SlideShare a Scribd company logo
1 of 8
Download to read offline
A QuEST White Paper




                                Quality Engineering & Software Technologies
                                        No. 55, QuEST Towers, Whitefield Main Road,
                                            Mahadevpura, Bangalore, 560 048, INDIA.
                                          Tel: 91 80-4119 0900 Fax: 91 80-4119 0901
                                                              www.quest-global.com




                      Cost Reduction of a product through
                       Value Analysis & Value Engineering




                                                           By Ajitanath Patil.




Date April 28, 2010
1. Introduction:


The current business scenario is very demanding with a continuous demand from the market
forces to reduce the product price. The pricing as demanded by the market, forces the businesses
to reduce product development and manufacturing costs to remain competitive.


Manufacturing costs of a product can be broadly categorized in the following heads:
 • Raw material
 • Labor
 • Process that is technology driven


Product engineers are constantly faced with the following challenges:
 • Reduce production cost
 • Reduce the material cost


Value Analysis & Value Engineering (VAVE) methods are very important and useful in driving
down the product cost which helps companies retain market share and sustain their profitability.


2. What is VAVE ?
Value engineering began at General Electric Co. during World War II. Because of the war, there
were shortages of skilled labor and raw materials. Lawrence Miles and Harry Erlicher at GE
looked for acceptable substitutes for materials. They noticed that these substitutions often
reduced costs, improved the product, and in some cases, both. What started out as an
experiment driven by necessity was turned into a systematic process. They called their technique
“Value Analysis”. As others adopted the technique, the name gradually changed to Value
Engineering.


VAVE is a systematic process used by a multidisciplinary team, directed at analyzing the
functions of a project, product, process, system, design, or service for the purpose of achieving
the essential functions at the lowest life cycle cost consistent with required performance,
reliability, availability, quality and safety.


VAVE is the process of reducing costs in a development project. This process is achieved by
assessing materials, processes and or products and offering alternatives. The outcome should

                                                                                                   2
result in savings to the client / end user without compromising the intent of the design, i.e. by
maintaining or improving performance and quality requirements of the product. The key
metric/factor is to achieve the desired results without compromising on quality and performance of
the product.


Projects that use Value Engineering in the early development or conceptual stages are generally
more successful due to common understanding of the objectives, deliverables, and requirements.
At this point, major design and development resources have not yet been committed and the
manner in which the basic function of the project is to perform has not been established, so
alternative ways may be identified and considered. Applied with flexibility and creativity, Value
Engineering is almost unlimited in its ability to identify areas of potential savings.


An important aspect of Value Engineering lies in its ability to respond with timeliness, flexibility,
and creativity. It can be used for new or existing programs, all phases of a project, and for
organizational processes. Value Engineering can be used to improve quality, achieve lower costs,
assure compliance, improve efficiency, build teamwork and reduce risks.


3. VAVE Approach :


At QuEST, we uncover those projects of our customer which have a good potential to improve
profits. QuEST has a team of engineers who specialize in VAVE to achieve cost reductions of
products.


A typical VAVE exercise could reduce the total cost of a product by 5-40%. The typical elements
of a VAVE exercise are as follows :


 • Information: Understand the current state of the project and constraints / requirements.
 • Function Analysis: Understand the project from a functional perspective; what must the
         project do, rather than how the project is currently conceived. The function describes
         what something does and function analysis is the process where the team reviews the
         project's functions to determine those that could be improved. Function Analysis can be
         enhanced through the use of a graphical mapping tool known as the Function Analysis
         System Technique (FAST). FAST applies intuitive logic to test functions, create a
         common language for a team, and test the validity of the functions in the project.

                                                                                                   3
• Creative: Generate a quantity of ideas related to other ways to perform the functions.
 • Evaluation: Reduce the quantity of ideas that have been identified to a short list of ideas with
        the greatest potential to improve the project and meet the Value Engineering study
        objective.
 • Development: Further analyze and develop the short list of ideas and develop those with
        merit into value alternatives.
 • Presentation Phase / Implementation: Present value alternatives to management team and
        other project stakeholders or decision makers.


4. Typical Flowchart




5. An example :


The approach to a real life problem and the methodology followed by QuEST to reduce the
product cost is demonstrated through the following example.


5.1 Background and Problem statement:
One of the customers of QuEST is a leading manufacturer of industrial components for control
applications. This unit is very popular in high end applications.


The customer wanted to develop a unit that not only costs 25% less but whose performance
exceeds that of the existing product.



                                                                                                 4
5.2 Challenges:
 • Redesign of parts considering minimum impact on existing tooling
 • Redesigned modules should enable field replacement
 • Logic/Software compatibility with field units
 • Ease of assembly
 • Design must match existing housings and connectors
 • No modification of standardized parts in the product family


5.4 Value Engineering Study :
QuEST team captured the detailed requirements
                                                                             CTQ (Critical to Quality)
of the project from the Voice of Customer (VOC)
                                                     Matches basic function and performance
during the kick off meeting. It helped to identify   characteristics
areas where cost could be reduced and which          One to one module replacement
functions needed to be improved to provide           Same Outer dimensions for the modules
competitive advantage. The requirements were         Logic/Software compatibility with field units
listed and prioritized as primary and secondary.     No modification in standardized parts in
                                                     Product family.
These prioritized “Needs and Wants” were             Design must match existing housings and
ranked. Quality Function Deployment (QFD) tool       connectors
                                                     Reduce the cost of direct material by 25% or
was used to prioritize the “How’s” that affected     more.
the “Needs and Wants” of the customer. The                     Bill of Material with Cost
customer also actively participated in this           ID         Part Description
                                                                                    Cost for No. of items
                                                                                                            Item cost
                                                                                                                          Cost unit    Cost    Percentage
                                                                                                                                                            Class
                                                                                    100 units    unit                                 Subtotal   of Cost
                                                       1   PART - 1                     658.50          2          3.29        6.59
exercise. Vital few options were prioritized from      2
                                                       3
                                                           PART - 2
                                                           PART - 3
                                                                                        566.13
                                                                                        422.15
                                                                                                        1
                                                                                                        1
                                                                                                                   5.66
                                                                                                                   4.22
                                                                                                                               5.66
                                                                                                                               4.22
                                                       4   PART - 4                     402.11          1          4.02        4.02
                                                                                                                                       56.78     73.8%       A
the trivial many. Design requirement ranks were        5
                                                       6
                                                           PART - 5
                                                           PART - 6
                                                                                        388.99
                                                                                        150.01
                                                                                                        1
                                                                                                        1
                                                                                                                   3.89
                                                                                                                   1.50
                                                                                                                               3.89
                                                                                                                               1.50
                                                       7   PART - 7                     146.26          1          1.46        1.46
                                                       8   PART - 8                     146.01          1          1.46        1.46
sorted in descending order and those which             9   PART - 9                     146.00          1          1.46        1.46
                                                      10
                                                      11
                                                           PART - 10
                                                           PART - 11
                                                                                        145.75
                                                                                        104.00
                                                                                                        1
                                                                                                        2
                                                                                                                   1.46
                                                                                                                   0.52
                                                                                                                               1.46
                                                                                                                               1.04
                                                                                                                                       12.81     16.7%       B
addressed 70% of the requirements were                12
                                                      13
                                                           PART - 12
                                                           PART - 13
                                                                                        272.96
                                                                                         37.89
                                                                                                        8
                                                                                                        1
                                                                                                                   0.34
                                                                                                                   0.38
                                                                                                                               2.73
                                                                                                                               0.38
                                                      14   PART - 14                     37.16          4          0.09        0.37

selected.    Thus    CTQs      or    performance      15
                                                      16
                                                           PART - 15
                                                           PART - 16
                                                                                         35.19
                                                                                         34.77
                                                                                                        4
                                                                                                        1
                                                                                                                   0.09
                                                                                                                   0.35
                                                                                                                               0.35
                                                                                                                               0.35
                                                      17   PART - 17                     31.86          6          0.05        0.32
                                                      18   PART - 18                     28.34          1          0.28        0.28
characteristics were identified and agreed upon       19   PART - 19                     28.34          1          0.28        0.28
                                                      20   PART - 20                     28.12          2          0.14        0.28
                                                      21   PART - 21                     27.96          2          0.14        0.28
with the customer.                                    22   PART - 22                     20.98          2          0.10        0.21
                                                                                                                                       7.30       9.5%       C
                                                      23   PART - 23                     18.72          4          0.05        0.19
                                                      24   PART - 24                     18.58          2          0.09        0.19
                                                      25   PART - 25                     88.08          4          0.22        0.88
                                                      26   PART - 26                     18.18          1          0.18        0.18
                                                      27   PART - 27                     18.18          1          0.18        0.18
                                                      28   PART - 28                     18.14          1          0.18        0.18
The team then carried out the ‘ABC analysis’ on       29   PART - 29                     18.14          1          0.18        0.18



the BOM. Components with more than 80% of
the product cost were identified.




                                                                                                                                                                    5
Next, the VAVE team laid down the Functions                                                                   Functional Analysis
of each item of the product for Value analysis.         Sl                              Part /                                  What Does it Do?
This enhanced the understanding of the                  No.                            Module                                 Verb           Noun
                                                         1                             Part - 1                               Pulls        Material
product functionality. This also helped to
                                                                                                                             Guides        Material
understand the Form, Fit & Functions of each of               2                          Part - 2                            Mounts    Interface board
                                                                                                                             Stabilize    Assembly
the items & sub-assemblies. With this study,                                                                                  Holds         Part - 8
the VAVE team had divided the main project                    3                          Part - 3                            Covers     Internal Parts
                                                                                                                             Guides        Material
into many sub-projects with respect to sub-                   4                          Part - 4                            Stabilize    Assenbly
assemblies to have diversified results for sub-                                                                               Holds         Part - 8
                                                              5                          Part - 5                             Drives       Material
assemblies and parts.
                                                              6                          Part - 6                             Drives       Material
                                                              7                          Part - 7                            Covers        Part - 12
This function diagram threw up many questions                 8                          Part - 8                             Holds         Part - 8
to the team which enabled them to come up                                                                        Pugh Matrix – n1
with a number of new ideas.                                                                                                                                  + = Better alternative                 Compare current concept
                                                                                                                                                                                                    with selected alternatives
                                                                                                                                                             - = Worse alternative
                                                                                                                              Pugh Matrix                    s = same alternative




   •   How the Product is sized? What design                             Project Title/
                                                                       Members present
                                                                                                                                                                                                        Date:


                                                               Pugh Concept
                                                              Selection Matrix                                Concept 1        Concept 2        Concept 3        Concept 4                               REMARKS
       parameters were employed for this                     Comarison Criteria
                                                              Brief explanation
                                                       Existing Mounting options as in field units to
                                                       match
                                                                                                                   S                 S              S
       product?                                        Matches basic function and performance
                                                       characteristics - same/better-
                                                                                                                   S                 S              S
                                                       1-2-1 module replacement- either of modules
                                                       are replaceble for the units in the field.
                                                                                                                   S                 -              -

   •   Focus on high cost components and               Same Outer dimensions for the feeder and
                                                       printer modules


                                                       Logic/Software compatibility with field units
                                                                                                                   S
                                                                                                                   S
                                                                                                                                     S
                                                                                                                                     -
                                                                                                                                                    S
                                                                                                                                                    -
                                                       Return on Investment - between 3K to 5K
                                                                                                                   +                 +              +
       challenge by asking “why do we need
                                                       parts


                                                       Less # of parts - w.r.t. present Module
                                                                                                                   S                 +              +
                                                       Parts standardised
                                                                                                                   S                 S              S
       this part and what value does it provide        Ease of manufacturing and sourcing
                                                                                                                   +                 -              S
                                                       Easy to assemble
                                                                                                                   S                 S              S
                                                                                                                   S                 S              S
       to our customer?”                               Environment factors,- Temp, Humidity




                                                                    Total # of "+"                                 2                 2              2

   •   How else we can design/make it.                               Total # of "-"                                0                 3              2
                                                                    Total # of "S"                                 9                 6              7

   •   Understand design change impact on                      Score - Decision                                    2
                                                                                                              Favorite 1
                                                                                                                                     -1
                                                                                                                               Favorite 3
                                                                                                                                                    0
                                                                                                                                                Favorite 2


       subassembly or overall product.                                                                           Pugh Matrix – n2
   •   System level appraisal is desirable to                                                                                                                                         + = Better alternative

                                                                                                                                                                                      - = Worse alternative
                                                                                                                                                                                                                Compare current
                                                                                                                                                                                                                concept
                                                                                                                                Pugh Matrix                                           s = same alternative
                                                                                                                                                                                                                with selected
                                                                                                                                                                                                                alternatives



       consider different methods or concepts                Project Title/ Project No.:
                                                                 Members present
                                                             Pugh Concept
                                                                                                                                                                                                                  Date:



                                                            Selection Matrix                           Concept 1 Concept 2 Concept 3 Concept 4 Concept 5 Concept 6                                              REMARKS
                                                           Comarison Criteria
       for delivering the same or better value.             Brief explanation
                                                      Existing Mounting options as in field units to
                                                      match                                               -            S         S          S           -              -

   •
                                                      Matches basic function and performance              S            -         S          S           S              -
       Component level assessment is looked-          characteristics - same/better-

                                                      1-2-1 module replacement- either of modules
                                                      are replaceble for the units in the field.
                                                                                                          S            S         S          S           S             S
                                                      Same Outer dimensions for the feeder and
                                                      printer modules                                     -            S         S          S           -             -
       for   to   consider   alternate   materials,   Logic/Software compatibility with field units
                                                      Return on Investment - between 3K to 5K
                                                      parts
                                                                                                          S
                                                                                                          -
                                                                                                                       -
                                                                                                                       +
                                                                                                                                 S
                                                                                                                                 +
                                                                                                                                            -
                                                                                                                                            -
                                                                                                                                                        -
                                                                                                                                                        +
                                                                                                                                                                      -
                                                                                                                                                                      -
                                                      Less # of parts - w.r.t. present Module             -            +         +          +           +             -
       processes, and more efficient designs.         Parts standardised

                                                      Ease of manufacturing and sourcing
                                                                                                          S
                                                                                                          -
                                                                                                                       S
                                                                                                                       S
                                                                                                                                 S
                                                                                                                                 +
                                                                                                                                            S
                                                                                                                                            -
                                                                                                                                                        S
                                                                                                                                                        +
                                                                                                                                                                      S
                                                                                                                                                                      +
                                                                                                          S            S         +          -           -             -
   •
                                                      Easy to assemble


       One of the guiding principles of lean          Environment factors,- Temp, Humidity                +            -         +          S           S             +

                                                              Total # of "+"                              1          2          6           1          3          2

       design is to “eliminate or standardize.”                Total # of "-"
                                                              Total # of "S"
                                                                                                          6
                                                                                                          5
                                                                                                                     4
                                                                                                                     6
                                                                                                                                0
                                                                                                                                6
                                                                                                                                            5
                                                                                                                                            6
                                                                                                                                                       5
                                                                                                                                                       4
                                                                                                                                                                  8
                                                                                                                                                                  2
                                                             Score - Decision                             -5         -2         6          -4         -2         -6
                                                                                                       Favorite 5 Favorite 3 Favorite 1 Favorite 4 Favorite 2 Favorite 6
       Can a part be combined with others and



                                                                                                                                                                                                                                  6
thereby be eliminated? If not, can it be made common with other parts in the product,
             without compromising FFF (Form Fit & Function). This typically provides quick savings.
      •      Identify and capture all cost reduction opportunities.


The team applied the concept of Pugh Matrix for system & component level. Rankings were
discussed with team, collated and analyzed for choosing the optimum concepts.


Next, FMEA was conducted on the selected concepts to further fine tune the results. Failure
modes with high Risk Priority Number (RPN) were identified. Failure modes were prioritized and
communicated to the designers to address these risks. Alternate solutions and improvement were
discussed and finalized.


3D solid modeling was done to visualize the product. It also helped to simulate the active and
passive conditions of the product. Components were standardized to reduce the part count.
Simulation and testing against the CTQs helped to optimize the product for performances. Design
calculations were performed to verify the design for gears, springs, snaps in the plastic members,
etc.. Also the DFMA was conducted on various aspects of the design & CTQs.


                             Cost Analysis

 Sl   Part /         Old                                             New
                                         Comments                           Savings   A detailed Differential Cost Analysis was
 No. Module          Cost                                            cost
  1 Part - 1         6.58   NO change, no savings                    6.58    0.00
                                                                                      conducted    with   the   customer   and   their
                            Replaced with plastic part. Functions
  2       Part - 2   5.66   of Part - 8 mounting bracket, nuts       0.41    5.26     suppliers. The result showed significant cost
                            are combined with this part.

  3       Part - 3   3.10   Replaced with thin plastic part, press   0.80    2.30     reduction of each part of the product. It was
                            Replaced with plastic part. Functions                     observed that the costs were reduced mainly
  4       Part - 4   4.00   of Part - 8 mounting bracket, nuts       0.47    3.53
                            are combined with this part.                              due to alternate materials usage, the process
  5       Part - 5   3.89   NO change, no savings                    3.89    0.00
                                                                                      and by elimination/replacement of a part by
  6       Part - 6   3.89   NO change, no savings                    3.89    0.00
  7       Part - 7   3.40   Replaced with thin plastic part, press   0.80    2.60     integrating with the adjacent one.
  8       Part - 8   3.60   Replaced with thick paper part.          0.47    3.13




                                                                                                                                    7
Costs of direct material were compared for the original and new design. A significant 38% of
savings in direct material cost was realized by this project. The team also achieved a reduction of
34% in the part count. This has resulted in many intangible benefits like savings in procurement
costs, Inspection costs, Inventory cost, transportation, reduced variation, reduced assembly costs
& Time, etc.


6. Conclusion:
QuEST ‘Value Engineering team’ achieved 38% of savings in direct material cost and reduced
part count by 34% in this project.


Having a Paint brush does not make one a painter. While we strive to implement the different
VAVE tools, we realize that the years of experience in product design & development is very
essential to achieve the desired objective. VAVE tools and techniques, if applied properly, with
trained & experienced resources will provide an extremely powerful suite to improve productivity,
lower cost, improve quality and also shorten the time-to-market.



Acronym:
VAVE : Value Analysis & Value Engineering
FAST : Function Analysis System Technique
VOC : Voice of Customer
QFD : Quality Function Deployment
CTQ : Critical To Quality
BOM : Bill of Material
FFF     : Form, Fit & Function
FMEA : Failure Mode and Effects Analysis
DFMA : Design for Manufacturing and Assembly



About the author:

Ajitanath Patil is the Sr. Tech Lead at QuEST Global (Engineering Services, Manufacturing and SEZ). Ajitanath has 16 years of
work experience in different roles within the purview of Design & Development of SPMs. He has a Bachelor of Engineering
(B.E) in Mechanical Engineering and a PGD in Robotics & Industrial Automation.




                                                                                                                           8

More Related Content

What's hot

Value analysis and Value Engineering
Value analysis and Value EngineeringValue analysis and Value Engineering
Value analysis and Value EngineeringTushar Lohani
 
Value engineering Short Over view ppt
Value engineering Short Over view pptValue engineering Short Over view ppt
Value engineering Short Over view pptMashfiq Albartross
 
DFM Design Principles
DFM Design PrinciplesDFM Design Principles
DFM Design PrinciplesNIELITA
 
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_GValue_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_GMohan Kumar G
 
Fundamentals of value engineering
Fundamentals of value engineering Fundamentals of value engineering
Fundamentals of value engineering Karim Ragab
 
Chapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGChapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGProf.Mayur Modi
 
Concurrent engineering
Concurrent engineering Concurrent engineering
Concurrent engineering Amol Chakankar
 
Value engineering seminar presentation
Value engineering seminar presentationValue engineering seminar presentation
Value engineering seminar presentationamrutrajbk
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)Victor Al
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing SystemVishal Jadhav
 
Product Design and Development
Product Design and DevelopmentProduct Design and Development
Product Design and DevelopmentSURYAPRAKASH S
 
Group technology, Production flow Analysis
Group technology, Production flow AnalysisGroup technology, Production flow Analysis
Group technology, Production flow AnalysisKEERTHIVASAN RAVI
 
Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing Joshua Miranda
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Pratik Gandhi
 

What's hot (20)

Value analysis and Value Engineering
Value analysis and Value EngineeringValue analysis and Value Engineering
Value analysis and Value Engineering
 
Value engineering Short Over view ppt
Value engineering Short Over view pptValue engineering Short Over view ppt
Value engineering Short Over view ppt
 
DFM Design Principles
DFM Design PrinciplesDFM Design Principles
DFM Design Principles
 
Value Engineering
Value EngineeringValue Engineering
Value Engineering
 
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_GValue_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G
 
Fundamentals of value engineering
Fundamentals of value engineering Fundamentals of value engineering
Fundamentals of value engineering
 
Chapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERINGChapter 3. CON CURRENT ENGINEERING
Chapter 3. CON CURRENT ENGINEERING
 
Lean vs agile manufacturing
Lean vs agile manufacturingLean vs agile manufacturing
Lean vs agile manufacturing
 
Concurrent engineering
Concurrent engineering Concurrent engineering
Concurrent engineering
 
Value engineering seminar presentation
Value engineering seminar presentationValue engineering seminar presentation
Value engineering seminar presentation
 
Fast method
Fast methodFast method
Fast method
 
COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)COMPUTER AIDED PROCESS PLANNING (CAPP)
COMPUTER AIDED PROCESS PLANNING (CAPP)
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing System
 
CAD/CAM
CAD/CAMCAD/CAM
CAD/CAM
 
Product Design and Development
Product Design and DevelopmentProduct Design and Development
Product Design and Development
 
Group technology, Production flow Analysis
Group technology, Production flow AnalysisGroup technology, Production flow Analysis
Group technology, Production flow Analysis
 
Product design and development
Product design and developmentProduct design and development
Product design and development
 
Value Engineering
Value EngineeringValue Engineering
Value Engineering
 
Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing Product Design & Process Selection-Manufacturing
Product Design & Process Selection-Manufacturing
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)
 

Similar to Cost Reduction of a product through Value Analysis & Value Engineering

572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...
572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...
572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...ssuser149600
 
OPS 571T Education Specialist |tutorialrank.com
OPS 571T Education Specialist |tutorialrank.comOPS 571T Education Specialist |tutorialrank.com
OPS 571T Education Specialist |tutorialrank.comladworkspaces
 
IRJET- Overview of Value Engineering and Value Analysis
IRJET- Overview of Value Engineering and Value AnalysisIRJET- Overview of Value Engineering and Value Analysis
IRJET- Overview of Value Engineering and Value AnalysisIRJET Journal
 
Performance Testing in Agile Process
Performance Testing in Agile ProcessPerformance Testing in Agile Process
Performance Testing in Agile ProcessIdexcel Technologies
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET Journal
 
Acceptance test driven development
Acceptance test driven developmentAcceptance test driven development
Acceptance test driven developmentEditor Jacotech
 
Unit4 reverse engineering
Unit4 reverse engineeringUnit4 reverse engineering
Unit4 reverse engineeringAtul Joshi
 
IRJET- A Case Study Analysis through the Implementation of Value Engineering
IRJET- A Case Study Analysis through the Implementation of Value EngineeringIRJET- A Case Study Analysis through the Implementation of Value Engineering
IRJET- A Case Study Analysis through the Implementation of Value EngineeringIRJET Journal
 
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...IRJET Journal
 
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...IRJET Journal
 
Ops 571 ops571 ops 571 best tutorials guide uopstudy.com
Ops 571 ops571 ops 571 best tutorials guide  uopstudy.comOps 571 ops571 ops 571 best tutorials guide  uopstudy.com
Ops 571 ops571 ops 571 best tutorials guide uopstudy.comULLPTT
 
Ops 571 ops571 ops 571 education for service uopstudy.com
Ops 571 ops571 ops 571 education for service   uopstudy.comOps 571 ops571 ops 571 education for service   uopstudy.com
Ops 571 ops571 ops 571 education for service uopstudy.comULLPTT
 
Ops 571 ops571 ops 571 effective communication uopstudy.com
Ops 571 ops571 ops 571 effective communication   uopstudy.comOps 571 ops571 ops 571 effective communication   uopstudy.com
Ops 571 ops571 ops 571 effective communication uopstudy.comULLPTT
 
Ops 571 ops571 ops 571 forecasting and strategic planning -uopstudy.com
Ops 571 ops571 ops 571 forecasting and strategic planning -uopstudy.comOps 571 ops571 ops 571 forecasting and strategic planning -uopstudy.com
Ops 571 ops571 ops 571 forecasting and strategic planning -uopstudy.comULLPTT
 
Value engineering and Analysis
Value engineering and AnalysisValue engineering and Analysis
Value engineering and AnalysisChaitanya Chenna
 

Similar to Cost Reduction of a product through Value Analysis & Value Engineering (20)

572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...
572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...
572021116-WINSEM2021-22-ECE3502-ETH-VL2021220501486-Reference-Material-I-15-0...
 
OPS 571T Education Specialist |tutorialrank.com
OPS 571T Education Specialist |tutorialrank.comOPS 571T Education Specialist |tutorialrank.com
OPS 571T Education Specialist |tutorialrank.com
 
Value analysis
Value analysisValue analysis
Value analysis
 
IRJET- Overview of Value Engineering and Value Analysis
IRJET- Overview of Value Engineering and Value AnalysisIRJET- Overview of Value Engineering and Value Analysis
IRJET- Overview of Value Engineering and Value Analysis
 
Performance Testing in Agile Process
Performance Testing in Agile ProcessPerformance Testing in Agile Process
Performance Testing in Agile Process
 
VALUE ANALYSIS
VALUE ANALYSISVALUE ANALYSIS
VALUE ANALYSIS
 
IRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and ProgramsIRJET- The Application of Value Engineering to Highway Projects and Programs
IRJET- The Application of Value Engineering to Highway Projects and Programs
 
iiBA babok onapage
iiBA babok onapageiiBA babok onapage
iiBA babok onapage
 
Acceptance test driven development
Acceptance test driven developmentAcceptance test driven development
Acceptance test driven development
 
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
Design and Development of Stamping Bracket of Snowmobile Using Computer Aided...
 
Unit4 reverse engineering
Unit4 reverse engineeringUnit4 reverse engineering
Unit4 reverse engineering
 
IRJET- A Case Study Analysis through the Implementation of Value Engineering
IRJET- A Case Study Analysis through the Implementation of Value EngineeringIRJET- A Case Study Analysis through the Implementation of Value Engineering
IRJET- A Case Study Analysis through the Implementation of Value Engineering
 
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
 
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
IRJET- Value Analysis for Cost Saving in Mechanical Pencil Manufacturing: A C...
 
Ops 571 ops571 ops 571 best tutorials guide uopstudy.com
Ops 571 ops571 ops 571 best tutorials guide  uopstudy.comOps 571 ops571 ops 571 best tutorials guide  uopstudy.com
Ops 571 ops571 ops 571 best tutorials guide uopstudy.com
 
Ops 571 ops571 ops 571 education for service uopstudy.com
Ops 571 ops571 ops 571 education for service   uopstudy.comOps 571 ops571 ops 571 education for service   uopstudy.com
Ops 571 ops571 ops 571 education for service uopstudy.com
 
Ops 571 ops571 ops 571 effective communication uopstudy.com
Ops 571 ops571 ops 571 effective communication   uopstudy.comOps 571 ops571 ops 571 effective communication   uopstudy.com
Ops 571 ops571 ops 571 effective communication uopstudy.com
 
Ops 571 ops571 ops 571 forecasting and strategic planning -uopstudy.com
Ops 571 ops571 ops 571 forecasting and strategic planning -uopstudy.comOps 571 ops571 ops 571 forecasting and strategic planning -uopstudy.com
Ops 571 ops571 ops 571 forecasting and strategic planning -uopstudy.com
 
Value engineering and Analysis
Value engineering and AnalysisValue engineering and Analysis
Value engineering and Analysis
 
Quality function development
Quality function developmentQuality function development
Quality function development
 

More from QuEST Global

NMAMIT’s iCar zooms into finals of engineering contest
NMAMIT’s iCar zooms into finals of engineering contestNMAMIT’s iCar zooms into finals of engineering contest
NMAMIT’s iCar zooms into finals of engineering contestQuEST Global
 
Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...
Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...
Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...QuEST Global
 
Productivity improvement in generation of so ps for oil & gas equipment manuf...
Productivity improvement in generation of so ps for oil & gas equipment manuf...Productivity improvement in generation of so ps for oil & gas equipment manuf...
Productivity improvement in generation of so ps for oil & gas equipment manuf...QuEST Global
 
Significance of technical publications
Significance of technical publicationsSignificance of technical publications
Significance of technical publicationsQuEST Global
 
Quest global overview
Quest global overviewQuest global overview
Quest global overviewQuEST Global
 
End to-end aerospace engineering solutions
End to-end aerospace engineering solutionsEnd to-end aerospace engineering solutions
End to-end aerospace engineering solutionsQuEST Global
 
QuEST for the skies
QuEST for the skiesQuEST for the skies
QuEST for the skiesQuEST Global
 
ನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶ
ನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶ
ನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶQuEST Global
 
QuEST, Cades Outbid Infy to Bag Airbus Deal
QuEST, Cades Outbid Infy to Bag Airbus DealQuEST, Cades Outbid Infy to Bag Airbus Deal
QuEST, Cades Outbid Infy to Bag Airbus DealQuEST Global
 
Trio wins engineering design contest
Trio wins engineering design contestTrio wins engineering design contest
Trio wins engineering design contestQuEST Global
 
Trio wins engineering design contestTrio wins engineering design contest
Trio wins engineering design contestTrio wins engineering design contestTrio wins engineering design contestTrio wins engineering design contest
Trio wins engineering design contestTrio wins engineering design contestQuEST Global
 
QuEST Ingenium 2011
QuEST Ingenium 2011QuEST Ingenium 2011
QuEST Ingenium 2011QuEST Global
 
क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र
क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र
क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र QuEST Global
 
Quest global acquires spanish company
Quest global acquires spanish companyQuest global acquires spanish company
Quest global acquires spanish companyQuEST Global
 
Airbus signs strategic agreement with indian supplier
Airbus signs strategic agreement with indian supplierAirbus signs strategic agreement with indian supplier
Airbus signs strategic agreement with indian supplierQuEST Global
 
Black Book of Outsourcing
Black Book of OutsourcingBlack Book of Outsourcing
Black Book of OutsourcingQuEST Global
 
Nuclear Capabilities
Nuclear CapabilitiesNuclear Capabilities
Nuclear CapabilitiesQuEST Global
 
Testing & Integration Capabilities
Testing & Integration CapabilitiesTesting & Integration Capabilities
Testing & Integration CapabilitiesQuEST Global
 
System & Accessories Capabilities
System & Accessories CapabilitiesSystem & Accessories Capabilities
System & Accessories CapabilitiesQuEST Global
 

More from QuEST Global (20)

NMAMIT’s iCar zooms into finals of engineering contest
NMAMIT’s iCar zooms into finals of engineering contestNMAMIT’s iCar zooms into finals of engineering contest
NMAMIT’s iCar zooms into finals of engineering contest
 
Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...
Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...
Studies on impact of inlet viscosity ratio, decay rate & length scales in a c...
 
Productivity improvement in generation of so ps for oil & gas equipment manuf...
Productivity improvement in generation of so ps for oil & gas equipment manuf...Productivity improvement in generation of so ps for oil & gas equipment manuf...
Productivity improvement in generation of so ps for oil & gas equipment manuf...
 
Significance of technical publications
Significance of technical publicationsSignificance of technical publications
Significance of technical publications
 
Quest global overview
Quest global overviewQuest global overview
Quest global overview
 
End to-end aerospace engineering solutions
End to-end aerospace engineering solutionsEnd to-end aerospace engineering solutions
End to-end aerospace engineering solutions
 
QuEST for the skies
QuEST for the skiesQuEST for the skies
QuEST for the skies
 
ನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶ
ನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶ
ನೂತನ ಕೊರ್ಸನಿಂದ ಉದ್ಯೋಗವಕಾಶ
 
QuEST, Cades Outbid Infy to Bag Airbus Deal
QuEST, Cades Outbid Infy to Bag Airbus DealQuEST, Cades Outbid Infy to Bag Airbus Deal
QuEST, Cades Outbid Infy to Bag Airbus Deal
 
Pudari
PudariPudari
Pudari
 
Trio wins engineering design contest
Trio wins engineering design contestTrio wins engineering design contest
Trio wins engineering design contest
 
Trio wins engineering design contestTrio wins engineering design contest
Trio wins engineering design contestTrio wins engineering design contestTrio wins engineering design contestTrio wins engineering design contest
Trio wins engineering design contestTrio wins engineering design contest
 
QuEST Ingenium 2011
QuEST Ingenium 2011QuEST Ingenium 2011
QuEST Ingenium 2011
 
क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र
क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र
क्वेस्ट जीआयटी यांचे प्रशिक्षण केंद्र
 
Quest global acquires spanish company
Quest global acquires spanish companyQuest global acquires spanish company
Quest global acquires spanish company
 
Airbus signs strategic agreement with indian supplier
Airbus signs strategic agreement with indian supplierAirbus signs strategic agreement with indian supplier
Airbus signs strategic agreement with indian supplier
 
Black Book of Outsourcing
Black Book of OutsourcingBlack Book of Outsourcing
Black Book of Outsourcing
 
Nuclear Capabilities
Nuclear CapabilitiesNuclear Capabilities
Nuclear Capabilities
 
Testing & Integration Capabilities
Testing & Integration CapabilitiesTesting & Integration Capabilities
Testing & Integration Capabilities
 
System & Accessories Capabilities
System & Accessories CapabilitiesSystem & Accessories Capabilities
System & Accessories Capabilities
 

Cost Reduction of a product through Value Analysis & Value Engineering

  • 1. A QuEST White Paper Quality Engineering & Software Technologies No. 55, QuEST Towers, Whitefield Main Road, Mahadevpura, Bangalore, 560 048, INDIA. Tel: 91 80-4119 0900 Fax: 91 80-4119 0901 www.quest-global.com Cost Reduction of a product through Value Analysis & Value Engineering By Ajitanath Patil. Date April 28, 2010
  • 2. 1. Introduction: The current business scenario is very demanding with a continuous demand from the market forces to reduce the product price. The pricing as demanded by the market, forces the businesses to reduce product development and manufacturing costs to remain competitive. Manufacturing costs of a product can be broadly categorized in the following heads: • Raw material • Labor • Process that is technology driven Product engineers are constantly faced with the following challenges: • Reduce production cost • Reduce the material cost Value Analysis & Value Engineering (VAVE) methods are very important and useful in driving down the product cost which helps companies retain market share and sustain their profitability. 2. What is VAVE ? Value engineering began at General Electric Co. during World War II. Because of the war, there were shortages of skilled labor and raw materials. Lawrence Miles and Harry Erlicher at GE looked for acceptable substitutes for materials. They noticed that these substitutions often reduced costs, improved the product, and in some cases, both. What started out as an experiment driven by necessity was turned into a systematic process. They called their technique “Value Analysis”. As others adopted the technique, the name gradually changed to Value Engineering. VAVE is a systematic process used by a multidisciplinary team, directed at analyzing the functions of a project, product, process, system, design, or service for the purpose of achieving the essential functions at the lowest life cycle cost consistent with required performance, reliability, availability, quality and safety. VAVE is the process of reducing costs in a development project. This process is achieved by assessing materials, processes and or products and offering alternatives. The outcome should 2
  • 3. result in savings to the client / end user without compromising the intent of the design, i.e. by maintaining or improving performance and quality requirements of the product. The key metric/factor is to achieve the desired results without compromising on quality and performance of the product. Projects that use Value Engineering in the early development or conceptual stages are generally more successful due to common understanding of the objectives, deliverables, and requirements. At this point, major design and development resources have not yet been committed and the manner in which the basic function of the project is to perform has not been established, so alternative ways may be identified and considered. Applied with flexibility and creativity, Value Engineering is almost unlimited in its ability to identify areas of potential savings. An important aspect of Value Engineering lies in its ability to respond with timeliness, flexibility, and creativity. It can be used for new or existing programs, all phases of a project, and for organizational processes. Value Engineering can be used to improve quality, achieve lower costs, assure compliance, improve efficiency, build teamwork and reduce risks. 3. VAVE Approach : At QuEST, we uncover those projects of our customer which have a good potential to improve profits. QuEST has a team of engineers who specialize in VAVE to achieve cost reductions of products. A typical VAVE exercise could reduce the total cost of a product by 5-40%. The typical elements of a VAVE exercise are as follows : • Information: Understand the current state of the project and constraints / requirements. • Function Analysis: Understand the project from a functional perspective; what must the project do, rather than how the project is currently conceived. The function describes what something does and function analysis is the process where the team reviews the project's functions to determine those that could be improved. Function Analysis can be enhanced through the use of a graphical mapping tool known as the Function Analysis System Technique (FAST). FAST applies intuitive logic to test functions, create a common language for a team, and test the validity of the functions in the project. 3
  • 4. • Creative: Generate a quantity of ideas related to other ways to perform the functions. • Evaluation: Reduce the quantity of ideas that have been identified to a short list of ideas with the greatest potential to improve the project and meet the Value Engineering study objective. • Development: Further analyze and develop the short list of ideas and develop those with merit into value alternatives. • Presentation Phase / Implementation: Present value alternatives to management team and other project stakeholders or decision makers. 4. Typical Flowchart 5. An example : The approach to a real life problem and the methodology followed by QuEST to reduce the product cost is demonstrated through the following example. 5.1 Background and Problem statement: One of the customers of QuEST is a leading manufacturer of industrial components for control applications. This unit is very popular in high end applications. The customer wanted to develop a unit that not only costs 25% less but whose performance exceeds that of the existing product. 4
  • 5. 5.2 Challenges: • Redesign of parts considering minimum impact on existing tooling • Redesigned modules should enable field replacement • Logic/Software compatibility with field units • Ease of assembly • Design must match existing housings and connectors • No modification of standardized parts in the product family 5.4 Value Engineering Study : QuEST team captured the detailed requirements CTQ (Critical to Quality) of the project from the Voice of Customer (VOC) Matches basic function and performance during the kick off meeting. It helped to identify characteristics areas where cost could be reduced and which One to one module replacement functions needed to be improved to provide Same Outer dimensions for the modules competitive advantage. The requirements were Logic/Software compatibility with field units listed and prioritized as primary and secondary. No modification in standardized parts in Product family. These prioritized “Needs and Wants” were Design must match existing housings and ranked. Quality Function Deployment (QFD) tool connectors Reduce the cost of direct material by 25% or was used to prioritize the “How’s” that affected more. the “Needs and Wants” of the customer. The Bill of Material with Cost customer also actively participated in this ID Part Description Cost for No. of items Item cost Cost unit Cost Percentage Class 100 units unit Subtotal of Cost 1 PART - 1 658.50 2 3.29 6.59 exercise. Vital few options were prioritized from 2 3 PART - 2 PART - 3 566.13 422.15 1 1 5.66 4.22 5.66 4.22 4 PART - 4 402.11 1 4.02 4.02 56.78 73.8% A the trivial many. Design requirement ranks were 5 6 PART - 5 PART - 6 388.99 150.01 1 1 3.89 1.50 3.89 1.50 7 PART - 7 146.26 1 1.46 1.46 8 PART - 8 146.01 1 1.46 1.46 sorted in descending order and those which 9 PART - 9 146.00 1 1.46 1.46 10 11 PART - 10 PART - 11 145.75 104.00 1 2 1.46 0.52 1.46 1.04 12.81 16.7% B addressed 70% of the requirements were 12 13 PART - 12 PART - 13 272.96 37.89 8 1 0.34 0.38 2.73 0.38 14 PART - 14 37.16 4 0.09 0.37 selected. Thus CTQs or performance 15 16 PART - 15 PART - 16 35.19 34.77 4 1 0.09 0.35 0.35 0.35 17 PART - 17 31.86 6 0.05 0.32 18 PART - 18 28.34 1 0.28 0.28 characteristics were identified and agreed upon 19 PART - 19 28.34 1 0.28 0.28 20 PART - 20 28.12 2 0.14 0.28 21 PART - 21 27.96 2 0.14 0.28 with the customer. 22 PART - 22 20.98 2 0.10 0.21 7.30 9.5% C 23 PART - 23 18.72 4 0.05 0.19 24 PART - 24 18.58 2 0.09 0.19 25 PART - 25 88.08 4 0.22 0.88 26 PART - 26 18.18 1 0.18 0.18 27 PART - 27 18.18 1 0.18 0.18 28 PART - 28 18.14 1 0.18 0.18 The team then carried out the ‘ABC analysis’ on 29 PART - 29 18.14 1 0.18 0.18 the BOM. Components with more than 80% of the product cost were identified. 5
  • 6. Next, the VAVE team laid down the Functions Functional Analysis of each item of the product for Value analysis. Sl Part / What Does it Do? This enhanced the understanding of the No. Module Verb Noun 1 Part - 1 Pulls Material product functionality. This also helped to Guides Material understand the Form, Fit & Functions of each of 2 Part - 2 Mounts Interface board Stabilize Assembly the items & sub-assemblies. With this study, Holds Part - 8 the VAVE team had divided the main project 3 Part - 3 Covers Internal Parts Guides Material into many sub-projects with respect to sub- 4 Part - 4 Stabilize Assenbly assemblies to have diversified results for sub- Holds Part - 8 5 Part - 5 Drives Material assemblies and parts. 6 Part - 6 Drives Material 7 Part - 7 Covers Part - 12 This function diagram threw up many questions 8 Part - 8 Holds Part - 8 to the team which enabled them to come up Pugh Matrix – n1 with a number of new ideas. + = Better alternative Compare current concept with selected alternatives - = Worse alternative Pugh Matrix s = same alternative • How the Product is sized? What design Project Title/ Members present Date: Pugh Concept Selection Matrix Concept 1 Concept 2 Concept 3 Concept 4 REMARKS parameters were employed for this Comarison Criteria Brief explanation Existing Mounting options as in field units to match S S S product? Matches basic function and performance characteristics - same/better- S S S 1-2-1 module replacement- either of modules are replaceble for the units in the field. S - - • Focus on high cost components and Same Outer dimensions for the feeder and printer modules Logic/Software compatibility with field units S S S - S - Return on Investment - between 3K to 5K + + + challenge by asking “why do we need parts Less # of parts - w.r.t. present Module S + + Parts standardised S S S this part and what value does it provide Ease of manufacturing and sourcing + - S Easy to assemble S S S S S S to our customer?” Environment factors,- Temp, Humidity Total # of "+" 2 2 2 • How else we can design/make it. Total # of "-" 0 3 2 Total # of "S" 9 6 7 • Understand design change impact on Score - Decision 2 Favorite 1 -1 Favorite 3 0 Favorite 2 subassembly or overall product. Pugh Matrix – n2 • System level appraisal is desirable to + = Better alternative - = Worse alternative Compare current concept Pugh Matrix s = same alternative with selected alternatives consider different methods or concepts Project Title/ Project No.: Members present Pugh Concept Date: Selection Matrix Concept 1 Concept 2 Concept 3 Concept 4 Concept 5 Concept 6 REMARKS Comarison Criteria for delivering the same or better value. Brief explanation Existing Mounting options as in field units to match - S S S - - • Matches basic function and performance S - S S S - Component level assessment is looked- characteristics - same/better- 1-2-1 module replacement- either of modules are replaceble for the units in the field. S S S S S S Same Outer dimensions for the feeder and printer modules - S S S - - for to consider alternate materials, Logic/Software compatibility with field units Return on Investment - between 3K to 5K parts S - - + S + - - - + - - Less # of parts - w.r.t. present Module - + + + + - processes, and more efficient designs. Parts standardised Ease of manufacturing and sourcing S - S S S + S - S + S + S S + - - - • Easy to assemble One of the guiding principles of lean Environment factors,- Temp, Humidity + - + S S + Total # of "+" 1 2 6 1 3 2 design is to “eliminate or standardize.” Total # of "-" Total # of "S" 6 5 4 6 0 6 5 6 5 4 8 2 Score - Decision -5 -2 6 -4 -2 -6 Favorite 5 Favorite 3 Favorite 1 Favorite 4 Favorite 2 Favorite 6 Can a part be combined with others and 6
  • 7. thereby be eliminated? If not, can it be made common with other parts in the product, without compromising FFF (Form Fit & Function). This typically provides quick savings. • Identify and capture all cost reduction opportunities. The team applied the concept of Pugh Matrix for system & component level. Rankings were discussed with team, collated and analyzed for choosing the optimum concepts. Next, FMEA was conducted on the selected concepts to further fine tune the results. Failure modes with high Risk Priority Number (RPN) were identified. Failure modes were prioritized and communicated to the designers to address these risks. Alternate solutions and improvement were discussed and finalized. 3D solid modeling was done to visualize the product. It also helped to simulate the active and passive conditions of the product. Components were standardized to reduce the part count. Simulation and testing against the CTQs helped to optimize the product for performances. Design calculations were performed to verify the design for gears, springs, snaps in the plastic members, etc.. Also the DFMA was conducted on various aspects of the design & CTQs. Cost Analysis Sl Part / Old New Comments Savings A detailed Differential Cost Analysis was No. Module Cost cost 1 Part - 1 6.58 NO change, no savings 6.58 0.00 conducted with the customer and their Replaced with plastic part. Functions 2 Part - 2 5.66 of Part - 8 mounting bracket, nuts 0.41 5.26 suppliers. The result showed significant cost are combined with this part. 3 Part - 3 3.10 Replaced with thin plastic part, press 0.80 2.30 reduction of each part of the product. It was Replaced with plastic part. Functions observed that the costs were reduced mainly 4 Part - 4 4.00 of Part - 8 mounting bracket, nuts 0.47 3.53 are combined with this part. due to alternate materials usage, the process 5 Part - 5 3.89 NO change, no savings 3.89 0.00 and by elimination/replacement of a part by 6 Part - 6 3.89 NO change, no savings 3.89 0.00 7 Part - 7 3.40 Replaced with thin plastic part, press 0.80 2.60 integrating with the adjacent one. 8 Part - 8 3.60 Replaced with thick paper part. 0.47 3.13 7
  • 8. Costs of direct material were compared for the original and new design. A significant 38% of savings in direct material cost was realized by this project. The team also achieved a reduction of 34% in the part count. This has resulted in many intangible benefits like savings in procurement costs, Inspection costs, Inventory cost, transportation, reduced variation, reduced assembly costs & Time, etc. 6. Conclusion: QuEST ‘Value Engineering team’ achieved 38% of savings in direct material cost and reduced part count by 34% in this project. Having a Paint brush does not make one a painter. While we strive to implement the different VAVE tools, we realize that the years of experience in product design & development is very essential to achieve the desired objective. VAVE tools and techniques, if applied properly, with trained & experienced resources will provide an extremely powerful suite to improve productivity, lower cost, improve quality and also shorten the time-to-market. Acronym: VAVE : Value Analysis & Value Engineering FAST : Function Analysis System Technique VOC : Voice of Customer QFD : Quality Function Deployment CTQ : Critical To Quality BOM : Bill of Material FFF : Form, Fit & Function FMEA : Failure Mode and Effects Analysis DFMA : Design for Manufacturing and Assembly About the author: Ajitanath Patil is the Sr. Tech Lead at QuEST Global (Engineering Services, Manufacturing and SEZ). Ajitanath has 16 years of work experience in different roles within the purview of Design & Development of SPMs. He has a Bachelor of Engineering (B.E) in Mechanical Engineering and a PGD in Robotics & Industrial Automation. 8