Solar Power Station
ProjectAnalysis Report for Power Plant of 10MW capacity
Rusiru Sanjaya 2016-08-19 SunPower Systems (PVT) LTD.
CONTENT
Page
Introduction………………………………………………………………………………………… 1
SWOT analysis of the Power Plant
Strengths……………………………………………………………………………………2
Weaknesses……………………………………………………………………………….3
Opportunities…………………………………………………………………………….4
Threats……………………………………………………………………………………….5
Project Implementation Process…………….…………………………………………….6
Pre-feasibility report and statutory approval……………………………………..…7
Financial Aspects of the project…………… ………………………………………………10
P a g e | 1
INTRODUCTION
At the moment according to the energy consultants, Sri Lanka is heading to an energy
crisis during early 2020s. Though the country has policies to get rid of fossil fuel generated
energy by 2030, there are stillprojects which are proposed and about to implement, that burn
fossil fuels to generate energy. But now the world trend has gone far more away than this
condition. Now most of foreign countries are implementing thousands of projects to
introduce renewable energy to their power systems whereas some countries have already
produce their total power required for the consumers using renewable energy. Due to
burning fossil fuels, global warming and environmental effects have increased day by day. At
this rate of CO2 emission to the air, sooner the earth will become place which is not suitable
for human to live anymore.
As responsible citizens and businessmen in the country, we should lead this country
to find environmental friendly power solutions to compete with the energy crisis. Among
these renewable energy solutions, Solar Power systems have become most important and
favourite energy source. Most of the foreign countries have implemented large scale of solar
power systems projects because using solar insolation, it could be easily obtain large amount
of energy with zero environmental pollution, for zero cost except for the installations and
zero noises.And this would not be a solution just for two three years, but itcan provide energy
free of charge as our Sun willprovide solarenergy for another thousands of years. So investing
on solar energy will be much better decision for the energy solutions.
This report will be focused on describing and analyse the strengths, weaknesses,
opportunities, treats as wellas guide on project implementation process,governing and ruling
bodies relevant to these kind of projects and also the sequence of process which has to be
done. And also brief financial analysis on the 10MW solar power plant is also included in this
report.
P a g e | 2
SWOT Analysis
Strengths
 Geographically, Sri Lanka is located near the equator which is the ideal position for a
country finding energy solution by solar energy because of the high sun irradiations.
Thus it would be really good decision to invest for solar power plant in this country as
the payback period is minimum compared to the other countries which are located in
away from the equator.
 As our company has done few other large scale solar projects, we have many
experiences regarding the maintenance problems and problems which would arise
after the installation of the system. Therefore prior steps can be taken to avoid those
issues happening in this kind of a project and it’llminimize or eliminatepotential losses
that company would incur by this project.
 As we have done so many other projects including moderately large scale projects
(200kW, 400kW), our company has engineers and technicians with full of experiences.
So there is no considerable issues regarding the technical skills required to operate
10MW solar power plant.
 Having all the experience obtaining by solar installation done so far, our company has
good knowledge of the quality of our products and also currently we are importing
components in best and reputed brands in the world. So durability and reliability of
our instruments and components is not an issue at all for this kind of a long term
investment.
 According to solarinstallations done so far around the country, our company has good
idea about the weather conditions around the country with experiences from installed
systems’ outputs behaviours during past years. So choosing suitable and best
geographical locations for the system becomes easy task.
 By implementing a Solar Power Plant, we can contribute to reduce CO2 emission to
atmosphere in millions of tons for each year. So that effects such as global warming
can be minimized.
P a g e | 3
Weaknesses
 All the projects we have done so far are below the 1MW capacity. But we are looking
about 10MW system in this project. Thus we may suffer out of numbers of engineers
and technicians to maintain such large system in once.
 If this project going to be implemented, large amount of money has to be invested
undoubtedly. Our company may not have that much of money to implement this
project. If our capitalstrength is not sufficientfor a project likethis,it will be disastrous
if it’s unable to complete the project because there is no return on investment until
the project has successfully done.
 If grid becomes unstable or go offline when during the operation of the power plant,
the generated energy will no more be transferred to the grid and hence that energy
will be lost due to lack technologies in large scale storage system. Hence lack of
storages become weakness point.
 Sri Lanka being an island, salty atmosphere may cause badly to the systemlifetime as
its components become corroded sooner.
 As Sri Lanka is a tropical country, panels’ temperature become increased due to hot
atmosphere and hence the efficiency of the panel get reduced.
 And also due to high relative humidity, solar irradiations may be reduced in some
areas.
P a g e | 4
Opportunities
 In around 2020s, Sri Lanka will be facing a huge power crisis as at the moment the
demand for the power in Sri Lanka is increasing rapidly. There are no any additional
power plants in near future to be run to meet this demand. So the government will
have to lookup renewable energy sources as it can be implement very quickly
compared to the other large scalepower plants. So in this scenario, Solar Power Plants
are the best solution and this creates many benefits to the firms who runs solar power
plants.
 The fossil fuel reserves in the world become over during next decades. So the only
solution for power crisis is become renewable energy and thus Solar energy for
countries near the equator.
 Now many firms are manufacturing solar panels and other products. Thus competency
among these firms become very high. Due to that price of the solar products become
less. This ensure to build the plant with quality products for minimum costs.
 It is well known that the efficiency of the PV panels are very low. But many R&A
projects are ongoing to maximize the efficiency of the solar panels. This will be a great
opportunity in the future improvements of the systems.
 Comparison to other power generating systems, solar power plants have less
operation and maintenance manpower required.
 A solar power plant will be running a very long time compared to other power
generating systems.
 In environmental perspective, solar power plants generates clean energy without
emitting any gas. This leads to maximum environmental clean development.
P a g e | 5
Threats
 It is obvious that after completing the project, if the solarinsolation failedto reach the
system properly due to some long term bad weather or clouds, there are no other
option except to bear the losses occurring initial capital cost and maintenance. So
weather would be uncontrollable threat for the project in the future.
 If the grid becomes unstable of the country or if the power cuts going to happen very
frequently, then power generated by our system won’t exported during that time. If
there is no other auxiliary system for storing that energy, it will cause huge losses to
the plant as that energy is wasted. So considering the grid stability of the country
should be very important.
 Nowadays as many companies are tending to install sola power systems and thus
there may be lack of employees who are well trained about the solar systems because
of the higher job demand for the employees such as technicians and engineers.
 When this project is implementing, company would have to look after its past
customers’ service to maintain its usual customer relationships as well as the project
which is going to implementing in future. If customers feel that they are not supplied
with the service which they deserved from the company, they will definitely be a huge
threat to the company.
 Villagers in this area may not willing to accept this kind of project in their area due to
varies reasons. So we have to consider villager’s concerns also because without their
support project won’t be able to implement and it’ll be great threat to the project.
P a g e | 6
Project Implementation process
1. Selecting a suitable site – According to the sola insolation and other requirements,
suitable area in the country should be selected.
2. Pre-feasibility study and financial analysis of the project –Before starting a renewable
energy project, it should be done a feasibilitystudy according to the regulations of SEA
and a Financial feasibility of basic inputs like land, labour, solar insolation, solar PV
systems etc. with the output which can obtain by the system.
3. Statutory Approvals and obtaining an Energy Permit – To implement the project,
company should obtain relevant statutory approvals from regulatory bodies. If the
project is approved by them, an energy permit will be granted by these authorities to
continue generating energy and sell it to the national grid.
4. Getting into power purchase agreement – A power purchase agreement is signed
between CEB and the company to get into an agreement which CEB buys the
electricity from the company.
5. Financing to solar project – This is usually very high investment because tools and
components used in a solar system are very expensive. And further there are more
other expenses that would incur during the implementation of the project. So it is
necessary to have a clear vision in financing the project.
6. Acquire the Land – If the project becomes financially feasible, then the Land space
should be leased or bought first.
7. Basic technological design of the system – The layout of the basic technological design
of solar power systemis prepared by the engineers and technicians having experience
in the field.
8. Testing and connecting to Grid – After the system is tested for the correct working
conditions, power plant is connected to the Grid to export energy in order to sellthem
to CEB.
9. Operating and Maintenance – A typical solar PV panel has 25 – 30 lifetime and an
inverter has 10 – 15 years lifetime. To expand their lifetime, it should be well
maintained and cleaned the components of the system.
P a g e | 7
Pre-feasibility Report and Statutory Approval
Sustainable Energy Authority (SEA) is the main legal body to manage and control over the
renewable energy sources in Sri Lanka. All the instructions and permissions will be given by
Sustainable Energy Authority regarding a renewable energy project is to be implemented. If
the proposed project is more than 10MW capacity, then acquiring a generation license from
CEB will be necessary as well. Since this project is of 10MW capacity, there is no need of
acquiring a generation license of CEB. Before applying a formal application to the SEA for
renewable energy project, recourses are provided in the On-Grid Renewable Energy Projects
Regulation 2009 to verify the availability of the suitable NRE site for development. And then
a formal application need to be prepared to submit to the SEA as prescribed in Section 16(2)
of the On-Grid Renewable Energy Projects Regulation 2011 and this application should be
accompanied with a Pre-feasibility study report. When the application is being submitting, a
non-refundable application fees should be paid to SEA.
 Pre-feasibility Study report
In this study report it should be include a Summary of the Pre-feasibility study,
Certification by the accredited Consultant and Study report based on the list of
contents.
 Standard format for Summary of the Pre-feasibility study
 Standard format for Certification by the accredited Consultant
 Standard format for Study report based on the list of contents
When preparing the pre-feasibility study report following aspects should be given focused
attention.
 Land issues must be sort out( availability of the land for the project, consent of the
agency to whom the land belongs to etc.) and clear identification of ownership
Format_F1.pdf
Format_F2.pdf
Format_F3.pdf
P a g e | 8
 Resource issues (availability of the resource for the project, conflicting uses of the
resource etc.) must be clearly understood by studying all aspects of the resources
such as seasonality and other uses (existing and future) of the resource which may
compromise the project feasibility.
 Issues with respect to affected communities will have to be understood and
documented to avoid conflicts during project implementation
 Making an Application
In this process proponent has to make the contact with SEA by making an application to
SEA. When applying for renewable energy project, proponent has to make an application
fee to the SEA as described below. Following main components should be included in the
Application form
a) Pre-feasibility report prepared by a Consultant accredited by SEA, with one page
summary
b) A copy of the map of the geographical location of the proposed project
c) A brief description of the project, including the amount of power to be
generated.
d) The total estimated cost and financial model including the optimisation criteria
adopted.
e) Proof of availability of adequate finances or the manner in which the required
finances for the project are to be obtained.
f) Project location, describing the relative location of the energy conversion plant
and equipment to the resource, as a further explanation of (b) above
g) A statement explaining how the Applicant intends to deliver electricity
generated by the project to the national grid, and geographical area travelled by
the power line to be constructed for that purpose.
h) A copy of the receipt obtained from the SEA, for the payment of the application
fee, which will be calculated according to the schedule given overleaf
 Application fee
Amount of power proposed to be
generated
Fee to be paid on application
1000kW or part thereof LKR 100,000
Each additional 1,000kW LKR 50,000 payable on pro rata basis
P a g e | 9
 Approval Phase
In this process, proponent has to obtain formal approval from several other agencies
to proceed with the project development. The approval of DivisionalSecretary Central
Environment Authority and an assurance from CEB on purchasing energy from the
proposed project will provide a strong acceptance to the project beforehand.
 Divisional Secretary’s Approval - Divisional Secretary is considered as the
representative of the Government at the grass root level who protects and
manages the state land and other natural resources. Under the 13th
Amendment to the constitution, getting the consent of the respective
Provincial Council is also compulsory.
 Letter of intent – This document is issued by CEB to signify the assurance of
CEB to procure the electricity generated by the project. When applying for this
letter proponent should be made an application fee of LKR 100,000 to CEB.
 Feasibility Study Phase
In this phase, the Developer makes detailed evaluation of the feasibilityof the project,
giving due consideration to the input resources and outcome of the project.
 Comprehensive Feasibility Study - The Developer is required to evaluate all
factors which influence the project, ranging from weather and climate
conditions to eventualities of relocating people who may be affected by the
project implementation.
 Environmental Examination - The Developer is required to make an
application to the Central Environmental Authority (CEA) seeking
environmental clearance. Depending on the severity of the environmental
impact of the project, the project may be required to undergo either an Initial
Environmental Examination (IEE) or a more comprehensive Environmental
Impact Assessment (EIA).
 Licensing Phase
Having obtained statutory clearance to proceed, the Developer is required to secure an
Energy Permit to use the renewable energy resource, a Generation License from PUCSL to
generate electricity and sell energy to the CEB.
 Energy Permit – All renewable energy resources are owned by the republic of
Sri Lanka. Hence the utilization of resources is granted through a20 year permit
P a g e | 10
system. Once all other approvals are secured by a project Developer, the PAC
grants a 20 year permit (extendable by a further 20 years after the successful
operation of the project during the initial 20 year period) to the Developer
allowing him to use the resource under several conditions. The Developer will
have to pay a fee of LKR 500,000/- (per MW of capacity) as the permit fee in
the caseof projects with capacities of 10MW or less. The Energy Permit carries
a grace period of 2 years to allow for construction activities, and the
Developers are required to complete implementation within this period.
 Generation License - The project Developer, possessing an Energy Permit is
required to obtain a Generation License from the Public Utilities Commission
of Sri Lanka (PUCSL) with the enactment of the Sri Lanka Electricity Act 20 of
2009. The annual fees payable to PUCSL for the Generation License will be LKR
10,000/- per MW.
 Power Purchase Agreement - All projects having capacities of 10MW or less
have to be taken under the Standardised Power Purchase Agreement (SPPA),
reached between the CEBand the power producer. The time tested agreement
is supported by tariffs offered to various technologies and are subject to
revisions based on project cost escalations, at appropriate intervals. The SPPA
is valid for a period of 20 years from the date of commercial operation.
Financial Aspects of the project
After obtaining the statutory permissions, company should manage the financial
resources to implement the project. Even though the project is in statutory clearance
procedures, company can handle financing resources because no sooner the required
approvals will be given for the project by the relevant parties if the necessary documents
and requirements are provided accordingly.
Financing methods should be decided based on the capital strength of the company and
required mount of investment to the project. Company has to decide whether the capital
strength of the company to implement this project is strong or else to obtain debt from
external parties. To decide these things, company has to do a proper analysis on all
expenditures on this project.
P a g e | 11
Let’s assume the solar irradiation of the site is 1kW/m2 and PV panel with the dimensions
1639*983 mm2 and efficiency of 16%. Then required panel area to generate 10MW
system capacity is as follows,
Therefore at least 5.053*105 m2 land area is required to establish the system. Thus
number of panels required is,
If a panel cost is around Rs.20, 000 then cost of the panels = 38,793*20,000
= 775.86 million rupees
If 1MW inverters are used, then required number of inverters = 10
Cost of each inverter = 2.5 million rupees
Then cost for the inverters = 25 million rupees
Then the total cost for the PV panels and Inverters = 800 million rupees
In additional to the above cost, there are many other costs associated with this projects such
as installation costs, transportation costs, system mounting costs, costs for developments of
infrastructures etc. Therefor total amount required for a 10MW project may be around 1.5 to
2.0 billion rupees.
Ceylon Electricity Board offers Three-Tier Tariff method which describes how the rates are
calculated.Accordingto theirtariffs,SolarPowerPlant will be offereda flat tariff of Rs. 23.10 / kWh
(non-escalable for20 years).Therefore requiredenergytobe generatedtorecoverthe cost incurred
for thisprojectcan be calculatedasfollowsbyassumingthe costis1.5 billionrupeesfor the project.
By considering average Sun time is 5 hours and energy generating in this sun hours is 10MW,
we can calculate the approximate payback period.
𝐴𝑟𝑒𝑎 =
10 × 106
1 × 103 × 0.16
= 62,500 𝑚2
𝑃𝑎𝑛𝑒𝑙 𝑛𝑜𝑠 =
62500
1639 × 983 × 10−6
= 38,793 𝑛𝑜𝑠
𝑅𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑒𝑛𝑒𝑟𝑔𝑦 𝑡𝑜 𝑟𝑒𝑐𝑜𝑣𝑒𝑟 𝑡ℎ𝑒 𝑐𝑜𝑠𝑡 =
𝑅𝑠.1.5 × 109
𝑅𝑠.23.1/𝑘𝑊ℎ
= 6.494 × 107 𝑘𝑊ℎ = 2.34 × 1011 𝑘𝐽
𝑇ℎ𝑒𝑟𝑒𝑓𝑜𝑟 𝑝𝑎𝑦𝑏𝑎𝑐𝑘 𝑝𝑒𝑟𝑖𝑜𝑑 𝑖𝑠 𝑎𝑝𝑝𝑟𝑜𝑥𝑖𝑚𝑎𝑡𝑒𝑙𝑦 =
2.34 × 1011 𝑘𝐽
10 × 5 × 3600 × 103 𝑘𝐽
= 1299 𝑑𝑎𝑦𝑠(≈ 3.6𝑦𝑒𝑎𝑟𝑠)
P a g e | 12
Above payback period is calculated without considering any interest rates. If interest rates
are considered, above payback period will be increased. For an instance let’s assume an
interest rate of 15% of financing method to be used. Then the actual payback period can be
calculated as follows.
𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑟𝑒𝑣𝑒𝑛𝑢𝑒 𝑡ℎ𝑎𝑡 𝑐𝑎𝑛 𝑏𝑒 𝑜𝑏𝑡𝑎𝑖𝑛 𝑏𝑦 𝑡ℎ𝑒 𝑠𝑦𝑠𝑡𝑒𝑚 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ
= 5 × 104 𝑘𝑊ℎ × 𝑅𝑠.23.1/𝑘𝑊ℎ × 30
= 𝑅𝑠 3.465 × 107
𝑇ℎ𝑒𝑟𝑒𝑓𝑜𝑟 𝑝𝑎𝑦𝑏𝑎𝑐𝑘 𝑝𝑒𝑟𝑖𝑜𝑑 𝑖𝑠 𝑎𝑝𝑝𝑟𝑜𝑥𝑖𝑚𝑎𝑡𝑒𝑙𝑦 = 1920 𝑑𝑎𝑦𝑠(≈ 5.3 𝑦𝑒𝑎𝑟𝑠)

More Related Content

What's hot

Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesPuneet Jaggi
 
Solar Power Plant System Sizing
Solar Power Plant System SizingSolar Power Plant System Sizing
Solar Power Plant System Sizingfirstgreen
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuidePrivate Consultants
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenanceLeonardo ENERGY
 
Solar Project Financing
Solar Project FinancingSolar Project Financing
Solar Project Financingfirstgreen
 
Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Engineering Limited
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Ashish Verma
 
IPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapIPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapFadi Maalouf, PMP
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsGensol Engineering Limited
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantDr Naim R Kidwai
 
Steinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportSteinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportShrikant Hiremath
 
Introduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power systemIntroduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power systemShoeb Ali Khan
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantShahbaz Makandar A.
 

What's hot (20)

Solar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best PracticesSolar Photovoltaic Power Plant: Best Practices
Solar Photovoltaic Power Plant: Best Practices
 
Solar Power Plant System Sizing
Solar Power Plant System SizingSolar Power Plant System Sizing
Solar Power Plant System Sizing
 
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s GuideUtility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
Utility-Scale Solar Photovoltaic Power Plants - A Project Developer’s Guide
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant Maintenance
 
Solar Project Financing
Solar Project FinancingSolar Project Financing
Solar Project Financing
 
Gensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality ManagementGensol Rooftop EPC - Steps & Quality Management
Gensol Rooftop EPC - Steps & Quality Management
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...
 
IPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development RoadmapIPP Utility Scale Solar PV Project Development Roadmap
IPP Utility Scale Solar PV Project Development Roadmap
 
Solar rooftop presentation
Solar rooftop presentationSolar rooftop presentation
Solar rooftop presentation
 
Basics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig GensolBasics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig Gensol
 
Gensol - EPC Services
Gensol - EPC ServicesGensol - EPC Services
Gensol - EPC Services
 
Jakson_report_Final
Jakson_report_FinalJakson_report_Final
Jakson_report_Final
 
Drawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar ProjectsDrawings & Documents Required for Solar Projects
Drawings & Documents Required for Solar Projects
 
Designing Solar PV Systems (Rooftops)
Designing Solar PV Systems(Rooftops)Designing Solar PV Systems(Rooftops)
Designing Solar PV Systems (Rooftops)
 
Financial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plantFinancial analysis of 1 MW Solar PV plant
Financial analysis of 1 MW Solar PV plant
 
roof top solar
roof top solarroof top solar
roof top solar
 
Steinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design reportSteinbeis 1MW Grid Connected System design report
Steinbeis 1MW Grid Connected System design report
 
Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)Designing Solar PV Systems ( Utility Scale)
Designing Solar PV Systems ( Utility Scale)
 
Introduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power systemIntroduction to Off Grid Solar Power system
Introduction to Off Grid Solar Power system
 
Study of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plantStudy of Large Scale Grid interactive Solar PV power plant
Study of Large Scale Grid interactive Solar PV power plant
 

Similar to 10 mw solar power plant

Staten solarprofile project development for spv power plants
Staten solarprofile project development for spv power plantsStaten solarprofile project development for spv power plants
Staten solarprofile project development for spv power plantsRakesh Singh
 
Staten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicantsStaten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicantsRakesh Singh
 
solar consultants corporate credentials (1).pdf
solar consultants corporate credentials  (1).pdfsolar consultants corporate credentials  (1).pdf
solar consultants corporate credentials (1).pdfsanjay vashishtha
 
Rauluk Testimony Final no pics
Rauluk Testimony Final no picsRauluk Testimony Final no pics
Rauluk Testimony Final no picsValerie Rauluk
 
Solar power generation
Solar power generationSolar power generation
Solar power generationAngel Dass
 
Solar power generation
Solar power generationSolar power generation
Solar power generationAngel Dass
 
Solar power generation
Solar power generationSolar power generation
Solar power generationAngel Dass
 
Ada power presentataion 30.03.2018
Ada  power presentataion  30.03.2018Ada  power presentataion  30.03.2018
Ada power presentataion 30.03.2018Avanindra Yadav
 
Solar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdf
Solar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdfSolar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdf
Solar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdfEnerco Energy Solutions LLP
 
Naveen Final Thesis with corrections (1)
Naveen Final Thesis with corrections (1)Naveen Final Thesis with corrections (1)
Naveen Final Thesis with corrections (1)Kadimcherla Naveen
 
Lobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantLobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantL'Obel Solar Power System
 
Garden-City-case-study
Garden-City-case-studyGarden-City-case-study
Garden-City-case-studyPeter Sweetnam
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.Hagi Sahib
 

Similar to 10 mw solar power plant (20)

Project solar
Project solar Project solar
Project solar
 
Staten solarprofile project development for spv power plants
Staten solarprofile project development for spv power plantsStaten solarprofile project development for spv power plants
Staten solarprofile project development for spv power plants
 
Staten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicantsStaten solarprofile epc for spv power plant applicants
Staten solarprofile epc for spv power plant applicants
 
Proposal solar
Proposal solarProposal solar
Proposal solar
 
SOLAR ENERGY CSP TECHNOLOGY TECHNICAL CONSULTANT
SOLAR ENERGY CSP TECHNOLOGY TECHNICAL CONSULTANTSOLAR ENERGY CSP TECHNOLOGY TECHNICAL CONSULTANT
SOLAR ENERGY CSP TECHNOLOGY TECHNICAL CONSULTANT
 
GREEN POWER PROJECT
GREEN POWER PROJECTGREEN POWER PROJECT
GREEN POWER PROJECT
 
solar consultants corporate credentials (1).pdf
solar consultants corporate credentials  (1).pdfsolar consultants corporate credentials  (1).pdf
solar consultants corporate credentials (1).pdf
 
Rauluk Testimony Final no pics
Rauluk Testimony Final no picsRauluk Testimony Final no pics
Rauluk Testimony Final no pics
 
Solar power generation
Solar power generationSolar power generation
Solar power generation
 
Solar power generation
Solar power generationSolar power generation
Solar power generation
 
Solar power generation
Solar power generationSolar power generation
Solar power generation
 
The MBA of Solar O&M
The MBA of Solar O&MThe MBA of Solar O&M
The MBA of Solar O&M
 
Ada power presentataion 30.03.2018
Ada  power presentataion  30.03.2018Ada  power presentataion  30.03.2018
Ada power presentataion 30.03.2018
 
Solar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdf
Solar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdfSolar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdf
Solar Energy Projects - 8 reasons for under-performance (ENERCO Energy).pdf
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Naveen Final Thesis with corrections (1)
Naveen Final Thesis with corrections (1)Naveen Final Thesis with corrections (1)
Naveen Final Thesis with corrections (1)
 
Lobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantLobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plant
 
Garden-City-case-study
Garden-City-case-studyGarden-City-case-study
Garden-City-case-study
 
solar street light project report.
solar street light project report.solar street light project report.
solar street light project report.
 
OHMS ENERGY SOLAR
OHMS ENERGY SOLAROHMS ENERGY SOLAR
OHMS ENERGY SOLAR
 

Recently uploaded

Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research DiscourseAnita GoswamiGiri
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQuiz Club NITW
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptxmary850239
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...DhatriParmar
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxSayali Powar
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWQuiz Club NITW
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptxmary850239
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1GloryAnnCastre1
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseCeline George
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptxDhatriParmar
 

Recently uploaded (20)

Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research Discourse
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
 
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptxINCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
INCLUSIVE EDUCATION PRACTICES FOR TEACHERS AND TRAINERS.pptx
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptxBIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
BIOCHEMISTRY-CARBOHYDRATE METABOLISM CHAPTER 2.pptx
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITW
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 Database
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
 

10 mw solar power plant

  • 1. Solar Power Station ProjectAnalysis Report for Power Plant of 10MW capacity Rusiru Sanjaya 2016-08-19 SunPower Systems (PVT) LTD.
  • 2. CONTENT Page Introduction………………………………………………………………………………………… 1 SWOT analysis of the Power Plant Strengths……………………………………………………………………………………2 Weaknesses……………………………………………………………………………….3 Opportunities…………………………………………………………………………….4 Threats……………………………………………………………………………………….5 Project Implementation Process…………….…………………………………………….6 Pre-feasibility report and statutory approval……………………………………..…7 Financial Aspects of the project…………… ………………………………………………10
  • 3. P a g e | 1 INTRODUCTION At the moment according to the energy consultants, Sri Lanka is heading to an energy crisis during early 2020s. Though the country has policies to get rid of fossil fuel generated energy by 2030, there are stillprojects which are proposed and about to implement, that burn fossil fuels to generate energy. But now the world trend has gone far more away than this condition. Now most of foreign countries are implementing thousands of projects to introduce renewable energy to their power systems whereas some countries have already produce their total power required for the consumers using renewable energy. Due to burning fossil fuels, global warming and environmental effects have increased day by day. At this rate of CO2 emission to the air, sooner the earth will become place which is not suitable for human to live anymore. As responsible citizens and businessmen in the country, we should lead this country to find environmental friendly power solutions to compete with the energy crisis. Among these renewable energy solutions, Solar Power systems have become most important and favourite energy source. Most of the foreign countries have implemented large scale of solar power systems projects because using solar insolation, it could be easily obtain large amount of energy with zero environmental pollution, for zero cost except for the installations and zero noises.And this would not be a solution just for two three years, but itcan provide energy free of charge as our Sun willprovide solarenergy for another thousands of years. So investing on solar energy will be much better decision for the energy solutions. This report will be focused on describing and analyse the strengths, weaknesses, opportunities, treats as wellas guide on project implementation process,governing and ruling bodies relevant to these kind of projects and also the sequence of process which has to be done. And also brief financial analysis on the 10MW solar power plant is also included in this report.
  • 4. P a g e | 2 SWOT Analysis Strengths  Geographically, Sri Lanka is located near the equator which is the ideal position for a country finding energy solution by solar energy because of the high sun irradiations. Thus it would be really good decision to invest for solar power plant in this country as the payback period is minimum compared to the other countries which are located in away from the equator.  As our company has done few other large scale solar projects, we have many experiences regarding the maintenance problems and problems which would arise after the installation of the system. Therefore prior steps can be taken to avoid those issues happening in this kind of a project and it’llminimize or eliminatepotential losses that company would incur by this project.  As we have done so many other projects including moderately large scale projects (200kW, 400kW), our company has engineers and technicians with full of experiences. So there is no considerable issues regarding the technical skills required to operate 10MW solar power plant.  Having all the experience obtaining by solar installation done so far, our company has good knowledge of the quality of our products and also currently we are importing components in best and reputed brands in the world. So durability and reliability of our instruments and components is not an issue at all for this kind of a long term investment.  According to solarinstallations done so far around the country, our company has good idea about the weather conditions around the country with experiences from installed systems’ outputs behaviours during past years. So choosing suitable and best geographical locations for the system becomes easy task.  By implementing a Solar Power Plant, we can contribute to reduce CO2 emission to atmosphere in millions of tons for each year. So that effects such as global warming can be minimized.
  • 5. P a g e | 3 Weaknesses  All the projects we have done so far are below the 1MW capacity. But we are looking about 10MW system in this project. Thus we may suffer out of numbers of engineers and technicians to maintain such large system in once.  If this project going to be implemented, large amount of money has to be invested undoubtedly. Our company may not have that much of money to implement this project. If our capitalstrength is not sufficientfor a project likethis,it will be disastrous if it’s unable to complete the project because there is no return on investment until the project has successfully done.  If grid becomes unstable or go offline when during the operation of the power plant, the generated energy will no more be transferred to the grid and hence that energy will be lost due to lack technologies in large scale storage system. Hence lack of storages become weakness point.  Sri Lanka being an island, salty atmosphere may cause badly to the systemlifetime as its components become corroded sooner.  As Sri Lanka is a tropical country, panels’ temperature become increased due to hot atmosphere and hence the efficiency of the panel get reduced.  And also due to high relative humidity, solar irradiations may be reduced in some areas.
  • 6. P a g e | 4 Opportunities  In around 2020s, Sri Lanka will be facing a huge power crisis as at the moment the demand for the power in Sri Lanka is increasing rapidly. There are no any additional power plants in near future to be run to meet this demand. So the government will have to lookup renewable energy sources as it can be implement very quickly compared to the other large scalepower plants. So in this scenario, Solar Power Plants are the best solution and this creates many benefits to the firms who runs solar power plants.  The fossil fuel reserves in the world become over during next decades. So the only solution for power crisis is become renewable energy and thus Solar energy for countries near the equator.  Now many firms are manufacturing solar panels and other products. Thus competency among these firms become very high. Due to that price of the solar products become less. This ensure to build the plant with quality products for minimum costs.  It is well known that the efficiency of the PV panels are very low. But many R&A projects are ongoing to maximize the efficiency of the solar panels. This will be a great opportunity in the future improvements of the systems.  Comparison to other power generating systems, solar power plants have less operation and maintenance manpower required.  A solar power plant will be running a very long time compared to other power generating systems.  In environmental perspective, solar power plants generates clean energy without emitting any gas. This leads to maximum environmental clean development.
  • 7. P a g e | 5 Threats  It is obvious that after completing the project, if the solarinsolation failedto reach the system properly due to some long term bad weather or clouds, there are no other option except to bear the losses occurring initial capital cost and maintenance. So weather would be uncontrollable threat for the project in the future.  If the grid becomes unstable of the country or if the power cuts going to happen very frequently, then power generated by our system won’t exported during that time. If there is no other auxiliary system for storing that energy, it will cause huge losses to the plant as that energy is wasted. So considering the grid stability of the country should be very important.  Nowadays as many companies are tending to install sola power systems and thus there may be lack of employees who are well trained about the solar systems because of the higher job demand for the employees such as technicians and engineers.  When this project is implementing, company would have to look after its past customers’ service to maintain its usual customer relationships as well as the project which is going to implementing in future. If customers feel that they are not supplied with the service which they deserved from the company, they will definitely be a huge threat to the company.  Villagers in this area may not willing to accept this kind of project in their area due to varies reasons. So we have to consider villager’s concerns also because without their support project won’t be able to implement and it’ll be great threat to the project.
  • 8. P a g e | 6 Project Implementation process 1. Selecting a suitable site – According to the sola insolation and other requirements, suitable area in the country should be selected. 2. Pre-feasibility study and financial analysis of the project –Before starting a renewable energy project, it should be done a feasibilitystudy according to the regulations of SEA and a Financial feasibility of basic inputs like land, labour, solar insolation, solar PV systems etc. with the output which can obtain by the system. 3. Statutory Approvals and obtaining an Energy Permit – To implement the project, company should obtain relevant statutory approvals from regulatory bodies. If the project is approved by them, an energy permit will be granted by these authorities to continue generating energy and sell it to the national grid. 4. Getting into power purchase agreement – A power purchase agreement is signed between CEB and the company to get into an agreement which CEB buys the electricity from the company. 5. Financing to solar project – This is usually very high investment because tools and components used in a solar system are very expensive. And further there are more other expenses that would incur during the implementation of the project. So it is necessary to have a clear vision in financing the project. 6. Acquire the Land – If the project becomes financially feasible, then the Land space should be leased or bought first. 7. Basic technological design of the system – The layout of the basic technological design of solar power systemis prepared by the engineers and technicians having experience in the field. 8. Testing and connecting to Grid – After the system is tested for the correct working conditions, power plant is connected to the Grid to export energy in order to sellthem to CEB. 9. Operating and Maintenance – A typical solar PV panel has 25 – 30 lifetime and an inverter has 10 – 15 years lifetime. To expand their lifetime, it should be well maintained and cleaned the components of the system.
  • 9. P a g e | 7 Pre-feasibility Report and Statutory Approval Sustainable Energy Authority (SEA) is the main legal body to manage and control over the renewable energy sources in Sri Lanka. All the instructions and permissions will be given by Sustainable Energy Authority regarding a renewable energy project is to be implemented. If the proposed project is more than 10MW capacity, then acquiring a generation license from CEB will be necessary as well. Since this project is of 10MW capacity, there is no need of acquiring a generation license of CEB. Before applying a formal application to the SEA for renewable energy project, recourses are provided in the On-Grid Renewable Energy Projects Regulation 2009 to verify the availability of the suitable NRE site for development. And then a formal application need to be prepared to submit to the SEA as prescribed in Section 16(2) of the On-Grid Renewable Energy Projects Regulation 2011 and this application should be accompanied with a Pre-feasibility study report. When the application is being submitting, a non-refundable application fees should be paid to SEA.  Pre-feasibility Study report In this study report it should be include a Summary of the Pre-feasibility study, Certification by the accredited Consultant and Study report based on the list of contents.  Standard format for Summary of the Pre-feasibility study  Standard format for Certification by the accredited Consultant  Standard format for Study report based on the list of contents When preparing the pre-feasibility study report following aspects should be given focused attention.  Land issues must be sort out( availability of the land for the project, consent of the agency to whom the land belongs to etc.) and clear identification of ownership Format_F1.pdf Format_F2.pdf Format_F3.pdf
  • 10. P a g e | 8  Resource issues (availability of the resource for the project, conflicting uses of the resource etc.) must be clearly understood by studying all aspects of the resources such as seasonality and other uses (existing and future) of the resource which may compromise the project feasibility.  Issues with respect to affected communities will have to be understood and documented to avoid conflicts during project implementation  Making an Application In this process proponent has to make the contact with SEA by making an application to SEA. When applying for renewable energy project, proponent has to make an application fee to the SEA as described below. Following main components should be included in the Application form a) Pre-feasibility report prepared by a Consultant accredited by SEA, with one page summary b) A copy of the map of the geographical location of the proposed project c) A brief description of the project, including the amount of power to be generated. d) The total estimated cost and financial model including the optimisation criteria adopted. e) Proof of availability of adequate finances or the manner in which the required finances for the project are to be obtained. f) Project location, describing the relative location of the energy conversion plant and equipment to the resource, as a further explanation of (b) above g) A statement explaining how the Applicant intends to deliver electricity generated by the project to the national grid, and geographical area travelled by the power line to be constructed for that purpose. h) A copy of the receipt obtained from the SEA, for the payment of the application fee, which will be calculated according to the schedule given overleaf  Application fee Amount of power proposed to be generated Fee to be paid on application 1000kW or part thereof LKR 100,000 Each additional 1,000kW LKR 50,000 payable on pro rata basis
  • 11. P a g e | 9  Approval Phase In this process, proponent has to obtain formal approval from several other agencies to proceed with the project development. The approval of DivisionalSecretary Central Environment Authority and an assurance from CEB on purchasing energy from the proposed project will provide a strong acceptance to the project beforehand.  Divisional Secretary’s Approval - Divisional Secretary is considered as the representative of the Government at the grass root level who protects and manages the state land and other natural resources. Under the 13th Amendment to the constitution, getting the consent of the respective Provincial Council is also compulsory.  Letter of intent – This document is issued by CEB to signify the assurance of CEB to procure the electricity generated by the project. When applying for this letter proponent should be made an application fee of LKR 100,000 to CEB.  Feasibility Study Phase In this phase, the Developer makes detailed evaluation of the feasibilityof the project, giving due consideration to the input resources and outcome of the project.  Comprehensive Feasibility Study - The Developer is required to evaluate all factors which influence the project, ranging from weather and climate conditions to eventualities of relocating people who may be affected by the project implementation.  Environmental Examination - The Developer is required to make an application to the Central Environmental Authority (CEA) seeking environmental clearance. Depending on the severity of the environmental impact of the project, the project may be required to undergo either an Initial Environmental Examination (IEE) or a more comprehensive Environmental Impact Assessment (EIA).  Licensing Phase Having obtained statutory clearance to proceed, the Developer is required to secure an Energy Permit to use the renewable energy resource, a Generation License from PUCSL to generate electricity and sell energy to the CEB.  Energy Permit – All renewable energy resources are owned by the republic of Sri Lanka. Hence the utilization of resources is granted through a20 year permit
  • 12. P a g e | 10 system. Once all other approvals are secured by a project Developer, the PAC grants a 20 year permit (extendable by a further 20 years after the successful operation of the project during the initial 20 year period) to the Developer allowing him to use the resource under several conditions. The Developer will have to pay a fee of LKR 500,000/- (per MW of capacity) as the permit fee in the caseof projects with capacities of 10MW or less. The Energy Permit carries a grace period of 2 years to allow for construction activities, and the Developers are required to complete implementation within this period.  Generation License - The project Developer, possessing an Energy Permit is required to obtain a Generation License from the Public Utilities Commission of Sri Lanka (PUCSL) with the enactment of the Sri Lanka Electricity Act 20 of 2009. The annual fees payable to PUCSL for the Generation License will be LKR 10,000/- per MW.  Power Purchase Agreement - All projects having capacities of 10MW or less have to be taken under the Standardised Power Purchase Agreement (SPPA), reached between the CEBand the power producer. The time tested agreement is supported by tariffs offered to various technologies and are subject to revisions based on project cost escalations, at appropriate intervals. The SPPA is valid for a period of 20 years from the date of commercial operation. Financial Aspects of the project After obtaining the statutory permissions, company should manage the financial resources to implement the project. Even though the project is in statutory clearance procedures, company can handle financing resources because no sooner the required approvals will be given for the project by the relevant parties if the necessary documents and requirements are provided accordingly. Financing methods should be decided based on the capital strength of the company and required mount of investment to the project. Company has to decide whether the capital strength of the company to implement this project is strong or else to obtain debt from external parties. To decide these things, company has to do a proper analysis on all expenditures on this project.
  • 13. P a g e | 11 Let’s assume the solar irradiation of the site is 1kW/m2 and PV panel with the dimensions 1639*983 mm2 and efficiency of 16%. Then required panel area to generate 10MW system capacity is as follows, Therefore at least 5.053*105 m2 land area is required to establish the system. Thus number of panels required is, If a panel cost is around Rs.20, 000 then cost of the panels = 38,793*20,000 = 775.86 million rupees If 1MW inverters are used, then required number of inverters = 10 Cost of each inverter = 2.5 million rupees Then cost for the inverters = 25 million rupees Then the total cost for the PV panels and Inverters = 800 million rupees In additional to the above cost, there are many other costs associated with this projects such as installation costs, transportation costs, system mounting costs, costs for developments of infrastructures etc. Therefor total amount required for a 10MW project may be around 1.5 to 2.0 billion rupees. Ceylon Electricity Board offers Three-Tier Tariff method which describes how the rates are calculated.Accordingto theirtariffs,SolarPowerPlant will be offereda flat tariff of Rs. 23.10 / kWh (non-escalable for20 years).Therefore requiredenergytobe generatedtorecoverthe cost incurred for thisprojectcan be calculatedasfollowsbyassumingthe costis1.5 billionrupeesfor the project. By considering average Sun time is 5 hours and energy generating in this sun hours is 10MW, we can calculate the approximate payback period. 𝐴𝑟𝑒𝑎 = 10 × 106 1 × 103 × 0.16 = 62,500 𝑚2 𝑃𝑎𝑛𝑒𝑙 𝑛𝑜𝑠 = 62500 1639 × 983 × 10−6 = 38,793 𝑛𝑜𝑠 𝑅𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑒𝑛𝑒𝑟𝑔𝑦 𝑡𝑜 𝑟𝑒𝑐𝑜𝑣𝑒𝑟 𝑡ℎ𝑒 𝑐𝑜𝑠𝑡 = 𝑅𝑠.1.5 × 109 𝑅𝑠.23.1/𝑘𝑊ℎ = 6.494 × 107 𝑘𝑊ℎ = 2.34 × 1011 𝑘𝐽 𝑇ℎ𝑒𝑟𝑒𝑓𝑜𝑟 𝑝𝑎𝑦𝑏𝑎𝑐𝑘 𝑝𝑒𝑟𝑖𝑜𝑑 𝑖𝑠 𝑎𝑝𝑝𝑟𝑜𝑥𝑖𝑚𝑎𝑡𝑒𝑙𝑦 = 2.34 × 1011 𝑘𝐽 10 × 5 × 3600 × 103 𝑘𝐽 = 1299 𝑑𝑎𝑦𝑠(≈ 3.6𝑦𝑒𝑎𝑟𝑠)
  • 14. P a g e | 12 Above payback period is calculated without considering any interest rates. If interest rates are considered, above payback period will be increased. For an instance let’s assume an interest rate of 15% of financing method to be used. Then the actual payback period can be calculated as follows. 𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑟𝑒𝑣𝑒𝑛𝑢𝑒 𝑡ℎ𝑎𝑡 𝑐𝑎𝑛 𝑏𝑒 𝑜𝑏𝑡𝑎𝑖𝑛 𝑏𝑦 𝑡ℎ𝑒 𝑠𝑦𝑠𝑡𝑒𝑚 𝑝𝑒𝑟 𝑚𝑜𝑛𝑡ℎ = 5 × 104 𝑘𝑊ℎ × 𝑅𝑠.23.1/𝑘𝑊ℎ × 30 = 𝑅𝑠 3.465 × 107 𝑇ℎ𝑒𝑟𝑒𝑓𝑜𝑟 𝑝𝑎𝑦𝑏𝑎𝑐𝑘 𝑝𝑒𝑟𝑖𝑜𝑑 𝑖𝑠 𝑎𝑝𝑝𝑟𝑜𝑥𝑖𝑚𝑎𝑡𝑒𝑙𝑦 = 1920 𝑑𝑎𝑦𝑠(≈ 5.3 𝑦𝑒𝑎𝑟𝑠)