Schneider Electric 1-– 2014 NEC Changes – 2013
2014 National Electrical Code
Top 10 Revisions Impacting
Electrical Installation
●Alan Manche, P.E.
●Director, Industry Standards
Tweet Live!
#SchneiderXE
Schneider Electric 2-– 2014 NEC Changes – 2013
Objectives
Upon completion, you will be able to:
● Identify key revisions to the 2014 NEC
● Identify new requirements for AFCI and GFCI
● Define and apply the lighting calculation to the NEC based on
the energy code lighting controls
● Apply the revised NEC requirements for:
● 1000V systems compared to 600V
● Energy Management
● Arc Energy Reduction
● EV Supply Equipment as applied using an Energy
Management system
● Identify new requires for new surge protection requirements on
emergency panels
Schneider Electric 3-– 2014 NEC Changes – 2013
2014 NEC Facts
● 3,745 Proposals
● 1,625 Comments
● 4 New Articles (393, 646, 728, 750)
● 19 Code Making Panels
● 473 Volunteer Code Making Panel Members
● NFPA Annual Meeting, June 2013
● 2014 NEC Published, September 2013
Schneider Electric 4-– 2014 NEC Changes – 2013
Article 750 Energy Management Systems
•Article proposed by the “Smart Grid Task
Group” appointed by the Technical
Correlating Committee
•Energy Management has become
common place in today’s electrical
infrastructure - control of utilization
equipment, energy storage and power
production
•Restricting the control of the system by
the energy management system becomes
critical to ensure safety
(Example: load shedding for an alternate
power source for fire pumps and
emergency systems)
Schneider Electric 5-– 2014 NEC Changes – 2013
Increasing 600 V requirements to 1000 V
●High Voltage Task Group Appointed
by the NEC Technical Correlating
Committee
●Identified demand for increasing voltage
levels in wind generation and
photovoltaic systems as the basis for
enhancing common voltage levels
●Chapters 1 – 8 reviewed
●Proposals were created in areas where
the TG agreed the change resulted in
minimal or no impact to the system
installation
● Article 100 (Definitions) and Article 110 (Requirements for
electrical installations retained the 600 V breakpoint
Schneider Electric 6-– 2014 NEC Changes – 2013
110.26(C)(3) – Personnel Doors
(3) Where there is equipment 800A
or greater and there are doors that
are within 25’ of the nearest edge
of the working space – the door
must have panic hardware and
must open outward
●Rules for two working space
entrances in 110.26(C)(2) are
unchanged (equipment is 1200A
or greater and the equipment is
over 6 feet wide)
Condition 1
Working Space
Equipment 800A
or greater
Sheetrock wall
Top Down View
<=25’
Door must open
outward and
have panic
hardware
Schneider Electric 7-– 2014 NEC Changes – 2013
210.8(A) – GFCI (Dwellings)
●All 125-volt, single-phase, 15- and
20-ampere receptacles installed in
the locations specified in
210.8(A)(1) through (10) shall have
ground-fault circuit-interrupter
protection for personnel.
●(10) Laundry Areas
(10) - Laundry
Schneider Electric 8-– 2014 NEC Changes – 2013
210.8(D) – GFCI (Dwellings)
●GFCI protection shall be provided
for outlets that supply dishwashers
Kitchen Dishwasher Branch Circuit
Schneider Electric 9-– 2014 NEC Changes – 2013
210.12 - AFCI
120V, 15A and 20A branch circuits that
supply outlets in dwelling unit:
Kitchens, family rooms, dining rooms,
living rooms, parlors, libraries, dens,
bedrooms, sunrooms, recreation
rooms, closets, hallways, laundry
areas, or similar rooms
(A) – Dwelling Units
Schneider Electric 10-– 2014 NEC Changes – 2013
210.12 - AFCI
120V, 15A and 20A branch
circuits that supply outlets
in dormitory unit:
Bedrooms, living rooms,
hallways, closets, and
similar rooms
(C) – Dormitory Units
Schneider Electric 11-– 2014 NEC Changes – 2013
210.12(A) – AFCI (Dwellings)
1. Combination type arc-fault circuit
interrupter, installed to provide
protection of the entire branch circuit
2. Branch/feeder type AFCI installed at
the origin of the branch circuit in
combination with an outlet branch
circuit type arc-fault circuit interrupter
installed at the first outlet box on the
branch circuit. (outlet box must be
marked to indicate that it is the first
outlet of the circuit)
Six Options now permitted for AFCI protection
Schneider Electric 12-– 2014 NEC Changes – 2013
210.12(A) – AFCI (Dwellings)
Six Options now permitted for AFCI protection (continued)
3.Supplemental arc protection circuit breaker installed at
the origin of the branch circuit in combination with a listed
outlet branch circuit type arc-fault circuit interrupter installed
at the first outlet box on the branch circuit where all of the
following conditions are met:
(a) Continuous branch circuit wiring from the branch breakers to
the outlet branch circuit AFCI
(b) Maximum length of the branch circuit wiring to the first outlet
must not exceed 50 ft for a 14 AWG or 70 ft for a 12 AWG
(c) First outlet box in the branch circuit shall be identified
Schneider Electric 13-– 2014 NEC Changes – 2013
210.12(A) – AFCI (Dwellings)
Six Options now permitted for AFCI protection (continued)
4. Outlet branch circuit type arc-fault circuit interrupter
installed at the first outlet box on the branch circuit in
combination with a listed branch circuit overcurrent
protective device where all of the following conditions are
met:
(a) Continuous branch circuit wiring from the branch circuit
overcurrent protective device to the outlet branch circuit AFCI
(b) The maximum length of the branch circuit wiring to the first
outlet must not exceed 50 ft for a 14 AWG or 70 ft for a 12
AWG
(c) The first outlet box in the branch circuit shall be identified
(d) The combination of the branch circuit overcurrent device
and outlet branch circuit AFCI is identified as meeting the
requirements for a "System Combination" type AFCI and is
listed as such.
Schneider Electric 14-– 2014 NEC Changes – 2013
210.12(A) – AFCI (Dwellings)
Six Options now permitted for AFCI protection (continued)
5. Outlet branch circuit type arc-fault circuit interrupter
installed at the first outlet box on the branch circuit in
combination with ...
● RMC, IMC, EMT, Type MC, or steel armored Type AC
cables meeting the requirements of 250.118,
● Metal wireways, metal auxiliary gutters and metal outlet
and junction boxes are installed for the portion of the
branch circuit between the branch-circuit overcurrent
device and the first outlet
Schneider Electric 15-– 2014 NEC Changes – 2013
210.12(A) – AFCI (Dwellings)
Six Options now permitted for AFCI protection (continued)
6. Outlet branch circuit type arc-fault circuit interrupter
installed at the first outlet box on the branch circuit in
combination with ...
● Listed metal or nonmetallic conduit or tubing or
● Type MC Cable and
● Encased in not less than 50mm (2 in.) of concrete for
the portion of the branch circuit between the branch
circuit overcurrent device and the first outlet
Exceptions (1) and (2) removed. Exception (3) for fire alarm systems retained
Schneider Electric 16-– 2014 NEC Changes – 2013
210.12(A) (5) & 210.12(A)(6)
Install outlet
branch circuit AFCI
at the first outlet
Provides protection for:
Wiring from panel to
first outlet must be
installed in RMC,
IMC, EMT, MC or
steel jacketed AC
cable.
Must also have metal
outlet and junction
boxes.
Also permits metallic
and nonmetallic
conduit or Tubing or
MC cable where
encased in 2” of
concrete
Schneider Electric 17-– 2014 NEC Changes – 2013
220.12 Exception – Lighting Loads for
Specified Occupancies
• New Exception allows lighting loads to
calculated using the adopted energy
code
• Building must be designed and
constructed to comply with the adopted
energy code and meet the following:
• Power monitoring system installed to provide
lighting load data
• Power monitoring system must have alarm(s) to
alert the building owner/manager if the lighting
load exceeds limits
• Demand factors in 220.42 do not apply
Schneider Electric 18-– 2014 NEC Changes – 2013
240.87 – Arc Energy Reduction
• Required for circuit breakers rated
1200 A and above
•Documentation on the circuit breaker
location and
•Reduced Clearing Time Method
• Zone-selective interlocking or
• Differential relaying or
• Energy-reducing maintenance
switching with local status
indicator or
• Energy-reducing active arc flash
mitigation system or
• An approved equivalent means
Schneider Electric 19-– 2014 NEC Changes – 2013
310.15(B)(7) – 120/240 V, Single Phase, Services
and Main Power Feeders (Dwellings)
●Table 310.15(B)(7) removed
●Service or Feeder ratings 100 through 400 A, an adjustment
factor of 0.83 of the service or feeder ampere rating can be used
to determine the size of the ungrounded conductors where
supplying the entire load
●Grounded conductor can be smaller than the ungrounded
conductors, see 215.2, 220.61, and 230.42
●Other correction or adjustment factors applicable to the conductor
installation apply
●New example added to Annex D
Schneider Electric 20-– 2014 NEC Changes – 2013
406.9(B)(1)
●Expands the “extra duty” cover
requirement to all wet location receptacle
locations not just those supported
from grade
●Similar revision to 590.4(D)(2)- clarifies
the “extra duty” requirements apply to all
wet location temporary
installations, including dwellings
Schneider Electric 21-– 2014 NEC Changes – 2013
Article 517 Healthcare Facilities
● Revisions align NEC requirements with NFPA 99
● Clarify the use of the term “Emergency” and where the
requirements of Article 700 apply
● Correlation of EES overcurrent device coordination
requirements
Schneider Electric 22-– 2014 NEC Changes – 2013
517.18(B) Patient Bed Location Receptacles
●This proposed change increases the minimum number of receptacles
required from four to eight.
●Aligns with NFPA 99 relative to the increases in quantity of
receptacles and normal care patient bed locations.
22
Schneider Electric 23-– 2014 NEC Changes – 201323
Schneider Electric 24-– 2014 NEC Changes – 2013
517.19(B) Patient Bed Location Receptacles –
Critical Care
●Section 517.19 addresses critical care patient bed locations. This
proposed revision in subdivision (B) changes the required minimum
number of receptacles from six to fourteen.
●List item (2) in this section was revised by removing the term
“emergency system” and replacing it with the term “critical branch.”
●Aligns with changes in NFPA 99-2012
24
Schneider Electric 25-– 2014 NEC Changes – 201325
Schneider Electric 26-– 2014 NEC Changes – 2013
517.19(C) Operating Room Receptacles
●The minimum number of receptacles required in an operating room is
thirty-six of which at least twelve of the thirty-six receptacles must be
connected to either the normal system branch or the critical system
branch.
●The grounding terminal of these receptacles must be connected to the
reference grounding point by means of an insulated copper equipment
grounding conductor.
26
Schneider Electric 27-– 2014 NEC Changes – 201327
Schneider Electric 28-– 2014 NEC Changes – 2013
517.26 Application of Other Articles
● Revision clarifies the application of other
code requirements with healthcare
facilities
● Life safety branch of the EES must
meet Article 700 requirements for
emergency systems
● Aligns NEC requirements with NFPA 99
Schneider Electric 29-– 2014 NEC Changes – 2013
Article 625 EV Supply Equipment
EV Supply Equipment requirements throughout
the article
●Electric Vehicle Supply Equipment System.
A system of components that provide an ac
output that is supplied to the vehicle for the
purpose of providing input power to an on-
board charger.
●625.14 Permits Energy Management system
to establish calculated load
●625.17 Cords and Cables added to cover the
Power Supply Cords and Output Cable to the
Electric Vehicle
●625.44 Sets requirements for Cord and Plug
Connected EV Supply Equipment
Schneider Electric 30-– 2014 NEC Changes – 2013
690.17(A) Disconnect Type
PV disconnecting means ... one of the
following devices:
(1) An industrial control switch marked for use in PV
systems.
(2) A molded case circuit breaker marked for use in PV
systems
(3) A molded case switch marked for use in PV systems.
(4) An enclosed switch marked for use in PV systems.
(5) An open-type switch marked for use in PV systems.
(6) A dc-rated molded case circuit breaker suitable for
backfeed operation.
(7) A dc-rated, molded case switch suitable for backfeed
operation.
(8) A dc-rated enclosed switch.
(9) A dc-rated open-type switch.
(10) A dc rated low voltage power circuit breaker.
Schneider Electric 31-– 2014 NEC Changes – 2013
700.8 – Surge Protection
Emergency systems are required to have
surge protection in or on all
●Switchboards and
●Panelboards
Schneider Electric 32-– 2014 NEC Changes – 2013
700.16 – Emergency Illumination
● Emergency illumination required in
the area of the disconnecting
means required by 225.31 and
230.70, as applicable, where the
disconnecting means are installed
indoors.
● Exception provided where an
alternative means is provided to
ensure emergency lighting
illumination is maintained.
Schneider Electric 33-– 2014 NEC Changes – 2013
705.31 – Location of Overcurrent Protection
Overcurrent protection for the
source conductors, connected to
the supply side of the service
disconnecting means in
accordance with 705.12(A), must
be located within (10 ft) of the point
where the electric power
production source conductors are
connected to the service.
Interconnected Electric Power Production Sources
Exception permits overcurrent protection more than 10 ft from the point of
connection where cable limiters or current limited circuit breakers for each
ungrounded conductor are installed at the connection point to the service.
Schneider Electric 34-– 2014 NEC Changes – 2013
About the Instructor
Alan Manche, P.E.
● Director, Industry Standards at Schneider Electric
● Member NEC Correlating Committee & NEC CMP 10
● Past Member of NEC CMP 8 and CMP 20
● Member of Technical Committee NFPA 110, 70B, and 73
● Past Chair of NFPA 70B
● Board of Directors Western Section IAEI
● Education Chair –International Association of Electrical
Inspectors (IAEI)
● Member, NEMA Codes and Standards
● Chair, NEMA Code Adoption Initiative
● Chair, NEMA Water and Fire Damaged Equipment
Committee

More Related Content

What's hot

Lvped318033 en 2018
Lvped318033 en 2018Lvped318033 en 2018
Lvped318033 en 2018Fane Pelin
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
 
Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...
Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...
Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...Littelfuse
 
Power Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic SystemsPower Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic SystemsVicor Corporation
 
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTDESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTDMahesh Chandra Manav
 
Introduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designIntroduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designAsif Eqbal
 
Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)Mahesh Chandra Manav
 
How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%Schneider Electric
 
Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...Magellan Power
 
Hioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogueHioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogueNIHON DENKEI SINGAPORE
 
Critical Power: Circuit Protection in Health Care Facilities
Critical Power: Circuit Protection in Health Care FacilitiesCritical Power: Circuit Protection in Health Care Facilities
Critical Power: Circuit Protection in Health Care FacilitiesConsultingSpecifyingEngineer
 

What's hot (20)

Lvped318033 en 2018
Lvped318033 en 2018Lvped318033 en 2018
Lvped318033 en 2018
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...
Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...
Preventing Over-temperature in USB Type-C Systems: Introducing the Littelfuse...
 
CWB Contactors
CWB ContactorsCWB Contactors
CWB Contactors
 
Abb rmu
Abb rmuAbb rmu
Abb rmu
 
Power Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic SystemsPower Adapter Design for 400 V DC Power Distribution in Electronic Systems
Power Adapter Design for 400 V DC Power Distribution in Electronic Systems
 
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTDESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
ESE Type Lightning Arretor NFC17-102(2011) Presentation by JMV LPS LTD
 
ABB Price List MCB DB
ABB Price List MCB DBABB Price List MCB DB
ABB Price List MCB DB
 
Company Profile - Adex
Company Profile - AdexCompany Profile - Adex
Company Profile - Adex
 
ABB Price List of Capacitors 008
ABB Price List of Capacitors 008ABB Price List of Capacitors 008
ABB Price List of Capacitors 008
 
Introduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical designIntroduction on indian codes as applied in electrical design
Introduction on indian codes as applied in electrical design
 
Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)Make india = make in india presentation by cs electric (2 files merged)
Make india = make in india presentation by cs electric (2 files merged)
 
How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%How to reduce energy consumption of pumping systems in mining by up to 30%
How to reduce energy consumption of pumping systems in mining by up to 30%
 
ABB Price List 2019
ABB Price List 2019ABB Price List 2019
ABB Price List 2019
 
ABB Switchgear Price list002
ABB Switchgear Price list002ABB Switchgear Price list002
ABB Switchgear Price list002
 
Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...Magellan Power - High Reliability Australian Technology Innovative, Customise...
Magellan Power - High Reliability Australian Technology Innovative, Customise...
 
ABB Contactor Price List
ABB Contactor Price List ABB Contactor Price List
ABB Contactor Price List
 
Hioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogueHioki Electrical measuring instruments 2022 catalogue
Hioki Electrical measuring instruments 2022 catalogue
 
Bảng catalog sản phảm máy cắt không khí ACB Easypact EVS Schneider
Bảng catalog sản phảm máy cắt không khí ACB Easypact EVS SchneiderBảng catalog sản phảm máy cắt không khí ACB Easypact EVS Schneider
Bảng catalog sản phảm máy cắt không khí ACB Easypact EVS Schneider
 
Critical Power: Circuit Protection in Health Care Facilities
Critical Power: Circuit Protection in Health Care FacilitiesCritical Power: Circuit Protection in Health Care Facilities
Critical Power: Circuit Protection in Health Care Facilities
 

Viewers also liked

Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10Don Joven
 
Policy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementationPolicy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementationMaria Theresa
 
Materials, tools, equipment and testing devices
Materials, tools, equipment and testing devicesMaterials, tools, equipment and testing devices
Materials, tools, equipment and testing devicesBrian Mary
 
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10Bogs De Castro
 
K-12 Module in TLE - ICT Grade 10 [All Gradings]
K-12 Module in TLE - ICT  Grade 10 [All Gradings]K-12 Module in TLE - ICT  Grade 10 [All Gradings]
K-12 Module in TLE - ICT Grade 10 [All Gradings]Daniel Manaog
 
Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0Bogs De Castro
 

Viewers also liked (8)

Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10
 
Policy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementationPolicy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementation
 
Materials, tools, equipment and testing devices
Materials, tools, equipment and testing devicesMaterials, tools, equipment and testing devices
Materials, tools, equipment and testing devices
 
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
 
K-12 Module in TLE - ICT Grade 10 [All Gradings]
K-12 Module in TLE - ICT  Grade 10 [All Gradings]K-12 Module in TLE - ICT  Grade 10 [All Gradings]
K-12 Module in TLE - ICT Grade 10 [All Gradings]
 
K to 12 PC Hardware Servicing Learning Module
K to 12 PC Hardware Servicing Learning ModuleK to 12 PC Hardware Servicing Learning Module
K to 12 PC Hardware Servicing Learning Module
 
K to 12 Electrical Learning Module
K to 12 Electrical Learning ModuleK to 12 Electrical Learning Module
K to 12 Electrical Learning Module
 
Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0
 

Similar to 2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installations

2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_advertsKhalid Sithari
 
Brochure_BMS..08_SG202168BEN_B06-0914
Brochure_BMS..08_SG202168BEN_B06-0914Brochure_BMS..08_SG202168BEN_B06-0914
Brochure_BMS..08_SG202168BEN_B06-0914Patrick Volluz
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolar Reference
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor correctorJoeChueng
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and StandardsSolarReference
 
Schneider electric tc indoor
Schneider electric tc indoorSchneider electric tc indoor
Schneider electric tc indoorRosmer Ocando
 
Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014Claude Colp
 
ABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum Contactors
ABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum ContactorsABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum Contactors
ABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum ContactorsThorne & Derrick International
 
228279816 philippine-electrical-code-summary
228279816 philippine-electrical-code-summary228279816 philippine-electrical-code-summary
228279816 philippine-electrical-code-summaryJoaquin Oronan
 
Air insulated sf6 ring main unit
Air insulated sf6 ring main unitAir insulated sf6 ring main unit
Air insulated sf6 ring main unitAUTO RECLOSER
 
Air insulated sf6 ring main unit
Air insulated sf6 ring main unitAir insulated sf6 ring main unit
Air insulated sf6 ring main unitJoeChueng
 
Air insulated sf6 ring main unit 36kv
Air insulated sf6 ring main unit 36kvAir insulated sf6 ring main unit 36kv
Air insulated sf6 ring main unit 36kvAUTO RECLOSER
 
Kyn28 metal clad switchgear
Kyn28 metal clad switchgearKyn28 metal clad switchgear
Kyn28 metal clad switchgearJoeChueng
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgearmichaeljmack
 
06612 iec zerti_rz11_e
06612 iec zerti_rz11_e06612 iec zerti_rz11_e
06612 iec zerti_rz11_eCesar Chilet
 
SolarEdge 82.8kW inverter with WiFi & SetApp - Primary unit
SolarEdge 82.8kW inverter with WiFi & SetApp - Primary unitSolarEdge 82.8kW inverter with WiFi & SetApp - Primary unit
SolarEdge 82.8kW inverter with WiFi & SetApp - Primary unitOptimus Energy Philippines
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterPaul Plavicheanu
 

Similar to 2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installations (20)

2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts
 
Brochure_BMS..08_SG202168BEN_B06-0914
Brochure_BMS..08_SG202168BEN_B06-0914Brochure_BMS..08_SG202168BEN_B06-0914
Brochure_BMS..08_SG202168BEN_B06-0914
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
11.docx
11.docx11.docx
11.docx
 
CWC - Contactor
CWC - ContactorCWC - Contactor
CWC - Contactor
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor corrector
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
Solar PV Codes and Standards
Solar PV Codes and StandardsSolar PV Codes and Standards
Solar PV Codes and Standards
 
Schneider electric tc indoor
Schneider electric tc indoorSchneider electric tc indoor
Schneider electric tc indoor
 
Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014
 
ABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum Contactors
ABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum ContactorsABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum Contactors
ABB IEC Indoor Vacuum Contactors VSC - Medium Voltage Vacuum Contactors
 
228279816 philippine-electrical-code-summary
228279816 philippine-electrical-code-summary228279816 philippine-electrical-code-summary
228279816 philippine-electrical-code-summary
 
Air insulated sf6 ring main unit
Air insulated sf6 ring main unitAir insulated sf6 ring main unit
Air insulated sf6 ring main unit
 
Air insulated sf6 ring main unit
Air insulated sf6 ring main unitAir insulated sf6 ring main unit
Air insulated sf6 ring main unit
 
Air insulated sf6 ring main unit 36kv
Air insulated sf6 ring main unit 36kvAir insulated sf6 ring main unit 36kv
Air insulated sf6 ring main unit 36kv
 
Kyn28 metal clad switchgear
Kyn28 metal clad switchgearKyn28 metal clad switchgear
Kyn28 metal clad switchgear
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
06612 iec zerti_rz11_e
06612 iec zerti_rz11_e06612 iec zerti_rz11_e
06612 iec zerti_rz11_e
 
SolarEdge 82.8kW inverter with WiFi & SetApp - Primary unit
SolarEdge 82.8kW inverter with WiFi & SetApp - Primary unitSolarEdge 82.8kW inverter with WiFi & SetApp - Primary unit
SolarEdge 82.8kW inverter with WiFi & SetApp - Primary unit
 
OneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft StarterOneGear SMC 15kV Soft Starter
OneGear SMC 15kV Soft Starter
 

More from Schneider Electric

Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design ConsiderationsSchneider Electric
 
Digital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsDigital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsSchneider Electric
 
32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing 32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing Schneider Electric
 
Key Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsKey Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsSchneider Electric
 
EcoStruxure™ for Cloud & Service Providers
 EcoStruxure™ for Cloud & Service Providers EcoStruxure™ for Cloud & Service Providers
EcoStruxure™ for Cloud & Service ProvidersSchneider Electric
 
Zelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingZelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingSchneider Electric
 
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSpacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSchneider Electric
 
Relay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingRelay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingSchneider Electric
 
Magelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingMagelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingSchneider Electric
 
Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Schneider Electric
 
EcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesEcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesSchneider Electric
 
Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Schneider Electric
 
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.Schneider Electric
 
It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580Schneider Electric
 
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...Schneider Electric
 
Connected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTConnected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTSchneider Electric
 
Telemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingTelemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingSchneider Electric
 
Telemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingTelemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingSchneider Electric
 
Telemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingTelemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingSchneider Electric
 

More from Schneider Electric (20)

Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design Considerations
 
Digital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsDigital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting Investors
 
32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing 32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing
 
Key Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsKey Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation Trends
 
EcoStruxure™ for Cloud & Service Providers
 EcoStruxure™ for Cloud & Service Providers EcoStruxure™ for Cloud & Service Providers
EcoStruxure™ for Cloud & Service Providers
 
Magelis Basic HMI Briefing
Magelis Basic HMI Briefing Magelis Basic HMI Briefing
Magelis Basic HMI Briefing
 
Zelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingZelio Time Electronic Relay Briefing
Zelio Time Electronic Relay Briefing
 
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSpacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
 
Relay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingRelay Control Zelio SSR Briefing
Relay Control Zelio SSR Briefing
 
Magelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingMagelis HMI, iPC and software Briefing
Magelis HMI, iPC and software Briefing
 
Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?
 
EcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesEcoStruxure for Intuitive Industries
EcoStruxure for Intuitive Industries
 
Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017
 
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
 
It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580
 
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
 
Connected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTConnected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoT
 
Telemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingTelemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories Briefing
 
Telemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingTelemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors Briefing
 
Telemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingTelemecanique Limit Switches Briefing
Telemecanique Limit Switches Briefing
 

Recently uploaded

WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 

Recently uploaded (20)

WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 

2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installations

  • 1. Schneider Electric 1-– 2014 NEC Changes – 2013 2014 National Electrical Code Top 10 Revisions Impacting Electrical Installation ●Alan Manche, P.E. ●Director, Industry Standards Tweet Live! #SchneiderXE
  • 2. Schneider Electric 2-– 2014 NEC Changes – 2013 Objectives Upon completion, you will be able to: ● Identify key revisions to the 2014 NEC ● Identify new requirements for AFCI and GFCI ● Define and apply the lighting calculation to the NEC based on the energy code lighting controls ● Apply the revised NEC requirements for: ● 1000V systems compared to 600V ● Energy Management ● Arc Energy Reduction ● EV Supply Equipment as applied using an Energy Management system ● Identify new requires for new surge protection requirements on emergency panels
  • 3. Schneider Electric 3-– 2014 NEC Changes – 2013 2014 NEC Facts ● 3,745 Proposals ● 1,625 Comments ● 4 New Articles (393, 646, 728, 750) ● 19 Code Making Panels ● 473 Volunteer Code Making Panel Members ● NFPA Annual Meeting, June 2013 ● 2014 NEC Published, September 2013
  • 4. Schneider Electric 4-– 2014 NEC Changes – 2013 Article 750 Energy Management Systems •Article proposed by the “Smart Grid Task Group” appointed by the Technical Correlating Committee •Energy Management has become common place in today’s electrical infrastructure - control of utilization equipment, energy storage and power production •Restricting the control of the system by the energy management system becomes critical to ensure safety (Example: load shedding for an alternate power source for fire pumps and emergency systems)
  • 5. Schneider Electric 5-– 2014 NEC Changes – 2013 Increasing 600 V requirements to 1000 V ●High Voltage Task Group Appointed by the NEC Technical Correlating Committee ●Identified demand for increasing voltage levels in wind generation and photovoltaic systems as the basis for enhancing common voltage levels ●Chapters 1 – 8 reviewed ●Proposals were created in areas where the TG agreed the change resulted in minimal or no impact to the system installation ● Article 100 (Definitions) and Article 110 (Requirements for electrical installations retained the 600 V breakpoint
  • 6. Schneider Electric 6-– 2014 NEC Changes – 2013 110.26(C)(3) – Personnel Doors (3) Where there is equipment 800A or greater and there are doors that are within 25’ of the nearest edge of the working space – the door must have panic hardware and must open outward ●Rules for two working space entrances in 110.26(C)(2) are unchanged (equipment is 1200A or greater and the equipment is over 6 feet wide) Condition 1 Working Space Equipment 800A or greater Sheetrock wall Top Down View <=25’ Door must open outward and have panic hardware
  • 7. Schneider Electric 7-– 2014 NEC Changes – 2013 210.8(A) – GFCI (Dwellings) ●All 125-volt, single-phase, 15- and 20-ampere receptacles installed in the locations specified in 210.8(A)(1) through (10) shall have ground-fault circuit-interrupter protection for personnel. ●(10) Laundry Areas (10) - Laundry
  • 8. Schneider Electric 8-– 2014 NEC Changes – 2013 210.8(D) – GFCI (Dwellings) ●GFCI protection shall be provided for outlets that supply dishwashers Kitchen Dishwasher Branch Circuit
  • 9. Schneider Electric 9-– 2014 NEC Changes – 2013 210.12 - AFCI 120V, 15A and 20A branch circuits that supply outlets in dwelling unit: Kitchens, family rooms, dining rooms, living rooms, parlors, libraries, dens, bedrooms, sunrooms, recreation rooms, closets, hallways, laundry areas, or similar rooms (A) – Dwelling Units
  • 10. Schneider Electric 10-– 2014 NEC Changes – 2013 210.12 - AFCI 120V, 15A and 20A branch circuits that supply outlets in dormitory unit: Bedrooms, living rooms, hallways, closets, and similar rooms (C) – Dormitory Units
  • 11. Schneider Electric 11-– 2014 NEC Changes – 2013 210.12(A) – AFCI (Dwellings) 1. Combination type arc-fault circuit interrupter, installed to provide protection of the entire branch circuit 2. Branch/feeder type AFCI installed at the origin of the branch circuit in combination with an outlet branch circuit type arc-fault circuit interrupter installed at the first outlet box on the branch circuit. (outlet box must be marked to indicate that it is the first outlet of the circuit) Six Options now permitted for AFCI protection
  • 12. Schneider Electric 12-– 2014 NEC Changes – 2013 210.12(A) – AFCI (Dwellings) Six Options now permitted for AFCI protection (continued) 3.Supplemental arc protection circuit breaker installed at the origin of the branch circuit in combination with a listed outlet branch circuit type arc-fault circuit interrupter installed at the first outlet box on the branch circuit where all of the following conditions are met: (a) Continuous branch circuit wiring from the branch breakers to the outlet branch circuit AFCI (b) Maximum length of the branch circuit wiring to the first outlet must not exceed 50 ft for a 14 AWG or 70 ft for a 12 AWG (c) First outlet box in the branch circuit shall be identified
  • 13. Schneider Electric 13-– 2014 NEC Changes – 2013 210.12(A) – AFCI (Dwellings) Six Options now permitted for AFCI protection (continued) 4. Outlet branch circuit type arc-fault circuit interrupter installed at the first outlet box on the branch circuit in combination with a listed branch circuit overcurrent protective device where all of the following conditions are met: (a) Continuous branch circuit wiring from the branch circuit overcurrent protective device to the outlet branch circuit AFCI (b) The maximum length of the branch circuit wiring to the first outlet must not exceed 50 ft for a 14 AWG or 70 ft for a 12 AWG (c) The first outlet box in the branch circuit shall be identified (d) The combination of the branch circuit overcurrent device and outlet branch circuit AFCI is identified as meeting the requirements for a "System Combination" type AFCI and is listed as such.
  • 14. Schneider Electric 14-– 2014 NEC Changes – 2013 210.12(A) – AFCI (Dwellings) Six Options now permitted for AFCI protection (continued) 5. Outlet branch circuit type arc-fault circuit interrupter installed at the first outlet box on the branch circuit in combination with ... ● RMC, IMC, EMT, Type MC, or steel armored Type AC cables meeting the requirements of 250.118, ● Metal wireways, metal auxiliary gutters and metal outlet and junction boxes are installed for the portion of the branch circuit between the branch-circuit overcurrent device and the first outlet
  • 15. Schneider Electric 15-– 2014 NEC Changes – 2013 210.12(A) – AFCI (Dwellings) Six Options now permitted for AFCI protection (continued) 6. Outlet branch circuit type arc-fault circuit interrupter installed at the first outlet box on the branch circuit in combination with ... ● Listed metal or nonmetallic conduit or tubing or ● Type MC Cable and ● Encased in not less than 50mm (2 in.) of concrete for the portion of the branch circuit between the branch circuit overcurrent device and the first outlet Exceptions (1) and (2) removed. Exception (3) for fire alarm systems retained
  • 16. Schneider Electric 16-– 2014 NEC Changes – 2013 210.12(A) (5) & 210.12(A)(6) Install outlet branch circuit AFCI at the first outlet Provides protection for: Wiring from panel to first outlet must be installed in RMC, IMC, EMT, MC or steel jacketed AC cable. Must also have metal outlet and junction boxes. Also permits metallic and nonmetallic conduit or Tubing or MC cable where encased in 2” of concrete
  • 17. Schneider Electric 17-– 2014 NEC Changes – 2013 220.12 Exception – Lighting Loads for Specified Occupancies • New Exception allows lighting loads to calculated using the adopted energy code • Building must be designed and constructed to comply with the adopted energy code and meet the following: • Power monitoring system installed to provide lighting load data • Power monitoring system must have alarm(s) to alert the building owner/manager if the lighting load exceeds limits • Demand factors in 220.42 do not apply
  • 18. Schneider Electric 18-– 2014 NEC Changes – 2013 240.87 – Arc Energy Reduction • Required for circuit breakers rated 1200 A and above •Documentation on the circuit breaker location and •Reduced Clearing Time Method • Zone-selective interlocking or • Differential relaying or • Energy-reducing maintenance switching with local status indicator or • Energy-reducing active arc flash mitigation system or • An approved equivalent means
  • 19. Schneider Electric 19-– 2014 NEC Changes – 2013 310.15(B)(7) – 120/240 V, Single Phase, Services and Main Power Feeders (Dwellings) ●Table 310.15(B)(7) removed ●Service or Feeder ratings 100 through 400 A, an adjustment factor of 0.83 of the service or feeder ampere rating can be used to determine the size of the ungrounded conductors where supplying the entire load ●Grounded conductor can be smaller than the ungrounded conductors, see 215.2, 220.61, and 230.42 ●Other correction or adjustment factors applicable to the conductor installation apply ●New example added to Annex D
  • 20. Schneider Electric 20-– 2014 NEC Changes – 2013 406.9(B)(1) ●Expands the “extra duty” cover requirement to all wet location receptacle locations not just those supported from grade ●Similar revision to 590.4(D)(2)- clarifies the “extra duty” requirements apply to all wet location temporary installations, including dwellings
  • 21. Schneider Electric 21-– 2014 NEC Changes – 2013 Article 517 Healthcare Facilities ● Revisions align NEC requirements with NFPA 99 ● Clarify the use of the term “Emergency” and where the requirements of Article 700 apply ● Correlation of EES overcurrent device coordination requirements
  • 22. Schneider Electric 22-– 2014 NEC Changes – 2013 517.18(B) Patient Bed Location Receptacles ●This proposed change increases the minimum number of receptacles required from four to eight. ●Aligns with NFPA 99 relative to the increases in quantity of receptacles and normal care patient bed locations. 22
  • 23. Schneider Electric 23-– 2014 NEC Changes – 201323
  • 24. Schneider Electric 24-– 2014 NEC Changes – 2013 517.19(B) Patient Bed Location Receptacles – Critical Care ●Section 517.19 addresses critical care patient bed locations. This proposed revision in subdivision (B) changes the required minimum number of receptacles from six to fourteen. ●List item (2) in this section was revised by removing the term “emergency system” and replacing it with the term “critical branch.” ●Aligns with changes in NFPA 99-2012 24
  • 25. Schneider Electric 25-– 2014 NEC Changes – 201325
  • 26. Schneider Electric 26-– 2014 NEC Changes – 2013 517.19(C) Operating Room Receptacles ●The minimum number of receptacles required in an operating room is thirty-six of which at least twelve of the thirty-six receptacles must be connected to either the normal system branch or the critical system branch. ●The grounding terminal of these receptacles must be connected to the reference grounding point by means of an insulated copper equipment grounding conductor. 26
  • 27. Schneider Electric 27-– 2014 NEC Changes – 201327
  • 28. Schneider Electric 28-– 2014 NEC Changes – 2013 517.26 Application of Other Articles ● Revision clarifies the application of other code requirements with healthcare facilities ● Life safety branch of the EES must meet Article 700 requirements for emergency systems ● Aligns NEC requirements with NFPA 99
  • 29. Schneider Electric 29-– 2014 NEC Changes – 2013 Article 625 EV Supply Equipment EV Supply Equipment requirements throughout the article ●Electric Vehicle Supply Equipment System. A system of components that provide an ac output that is supplied to the vehicle for the purpose of providing input power to an on- board charger. ●625.14 Permits Energy Management system to establish calculated load ●625.17 Cords and Cables added to cover the Power Supply Cords and Output Cable to the Electric Vehicle ●625.44 Sets requirements for Cord and Plug Connected EV Supply Equipment
  • 30. Schneider Electric 30-– 2014 NEC Changes – 2013 690.17(A) Disconnect Type PV disconnecting means ... one of the following devices: (1) An industrial control switch marked for use in PV systems. (2) A molded case circuit breaker marked for use in PV systems (3) A molded case switch marked for use in PV systems. (4) An enclosed switch marked for use in PV systems. (5) An open-type switch marked for use in PV systems. (6) A dc-rated molded case circuit breaker suitable for backfeed operation. (7) A dc-rated, molded case switch suitable for backfeed operation. (8) A dc-rated enclosed switch. (9) A dc-rated open-type switch. (10) A dc rated low voltage power circuit breaker.
  • 31. Schneider Electric 31-– 2014 NEC Changes – 2013 700.8 – Surge Protection Emergency systems are required to have surge protection in or on all ●Switchboards and ●Panelboards
  • 32. Schneider Electric 32-– 2014 NEC Changes – 2013 700.16 – Emergency Illumination ● Emergency illumination required in the area of the disconnecting means required by 225.31 and 230.70, as applicable, where the disconnecting means are installed indoors. ● Exception provided where an alternative means is provided to ensure emergency lighting illumination is maintained.
  • 33. Schneider Electric 33-– 2014 NEC Changes – 2013 705.31 – Location of Overcurrent Protection Overcurrent protection for the source conductors, connected to the supply side of the service disconnecting means in accordance with 705.12(A), must be located within (10 ft) of the point where the electric power production source conductors are connected to the service. Interconnected Electric Power Production Sources Exception permits overcurrent protection more than 10 ft from the point of connection where cable limiters or current limited circuit breakers for each ungrounded conductor are installed at the connection point to the service.
  • 34. Schneider Electric 34-– 2014 NEC Changes – 2013 About the Instructor Alan Manche, P.E. ● Director, Industry Standards at Schneider Electric ● Member NEC Correlating Committee & NEC CMP 10 ● Past Member of NEC CMP 8 and CMP 20 ● Member of Technical Committee NFPA 110, 70B, and 73 ● Past Chair of NFPA 70B ● Board of Directors Western Section IAEI ● Education Chair –International Association of Electrical Inspectors (IAEI) ● Member, NEMA Codes and Standards ● Chair, NEMA Code Adoption Initiative ● Chair, NEMA Water and Fire Damaged Equipment Committee