ 2011. All rights reserved What Do We Mean By Delay and Disruption?  Disruption  Delay to progress which is a delay which will merely cause delay to the Contractor’s progress without causing a contract completion date not to be met.  Disruption (as distinct from delay) is disturbance, hindrance or interruption to a Contractor’s normal working methods, resulting in lower efficiency. If caused by the Employer, it may give rise to a right to compensation either under the contract or as a breach of contract. (SCL Delay and Disruption Protocol at page 9) emaclean@brg-expert.com
  • 7. Copyright @ 2011. All rights reserved Delay and its Consequences  Disturbance of regular progress of the work  Non-critical delay  Additional costs associated with local disturbance to progress  Delay to progress emaclean@brg-expert.com
  • 8. Copyright @ 2011. All rights reserved Types of Delay and Purpose of Extension of Time Clause  Types of delay  Employer default / responsibility  Contractor default / responsibility  “Neutral” cause  Purpose of EOT clause:  Risk allocation  Common EOT clause: any cause for which E responsible emaclean@brg-expert.com
  • 9. Copyright @ 2011. All rights reserved Employer’s cause Delay = EoT and money Employer Delay emaclean@brg-expert.com
  • 10. Copyright @ 2011. All rights reserved Contractor’s cause Delay = No EoT and no money Contractor Delay emaclean@brg-expert.com
  • 11. Copyright @ 2011. All rights reserved Concurrency  Both events must be effective causes of delay to critical path EoT but, no prolongation money Employer’s cause Contractor’s cause Delay emaclean@brg-expert.com
  • 12. Copyright @ 2011. All rights reserved 2. Definitions in Delay and Disruption Analysis  Prospective v retrospective analysis of delay  The Critical Path  Float  Causation emaclean@brg-expert.com
  • 13. Copyright @ 2011. All rights reserved Prospective vs. Retrospective Delay  Prospective:  Refer to the future and seek to determine the likely impact of actual progress or a particular event(s) on project completion  During currency of project  Per SCL Protocol  Contract requirement (e.g. NEC)  Avoid disputes emaclean@brg-expert.com
  • 14. Copyright @ 2011. All rights reserved Prospective vs. Retrospective Delay  Retrospective:  Refer to the historic and usually seek to determine the actual impact of events upon progress and completion  During currency of project (after the event)  Claim preparation  Dispute resolution (expert analysis) emaclean@brg-expert.com
  • 15. Copyright @ 2011. All rights reserved Critical Path  The critical path is the path or sequence of activities, which represents the longest total time required to complete the project.  A delay in any activity on the critical path causes a delay in the completion of the project.  There may also be more than one critical path depending upon the logical dependencies between activities.  Additionally, the critical path is not fixed for any particular project, but may change as activities are either delayed or able to progress ahead of programme. emaclean@brg-expert.com
  • 16. Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 emaclean@brg-expert.com
  • 17. Copyright @ 2011. All rights reserved Float ‘The time available for an activity in addition to its duration’ (BS4335) Or The period by which a task can be delayed without affecting other tasks or the project end date. emaclean@brg-expert.com
  • 18. Copyright @ 2011. All rights reserved Types of Float  ‘Free float - the period by which a task can be delayed or extended without affecting any other tasks, or the completion of the project.  Total float - the period by which a task can be delayed or extended without delaying the completion of the project.  Terminal Float: the float between the planned completion date and the date for completion in the contract  Who owns the float? emaclean@brg-expert.com
  • 19. Copyright @ 2011. All rights reserved Causation  Part of legal requirement to demonstrate that event was causal of the delay or loss (cause and effect) emaclean@brg-expert.com
  • 20. Copyright @ 2011. All rights reserved Delay Analysis  Components  Programme  Events  Progress Records/As-built  Contract requirements  Other supporting evidence emaclean@brg-expert.com
  • 21. Copyright @ 2011. All rights reserved Programme  The objectives of a programme:  to determine the earliest date upon which completion can be achieved;  to show the interrelationship of activities  to show the rationale of the sequence of site operations;  to identify the time constraints imposed by labour, plant and materials. emaclean@brg-expert.com
  • 22. Copyright @ 2011. All rights reserved Programme as basis of delay analysis  Complete and reliable  Accurate and reasonable activity durations  Logical relationships between activities  Plant and equipment delivery dates  Milestone dates  Includes all work to be carried out by sub-contractors  Includes all public holidays  Includes all employer constraints  Makes appropriate allowances for seasonal weather conditions  Compliant with conditions of contract/specification emaclean@brg-expert.com
  • 23. Copyright @ 2011. All rights reserved Master/Baseline Programme  Allows comparison of what would have happened with what actually happened  Needs to:  Meet contract requirements  Be a workable management tool  Be current  Be shared emaclean@brg-expert.com
  • 24. Copyright @ 2011. All rights reserved Progress records  Allow comparison of what would have happened with what actually happened  Need to:  Meet contract requirements  Be expressed by reference to a programme  Be quantitative  Be accurate  Be regularly kept  Be public  Be consistent  Record context emaclean@brg-expert.com
  • 25. Copyright @ 2011. All rights reserved Records  Minimum requirements:  Meet contract requirements  Start and finish  Degree of completion  Labour resources  Plant resources  Key procurement activities  Consider:  Marked up drawings  Photographs  Videos  More sophisticated techniques emaclean@brg-expert.com
  • 26. Copyright @ 2011. All rights reserved 3. Delay Analysis and its Methodologies  Common Methods of Delay Analysis  As-planned vs As-built  Impacted as-planned  Collapsed as-built  Time impact analysis emaclean@brg-expert.com
  • 27. Copyright @ 2011. All rights reserved Parameters  Relevant conditions of contract  Nature of causative events  Value of the dispute  Time available  Records available  Programme information available  Programmer’s skill level emaclean@brg-expert.com
  • 28. Copyright @ 2011. All rights reserved A. As-planned vs As-built  Essentials  Good base programme (ideally agreed at start)  Programme as closely as possible reflects project logic  As-built information to establish as-built comparison  May be chosen where issues are simple and liability is clear  No CPA required  Steps  Determine baseline programme  Determine as-built programme and plot against planned emaclean@brg-expert.com
  • 29. Copyright @ 2011. All rights reserved A. As-planned vs As-built As-built Claim As-planned emaclean@brg-expert.com
  • 30. Copyright @ 2011. All rights reserved A. As-planned vs As-built  ‘As-planned’ vs ‘As-built’  Only retrospective  No cause and effect  Takes no account of concurrency  Assumes fault lies with others  Unreliable in dispute resolution emaclean@brg-expert.com
  • 31. Copyright @ 2011. All rights reserved B. Impacted ‘As-planned’  Essentials  Good base programme (ideally agreed at start)  Programme reflects project logic  Likely choice where programme not updated and limited/no as-built information available  Steps  Impact all events on planned programme  Can be done in steps of time intervals - cross checked with key as-built milestones emaclean@brg-expert.com
  • 32. Copyright @ 2011. All rights reserved B. Impacted ‘As-planned’ - illustrated Claim Baseline EOT eventAs-built emaclean@brg-expert.com
  • 33. Copyright @ 2011. All rights reserved B. Impacted ‘As-planned’  Impacted ‘As-planned’  Prospective/Retrospective  Limited cause and effect  Takes no account of:  Progress  Resources  Changing logic  Unreliable in dispute resolution emaclean@brg-expert.com
  • 34. Copyright @ 2011. All rights reserved C. Collapsed ‘As-built’  Essentials  Detailed as-built records  Detailed understanding of construction logic  Access to site team  Basis for measuring and identifying the extent of delays  Steps  Reconstruct As-built programme & determine Logic  Identify delay periods & responsibility for delays  Carry out delay analysis  Explain approach and results emaclean@brg-expert.com
  • 35. Copyright @ 2011. All rights reserved C. Collapsed ‘As-built’  Identify Employer Delays Contract period As-built Project Completion Actual Completion emaclean@brg-expert.com
  • 36. Copyright @ 2011. All rights reserved C. Collapsed ‘As-built’  Zero the Employer Delays Contract period As-built Actual Completion ‘but for’ Employer Delays Actual Completion emaclean@brg-expert.com
  • 37. Copyright @ 2011. All rights reserved C. Collapsed ‘As-built’  Entitlement Contract period As-built Contractor culpable delays Contractor EoT entitlement Actual Completion emaclean@brg-expert.com
  • 38. Copyright @ 2011. All rights reserved C. Collapsed ‘As-built’  Collapsed ‘As-built’  Retrospective (limited Prospective)  Factually based  If done properly:  Demonstrates cause and effect  Takes account of concurrency  Relatively quick  Reliable in dispute resolution emaclean@brg-expert.com
  • 39. Copyright @ 2011. All rights reserved D. Time Impact Analysis  Essentials  Good base programme (ideally agreed at start)  Programme reflects project logic  Reliable and consistent progress data, in sufficient detail and at small enough intervals to make the analysis meaningful emaclean@brg-expert.com
  • 40. Copyright @ 2011. All rights reserved D. Time Impact Analysis  Steps  Verify base programme and correct for errors  Identify delay events and periods  Input progress up to start of first window period or first delay  Reschedule and check completion  Impact delay and record any logic changes to deal with mitigation  Reschedule and check completion and record any further delay emaclean@brg-expert.com
  • 41. Copyright @ 2011. All rights reserved D. Time Impact Analysis  Master Programme Activity 1 Activity 2 Activity 3 Project completion emaclean@brg-expert.com
  • 42. Copyright @ 2011. All rights reserved D. Time Impact Analysis - illustrated  Step 2, Enter progress & record effect Activity 1 Activity 2 Activity 3 Project completionTime Now Delay to Project completion emaclean@brg-expert.com
  • 43. Copyright @ 2011. All rights reserved D. Time Impact Analysis - illustrated  Step 3, Analyse the delaying event Activity 1 Activity 2 Activity 3 Project completionTime Now Delaying Event Delay to Project completion Period of EoT emaclean@brg-expert.com
  • 44. Copyright @ 2011. All rights reserved D. Time Impact Analysis  Time Impact analysis  Prospective/Retrospective  Cause and Effect  Takes account of Progress/Resource/Logic  Reliable in Dispute Resolution  Preferred method of SCL Protocol  Complicated (and therefore slow)  Difficult to communicate (Skanska v Egger [2004]) emaclean@brg-expert.com
  • 45. Copyright @ 2011. All rights reserved FIDIC Claims and Extensions of Time Claims Under the Yellow Book Clause EoT Costs Profit 1.9 (Errors in the Employer's Requirements) ✓ ✓ ✓ 2.1 (Right of Access to the Site) ✓ ✓ ✓ 4.7 (Setting Out) ✓ ✓ ✓ 4.12 (Unforeseeable Physical Conditions) ✓ ✓ 4.24 (Fossils) ✓ ✓ 7.4 (Testing) ✓ ✓ ✓ 8.4 (a) (Extension of Time for Completion) - Variations ✓ 8.4 (c) (Extension of Time for Completion) - Exceptionally Adverse Climatic Conditions ✓ 8.4 (d) (Extension of Time for Completion) - Unforeseeable shortages caused by Epidemic or Government Actions ✓ 8.4 (e) (Extension of Time for Completion) - Delay, Impediment by Employer or his Agents or Contractors ✓ 8.9 (Consequences of Suspension) ✓ ✓ 10.2 (Taking Over of Parts of the Works) ✓ ✓ 10.3 (Interference with Tests on Completion) ✓ ✓ ✓ 12.2 (Delayed Tests) ✓ ✓ 12.4 (Failure to Pass Tests after Completion) ✓ ✓ 13.7 (Adjustment for Changes in Legislation) ✓ ✓ 16.1 (Contractor's Entitlement to Suspend Work) ✓ ✓ ✓ 17.4 (Consequences of the Employer's Risks) ✓ ✓ ✓ 18.1 (General Requirements for Insurances) ✓ ✓ 19.4 (Consequences of Force Majeure) ✓ ✓ For the Silver Book, see Sub-Clauses 2.1, 4.24, 7.4, 8.4, 8.9, 10.3, 12.2, 12.4, 13.7, 16.1, 17.4, 18.1 and 19.4. emaclean@brg-expert.com
  • 46. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Contractor’s obligations (Yellow Book)  to commence the design and execution of the Works as soon as reasonably practicable after the Commencement Date &  to proceed with the Works with due expedition and without delay – Sub-clause 8.1  to complete within the Time for Completion – Sub-clauses 8.2  to submit a programme and revised programmes: Sub-clause 8.3  NB Clause 9 for other FIDIC Gold Book emaclean@brg-expert.com
  • 47. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Entitlement to an extension of time – Sub-clause 8.4 (Yellow Book) “The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims], to an extension of the Time for Completion if and to the extent that completion… is or will be delayed by any of the following causes:”  Delay must be due to a cause listed in Sub-clause 8.4  A Variation, Sub-clause, adverse climatic conditions, unforeseeable shortages; and an Employer default  Contractor must give notice pursuant to Sub-clause 20.1  “is or will be delayed” indicates that an entitlement can arise prior to the effects of the delay having ceased  Once awarded, the EOT cannot be decreased emaclean@brg-expert.com
  • 48. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Employer’s right to delay damages – Sub-clause 8.7 (Yellow Book)  Right under Sub-clause 8.7  At rate and to the maximum stated in the Appendix to Tender  Subject to requirements to sub-clause 2.5 – notice to the Contractor “If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor shall, subject to Sub-Clause 2.5 [Employer's Claims], pay delay damages to the Employer for this default. These delay damages shall be the sum stated in the Appendix to Tender, which shall be paid for every day which shall elapse between the relevant Time for Completion and the date stated in the Taking Over Certificate. However, the total amount due under this Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the Appendix to Tender.” emaclean@brg-expert.com
  • 49. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Claims, Disputes and Arbitration  Sub-clause 20.1 Contractor’s Claims (Yellow Book - Notices) “If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Engineer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance.” “If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim…” emaclean@brg-expert.com
  • 50. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Sub-clause 20.1 Contractor’s Claims (Yellow Book – Contemporary Records) “The Contractor shall keep such contemporary records as may be necessary to substantiate any claim, either on the Site or at another location acceptable to the Engineer. Without admitting the Employer's liability, the Engineer may, after receiving any notice under this Sub-Clause, monitor the record-keeping and/or instruct the Contractor to keep further contemporary records. The Contractor shall permit the Engineer to inspect all these records, and shall (if instructed) submit copies to the Engineer.” emaclean@brg-expert.com
  • 51. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Sub-clause 20.1 (Yellow Book - Details and particulars ) “Within 42 days after the Contractor became aware (or should have become aware) of the event or circumstance giving rise to the claim, or within such other period as may be proposed by the Contractor and approved by the Engineer, the Contractor shall send to the Engineer a fully detailed claim which includes full supporting particulars of (the basis of the claim and of the extension of time and/or additional payment claimed. If the event or circumstance giving rise to the claim has a continuing effect: emaclean@brg-expert.com
  • 52. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Sub-clause 20.1 (Yellow Book - Details and particulars ) “If the event or circumstance giving rise to the claim has a continuing effect: (a) this fully detailed claim shall be considered as interim; (b) the Contractor shall send further interim claims at monthly intervals, giving the accumulated delay and/or amount claimed, and such further particulars as the Engineer may reasonably require; and (c) the Contractor shall send a final claim within 28 days after the end of the effects resulting from the event or circumstance, or within such other period as may be proposed by the Contractor and approved by the Engineer. emaclean@brg-expert.com
  • 53. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Sub-clause 20.1 (Yellow Book- Engineer’s Response ) “Within 42 days after receiving a claim or any further particulars supporting a previous claim, or within such other period as may be proposed by the Engineer and approved by the Contractor, the Engineer shall respond with approval, or with disapproval and detailed comments. He may also request any necessary further particulars, but shall nevertheless give his response on the principles of the claim within such time.” emaclean@brg-expert.com
  • 54. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Sub-clause 20.1 (Yellow Book- Engineer’s Response ) “Each Payment Certificate shall include such amounts for any claim as have been reasonably substantiated as due under the relevant provision of the Contract. Unless and until the particulars supplied are sufficient to substantiate the whole of the claim, the Contractor shall only be entitled to payment for such part of the claim as he has been able to substantiate. The Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine (i) the extension (if any) of the Time for Completion (before or after its expiry) in accordance with Sub-Clause 8.4 [Extension of Time for Completion], and/or (ii) the additional payment (if any) to which the Contractor is entitled under the Contract. The requirements of this Sub-Clause are in addition to those of any other Sub-Clause which may apply to a claim. If the Contractor fails to comply with this or another Sub-clause in relation to any claim, any extension of time and/or additional payment shall take account of the extent (if any) to which the failure has prevented or prejudiced proper investigation of the claim, unless the claim is excluded under the second paragraph of this Sub-Clause.” emaclean@brg-expert.com
  • 55. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time  Sub-clause 2.5 (Employer’s Claims) (Yellow Book) “If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract, and/or to any extension of the Defects Notification Period, the Employer or the Engineer shall give notice and particulars to the Contractor… The notice shall be given as soon as practicable after the Employer became aware of the event or circumstances giving rise to the claim... A notice relating to any extension of the Defects Notification Period shall be given before the expiry of such period. The particulars shall specify the Clause or other basis of the claim, and shall include substantiation of the amount and/or extension to which the Employer considers himself to be entitled in connection with the Contract. The Engineer shall then proceed in accordance with Sub- Clause 3.5 [Determinations] to agree or determine (i) the amount (if any) which the Employer is entitled to be paid by the Contractor, and/or (ii) the extension (if any) of the Defects Notification Period in accordance with Sub-Clause 11.3 [Extension of Defects Notification Period].” emaclean@brg-expert.com
  • 56. Copyright @ 2011. All rights reserved 4. FIDIC Claims and Extensions of Time 13 Oct 15: Contractor became or should have become aware of the event Oct 24 Nov 15: Contractor provides fully detailed claim Nov 10 Nov 15: Contractor gives Notice to the Engineer 2016 ≤ 28 days Dec 05 Jan 16: Engineer’s Response ≤ 42 days ≤ 42 days 2015 Jan emaclean@brg-expert.com
  • 57. Copyright @ 2011. All rights reserved 5. Scenario  Delay Analysis In Action! emaclean@brg-expert.com
  • 58. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical As-Planned versus As-Built Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 59. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical As-Planned versus As-Built with Events Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 60. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Contractor’s Global Claim Employer late clearing site Fire Change in Law Design Issues Strike 19 weeks 1 day Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 61. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Employer’s Impacted As-Planned Response Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 62. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Employer’s Impacted As-Planned Response Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1 (Riot) 4 weeks Contractor 100 weeks 0 weeks Employer blames whole delay on riot caused by Contractor Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 63. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Employer’s Impacted As-Planned Response Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1 (Riot) 4 weeks Contractor 100 weeks 0 weeks 2 (Fire) 5 weeks Contractor 100 weeks 0 weeks Employer claims fire is a Contractor responsibility Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 64. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Employer’s Impacted As-Planned Response Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1 (Riot) 4 weeks Contractor 100 weeks 0 weeks 2 (Fire) 5 weeks Contractor 100 weeks 0 weeks 3 (Change in Law) 1 week Employer 100 weeks 0 weeks Employer notes change in law not critical Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 65. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Employer’s Impacted As-Planned Response Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1 (Riot) 4 weeks Contractor 100 weeks 0 weeks 2 (Fire) 5 weeks Contractor 100 weeks 0 weeks 3 (Change in Law) 1 week Employer 100 weeks 0 weeks 4 (Strike) 1 day Force Majeure 100 weeks 0 weeks Employer says 1 day delay not significant and can be mitigated Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 66. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Employer’s Impacted As-Planned Response Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1 (Riot) 4 weeks Contractor 100 weeks 0 weeks 2 (Fire) 5 weeks Contractor 100 weeks 0 weeks 3 (Change in Law) 1 week Employer 100 weeks 0 weeks 4 (Strike) 1 day Force Majeure 100 weeks 0 weeks 5 (Subcontractor) 10 weeks Contractor 100 weeks 0 weeks Employer only notes subcontractor delay Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 67. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Hired Consultant Collapsed As-built View Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 68. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Hired Consultant Collapsed As-built View Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks Consultant believes concurrent and claims EOT but no money Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 69. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Hired Consultant Collapsed As-built View Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks 4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day Consultant believes strike is a Force Majeure event Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 70. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Hired Consultant Collapsed As-built View Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks 4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day 3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks Consultant acknowledges change in law not critical Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 71. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Hired Consultant Collapsed As-built View Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks 4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day 3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks 2 (Fire) 5 weeks Contractor 110 weeks 1 day 0 weeks Consultant acknowledges fire as a Contractor responsibility Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 72. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Hired Consultant Collapsed As-built View Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 5 (Design & Subcon) 10 weeks Emp / Con 110 weeks 10 weeks 4 (Strike) 1 day Force Majeure 110 weeks 1 day 1 day 3 (Change in Law) 1 week Employer 110 weeks 1 day 0 weeks 2 (Fire) 5 weeks Contractor 110 weeks 1 day 0 weeks 1 (Late Clear & Riot) 4 weeks Employer 114 weeks 1 day 4 weeks Consultant claims late clearance of site dominant cause of delay Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 73. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 74. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 75. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 76. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks Riot is not critical after impact of late clearance Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 77. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 78. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks Fire considered to be a Contractor responsibility Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 79. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 80. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks 3 (Change in Law) 1 week Employer 104 weeks 0 weeks Change in Law not critical Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 81. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks 3 (Change in Law) 1 week Employer 104 weeks 0 weeks Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 82. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks 3 (Change in Law) 1 week Employer 104 weeks 0 weeks 4 (Strike) 1 week Force Majeure Mitigation Mitigation Force Majeure shown as 1 week effect Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 83. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks 3 (Change in Law) 1 week Employer 104 weeks 0 weeks 4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day Force Majeure shown as 1 day effect after mitigation Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 84. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks 3 (Change in Law) 1 week Employer 104 weeks 0 weeks 4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 85. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks 3 (Change in Law) 1 week Employer 104 weeks 0 weeks 4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day 5 (Design & Subcon) 10 weeks Contractor 104 weeks 1 day 0 weeks Design is critical delay & subcontractor delay not critical. However, design can be attributed to Employer if required Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 86. 4 8 10 14 18 24 28 32 36 40 44 48 52 56 60 64 68 72 76 80 84 88 92 96 100 104 108 112 116 120 Infrastructure Substructure Superstructure Mechanical Commissioning Enabling Works Electrical Expert Opinion: Time Impact Analysis Event Delay Responsibility Time for Completion EoT Commencement - - 100 weeks - 1a (Late Clearance) 4 weeks Employer 104 weeks 4 weeks 1b (Riot) 1 week Contractor 104 weeks 0 weeks 2 (Fire) 5 weeks Contractor 104 weeks 0 weeks 3 (Change in Law) 1 week Employer 104 weeks 0 weeks 4 (Strike) 1 day Force Majeure 104 weeks 1 day 1 day 5 (Design & Subcon) 10 weeks Contractor 104 weeks 1 day 0 weeks Ewen Maclean Eur Ing MEng(Hons) MSc (Const. Law & Arb) CEng FICE FCIArb O +44 (0)203 725 8362 | M +44 (0)7876 686036 | emaclean@brg-expert.com
  • 87. Copyright @ 2011. All rights reserved Summary of Extension of Time Claims 1. Contractor’s claim: 19 weeks and 1 day 2. Employer’s Response: 00 weeks 3. Hired Consultant’s View: 14 weeks 1 day 4. Expert Opinion: 04 weeks 1 day emaclean@brg-expert.com
  • 88. Copyright @ 2011. All rights reserved Why the Difference? 1. The Contractor’s claim was global and did not consider progress, concurrency, culpable delay or criticality. 2. The Employer’s Response was one sided and did not consider progress, concurrency, valid claims and actual criticality. 3. Hired Consultant’s view did not fully adjust for progress, concurrency or actual criticality. 4. Expert Opinion considered progress, concurrency, liability and criticality. emaclean@brg-expert.com
  • 89. Copyright @ 2011. All rights reserved Delay Analysis Conclusions  Meet contract requirements  Focus upon what has to be established  Review the available records  Select the method accordingly  Record at each stage  Do it properly  Do it accurately! emaclean@brg-expert.com