Project Value Delivery
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
How
Governance
Makes or Breaks a Project
v0 – May 2017
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 2
The Project Governance Issue
• Projects and associated Capex are the decisive
long term success factor of facilities and
companies
• A large proportion of projects fail to deliver the
expected value. Some projects might even bring
companies on the brink of restructuring
• Beyond project execution issues, Governance is
often the real cause of failure
• This presentation focuses on Large, Complex
Projects.
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 3
Contents
• What is project/program governance for?
• General governance issues
• Governance at Contractor level: specific issues
• Governance at Owner level: specific issues
• Summary and recommendations
Section
1
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
What is project/program
governance for?
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 5
What is Project Governance For?
Engagement and decision-making beyond
remit/capability of Project Manager:
• Engage stakeholders:
– Politics (local, national)
– Financing
– Board of Directors
– Project Resource providers at executive level
– Owner (for contractors)
• Mobilize internal resources as required and liaise with the
rest of the organization
• Drive strategy alignment
• Take the key decisions at Decision Points and for
Changes
• Release of management reserves
Section
2
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
General governance issues
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 7
Types of governance issues
1. Organization does not understand the specifics of
Project Management
2. Ineffective Governance organization
3. Inadequate decision-making framework
4. Inadequate reporting / information from Project
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 8
Type 1: organization does not
understand the specifics of Project
Management
• In many organizations, Project Management is not the core
activity. Executive managers do not have project execution
background. They run repetitive businesses.
• Project execution requires a specific approach and specific
reflex behaviors that can be opposite to usual management
practices
 Governance body does not provide useful support to Project
Manager, takes decision opposite to project good practice
that are detrimental
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 9
Type 1: organization does not
understand the specifics of Project
Management
Examples
• Underestimation of required Project Management Team
– (alternate): easier savings is cutting PMT team
– (alternate): delegation without control to EPCm contractor whose
incentives are not aligned with Owner’s project objectives
• Insufficient investment in Project Control tools and
infrastructure at project setup
• Inadequate planning at the start of the project
• Does not setup an integrated project team with all relevant
functions
• Too late involvement of Operations personnel
• Etc.
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 10
Type 1: organization does not
understand the specifics of Project
Management
• What many CEOs do not realize is that Capex
projects even with limited yearly expenditure
compared to overall revenue can make or break
the company on the short/medium term
• Typically Capex projects of total value above 10%
of company revenue can be critical. This varies per
industry
– 2.5% of revenue per year
OOM calculation: suppose Revenue/Capex leverage factor of 5, net
margin of 10%, typical large Capex project over 4 years.
Critical Capex project value of 5% of annual revenue = 25% of current
asset base
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 11
Type 2: Ineffective governance
organization
• Governance must be effective
– Be clear about scope of governance so as not to intrude into
Project Manager’s remit (governance charter)
– Make decisions effectively and quickly
– With a single voice give clear guidance to the Project
Manager
– Ensure alignment with organization’s strategy
– Provide an avenue for difficult, deep, frank conversations that
really address the issues
– Provide an avenue for resolving conflicts with external
stakeholder above project level to preserve momentum and
relations
• Governance must be at the right level
– Major/key Capex projects must report to executive
committee member or even directly to the CEO
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 12
Type 2: Ineffective governance
organization
• Too many people…
“Too many governance
teams are stacked with
‘stakeholders’ to secure buy-
in rather than people with
proven ability to govern
projects. These people are
often heavily conflicted and
have no accountability for
their project governance
role” - Graeme Cocks,
Melbourne Business School
associate professor.
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 13
Type 2: Ineffective governance
organization
• No possibility to really feedback reality to single
decision-maker…
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 14
Type 2: Ineffective governance
organization
• Comitology…
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 15
Type 2: Ineffective governance
organization
• Special for long
projects: the lack of
accountability over
the duration of the
project because of
the change of
Steering committee
and Project Manager • Also lack of
continuity and
knowledge
management
impedes
performance
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 16
Type 3: Inadequate decision-making
framework
Key decision-making effectiveness factors
– timeliness, speed and relevance of decisions
– structured approach to governance decision-
making (e.g. Gate-based governance)
– Timeliness of decision-making/commitments +
availability for unexpected events is essential
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 17
Type 3: Inadequate decision-making
framework
Examples
• No clear decision points defined in advance lead to decisions
being taken after the fact
• Commitments taking too long impacting project delivery
severely
• No list checks and required available material at various gates
• No discipline in the application of gate-based governance
process
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 18
Type 4: Inadequate reporting/
information from Project
• Project control not effective – does not provide
accurate status
– Often due to insufficient investment due to
governance
• No independent / peer review to give alternate
opinion on the project
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 19
Type 4: Inadequate reporting/
information from Project
• Analysis and information need to be able to
provide insight and early warning of
potential future issues
Section
3
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Governance at Contractor
level: specific issues
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 21
Governance issues at Contractor
Level
• Lack of designation/commitment of Project Sponsor
• No setup of sponsor committee with Owner at a
sufficiently high level
• Lack of authority of the Project Manager causing
delays in decision-making for key subcontracts and
commitments
• JV/consortium levels governance not always
adequate for project execution (participants to
steering committee, JV agreement)
– Includes sometimes even internal issues within
contractor between BUs
• Interface management with other parties in the
project not properly managed
Section
4
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Governance at Owner level:
specific issues
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 23
Governance issues at Owner Level
• Lack of understanding of Project Management by executive
management
– Inadequate decisions can jeopardize the business by
– Lack of investment into proper people, tools and processes
• No/Poor project governance framework
• Lack of recognition of Project Manager
– For major Capex should report directly to CXO
• Lack of internal expertise and lack of appetence for
mobilizing external experts
• Procurement process does not select best contractor for the
work or proper contractual framework
• Use of EPC management contractor to act on its behalf
preventing project success through lack of Owner
involvement and lack of willingness of management
contractor to accept beneficial compromises
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 24
Governance issues at Owner Level
• Lack of adoption of proper pre-Final Investment Decision (FID)
process (FEL type gate process)
• Insufficient pre-FID investment and budgets
• Lack of discipline at gate review leading to project FID with
lack of maturity of engineering
• Lack of discipline in business case analysis and assumptions
Conclusion
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Summary and
recommendations
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 26
Governance issues are major contributors to poor Project
performance
And…
They make the life of the Project Team miserable
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 27
Project governance general
recommendations
• Ensure clear roles and responsibilities between Steering
committee and project
• Ensure a Project Sponsor is part of the Steering Committee and
is its single voice and its single point of contact
• Recognize that Project Management requires specific skills,
experience, tools
– Executive level education required in non-project organizations
• The reporting level of the Project Manager is an essential
indicator/parameter in Owner organizations
• Make sure that there is sufficient budget for PMT and that it is
invested early (before FID, at the start of the project…)
• When there are difficulties in Project Execution do not hesitate
to investigate the influence of actual project governance. It is
often a key factor
© Project Value Delivery, 2017
w w w . P r o j e c t V a l u e D e l i v e r y . c o m 28
Inadequate Project
governance is not
inevitable
Focus on and invest
in proper
governance to be
successful in
project execution
W e E m p o w e r O r g a n i z a t i o n s
T o b e R e l i a b l y S u c c e s s f u l i n
E x e c u t i n g L a r g e , C o m p l e x P r o j e c t s
Discover more on
w w w . P r o j e c t V a l u e D e l i v e r y . c o m
Project Value Delivery
Project Soft Power
Unleashing Value
from Your
Large, Complex
Projects
Project Health Check
Project Coaching
Organizational maturity
Team effectivenessIntercultural leadership
Advanced project trainingProject Startup support
Project Recovery
Advanced risk management
Project Control and Reporting
Support systems integration
Convergence planning
Remote sites integration
Leadership development

More Related Content

What's hot

Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesJeremie Averous
 
Specifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsSpecifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsJeremie Averous
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsJeremie Averous
 
Project Control Basics
Project Control BasicsProject Control Basics
Project Control Basicsprojectcompany
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projectsWalter Akers
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsIbrahim Al-Hudhaif
 
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...Egyptian Engineers Association
 
-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...
-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...
-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...Egyptian Engineers Association
 
Jiby\'s Resume
Jiby\'s ResumeJiby\'s Resume
Jiby\'s Resumejibymanuel
 
Robert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_ManagerRobert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_ManagerRobert Hesketh
 
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryDavid Pires
 
Creating successful R&D proposals to benefit small and medium enterprises
Creating successful R&D proposals to benefit small and medium enterprisesCreating successful R&D proposals to benefit small and medium enterprises
Creating successful R&D proposals to benefit small and medium enterprisesPMI-Montréal
 

What's hot (19)

Advanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedulesAdvanced project scheduling: proper practices for integrated project schedules
Advanced project scheduling: proper practices for integrated project schedules
 
Project Soft Power
Project Soft PowerProject Soft Power
Project Soft Power
 
Specifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex ProjectsSpecifics of Managing Large, Complex Projects
Specifics of Managing Large, Complex Projects
 
Practical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex ProjectsPractical Project Cost Control for Large Complex Projects
Practical Project Cost Control for Large Complex Projects
 
Project Control Basics
Project Control BasicsProject Control Basics
Project Control Basics
 
What goes wrong on complex projects
What goes wrong on complex projectsWhat goes wrong on complex projects
What goes wrong on complex projects
 
Addressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega ProjectsAddressing the challenges of delivering Mega Projects
Addressing the challenges of delivering Mega Projects
 
Complex project management
Complex project managementComplex project management
Complex project management
 
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
م.58-مبادرة#تواصل_تطوير-د.وليد محفوظ-إدارة مشاركة المعنيين في مشاريع وبرامج ا...
 
-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...
-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...
-THE ROAD MAP TO START THE WAY TO BE AN INTERNATIONAL PROJECT MANAGER-م.44-مب...
 
MPA: Some perspectives on project delivery
MPA: Some perspectives on project deliveryMPA: Some perspectives on project delivery
MPA: Some perspectives on project delivery
 
Jiby\'s Resume
Jiby\'s ResumeJiby\'s Resume
Jiby\'s Resume
 
Portfolio management in Rolls-Royce today
Portfolio management in Rolls-Royce todayPortfolio management in Rolls-Royce today
Portfolio management in Rolls-Royce today
 
Robert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_ManagerRobert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_Manager
 
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
Project Controls Expo - 31st Oct 2012 - Lessons Learned from an Interna.onal ...
 
Integrating project life cycle with process groups
Integrating project life cycle with process groupsIntegrating project life cycle with process groups
Integrating project life cycle with process groups
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Front-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas IndustryFront-End Loading in the Oil and Gas Industry
Front-End Loading in the Oil and Gas Industry
 
Creating successful R&D proposals to benefit small and medium enterprises
Creating successful R&D proposals to benefit small and medium enterprisesCreating successful R&D proposals to benefit small and medium enterprises
Creating successful R&D proposals to benefit small and medium enterprises
 

Similar to How Governance Makes or Breaks a Project

Project success post_implementation & management
Project success post_implementation & managementProject success post_implementation & management
Project success post_implementation & managementKhushboo Sorthiya
 
PMO Development - Line of Sight
PMO Development - Line of SightPMO Development - Line of Sight
PMO Development - Line of SightLine of Sight
 
Project management lecture 1
Project management lecture 1Project management lecture 1
Project management lecture 1Abeera Malik
 
Lecture Presentation on Project Proposal
Lecture Presentation on Project ProposalLecture Presentation on Project Proposal
Lecture Presentation on Project ProposalJo Balucanag - Bitonio
 
Project management
Project managementProject management
Project managementobsession56
 
Project failure reason 1
Project failure reason 1Project failure reason 1
Project failure reason 1Arash Moto
 
Project Management Pocket Skills Guide
Project Management Pocket Skills GuideProject Management Pocket Skills Guide
Project Management Pocket Skills GuideEmily Robinson
 
Capital Program Assessment Overview
Capital Program Assessment OverviewCapital Program Assessment Overview
Capital Program Assessment OverviewScottMadden, Inc.
 
Project Governance - Past, Present and Future the Key to Success slides.pdf
Project Governance - Past, Present and Future the Key to Success slides.pdfProject Governance - Past, Present and Future the Key to Success slides.pdf
Project Governance - Past, Present and Future the Key to Success slides.pdfAssociation for Project Management
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounPMILebanonChapter
 
Project Implementation
Project ImplementationProject Implementation
Project ImplementationShidin Divakar
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)Rintu Das
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE S. Sathishkumar
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementYamanta Raj Niroula, PMP
 
CDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptxCDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptxssuserb5044d
 

Similar to How Governance Makes or Breaks a Project (20)

Project governance
Project governanceProject governance
Project governance
 
Project success post_implementation & management
Project success post_implementation & managementProject success post_implementation & management
Project success post_implementation & management
 
PMO Development - Line of Sight
PMO Development - Line of SightPMO Development - Line of Sight
PMO Development - Line of Sight
 
Project management lecture 1
Project management lecture 1Project management lecture 1
Project management lecture 1
 
Lecture Presentation on Project Proposal
Lecture Presentation on Project ProposalLecture Presentation on Project Proposal
Lecture Presentation on Project Proposal
 
Project management
Project managementProject management
Project management
 
Project failure reason 1
Project failure reason 1Project failure reason 1
Project failure reason 1
 
Project Management Pocket Skills Guide
Project Management Pocket Skills GuideProject Management Pocket Skills Guide
Project Management Pocket Skills Guide
 
Capital Program Assessment Overview
Capital Program Assessment OverviewCapital Program Assessment Overview
Capital Program Assessment Overview
 
Project Governance - Past, Present and Future the Key to Success slides.pdf
Project Governance - Past, Present and Future the Key to Success slides.pdfProject Governance - Past, Present and Future the Key to Success slides.pdf
Project Governance - Past, Present and Future the Key to Success slides.pdf
 
Another Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham ZeinounAnother Project Hit the wall by Eng Hisham Zeinoun
Another Project Hit the wall by Eng Hisham Zeinoun
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
PRESTO Change Management
PRESTO Change ManagementPRESTO Change Management
PRESTO Change Management
 
Project management.pptx
Project management.pptxProject management.pptx
Project management.pptx
 
Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project Management
 
Project
Project Project
Project
 
CDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptxCDM_2015_no_speaker_notes.pptx
CDM_2015_no_speaker_notes.pptx
 

More from Jeremie Averous

Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsJeremie Averous
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsJeremie Averous
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsJeremie Averous
 
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Jeremie Averous
 
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Jeremie Averous
 
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous
 

More from Jeremie Averous (6)

Dealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration MegaprojectsDealing with Extra Long Duration Megaprojects
Dealing with Extra Long Duration Megaprojects
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
 
Project Value Delivery methodology and interventions
Project Value Delivery methodology and interventionsProject Value Delivery methodology and interventions
Project Value Delivery methodology and interventions
 
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
Grands projets industriels complexes: Rôle spécifique du Maître d’Ouvrage et ...
 
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
Estimation et contrôle des coûts sur les projets: répondre aux défis d'aujour...
 
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
Jeremie Averous speaking at Lycee Hoche, May 2014 (Presentation au Lycee Hoch...
 

Recently uploaded

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 

Recently uploaded (20)

Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 

How Governance Makes or Breaks a Project

  • 1. Project Value Delivery © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m How Governance Makes or Breaks a Project v0 – May 2017
  • 2. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 2 The Project Governance Issue • Projects and associated Capex are the decisive long term success factor of facilities and companies • A large proportion of projects fail to deliver the expected value. Some projects might even bring companies on the brink of restructuring • Beyond project execution issues, Governance is often the real cause of failure • This presentation focuses on Large, Complex Projects.
  • 3. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 3 Contents • What is project/program governance for? • General governance issues • Governance at Contractor level: specific issues • Governance at Owner level: specific issues • Summary and recommendations
  • 4. Section 1 © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m What is project/program governance for?
  • 5. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 5 What is Project Governance For? Engagement and decision-making beyond remit/capability of Project Manager: • Engage stakeholders: – Politics (local, national) – Financing – Board of Directors – Project Resource providers at executive level – Owner (for contractors) • Mobilize internal resources as required and liaise with the rest of the organization • Drive strategy alignment • Take the key decisions at Decision Points and for Changes • Release of management reserves
  • 6. Section 2 © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m General governance issues
  • 7. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 7 Types of governance issues 1. Organization does not understand the specifics of Project Management 2. Ineffective Governance organization 3. Inadequate decision-making framework 4. Inadequate reporting / information from Project
  • 8. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 8 Type 1: organization does not understand the specifics of Project Management • In many organizations, Project Management is not the core activity. Executive managers do not have project execution background. They run repetitive businesses. • Project execution requires a specific approach and specific reflex behaviors that can be opposite to usual management practices  Governance body does not provide useful support to Project Manager, takes decision opposite to project good practice that are detrimental
  • 9. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 9 Type 1: organization does not understand the specifics of Project Management Examples • Underestimation of required Project Management Team – (alternate): easier savings is cutting PMT team – (alternate): delegation without control to EPCm contractor whose incentives are not aligned with Owner’s project objectives • Insufficient investment in Project Control tools and infrastructure at project setup • Inadequate planning at the start of the project • Does not setup an integrated project team with all relevant functions • Too late involvement of Operations personnel • Etc.
  • 10. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 10 Type 1: organization does not understand the specifics of Project Management • What many CEOs do not realize is that Capex projects even with limited yearly expenditure compared to overall revenue can make or break the company on the short/medium term • Typically Capex projects of total value above 10% of company revenue can be critical. This varies per industry – 2.5% of revenue per year OOM calculation: suppose Revenue/Capex leverage factor of 5, net margin of 10%, typical large Capex project over 4 years. Critical Capex project value of 5% of annual revenue = 25% of current asset base
  • 11. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 11 Type 2: Ineffective governance organization • Governance must be effective – Be clear about scope of governance so as not to intrude into Project Manager’s remit (governance charter) – Make decisions effectively and quickly – With a single voice give clear guidance to the Project Manager – Ensure alignment with organization’s strategy – Provide an avenue for difficult, deep, frank conversations that really address the issues – Provide an avenue for resolving conflicts with external stakeholder above project level to preserve momentum and relations • Governance must be at the right level – Major/key Capex projects must report to executive committee member or even directly to the CEO
  • 12. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 12 Type 2: Ineffective governance organization • Too many people… “Too many governance teams are stacked with ‘stakeholders’ to secure buy- in rather than people with proven ability to govern projects. These people are often heavily conflicted and have no accountability for their project governance role” - Graeme Cocks, Melbourne Business School associate professor.
  • 13. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 13 Type 2: Ineffective governance organization • No possibility to really feedback reality to single decision-maker…
  • 14. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 14 Type 2: Ineffective governance organization • Comitology…
  • 15. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 15 Type 2: Ineffective governance organization • Special for long projects: the lack of accountability over the duration of the project because of the change of Steering committee and Project Manager • Also lack of continuity and knowledge management impedes performance
  • 16. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 16 Type 3: Inadequate decision-making framework Key decision-making effectiveness factors – timeliness, speed and relevance of decisions – structured approach to governance decision- making (e.g. Gate-based governance) – Timeliness of decision-making/commitments + availability for unexpected events is essential
  • 17. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 17 Type 3: Inadequate decision-making framework Examples • No clear decision points defined in advance lead to decisions being taken after the fact • Commitments taking too long impacting project delivery severely • No list checks and required available material at various gates • No discipline in the application of gate-based governance process
  • 18. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 18 Type 4: Inadequate reporting/ information from Project • Project control not effective – does not provide accurate status – Often due to insufficient investment due to governance • No independent / peer review to give alternate opinion on the project
  • 19. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 19 Type 4: Inadequate reporting/ information from Project • Analysis and information need to be able to provide insight and early warning of potential future issues
  • 20. Section 3 © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Governance at Contractor level: specific issues
  • 21. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 21 Governance issues at Contractor Level • Lack of designation/commitment of Project Sponsor • No setup of sponsor committee with Owner at a sufficiently high level • Lack of authority of the Project Manager causing delays in decision-making for key subcontracts and commitments • JV/consortium levels governance not always adequate for project execution (participants to steering committee, JV agreement) – Includes sometimes even internal issues within contractor between BUs • Interface management with other parties in the project not properly managed
  • 22. Section 4 © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Governance at Owner level: specific issues
  • 23. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 23 Governance issues at Owner Level • Lack of understanding of Project Management by executive management – Inadequate decisions can jeopardize the business by – Lack of investment into proper people, tools and processes • No/Poor project governance framework • Lack of recognition of Project Manager – For major Capex should report directly to CXO • Lack of internal expertise and lack of appetence for mobilizing external experts • Procurement process does not select best contractor for the work or proper contractual framework • Use of EPC management contractor to act on its behalf preventing project success through lack of Owner involvement and lack of willingness of management contractor to accept beneficial compromises
  • 24. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 24 Governance issues at Owner Level • Lack of adoption of proper pre-Final Investment Decision (FID) process (FEL type gate process) • Insufficient pre-FID investment and budgets • Lack of discipline at gate review leading to project FID with lack of maturity of engineering • Lack of discipline in business case analysis and assumptions
  • 25. Conclusion © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m Summary and recommendations
  • 26. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 26 Governance issues are major contributors to poor Project performance And… They make the life of the Project Team miserable
  • 27. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 27 Project governance general recommendations • Ensure clear roles and responsibilities between Steering committee and project • Ensure a Project Sponsor is part of the Steering Committee and is its single voice and its single point of contact • Recognize that Project Management requires specific skills, experience, tools – Executive level education required in non-project organizations • The reporting level of the Project Manager is an essential indicator/parameter in Owner organizations • Make sure that there is sufficient budget for PMT and that it is invested early (before FID, at the start of the project…) • When there are difficulties in Project Execution do not hesitate to investigate the influence of actual project governance. It is often a key factor
  • 28. © Project Value Delivery, 2017 w w w . P r o j e c t V a l u e D e l i v e r y . c o m 28 Inadequate Project governance is not inevitable Focus on and invest in proper governance to be successful in project execution
  • 29. W e E m p o w e r O r g a n i z a t i o n s T o b e R e l i a b l y S u c c e s s f u l i n E x e c u t i n g L a r g e , C o m p l e x P r o j e c t s Discover more on w w w . P r o j e c t V a l u e D e l i v e r y . c o m Project Value Delivery Project Soft Power Unleashing Value from Your Large, Complex Projects Project Health Check Project Coaching Organizational maturity Team effectivenessIntercultural leadership Advanced project trainingProject Startup support Project Recovery Advanced risk management Project Control and Reporting Support systems integration Convergence planning Remote sites integration Leadership development