SlideShare a Scribd company logo
1 of 21
Download to read offline
Levelling in Surveying
For GATE
By
Introduction(Refer next slide)
 Leveling is the general term applied to any of the various processes by which
elevations of points or differences in elevation are determined.
Basic terms:
 Vertical line. A line that follows the local direction of gravity as indicated by
a plumb line.
 Level surface. A curved surface that, at every point is perpendicular to the
local plumb line (the direction in which gravity acts).
 Level line. A line in a level surface
 Horizontal plane. A plane perpendicular to the local direction of gravity. In
plane surveying, it is a plane perpendicular to the local vertical line.
 Horizontal line. A line in a horizontal plane. In plane surveying, it is a line
perpendicular to the local vertical.
 Vertical datum. Any level surface to which elevations are referenced. This is
the surface that is arbitrarily assigned an elevation of zero.
 Elevation. The distance measured along a vertical line from a vertical datum
to a point or object.
Leveling terms.
 Benchmark (BM).
A relatively
permanent object,
natural or artificial,
having a marked
point whose elevation
above or below a
reference datum is
known or assumed.
Levelling terms
 Station: A point where the levelling staff is kept.
 Height of instrument: It is the elevation of the plane of sight with
respect to assumed datum. It is also known as plane of collimation.
 Back sight(BS): It is the sight taken on the level staff, of a known
elevation with the intention to obtain the elevation of plane of
collimation. It is called PLUS sight because it is added to elevation of
that point to get height of instrument or plane of collimation.
 Intermediate sights(IS): These are the sight taken after back sight and
before sighting the final point. These are called MINUS sights. These
are subtracted from plane of collimation to find the reduced level of
different points.
 Fore sight(FS): The last reading taken from the instrument. This is also
a MINUS sight.
 Change point(CP) or turning point(TP): The point at which both BS and
FS are taken.
 Reduced level(RL): The elevations of the points with respect to
assumed datum.
Types of levelling
 Simple levelling
 Differential levelling
 Fly levelling
 Profile levelling
 Cross sectional levelling
 Reciprocal levelling
There are two methods for obtaining the elevations at different points:
 Height of instrument (or plane of collimation) method
 Rise and fall method
Height of Instrument method
 The basic equations are
 Height of instrument for the first setting= RL of BM + BS(at BM)
 Subtract the IS and FS from HI to get RL of intermediate stations and change
points.
 Checking: ∑BS - ∑FS = Last RL – First RL. This is –ve for FALL and +ve for
RISE.
 In this method the difference of the present staff reading is subtracted
from the previous staff reading.
 Previous reading – present staff reading = +ve, denotes RISE
 Previous reading – present staff reading = -ve, denotes FALL
 Checking: ∑BS - ∑FS = Last RL – First RL= ∑Rise - ∑Fall
Rise and Fall method
Simple leveling
 When the difference in the
elevation of two nearby points is
required then simple levelling is
performed.
 Assume the elevation of BM Rock is
known to be 820.00 ft.
 The BS at BM Rock is 8.42ft.
 So HI = (820 + 8.42)ft.
 Now the FS on “X” is 1.2ft.
 So the RL at “X” = HI – FS =
828.42ft
 Note that the RL of the instrument
station will never comes in the
calculation.
Differential levelling(table is in the next slide)
 Performed when the final point is very far
from the final point.
 We have to find RL at B.
 It is given that RL at A is 100m and BS at A
is 2.45m
 So, HI at L1=(100+2.45)=102.45m
 FS at CP1=2.41m
 RL at CP1=(102.45-2.14)=100.31m
 Now BS at CP1=1.43m
 HI at L2=(100.31+1.43)=101.74m
 FS at CP2=2.18m
 RL at CP2=(101.74-2.18)=99.56m
 BS at CP2=1.38m
 HI at L3=(99.56+1.38)m=100.94m
 FS at B=1.54m
 RL at B= (100.94-1.54)=99.4m (ans)
Table of previous example
(height of instrument method)
 Note that ∑BS- ∑FS=last RL – first RL
Table of previous example (Rise and Fall method)
Fly levelling
 Performed when the work site is very far away from the bench mark.
 The surveyor starts by taking BS at BM and proceed towards worksite till he
finds a suitable place for temporary BM. All works are done with respect to
temporary BM.
 At the end of the day the surveyor comes back to original BM.
 This is called fly levelling.
Profile levelling(figures are in next slide)
 Profile leveling, which yields elevations at
definite points along a reference line,
provides the needed data for designing
facilities such as highways, railroads,
transmission lines.
 Reduced levels at various points at regular
interval along the line is calculated.
 After getting the RL of various points the
profile is drawn. Normally vertical scale is
much larger than horizontal scale for the
clear view of the profile.
Plan view
Drawn profile (sectional view)
Cross sectioning
 In many projects not only profile along the line is required but also profile of cross
– section at a regular interval is required. (here 20m)
 Levels are taken at every 3m distance (till 9m i.e. 3 readings on one side) to left
and right of the line AB and BC for cross section profile.
curvature correction(Cc)
 Cc is always negative.
 A properly adjusted instrument take the readings with
respect to horizontal line.
 So something has to be subtracted from the staff
reading to get actual reading.
 Cc= d2/2R and -ve
 D is distance of the staff from the point of tangency
and R is the radius of the Earth = 6370km
 Cc= -7.849 x 10-8 x d2 meters, if d is in meters.
Effect of refraction (Cr)
 Air is denser near the earth and becomes thinner as we
go far from the surface of the earth. This causes
refraction.
 Cr=(1/7) x (d2/2R) and +ve
Combined effect
 Cc + Cr = - (6/7) x (d2/2R) = - 6.728 x 10-8 x d2 meters,
if d is in meters.
Distance of visible horizon
 Let P be the point of observation which is “h” meters
above mean seal level.
 “d” is called distance of visible horizon.
 Taking refraction and curvature into account.
Note
 If the instrument is kept, such that the distance of BS point and the FS point
are same (from the instrument) then the difference in elevation of the two
points will be free from curvature and refraction error.
Reciprocal levelling(refer next slide for pictures)
 When levelling across river is required then this
method is applied to get rid of various errors.
 The correct elevation is given as:
 The instrument is set very close to A. so ha will
be correct. Let the error in hb be “e”.
Therefore, correct reading at B is (hb - e)
 Difference in the elevation= ha – (hb - e)
 The instrument is set very close to B. so h’b will
be correct. Let the error in h’a be “e”.
Therefore, correct reading at B is (h’a - e)
 Difference in the elevation= (ha – e) – hb
 2H = [ha – (hb - e) + (h’a – e) – h’b]
 H = [(ha - hb) + (h’a – h’b)]/2
 e = [(h’a – h’b) - (ha - hb)]/2
 Thus the true elevation is given by mean of two
apparent differences in elevations.
Note
 e = collimation error + combined effect of curvature and refraction error
 e = D x tan(α) + (6/7) x (D2 / 2R)
 This “e” has to be subtracted from the staff reading to get original
reading.
Difficulties in the levelling
 Taking level of an overhead point
 If we need RL of points like on chejja of the window, then the
staff is inverted. This reading is entered as a negative reading.
 To get RL
 RL = HI – (- y), where “y” is the inverted reading.
 RL = HI + y
 Levelling across the summit
 The instrument set on one side of the summit, such
that line of sight just passes over the summit.
 Levelling across a hollow
 Instrument should set such that the reading at lowest
point of the hollow is maximum staff reading.
THANK YOU
(for more presentations)
Please visit
www.slideshare.net/RAHULSINHA1993

More Related Content

What's hot (20)

Levelling
LevellingLevelling
Levelling
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 
Levelling
LevellingLevelling
Levelling
 
Theodolite surveying
Theodolite surveyingTheodolite surveying
Theodolite surveying
 
Theodolite surveying part 1 (I scheme MSBTE)
Theodolite surveying part 1 (I scheme MSBTE)Theodolite surveying part 1 (I scheme MSBTE)
Theodolite surveying part 1 (I scheme MSBTE)
 
Angular measurement for surveying
Angular measurement for surveyingAngular measurement for surveying
Angular measurement for surveying
 
traversing of survey
traversing of surveytraversing of survey
traversing of survey
 
Trigonometric levelling
Trigonometric  levellingTrigonometric  levelling
Trigonometric levelling
 
Tacheometric survey
Tacheometric surveyTacheometric survey
Tacheometric survey
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
Tacheometry ppt
Tacheometry pptTacheometry ppt
Tacheometry ppt
 
Theodolite surveying
Theodolite surveying Theodolite surveying
Theodolite surveying
 
Curve setting ppt
Curve setting pptCurve setting ppt
Curve setting ppt
 
Types of level
Types of levelTypes of level
Types of level
 
LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
 
Triangulation survey
Triangulation surveyTriangulation survey
Triangulation survey
 
Theodolite Surveying
Theodolite Surveying Theodolite Surveying
Theodolite Surveying
 
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptx
 
Contouring pdf
Contouring pdfContouring pdf
Contouring pdf
 
Curves and there application in Survey
Curves and there application in SurveyCurves and there application in Survey
Curves and there application in Survey
 

Viewers also liked

Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveyingMohammed_82
 
Booking sheets, 2011 v1
Booking sheets, 2011 v1Booking sheets, 2011 v1
Booking sheets, 2011 v1jbusse
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
6 dumpy levels. example of use
6 dumpy levels. example of use6 dumpy levels. example of use
6 dumpy levels. example of usevigyanashram
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Haziq1511
 

Viewers also liked (6)

Levelling
LevellingLevelling
Levelling
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveying
 
Booking sheets, 2011 v1
Booking sheets, 2011 v1Booking sheets, 2011 v1
Booking sheets, 2011 v1
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
6 dumpy levels. example of use
6 dumpy levels. example of use6 dumpy levels. example of use
6 dumpy levels. example of use
 
Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)Site Surveying Report 1 (Levelling)
Site Surveying Report 1 (Levelling)
 

Similar to Levelling in Surveying

Surveying
SurveyingSurveying
Surveyingredaasd
 
Site surveying-report-leveling
Site surveying-report-levelingSite surveying-report-leveling
Site surveying-report-levelingXinYee Khoo
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - TraversingXinYee Khoo
 
S2 2 leveling
S2 2 levelingS2 2 leveling
S2 2 levelingEst
 
Fly Levelling
Fly LevellingFly Levelling
Fly LevellingBahzad5
 
Mathematical Background in Physics.pdf
Mathematical Background in Physics.pdfMathematical Background in Physics.pdf
Mathematical Background in Physics.pdfGajananHarde
 
Site Surveying Leveling
Site Surveying LevelingSite Surveying Leveling
Site Surveying Levelingashleyyeap
 
Step by step Engineering Mechanics updated
Step by step Engineering Mechanics updatedStep by step Engineering Mechanics updated
Step by step Engineering Mechanics updatedProf. S.Rajendiran
 
3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTU
3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTU3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTU
3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTUVATSAL PATEL
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfLeulDamtew
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1Doreen Yeo
 
Theodolite surveying part2
Theodolite surveying part2Theodolite surveying part2
Theodolite surveying part2Naufil Sayyad
 

Similar to Levelling in Surveying (20)

Leveling
Leveling Leveling
Leveling
 
levelling survey
levelling surveylevelling survey
levelling survey
 
Surveying
SurveyingSurveying
Surveying
 
Site surveying-report-leveling
Site surveying-report-levelingSite surveying-report-leveling
Site surveying-report-leveling
 
Site Surveying Report - Traversing
Site Surveying Report - TraversingSite Surveying Report - Traversing
Site Surveying Report - Traversing
 
S2 2 leveling
S2 2 levelingS2 2 leveling
S2 2 leveling
 
Altimetria (1ra clase)
Altimetria (1ra clase)Altimetria (1ra clase)
Altimetria (1ra clase)
 
Fly Levelling
Fly LevellingFly Levelling
Fly Levelling
 
Mathematical Background in Physics.pdf
Mathematical Background in Physics.pdfMathematical Background in Physics.pdf
Mathematical Background in Physics.pdf
 
Laboratory manual surveying_ii
Laboratory manual surveying_iiLaboratory manual surveying_ii
Laboratory manual surveying_ii
 
1 st report
1 st report1 st report
1 st report
 
Levelling
LevellingLevelling
Levelling
 
Site Surveying Leveling
Site Surveying LevelingSite Surveying Leveling
Site Surveying Leveling
 
Step by step Engineering Mechanics updated
Step by step Engineering Mechanics updatedStep by step Engineering Mechanics updated
Step by step Engineering Mechanics updated
 
3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTU
3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTU3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTU
3. TRIGONOMETRIC LEVELLING (SUR) 3140601 GTU
 
LEVELING.pdf
LEVELING.pdfLEVELING.pdf
LEVELING.pdf
 
chapter 3 up to booking method.pdf
chapter 3 up to booking method.pdfchapter 3 up to booking method.pdf
chapter 3 up to booking method.pdf
 
ch5.pdf
ch5.pdfch5.pdf
ch5.pdf
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1
 
Theodolite surveying part2
Theodolite surveying part2Theodolite surveying part2
Theodolite surveying part2
 

More from RAHUL SINHA

Rahul sinha foundation engineering
Rahul sinha foundation engineeringRahul sinha foundation engineering
Rahul sinha foundation engineeringRAHUL SINHA
 
Rahul sinha soil mech. basics
Rahul sinha soil mech. basicsRahul sinha soil mech. basics
Rahul sinha soil mech. basicsRAHUL SINHA
 
Rahul sinha geotechnical engineering
Rahul sinha geotechnical engineeringRahul sinha geotechnical engineering
Rahul sinha geotechnical engineeringRAHUL SINHA
 
Maths and apti rahul sinha
Maths and apti rahul sinhaMaths and apti rahul sinha
Maths and apti rahul sinhaRAHUL SINHA
 
Transportation engineering rahul sinha
Transportation engineering rahul sinhaTransportation engineering rahul sinha
Transportation engineering rahul sinhaRAHUL SINHA
 
Seepage through soil
Seepage through soilSeepage through soil
Seepage through soilRAHUL SINHA
 
BASIC OF PERMEABILITY OF SOIL
BASIC OF PERMEABILITY OF SOILBASIC OF PERMEABILITY OF SOIL
BASIC OF PERMEABILITY OF SOILRAHUL SINHA
 
Open channel flow rahul sinha
Open channel flow rahul sinhaOpen channel flow rahul sinha
Open channel flow rahul sinhaRAHUL SINHA
 
Fluid mechanics rahul sinha
Fluid mechanics rahul sinhaFluid mechanics rahul sinha
Fluid mechanics rahul sinhaRAHUL SINHA
 
Structural analysis rahul sinha
Structural analysis rahul sinhaStructural analysis rahul sinha
Structural analysis rahul sinhaRAHUL SINHA
 
Mechanics of materials rahul sinha
Mechanics of materials rahul sinhaMechanics of materials rahul sinha
Mechanics of materials rahul sinhaRAHUL SINHA
 
Compass surveying
Compass surveyingCompass surveying
Compass surveyingRAHUL SINHA
 
Joukowski's airfoils, introduction to conformal mapping
Joukowski's  airfoils, introduction to conformal mappingJoukowski's  airfoils, introduction to conformal mapping
Joukowski's airfoils, introduction to conformal mappingRAHUL SINHA
 
pointing, plastering, bonding
pointing, plastering, bondingpointing, plastering, bonding
pointing, plastering, bondingRAHUL SINHA
 
Ventilation/Roofing
Ventilation/RoofingVentilation/Roofing
Ventilation/RoofingRAHUL SINHA
 
The cost of production/Chapter 7(pindyck)
The cost of production/Chapter 7(pindyck)The cost of production/Chapter 7(pindyck)
The cost of production/Chapter 7(pindyck)RAHUL SINHA
 
Joints and unconformity
Joints and unconformityJoints and unconformity
Joints and unconformityRAHUL SINHA
 
Folds and foldings
Folds and foldingsFolds and foldings
Folds and foldingsRAHUL SINHA
 
cost of production / Chapter 6(pindyck)
cost of production / Chapter 6(pindyck)cost of production / Chapter 6(pindyck)
cost of production / Chapter 6(pindyck)RAHUL SINHA
 

More from RAHUL SINHA (20)

Rahul sinha foundation engineering
Rahul sinha foundation engineeringRahul sinha foundation engineering
Rahul sinha foundation engineering
 
Rahul sinha soil mech. basics
Rahul sinha soil mech. basicsRahul sinha soil mech. basics
Rahul sinha soil mech. basics
 
Rahul sinha geotechnical engineering
Rahul sinha geotechnical engineeringRahul sinha geotechnical engineering
Rahul sinha geotechnical engineering
 
Maths and apti rahul sinha
Maths and apti rahul sinhaMaths and apti rahul sinha
Maths and apti rahul sinha
 
Transportation engineering rahul sinha
Transportation engineering rahul sinhaTransportation engineering rahul sinha
Transportation engineering rahul sinha
 
Seepage through soil
Seepage through soilSeepage through soil
Seepage through soil
 
BASIC OF PERMEABILITY OF SOIL
BASIC OF PERMEABILITY OF SOILBASIC OF PERMEABILITY OF SOIL
BASIC OF PERMEABILITY OF SOIL
 
Open channel flow rahul sinha
Open channel flow rahul sinhaOpen channel flow rahul sinha
Open channel flow rahul sinha
 
Fluid mechanics rahul sinha
Fluid mechanics rahul sinhaFluid mechanics rahul sinha
Fluid mechanics rahul sinha
 
Structural analysis rahul sinha
Structural analysis rahul sinhaStructural analysis rahul sinha
Structural analysis rahul sinha
 
Mechanics of materials rahul sinha
Mechanics of materials rahul sinhaMechanics of materials rahul sinha
Mechanics of materials rahul sinha
 
Compass surveying
Compass surveyingCompass surveying
Compass surveying
 
Joukowski's airfoils, introduction to conformal mapping
Joukowski's  airfoils, introduction to conformal mappingJoukowski's  airfoils, introduction to conformal mapping
Joukowski's airfoils, introduction to conformal mapping
 
pointing, plastering, bonding
pointing, plastering, bondingpointing, plastering, bonding
pointing, plastering, bonding
 
Ventilation/Roofing
Ventilation/RoofingVentilation/Roofing
Ventilation/Roofing
 
The cost of production/Chapter 7(pindyck)
The cost of production/Chapter 7(pindyck)The cost of production/Chapter 7(pindyck)
The cost of production/Chapter 7(pindyck)
 
Joints and unconformity
Joints and unconformityJoints and unconformity
Joints and unconformity
 
Folds and foldings
Folds and foldingsFolds and foldings
Folds and foldings
 
cost of production / Chapter 6(pindyck)
cost of production / Chapter 6(pindyck)cost of production / Chapter 6(pindyck)
cost of production / Chapter 6(pindyck)
 
Faults
FaultsFaults
Faults
 

Recently uploaded

Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 

Recently uploaded (20)

Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 

Levelling in Surveying

  • 2. Introduction(Refer next slide)  Leveling is the general term applied to any of the various processes by which elevations of points or differences in elevation are determined. Basic terms:  Vertical line. A line that follows the local direction of gravity as indicated by a plumb line.  Level surface. A curved surface that, at every point is perpendicular to the local plumb line (the direction in which gravity acts).  Level line. A line in a level surface  Horizontal plane. A plane perpendicular to the local direction of gravity. In plane surveying, it is a plane perpendicular to the local vertical line.  Horizontal line. A line in a horizontal plane. In plane surveying, it is a line perpendicular to the local vertical.  Vertical datum. Any level surface to which elevations are referenced. This is the surface that is arbitrarily assigned an elevation of zero.  Elevation. The distance measured along a vertical line from a vertical datum to a point or object.
  • 3. Leveling terms.  Benchmark (BM). A relatively permanent object, natural or artificial, having a marked point whose elevation above or below a reference datum is known or assumed.
  • 4. Levelling terms  Station: A point where the levelling staff is kept.  Height of instrument: It is the elevation of the plane of sight with respect to assumed datum. It is also known as plane of collimation.  Back sight(BS): It is the sight taken on the level staff, of a known elevation with the intention to obtain the elevation of plane of collimation. It is called PLUS sight because it is added to elevation of that point to get height of instrument or plane of collimation.  Intermediate sights(IS): These are the sight taken after back sight and before sighting the final point. These are called MINUS sights. These are subtracted from plane of collimation to find the reduced level of different points.  Fore sight(FS): The last reading taken from the instrument. This is also a MINUS sight.  Change point(CP) or turning point(TP): The point at which both BS and FS are taken.  Reduced level(RL): The elevations of the points with respect to assumed datum.
  • 5. Types of levelling  Simple levelling  Differential levelling  Fly levelling  Profile levelling  Cross sectional levelling  Reciprocal levelling There are two methods for obtaining the elevations at different points:  Height of instrument (or plane of collimation) method  Rise and fall method
  • 6. Height of Instrument method  The basic equations are  Height of instrument for the first setting= RL of BM + BS(at BM)  Subtract the IS and FS from HI to get RL of intermediate stations and change points.  Checking: ∑BS - ∑FS = Last RL – First RL. This is –ve for FALL and +ve for RISE.  In this method the difference of the present staff reading is subtracted from the previous staff reading.  Previous reading – present staff reading = +ve, denotes RISE  Previous reading – present staff reading = -ve, denotes FALL  Checking: ∑BS - ∑FS = Last RL – First RL= ∑Rise - ∑Fall Rise and Fall method
  • 7. Simple leveling  When the difference in the elevation of two nearby points is required then simple levelling is performed.  Assume the elevation of BM Rock is known to be 820.00 ft.  The BS at BM Rock is 8.42ft.  So HI = (820 + 8.42)ft.  Now the FS on “X” is 1.2ft.  So the RL at “X” = HI – FS = 828.42ft  Note that the RL of the instrument station will never comes in the calculation.
  • 8. Differential levelling(table is in the next slide)  Performed when the final point is very far from the final point.  We have to find RL at B.  It is given that RL at A is 100m and BS at A is 2.45m  So, HI at L1=(100+2.45)=102.45m  FS at CP1=2.41m  RL at CP1=(102.45-2.14)=100.31m  Now BS at CP1=1.43m  HI at L2=(100.31+1.43)=101.74m  FS at CP2=2.18m  RL at CP2=(101.74-2.18)=99.56m  BS at CP2=1.38m  HI at L3=(99.56+1.38)m=100.94m  FS at B=1.54m  RL at B= (100.94-1.54)=99.4m (ans)
  • 9. Table of previous example (height of instrument method)  Note that ∑BS- ∑FS=last RL – first RL
  • 10. Table of previous example (Rise and Fall method)
  • 11. Fly levelling  Performed when the work site is very far away from the bench mark.  The surveyor starts by taking BS at BM and proceed towards worksite till he finds a suitable place for temporary BM. All works are done with respect to temporary BM.  At the end of the day the surveyor comes back to original BM.  This is called fly levelling. Profile levelling(figures are in next slide)  Profile leveling, which yields elevations at definite points along a reference line, provides the needed data for designing facilities such as highways, railroads, transmission lines.  Reduced levels at various points at regular interval along the line is calculated.  After getting the RL of various points the profile is drawn. Normally vertical scale is much larger than horizontal scale for the clear view of the profile.
  • 12. Plan view Drawn profile (sectional view)
  • 13. Cross sectioning  In many projects not only profile along the line is required but also profile of cross – section at a regular interval is required. (here 20m)  Levels are taken at every 3m distance (till 9m i.e. 3 readings on one side) to left and right of the line AB and BC for cross section profile.
  • 14. curvature correction(Cc)  Cc is always negative.  A properly adjusted instrument take the readings with respect to horizontal line.  So something has to be subtracted from the staff reading to get actual reading.  Cc= d2/2R and -ve  D is distance of the staff from the point of tangency and R is the radius of the Earth = 6370km  Cc= -7.849 x 10-8 x d2 meters, if d is in meters. Effect of refraction (Cr)  Air is denser near the earth and becomes thinner as we go far from the surface of the earth. This causes refraction.  Cr=(1/7) x (d2/2R) and +ve Combined effect  Cc + Cr = - (6/7) x (d2/2R) = - 6.728 x 10-8 x d2 meters, if d is in meters.
  • 15. Distance of visible horizon  Let P be the point of observation which is “h” meters above mean seal level.  “d” is called distance of visible horizon.  Taking refraction and curvature into account.
  • 16. Note  If the instrument is kept, such that the distance of BS point and the FS point are same (from the instrument) then the difference in elevation of the two points will be free from curvature and refraction error. Reciprocal levelling(refer next slide for pictures)  When levelling across river is required then this method is applied to get rid of various errors.  The correct elevation is given as:  The instrument is set very close to A. so ha will be correct. Let the error in hb be “e”. Therefore, correct reading at B is (hb - e)  Difference in the elevation= ha – (hb - e)  The instrument is set very close to B. so h’b will be correct. Let the error in h’a be “e”. Therefore, correct reading at B is (h’a - e)  Difference in the elevation= (ha – e) – hb  2H = [ha – (hb - e) + (h’a – e) – h’b]  H = [(ha - hb) + (h’a – h’b)]/2  e = [(h’a – h’b) - (ha - hb)]/2  Thus the true elevation is given by mean of two apparent differences in elevations.
  • 17.
  • 18. Note  e = collimation error + combined effect of curvature and refraction error  e = D x tan(α) + (6/7) x (D2 / 2R)  This “e” has to be subtracted from the staff reading to get original reading.
  • 19. Difficulties in the levelling  Taking level of an overhead point  If we need RL of points like on chejja of the window, then the staff is inverted. This reading is entered as a negative reading.  To get RL  RL = HI – (- y), where “y” is the inverted reading.  RL = HI + y  Levelling across the summit  The instrument set on one side of the summit, such that line of sight just passes over the summit.  Levelling across a hollow  Instrument should set such that the reading at lowest point of the hollow is maximum staff reading.
  • 20.
  • 21. THANK YOU (for more presentations) Please visit www.slideshare.net/RAHULSINHA1993