National Electrical Code:
2014 Code Changes
A quick reference guide
For more information, visit
www.schneider-electric.com/us
TM
TM
©2014 Schneider Electric. All Rights Reserved.
	NEC 100 – Definitions................................................................................................................4-5
	NEC 110 — Requirements for Electrical Installations..................................................................... 6
	NEC 210 — Branch Circuits.....................................................................................................7-17
	NEC 250 — Grounding and Bonding.....................................................................................18-20
	NEC 310 — Conductors for General Wiring................................................................................ 21
	NEC 314 — Outlet, Device, Pull and Junction Boxes; Conduit Bodies; Fittings;
and Handhole Enclosures............................................................................................................ 22
	NEC 334 — NM Cable: Types NM, NMC, and NMS.................................................................... 23
Table of contents
TM
©2014 Schneider Electric. All Rights Reserved.
	NEC 386 — Surface Metal Raceway........................................................................................... 24
	NEC 400 — Flexible Cords and Cables....................................................................................... 25
	NEC 404 — Switches................................................................................................................. 26
	NEC 406 — Receptacles, Cord Connectors, and Attachment Plugs (Caps)................................ 27
	NEC 410 — Luminaires, Lampholders, and Lamps..................................................................... 28
	NEC 445 — Generators.........................................................................................................29-30
	NEC 625 — Electric Vehicle Charging System........................................................................31-33
	NEC 702 — Optional Standby Systems...................................................................................... 34
Table of contents (cont.)
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
4
Impact on engineers,
contractors, inspectors:
Revision of the definition for separately
derived systems adds clarity that the
determination of system type is based
on the connection of sources into
the system and not how loads are
connected. The revised definition also
recognizes that interconnection of the
sources through the grounding and
bonding of the system equipment
does not impact this determination of
system type.
An electrical source, other than a service, having no
direct connection(s) to circuit conductors of any other
electrical source other than those established by
grounding and bonding connections.
Section 100
Definition of Separately Derived System
NEC 100 — Definitions
Transfer Equipment
GEC GEC
SBJSBJ
LOAD
EGC
EGC
MBJ
NDL NDL
N
G
N
G
Feeder
Disconnect
(SUSE)
Feeder
Disconnect
(SUSE)
Phase PhasePhase Phase
G
Service
Disconnect
(SUSE)
Service
Disconnect
(SUSE)
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
5
Impact on engineers, contractors, inspectors:
The NEC requires many devices such as AFCIs and GFCIs
to be readily accessible. Providing this ability is usually
straight forward for protection located in the electrical
panel but other locations need to consider the room
use and layout. Any obstacles in front of these devices
renders the installation non-compliant such as a behind a
refrigerator or a washing machine where the GFCI cannot
be regularly tested in accordance with its instructions.
Capable of being
reached quickly for
operation, renewal, or
inspections. Installations
which require the use
of tools or present
obstacles to access are
not permitted.
Definition of Readily Accessible
Section 100
NEC 100 — Definitions
New
©2014 Schneider Electric. All Rights Reserved.
TM
6
Impact on engineers, contractors, inspectors:
Dedicated equipment space requirements were added
for outdoor installations where items such as gas
piping, water piping, mechanical refrigeration lines,
irrigation equipment, phone equipment, air lines, and
other non-electrical equipment often impede access
to the electrical equipment. Existing requirements
covered indoor installations and this revision
recognizes that outdoor installations also need space
to permit the installation of conduit and other electrical
equipment above the equipment.
•	Outdoor installations to meet dedicated
equipment space requirements
•	Space equal to width and depth of
equipment and extending from grade
to a height of 6 ft above the equipment
•	No equipment outside of the electrical
installation allowed in this space
Section 110.26(E)(2)(b)
Dedicated Equipment Space
NEC 110 — Requirements
for Electrical Installations
New
©2014 Schneider Electric. All Rights Reserved.
TM
7
Impact on engineers, contractors,
inspectors:
The NEC definition for a bathroom requires a
sink and one or more fixtures. Many interior
designs place the sink in an area separate
from the bathtub or shower. Without the area
having a sink near the shower or tub, the GFCI
protection requirement for receptacles near a
shower can be called into question as not being
a bathroom. Although most installers provide
GFCI protection, this code change will ensure
these areas have GFCI protection identical
to bathrooms.
•	125 V, single-phase, 15 and 20 A receptacles
within 6ft of a bathtub or shower stall must be
GFCI protected
•	Requirements cover installations where the
bathtub or shower location is not a bathroom
based on the definition in Article 100
GFCI (Dwellings) — Bathtubs and Shower Stalls
Section 210.8(A)(9)
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
8
Impact on engineers, contractors, inspectors:
GFCI requirements for dwellings have positively impacted
the incidents of electrical shocks in the home and the
expansion to laundry areas is a rational step to further
enhance this protection. The GFCI protection applies to
all 125 V, 15 and 20 A receptacles in the laundry area and
must be installed in a readily accessible location. Where
the laundry connections are not located in a “laundry
room,” a determination will need to be made as to which
receptacles serve the laundry area. The area may include
a closet, location in a basement or garage, or connected
adjacent to the kitchen.
All 125 V, single-
phase, 15 and
20 A receptacles
installed in the
locations specified
in 210.8(A)(1)
through (10),
including laundry
areas, shall have
ground-fault
circuit-interrupter
protection
for personnel.
Section 210.8(A)(10)
GFCI (Dwellings) – Laundry
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
9
Impact on engineers, contractors, inspectors:
Expansion of GFCI requirements to dishwashers installed
in dwelling kitchens provides needed safety enhancements
where product end of life failure can result in a shock
hazard. The revision applies to both cord and plug and
“hard wired” dishwasher installations. In order to protect
the outlet for the dishwasher, the GFCI must be installed
in a readily accessible location ahead of the receptacle
or outlet serving the dishwasher. Since kitchen branch
circuits are now required to be AFCI protected, this may be
accomplished with either an AFCI circuit breaker feeding
a GFCI ahead of the dishwasher outlet or a dual function
circuit breaker that includes both
AFCI and GFCI protection.
GFCI protection shall be provided for
outlets that supply dishwashers.
Note: This is not a GFCI receptacle requirement.
GFCI (Dwellings) – Kitchen Dishwasher Branch Circuit
NEC 210 — Branch Circuits
Section 210.8(D)
New
©2014 Schneider Electric. All Rights Reserved.
TM
10
Section NEC 210.12(A)
Impact on contractors, inspectors:
The inclusion of AFCI protection in the kitchen includes
the small appliance branch circuits, lighting and all
individual appliance circuits such as the garbage disposal,
dishwasher, microwave, refrigerator, and range hood.
AFCI protection in the laundry area may include the
washer circuit, lighting, or other outlets. The laundry area
may be a well-defined laundry room or an area where
laundry equipment is installed.
AFCI circuit breaker protection is compatible with GFCI
receptacle protection in these areas, or protection may
be provided by a dual function
AFCI/GFCI circuit breaker.
AFCI protection is
required for all 120 V,
15 and 20 A branch
circuits that supply
outlets or devices in
dwelling units. This
includes kitchens,
family rooms, living
rooms, parlors,
libraries, dens, bedrooms, sunrooms,
recreation rooms, closets, hallways,
laundry areas, or similar rooms.
AFCI — Dwelling Units
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
11
Section 210.12(A)
Impact on engineers,
contractors, inspectors:
Method 1 is the most common and
simplest choice for new construction.
Methods 3 and 4 are currently not
viable solutions at this time. Standard
thermal magnetic circuit breakers are not
acceptable for use in either method.
Methods 5 and 6 are used when the
installation utilizes a conduit system.
The 2014 NEC has introduced multiple methods to
provide AFCI protection:
1)	Combination type AFCI circuit breaker
2)	Branch/feeder type AFCI circuit breaker + outlet
branch-circuit type AFCI
3)	Supplemental arc protection circuit breaker + outlet
branch-circuit type AFCI with restrictions
4)	Circuit breaker + outlet branch-circuit type AFCI listed
as a “combination-type AFCI” with restrictions
5)	Home run in a steel wiring method + outlet branch-
circuit type AFCI installed in first outlet
6)	Home run encased in 2" of concrete + outlet branch-
circuit type AFCI installed in first outlet
AFCIs
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
12
Impact on engineers, contractors, inspectors:
Renovation or modification of existing wiring in dwellings
often includes replacing the electrical panel or extending
one or more branch circuits to accommodate equipment
or appliance replacement. This exception prohibits
additional outlets and sets limits on the extension length
in order to not trigger the AFCI protection required in this
section. New service panels are often larger than the
older ones that are being replaced so this provides the
permission necessary to extend existing circuits within the
panel to reach the new circuit breaker.
AFCI is not required where:
•	Extension does not exceed 6 ft
•	No additional outlets or devices
installed
Branch Circuit Extensions or Modifications — Dwelling Units
Section 210.12(B) Ex.
NEC 210 — Branch Circuits
Equipment
replacement
requiring extension
of the branch
circuit in an area
where the outlets
are required to be
AFCI protected.
New
©2014 Schneider Electric. All Rights Reserved.
TM
13
AFCI — Dormitory Units
AFCI protection is required for all
120 V, 15 and 20 A branch circuits
that supply outlets in dormitory unit
bedrooms, living rooms, hallways,
closets, and similar rooms.
Impact on engineers, contractors, inspectors:
The code panel has recognized that student dorms are a
living space similar to dwelling units and protecting those
living spaces from an electrical arc hazard is very similar to
a dwelling unit. A number of campuses across the country
have recognized the safety aspect and have included
arc fault protection as a standard specification for new
dormitory construction. Although this is a new requirement
in the 2014 NEC, arc-fault protection has been protecting
circuits in dorms for a number of years where college
campuses recognized the enhanced protection it provides.
Section 210.12(C)
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
14
Section 210.17
Impact on engineers, contractors, inspectors:
In recognition of the recent growth in electrical vehicle use,
the NEC addressed how this additional load should be
connected to the electrical system when electric vehicle
supply equipment is installed.
Electric vehicle supply equipment is considered a
continuous building load and a dedicated branch circuit is
needed to prevent circuit overload and nuisance tripping
of the supply overcurrent protective device.
Outlet(s) installed for the purpose of
charging electric vehicles shall be
supplied by a separate branch circuit.
This circuit shall have no other outlets.
Electric Vehicle Branch Circuit
NEC 210 — Branch Circuits
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
15
Impact on engineers, contractors, inspectors:
Installations intending to utilize a porch or deck receptacle
outlet to meet the outdoor receptacle requirements of this
section must ensure that the placement of the receptacle
permits ready access from grade and is within the specified
height limitation. A deck can preclude such accessibility
and drive the need for another outdoor receptacle outlet
beneath the deck accessible at grade level.
•	Outdoor receptacle outlets must be
readily accessible from grade level
•	Installed no higher than 6-1/2 ft
above grade level
•	At least one receptacle outlet at the
front and rear of dwelling
Outdoor Outlets (Dwellings)
Section 210.52(E)(1)/(E)(2)
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
16
•	A receptacle outlet is required to be
installed for each car space in an
attached or detached garage with
electric power
•	The branch circuit supplying the
receptacle(s) can only serve outlets
in the garage
Impact on engineers, contractors, inspectors:
The single garage receptacle permitted in existing
requirements creates a safety issue by fostering the
permanent use of extension cords where the receptacle
was not conveniently located or in multi-car garages where
distance to the receptacle was too far. The new requirements
address this concern by specifying the intended area the
receptacle serves and including one for each space.
The garage branch circuit must only serve garage outlets.
Flood lights and other luminaires mounted on the exterior
of the garage will need to be supplied from a separate
branch circuit.
Garages (one family dwellings)
Section 210.52(G)(1)
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
17
Impact on engineers, contractors, inspectors:
Aside from one- and two-family dwellings, the new
requirements for a receptacle outlet for maintenance and
servicing of electrical service areas apply to all service
equipment regardless of the application.
Small services for signs, community irrigation, and 240 V
loads are examples where this requirement will impact the
installation to supply the required 125 V receptacle.
•	New section requires at least one
125 V, single-phase, 15 or 20 A
rated receptacle outlet within
15 m (50 ft) of the electrical
service equipment
•	Exception for one- and two-
family dwellings
Section 210.64
Electrical Service Areas
NEC 210 — Branch Circuits
New
©2014 Schneider Electric. All Rights Reserved.
TM
18
Impact on engineers, contractors,
inspectors:
Grounding electrode conductors and
grounding electrode bonding jumpers are
required to be installed with protection where
exposed to physical damage. This revision
clarifies that the portions of these conductors
which are direct buried are considered
protected and the burial depth requirements
normally associated with underground wiring
do not apply.
•	Table 300.5 sets the minimum cover requirements
•	Grounding electrode conductors and bonding
jumpers do not have to meet the burial depth
requirements for direct-buried conductors
Grounding Electrode Installation — Securing and
Protection Against Physical Damage
Section 250.64(B)NEC 250 — Grounding
and Bonding
Grounding electrode
conductor
Bonding jumper
New
©2014 Schneider Electric. All Rights Reserved.
TM
19
Impact on engineers, contractors,
inspectors:
The connection to a concrete-encased
electrode can be disruptive to the normal
construction schedule since concrete
is usually installed early in the building
process. The allowance to use an extension
provides a convenient method of connection
and inspection during the normal electrical
installation and verification phases
of construction.
•	Allows extension of
the electrode to area
above the concrete
•	Must be accessible
to allow for
inspection of the
connection
•	Applies to conductor,
reinforcing rod, and
bar types
Grounding Electrode Connections — Concrete-encased
Electrode Extension
Section 250.68(C)(3)NEC 250 — Grounding
and Bonding
New
©2014 Schneider Electric. All Rights Reserved.
TM
20
•	Allows extension
of a grounding
electrode
conductor
from another
branch circuit
•	Branch circuits
must originate
in the same
panelboard
Impact on engineers,
contractors, inspectors:
Replacing non-grounding receptacles
or extending a branch circuit without an
equipment grounding conductor (EGC)
can be a challenge in many existing
installations. This allowance provides
relief from installing a separate EGC from
the panelboard while addressing the
safety aspects of the installation.
Equipment Grounding Connections — Non-grounding
Receptacle Replacement or Branch Circuit Extensions
Section 250.130(C)(4)NEC 250 — Grounding
and Bonding
Extension
from another
branch circuit
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
21
Section 310.15(B)(7)
Impact on engineers,
contractors, inspectors:
The existing service conductor size
table has been replaced with an 0.83
adjustment factor which results in
the same base conductor size as
the original table value. Conductor
correction or adjustment factors may
now apply to the installation.
•	Table 310.15(B)(7) removed
•	Service or Feeder ratings
100 A through 400 A, an
adjustment factor of 0.83
of the service or feeder
ampere rating can be used
to determine the size of the
ungrounded conductors where supplying the entire load
•	Other correction or adjustment factors applicable
to the conductor installation apply
120/240 V, Single-phase, Services and Main Power
Feeders (Dwellings)
NEC 310 — Conductors for
General Wiring
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
22
•	Standard ceiling
outlet boxes
for luminaire or
lampholder use
must support 50 lbs
•	Luminaires
exceeding 50 lbs
and supported from
the ceiling box must
use a box which is
marked with the
maximum weight
allowed
Impact on engineers,
contractors, inspectors:
Large luminaires can exceed the
rated weight support of standard
ceiling outlet boxes. Many
installations utilize independent
support for such luminaires, but this
code revision recognizes that special
boxes marked with the support rating
are suitable for this application.
Boxes at Luminaire or Lampholder Outlets — Ceiling Outlets
Section 314.27(A)(2)
NEC 314 — Outlet, Device, Pull and
Junction Boxes; Conduit Bodies;
Fittings; and Handhole Enclosures
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
23
Impact on engineers, contractors, inspectors:
Modifying or repairing an existing wiring installation
can be a difficult installation and code compliance
challenge. The devices added to this section provide a
permanent installation method for exposed and concealed
modifications to the wiring system. The listing requirement
ensures evaluation for the intended use and safety aspects
of installing without a box.
•	Removes the
requirement for a box
when installing self-
contained switches,
self-contained
receptacles, or NM
interconnectors
•	Applies to exposed
cable wiring and
concealed repair wiring
•	Devices must be listed
Devices of Insulating Material
Section 334.40(B)NEC 334 — NM Cable:
Types NM, NMC, and NMS
New
©2014 Schneider Electric. All Rights Reserved.
TM
24
Impact on engineers,
contractors, inspectors:
Surface raceways must be installed as
a complete system with the appropriate
components as intended by the product
manufacturer. The marking requirement
added in this section will assist in verifying
that the system is installed as intended.
•	New marking requirement for each length of raceway
•	Manufacturer’s name or unique identification
•	Similar revision for non-metallic surface raceways
in 388.120
Surface Metal Raceway Marking
Section 386.120NEC 386 — Surface
Metal Raceway
New
©2014 Schneider Electric. All Rights Reserved.
TM
25
Impact on engineers, contractors,
inspectors:
Flexible cords and cables are not permitted to
be concealed or as a substitute for the fixed
wiring of a structure. This presents a challenge
when wall mounting a television, monitor, or
device where the existing wiring system did not
place a receptacle in the desired location. In
utilizing a listed assembly, this revision provides
a compliant method for addressing common
applications where the use of flexible cords and
cables is desired.
•	Permits flexible cord connection between a
receptacle outlet and an inlet
•	Inlet is permanently wired using a standard
wiring method to a single receptacle outlet
•	Wall mounting of flat screen televisions or
monitors is a common application
Section 400.7(A)(11)
Flexible Cords and Cables
NEC 400 — Flexible Cords
and Cables
Photo courtesy of
DataComm Electronics
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
26
A grounded circuit conductor must be provided at the
switch location unless one of the follow apply:
•	Raceway sized to
accommodate a
grounded conductor
•	Box enclosing the switch
is accessible without
removing finish materials
•	Snap switches with
integral enclosures
•	Switch does not serve a habitable room or bathroom
•	Multiple switch locations control the same lighting load and
the entire floor area is visible from one or more switches
•	Area lighting is automatically controlled
•	Switch controls a receptacle load
Impact on engineers,
contractors, inspectors:
The requirement to provide a
grounded circuit conductor at each
switch location has been revised to
provide needed relief. Where multiple
switches are installed in the same
area, the addition of a grounded
conductor is no longer required at
all locations. Permission to install the
grounded conductor at a future date
is allowed where access is available to
the switch.
Switches Controlling Lighting Loads
Section 404.2(C)
NEC 404 — Switches
Habitable Room
Lighting outlet
Power source
Visible from most areas and
all room entry points
Grounded
circuit
conductor
Provided
Not
required
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
27
Impact on engineers,
contractors, inspectors:
Revisions to this section recognize the
added safety benefit for “extra duty”
covers for wet location receptacles.
Extra duty covers provide enhanced
mechanical strength and “in-use”
protection for outdoor and other wet
location receptacles.
•	Expands the “extra duty” cover
requirement to all wet location
receptacle locations, not just
those supported from grade
•	Similar revision to 590.4(D)(2) –
clarifies the “extra duty”
requirements apply to all wet
location temporary installations,
including dwellings
Section 406.9(B)(1)
15 and 20 A Receptacles in a Wet Location
NEC406—Receptacles,Cord
Connectors, and Attachment
Plugs (Caps)
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
28
Impact on engineers,
contractors, inspectors:
Improving the energy efficiency
of installed lighting systems can
be a challenge when the existing
luminaires require field conversion to
support the efficiency upgrade. Listed
retrofit kits ensure that the safety
aspects of the conversion have been
considered and are in compliance
with the product safety standard.
•	Expands the listing requirements to retrofit kits for
lampholders and luminaires
•	Retrofit kit definition added to Article 100 which provides
clarity and distinguishes retrofit kits from re-lamping
activities (no field conversion of the utilization equipment)
Luminaires, Lampholders, and Lamps — Listing Required
Section 410.6NEC 410 — Luminaires,
Lampholders, and Lamps
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
29
Section 445.11
Impact on contractors, inspectors:
Generators will now include a marking indicating if it is
bonded. If the generator is not bonded, markings such as
“floating” or “ungrounded” may be included. This marking
is important when generators are used in home standby
applications and must be coordinated with the system
transfer equipment.
Marking
NEC 445 — Generators
Revision requires marking when the
neutral of a generator is bonded to
the generator frame.
New
©2014 Schneider Electric. All Rights Reserved.
TM
30
GFCI Protection for Receptacles on
Portable Generators (< 15 kW)
Section 445.20
NEC 445 — Generators
Impact on engineers, contractors,
inspectors:
Portable generator installations which utilize
a 125/250 V locking-type receptacle in home
back-up applications will be impacted by
this change. Such use requires connection
as a separately derived system and transfer
equipment which switches the neutral unless
the generator configuration prevents use of
the 125 V, 15 and 20 A receptacle outlets.
•	All 125 V, single-phase,
15 and 20 A receptacle
outlets shall..…
»» Have GFCI integral to the
generator or receptacle or
»» Be arranged so that these
receptacles are not be available for use when
the 125/250 V locking receptacle is in use
•	Generators without a 125/250 V locking-type
receptacle are exempt
•	Listed cord sets or devices incorporating listed
GFCI protection are permitted for installations of
generators manufactured or re-manufactured prior
to January 1, 2015
New
©2014 Schneider Electric. All Rights Reserved.
TM
31
Impact on engineers, contractors,
inspectors:
EV supply equipment installations must
comply with the appropriate ratings to
demonstrate suitability for the environment
where it is located, intended use and
access, and exposure to physical
damage. The EV charging station branch
circuit breaker and wire must also be sized
at 125 percent of its rated load, unless an
energy management feature is associated
with the EV charging infrastructure.
A system of components that provides an AC output
that is supplied to the vehicle for the purpose of
providing input power to an on-board charger.
•	625.17 cords and cables added to
cover the power supply cords and
output cable to the EV
•	625.41 permits an energy
management system to establish
calculated load
•	625.44 sets requirements for
cord and plug connected EV
supply equipment
Electric Vehicle (EV) Supply Equipment System
Section 625NEC 625 — Electric Vehicle
Charging System
New
©2014 Schneider Electric. All Rights Reserved.
TM
32
•	Supplied from 125 V
receptacle outlets
where rated 15 or
20 A, non-locking,
2-pole, 3-wire,
grounding type
or
•	Supplied at less
than 50 V DC
Impact on engineers, contractors,
inspectors:
Cord and plug connection requirements
of EV supply equipment are divided into
separate sections based on the rated
voltage of the supply. The 125 V receptacle
outlets must be non-locking to provide
physical protection should the vehicle move
while connected. Section 210.17 requires a
dedicated branch circuit for outlets intended
for this use.
Electric Vehicle (EV) Supply Equipment Connections to
125 V, Single-phase, 15 A, and 20 A Receptable Outlets
Section 625.44(A)NEC 625 — Electric Vehicle
Charging System
New
©2014 Schneider Electric. All Rights Reserved.
TM
33
Impact on engineers, contractors,
inspectors:
EVSE rated 250 V or greater must be fastened
in place and located based on the rated
environmental conditions. The supply cord to the
EVSE presents a challenge in ensuring physical
damage exposure does not create a hazard. This
is especially difficult when the EVSE is intended
for public use. The installer may consider using a
hard-wired connection for the EVSE to eliminate
any concerns with damage to the supply cord of
the EVSE.
Receptacle outlets must comply with all of
the following:
•	Rated 250 V maximum
•	50 A or less
•	Non-locking, 2-pole, 3-wire, and
3-pole, 4-wire, grounding type
•	EVSE fastened in place
•	Supply cord limited to 6 ft length
•	Located to avoid physical
damage to the supply cord
All other EVSE (over 250 V) must be
permanently wired and fastened in place
Electric Vehicle Supply Equipment (EVSE) — Connections
to Other Receptacle Outlets
Section 625.44(B)NEC 625 — Electric Vehicle
Charging System
Revision
TM
©2014 Schneider Electric. All Rights Reserved.
34
Impact on engineers,
contractors, inspectors:
Small portable generators used
in optional standby systems are
frequently connected using cord- and
plug-type connections. This revision
allows this connection to serve
as the building disconnect for the
generator supply. The cord and plug
and associated flanged inlet must be
rated for the conditions of use and
outdoor installation location.
structure disconnect
•	Power inlet installations
must include the 702.7(C)
sign requirements
indicating if the system
is separately derived or
non-separately derived
•	Flanged inlet or other cord- and plug-type connections
of small portable generators can serve as the building or
Outdoor Generator Sets — Portable Generators (< 15 kW)
Section 702.12(B)NEC 702 — Optional
Standby Systems

More Related Content

What's hot

Mechanical engineering tools
Mechanical engineering toolsMechanical engineering tools
Mechanical engineering toolsAlma Soriano
 
Electrical safety ppt
Electrical safety pptElectrical safety ppt
Electrical safety pptEr Ramgarhia
 
Y2 module1-preparing of construction materials& tools
Y2 module1-preparing of construction materials& toolsY2 module1-preparing of construction materials& tools
Y2 module1-preparing of construction materials& toolsMacky Mac Faller
 
World day for safety and health at work
World day for safety and health at workWorld day for safety and health at work
World day for safety and health at workAhmed-Refat Refat
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Gensol Engineering Limited
 
Industrial inspection sample report
Industrial inspection sample reportIndustrial inspection sample report
Industrial inspection sample reportpropertyinspectir
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety Reliance
 
ISO 45001 Employee Awareness Training
ISO 45001 Employee Awareness TrainingISO 45001 Employee Awareness Training
ISO 45001 Employee Awareness TrainingDr Madhu Aman Sharma
 
Refrigeration and Air Conditioning Services
Refrigeration and Air Conditioning ServicesRefrigeration and Air Conditioning Services
Refrigeration and Air Conditioning Serviceslalaineole0321
 
COMPUTER HARDWARE TOOLS IN CHS AND CSS
COMPUTER HARDWARE TOOLS IN CHS AND CSSCOMPUTER HARDWARE TOOLS IN CHS AND CSS
COMPUTER HARDWARE TOOLS IN CHS AND CSSBelindaLapidCamullo
 
Electrical safety & protection
Electrical safety & protectionElectrical safety & protection
Electrical safety & protectionSyed Lateef
 
86548526 installation-for-generator-set
86548526 installation-for-generator-set86548526 installation-for-generator-set
86548526 installation-for-generator-setArmando Aguilar
 
Fr4 best practices-in-low-voltage-systems
Fr4 best practices-in-low-voltage-systemsFr4 best practices-in-low-voltage-systems
Fr4 best practices-in-low-voltage-systemsRayan Darine
 
Electrical safety slideshare
Electrical safety slideshareElectrical safety slideshare
Electrical safety slideshareYokeshDhanabal
 
Electrical maintenance-1
Electrical maintenance-1Electrical maintenance-1
Electrical maintenance-1Vijay Raskar
 
Personal Protective Equipment(PPE)
Personal Protective Equipment(PPE)Personal Protective Equipment(PPE)
Personal Protective Equipment(PPE)AsmaraAslam1
 

What's hot (20)

Butterfly valve
Butterfly valveButterfly valve
Butterfly valve
 
Mechanical engineering tools
Mechanical engineering toolsMechanical engineering tools
Mechanical engineering tools
 
Electrical safety ppt
Electrical safety pptElectrical safety ppt
Electrical safety ppt
 
Maintenance strategies
Maintenance strategiesMaintenance strategies
Maintenance strategies
 
Y2 module1-preparing of construction materials& tools
Y2 module1-preparing of construction materials& toolsY2 module1-preparing of construction materials& tools
Y2 module1-preparing of construction materials& tools
 
Electrical Safety by OSHA
Electrical Safety by OSHAElectrical Safety by OSHA
Electrical Safety by OSHA
 
World day for safety and health at work
World day for safety and health at workWorld day for safety and health at work
World day for safety and health at work
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
 
Industrial inspection sample report
Industrial inspection sample reportIndustrial inspection sample report
Industrial inspection sample report
 
Electrical Safety
Electrical  Safety Electrical  Safety
Electrical Safety
 
ISO 45001 Employee Awareness Training
ISO 45001 Employee Awareness TrainingISO 45001 Employee Awareness Training
ISO 45001 Employee Awareness Training
 
Refrigeration and Air Conditioning Services
Refrigeration and Air Conditioning ServicesRefrigeration and Air Conditioning Services
Refrigeration and Air Conditioning Services
 
COMPUTER HARDWARE TOOLS IN CHS AND CSS
COMPUTER HARDWARE TOOLS IN CHS AND CSSCOMPUTER HARDWARE TOOLS IN CHS AND CSS
COMPUTER HARDWARE TOOLS IN CHS AND CSS
 
Electrical safety & protection
Electrical safety & protectionElectrical safety & protection
Electrical safety & protection
 
86548526 installation-for-generator-set
86548526 installation-for-generator-set86548526 installation-for-generator-set
86548526 installation-for-generator-set
 
Fr4 best practices-in-low-voltage-systems
Fr4 best practices-in-low-voltage-systemsFr4 best practices-in-low-voltage-systems
Fr4 best practices-in-low-voltage-systems
 
Electrical safety slideshare
Electrical safety slideshareElectrical safety slideshare
Electrical safety slideshare
 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
 
Electrical maintenance-1
Electrical maintenance-1Electrical maintenance-1
Electrical maintenance-1
 
Personal Protective Equipment(PPE)
Personal Protective Equipment(PPE)Personal Protective Equipment(PPE)
Personal Protective Equipment(PPE)
 

Viewers also liked

Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10Don Joven
 
Policy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementationPolicy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementationMaria Theresa
 
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...Schneider Electric
 
Materials, tools, equipment and testing devices
Materials, tools, equipment and testing devicesMaterials, tools, equipment and testing devices
Materials, tools, equipment and testing devicesBrian Mary
 
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10Bogs De Castro
 
K-12 Module in TLE - ICT Grade 10 [All Gradings]
K-12 Module in TLE - ICT  Grade 10 [All Gradings]K-12 Module in TLE - ICT  Grade 10 [All Gradings]
K-12 Module in TLE - ICT Grade 10 [All Gradings]Daniel Manaog
 
Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0Bogs De Castro
 

Viewers also liked (9)

Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10Electrical Installation and Maintenance for grades_7 to 10
Electrical Installation and Maintenance for grades_7 to 10
 
Policy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementationPolicy guidelines on the k to 12 implementation
Policy guidelines on the k to 12 implementation
 
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
2014 National Electrical Code: Top 10 Revisions Impacting Electrical Installa...
 
Materials, tools, equipment and testing devices
Materials, tools, equipment and testing devicesMaterials, tools, equipment and testing devices
Materials, tools, equipment and testing devices
 
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
DepEd TLE Computer Hardware Servicing Curriculum Guide Grade 7-10
 
K-12 Module in TLE - ICT Grade 10 [All Gradings]
K-12 Module in TLE - ICT  Grade 10 [All Gradings]K-12 Module in TLE - ICT  Grade 10 [All Gradings]
K-12 Module in TLE - ICT Grade 10 [All Gradings]
 
K to 12 PC Hardware Servicing Learning Module
K to 12 PC Hardware Servicing Learning ModuleK to 12 PC Hardware Servicing Learning Module
K to 12 PC Hardware Servicing Learning Module
 
K to 12 Electrical Learning Module
K to 12 Electrical Learning ModuleK to 12 Electrical Learning Module
K to 12 Electrical Learning Module
 
Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0Computer Hardware Servicing Learning Module v.2.0
Computer Hardware Servicing Learning Module v.2.0
 

Similar to National Electrical Code 2014 Changes Quick Reference

PT-9018-ConnProvGenSets-en
PT-9018-ConnProvGenSets-enPT-9018-ConnProvGenSets-en
PT-9018-ConnProvGenSets-enMunir Kaderbhai
 
Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014Claude Colp
 
DATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LVDATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LVgrupopridesolar
 
New Approaches for Maintenance Grounding in Medium Voltage Switchgear
New Approaches for Maintenance Grounding in Medium Voltage SwitchgearNew Approaches for Maintenance Grounding in Medium Voltage Switchgear
New Approaches for Maintenance Grounding in Medium Voltage SwitchgearSchneider Electric
 
Ricardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMIRicardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMIFrank Warnes
 
Catalog cs switch disconnectors_dienhathe.vn
Catalog cs switch disconnectors_dienhathe.vnCatalog cs switch disconnectors_dienhathe.vn
Catalog cs switch disconnectors_dienhathe.vnDien Ha The
 
WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914Ryan Bolduc, PE
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Living Online
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Living Online
 
EATON-2020-NEC-code-changes-presentation
EATON-2020-NEC-code-changes-presentationEATON-2020-NEC-code-changes-presentation
EATON-2020-NEC-code-changes-presentationsnbg2
 
CS243I1410B1_low.pdf
CS243I1410B1_low.pdfCS243I1410B1_low.pdf
CS243I1410B1_low.pdfNelsonYucra7
 
Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...
Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...
Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...Dien Ha The
 
Delta vfd c200-m_en_20120601
Delta vfd c200-m_en_20120601Delta vfd c200-m_en_20120601
Delta vfd c200-m_en_20120601Toàn Huỳnh
 
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC GridsNeil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC GridsEnergyTech2015
 
Level 3 ais-manual-12kv
Level 3 ais-manual-12kvLevel 3 ais-manual-12kv
Level 3 ais-manual-12kvHamZer
 
Fs10 11 100nim En
Fs10 11 100nim EnFs10 11 100nim En
Fs10 11 100nim Enguest8e065b
 
Giuliano david catalogo seco gear_17-5kv
Giuliano david catalogo seco gear_17-5kvGiuliano david catalogo seco gear_17-5kv
Giuliano david catalogo seco gear_17-5kvgiuliano45
 

Similar to National Electrical Code 2014 Changes Quick Reference (20)

PT-9018-ConnProvGenSets-en
PT-9018-ConnProvGenSets-enPT-9018-ConnProvGenSets-en
PT-9018-ConnProvGenSets-en
 
Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014Rapid shutdown arc fault presentation SPI 2014
Rapid shutdown arc fault presentation SPI 2014
 
DATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LVDATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LV
 
New Approaches for Maintenance Grounding in Medium Voltage Switchgear
New Approaches for Maintenance Grounding in Medium Voltage SwitchgearNew Approaches for Maintenance Grounding in Medium Voltage Switchgear
New Approaches for Maintenance Grounding in Medium Voltage Switchgear
 
Ricardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMIRicardo DC-DC Converter Presentation for NMI
Ricardo DC-DC Converter Presentation for NMI
 
Catalog cs switch disconnectors_dienhathe.vn
Catalog cs switch disconnectors_dienhathe.vnCatalog cs switch disconnectors_dienhathe.vn
Catalog cs switch disconnectors_dienhathe.vn
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914WM Siemens IEC 61850 Flyer 081914
WM Siemens IEC 61850 Flyer 081914
 
Thông số kĩ thuật siemens miniature circuit breakers
Thông số kĩ thuật siemens miniature circuit breakersThông số kĩ thuật siemens miniature circuit breakers
Thông số kĩ thuật siemens miniature circuit breakers
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...
 
Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...Installing, Programming & Commissioning of Power System Protection Relays and...
Installing, Programming & Commissioning of Power System Protection Relays and...
 
EATON-2020-NEC-code-changes-presentation
EATON-2020-NEC-code-changes-presentationEATON-2020-NEC-code-changes-presentation
EATON-2020-NEC-code-changes-presentation
 
CS243I1410B1_low.pdf
CS243I1410B1_low.pdfCS243I1410B1_low.pdf
CS243I1410B1_low.pdf
 
Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...
Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...
Ls catalog thiet bi dien solution power v mv switchgear_catalog_e_0901_dienha...
 
Delta vfd c200-m_en_20120601
Delta vfd c200-m_en_20120601Delta vfd c200-m_en_20120601
Delta vfd c200-m_en_20120601
 
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC GridsNeil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
Neil Kirby: VSC HVDC Transmission and Emerging Technologies in DC Grids
 
Level 3 ais-manual-12kv
Level 3 ais-manual-12kvLevel 3 ais-manual-12kv
Level 3 ais-manual-12kv
 
Fs10 11 100nim En
Fs10 11 100nim EnFs10 11 100nim En
Fs10 11 100nim En
 
Schneider GenieEvo MV Modular Switchboard (13.8kV)
Schneider GenieEvo MV Modular Switchboard (13.8kV)Schneider GenieEvo MV Modular Switchboard (13.8kV)
Schneider GenieEvo MV Modular Switchboard (13.8kV)
 
Giuliano david catalogo seco gear_17-5kv
Giuliano david catalogo seco gear_17-5kvGiuliano david catalogo seco gear_17-5kv
Giuliano david catalogo seco gear_17-5kv
 

More from Schneider Electric

Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design ConsiderationsSchneider Electric
 
Digital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsDigital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsSchneider Electric
 
32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing 32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing Schneider Electric
 
Key Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsKey Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsSchneider Electric
 
EcoStruxure™ for Cloud & Service Providers
 EcoStruxure™ for Cloud & Service Providers EcoStruxure™ for Cloud & Service Providers
EcoStruxure™ for Cloud & Service ProvidersSchneider Electric
 
Zelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingZelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingSchneider Electric
 
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSpacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSchneider Electric
 
Relay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingRelay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingSchneider Electric
 
Magelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingMagelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingSchneider Electric
 
Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Schneider Electric
 
EcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesEcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesSchneider Electric
 
Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Schneider Electric
 
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.Schneider Electric
 
It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580Schneider Electric
 
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...Schneider Electric
 
Connected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTConnected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTSchneider Electric
 
Telemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingTelemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingSchneider Electric
 
Telemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingTelemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingSchneider Electric
 
Telemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingTelemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingSchneider Electric
 

More from Schneider Electric (20)

Secure Power Design Considerations
Secure Power Design ConsiderationsSecure Power Design Considerations
Secure Power Design Considerations
 
Digital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting InvestorsDigital International Colo Club: Attracting Investors
Digital International Colo Club: Attracting Investors
 
32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing 32 phaseo power supplies and transformers briefing
32 phaseo power supplies and transformers briefing
 
Key Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation TrendsKey Industry Trends, M&A Valuation Trends
Key Industry Trends, M&A Valuation Trends
 
EcoStruxure™ for Cloud & Service Providers
 EcoStruxure™ for Cloud & Service Providers EcoStruxure™ for Cloud & Service Providers
EcoStruxure™ for Cloud & Service Providers
 
Magelis Basic HMI Briefing
Magelis Basic HMI Briefing Magelis Basic HMI Briefing
Magelis Basic HMI Briefing
 
Zelio Time Electronic Relay Briefing
Zelio Time Electronic Relay BriefingZelio Time Electronic Relay Briefing
Zelio Time Electronic Relay Briefing
 
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures BriefingSpacial, Thalassa, ClimaSys Universal enclosures Briefing
Spacial, Thalassa, ClimaSys Universal enclosures Briefing
 
Relay Control Zelio SSR Briefing
Relay Control Zelio SSR BriefingRelay Control Zelio SSR Briefing
Relay Control Zelio SSR Briefing
 
Magelis HMI, iPC and software Briefing
Magelis HMI, iPC and software BriefingMagelis HMI, iPC and software Briefing
Magelis HMI, iPC and software Briefing
 
Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?Where will the next 80% improvement in data center performance come from?
Where will the next 80% improvement in data center performance come from?
 
EcoStruxure for Intuitive Industries
EcoStruxure for Intuitive IndustriesEcoStruxure for Intuitive Industries
EcoStruxure for Intuitive Industries
 
Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017Systems Integrator Alliance Program 2017
Systems Integrator Alliance Program 2017
 
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
EcoStruxure, IIoT-enabled architecture, delivering value in key segments.
 
It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580It's time to modernize your industrial controls with Modicon M580
It's time to modernize your industrial controls with Modicon M580
 
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
A Practical Guide to Ensuring Business Continuity and High Performance in Hea...
 
Connected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoTConnected Services Study – Facility Managers Respond to IoT
Connected Services Study – Facility Managers Respond to IoT
 
Telemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories BriefingTelemecanqiue Cabling and Accessories Briefing
Telemecanqiue Cabling and Accessories Briefing
 
Telemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors BriefingTelemecanique Photoelectric Sensors Briefing
Telemecanique Photoelectric Sensors Briefing
 
Telemecanique Limit Switches Briefing
Telemecanique Limit Switches BriefingTelemecanique Limit Switches Briefing
Telemecanique Limit Switches Briefing
 

Recently uploaded

Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesKari Kakkonen
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024TopCSSGallery
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesBernd Ruecker
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterMydbops
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Kaya Weers
 
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS:  6 Ways to Automate Your Data IntegrationBridging Between CAD & GIS:  6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integrationmarketing932765
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructureitnewsafrica
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxfnnc6jmgwh
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...Karmanjay Verma
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...itnewsafrica
 

Recently uploaded (20)

Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examples
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architectures
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL Router
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)Design pattern talk by Kaya Weers - 2024 (v2)
Design pattern talk by Kaya Weers - 2024 (v2)
 
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS:  6 Ways to Automate Your Data IntegrationBridging Between CAD & GIS:  6 Ways to Automate Your Data Integration
Bridging Between CAD & GIS: 6 Ways to Automate Your Data Integration
 
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical InfrastructureVarsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
Varsha Sewlal- Cyber Attacks on Critical Critical Infrastructure
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...React JS; all concepts. Contains React Features, JSX, functional & Class comp...
React JS; all concepts. Contains React Features, JSX, functional & Class comp...
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
 

National Electrical Code 2014 Changes Quick Reference

  • 1. National Electrical Code: 2014 Code Changes A quick reference guide For more information, visit www.schneider-electric.com/us TM
  • 2. TM ©2014 Schneider Electric. All Rights Reserved. NEC 100 – Definitions................................................................................................................4-5 NEC 110 — Requirements for Electrical Installations..................................................................... 6 NEC 210 — Branch Circuits.....................................................................................................7-17 NEC 250 — Grounding and Bonding.....................................................................................18-20 NEC 310 — Conductors for General Wiring................................................................................ 21 NEC 314 — Outlet, Device, Pull and Junction Boxes; Conduit Bodies; Fittings; and Handhole Enclosures............................................................................................................ 22 NEC 334 — NM Cable: Types NM, NMC, and NMS.................................................................... 23 Table of contents
  • 3. TM ©2014 Schneider Electric. All Rights Reserved. NEC 386 — Surface Metal Raceway........................................................................................... 24 NEC 400 — Flexible Cords and Cables....................................................................................... 25 NEC 404 — Switches................................................................................................................. 26 NEC 406 — Receptacles, Cord Connectors, and Attachment Plugs (Caps)................................ 27 NEC 410 — Luminaires, Lampholders, and Lamps..................................................................... 28 NEC 445 — Generators.........................................................................................................29-30 NEC 625 — Electric Vehicle Charging System........................................................................31-33 NEC 702 — Optional Standby Systems...................................................................................... 34 Table of contents (cont.)
  • 4. Revision TM ©2014 Schneider Electric. All Rights Reserved. 4 Impact on engineers, contractors, inspectors: Revision of the definition for separately derived systems adds clarity that the determination of system type is based on the connection of sources into the system and not how loads are connected. The revised definition also recognizes that interconnection of the sources through the grounding and bonding of the system equipment does not impact this determination of system type. An electrical source, other than a service, having no direct connection(s) to circuit conductors of any other electrical source other than those established by grounding and bonding connections. Section 100 Definition of Separately Derived System NEC 100 — Definitions Transfer Equipment GEC GEC SBJSBJ LOAD EGC EGC MBJ NDL NDL N G N G Feeder Disconnect (SUSE) Feeder Disconnect (SUSE) Phase PhasePhase Phase G Service Disconnect (SUSE) Service Disconnect (SUSE)
  • 5. Revision TM ©2014 Schneider Electric. All Rights Reserved. 5 Impact on engineers, contractors, inspectors: The NEC requires many devices such as AFCIs and GFCIs to be readily accessible. Providing this ability is usually straight forward for protection located in the electrical panel but other locations need to consider the room use and layout. Any obstacles in front of these devices renders the installation non-compliant such as a behind a refrigerator or a washing machine where the GFCI cannot be regularly tested in accordance with its instructions. Capable of being reached quickly for operation, renewal, or inspections. Installations which require the use of tools or present obstacles to access are not permitted. Definition of Readily Accessible Section 100 NEC 100 — Definitions
  • 6. New ©2014 Schneider Electric. All Rights Reserved. TM 6 Impact on engineers, contractors, inspectors: Dedicated equipment space requirements were added for outdoor installations where items such as gas piping, water piping, mechanical refrigeration lines, irrigation equipment, phone equipment, air lines, and other non-electrical equipment often impede access to the electrical equipment. Existing requirements covered indoor installations and this revision recognizes that outdoor installations also need space to permit the installation of conduit and other electrical equipment above the equipment. • Outdoor installations to meet dedicated equipment space requirements • Space equal to width and depth of equipment and extending from grade to a height of 6 ft above the equipment • No equipment outside of the electrical installation allowed in this space Section 110.26(E)(2)(b) Dedicated Equipment Space NEC 110 — Requirements for Electrical Installations
  • 7. New ©2014 Schneider Electric. All Rights Reserved. TM 7 Impact on engineers, contractors, inspectors: The NEC definition for a bathroom requires a sink and one or more fixtures. Many interior designs place the sink in an area separate from the bathtub or shower. Without the area having a sink near the shower or tub, the GFCI protection requirement for receptacles near a shower can be called into question as not being a bathroom. Although most installers provide GFCI protection, this code change will ensure these areas have GFCI protection identical to bathrooms. • 125 V, single-phase, 15 and 20 A receptacles within 6ft of a bathtub or shower stall must be GFCI protected • Requirements cover installations where the bathtub or shower location is not a bathroom based on the definition in Article 100 GFCI (Dwellings) — Bathtubs and Shower Stalls Section 210.8(A)(9) NEC 210 — Branch Circuits
  • 8. New ©2014 Schneider Electric. All Rights Reserved. TM 8 Impact on engineers, contractors, inspectors: GFCI requirements for dwellings have positively impacted the incidents of electrical shocks in the home and the expansion to laundry areas is a rational step to further enhance this protection. The GFCI protection applies to all 125 V, 15 and 20 A receptacles in the laundry area and must be installed in a readily accessible location. Where the laundry connections are not located in a “laundry room,” a determination will need to be made as to which receptacles serve the laundry area. The area may include a closet, location in a basement or garage, or connected adjacent to the kitchen. All 125 V, single- phase, 15 and 20 A receptacles installed in the locations specified in 210.8(A)(1) through (10), including laundry areas, shall have ground-fault circuit-interrupter protection for personnel. Section 210.8(A)(10) GFCI (Dwellings) – Laundry NEC 210 — Branch Circuits
  • 9. New ©2014 Schneider Electric. All Rights Reserved. TM 9 Impact on engineers, contractors, inspectors: Expansion of GFCI requirements to dishwashers installed in dwelling kitchens provides needed safety enhancements where product end of life failure can result in a shock hazard. The revision applies to both cord and plug and “hard wired” dishwasher installations. In order to protect the outlet for the dishwasher, the GFCI must be installed in a readily accessible location ahead of the receptacle or outlet serving the dishwasher. Since kitchen branch circuits are now required to be AFCI protected, this may be accomplished with either an AFCI circuit breaker feeding a GFCI ahead of the dishwasher outlet or a dual function circuit breaker that includes both AFCI and GFCI protection. GFCI protection shall be provided for outlets that supply dishwashers. Note: This is not a GFCI receptacle requirement. GFCI (Dwellings) – Kitchen Dishwasher Branch Circuit NEC 210 — Branch Circuits Section 210.8(D)
  • 10. New ©2014 Schneider Electric. All Rights Reserved. TM 10 Section NEC 210.12(A) Impact on contractors, inspectors: The inclusion of AFCI protection in the kitchen includes the small appliance branch circuits, lighting and all individual appliance circuits such as the garbage disposal, dishwasher, microwave, refrigerator, and range hood. AFCI protection in the laundry area may include the washer circuit, lighting, or other outlets. The laundry area may be a well-defined laundry room or an area where laundry equipment is installed. AFCI circuit breaker protection is compatible with GFCI receptacle protection in these areas, or protection may be provided by a dual function AFCI/GFCI circuit breaker. AFCI protection is required for all 120 V, 15 and 20 A branch circuits that supply outlets or devices in dwelling units. This includes kitchens, family rooms, living rooms, parlors, libraries, dens, bedrooms, sunrooms, recreation rooms, closets, hallways, laundry areas, or similar rooms. AFCI — Dwelling Units NEC 210 — Branch Circuits
  • 11. New ©2014 Schneider Electric. All Rights Reserved. TM 11 Section 210.12(A) Impact on engineers, contractors, inspectors: Method 1 is the most common and simplest choice for new construction. Methods 3 and 4 are currently not viable solutions at this time. Standard thermal magnetic circuit breakers are not acceptable for use in either method. Methods 5 and 6 are used when the installation utilizes a conduit system. The 2014 NEC has introduced multiple methods to provide AFCI protection: 1) Combination type AFCI circuit breaker 2) Branch/feeder type AFCI circuit breaker + outlet branch-circuit type AFCI 3) Supplemental arc protection circuit breaker + outlet branch-circuit type AFCI with restrictions 4) Circuit breaker + outlet branch-circuit type AFCI listed as a “combination-type AFCI” with restrictions 5) Home run in a steel wiring method + outlet branch- circuit type AFCI installed in first outlet 6) Home run encased in 2" of concrete + outlet branch- circuit type AFCI installed in first outlet AFCIs NEC 210 — Branch Circuits
  • 12. New ©2014 Schneider Electric. All Rights Reserved. TM 12 Impact on engineers, contractors, inspectors: Renovation or modification of existing wiring in dwellings often includes replacing the electrical panel or extending one or more branch circuits to accommodate equipment or appliance replacement. This exception prohibits additional outlets and sets limits on the extension length in order to not trigger the AFCI protection required in this section. New service panels are often larger than the older ones that are being replaced so this provides the permission necessary to extend existing circuits within the panel to reach the new circuit breaker. AFCI is not required where: • Extension does not exceed 6 ft • No additional outlets or devices installed Branch Circuit Extensions or Modifications — Dwelling Units Section 210.12(B) Ex. NEC 210 — Branch Circuits Equipment replacement requiring extension of the branch circuit in an area where the outlets are required to be AFCI protected.
  • 13. New ©2014 Schneider Electric. All Rights Reserved. TM 13 AFCI — Dormitory Units AFCI protection is required for all 120 V, 15 and 20 A branch circuits that supply outlets in dormitory unit bedrooms, living rooms, hallways, closets, and similar rooms. Impact on engineers, contractors, inspectors: The code panel has recognized that student dorms are a living space similar to dwelling units and protecting those living spaces from an electrical arc hazard is very similar to a dwelling unit. A number of campuses across the country have recognized the safety aspect and have included arc fault protection as a standard specification for new dormitory construction. Although this is a new requirement in the 2014 NEC, arc-fault protection has been protecting circuits in dorms for a number of years where college campuses recognized the enhanced protection it provides. Section 210.12(C) NEC 210 — Branch Circuits
  • 14. New ©2014 Schneider Electric. All Rights Reserved. TM 14 Section 210.17 Impact on engineers, contractors, inspectors: In recognition of the recent growth in electrical vehicle use, the NEC addressed how this additional load should be connected to the electrical system when electric vehicle supply equipment is installed. Electric vehicle supply equipment is considered a continuous building load and a dedicated branch circuit is needed to prevent circuit overload and nuisance tripping of the supply overcurrent protective device. Outlet(s) installed for the purpose of charging electric vehicles shall be supplied by a separate branch circuit. This circuit shall have no other outlets. Electric Vehicle Branch Circuit NEC 210 — Branch Circuits
  • 15. Revision TM ©2014 Schneider Electric. All Rights Reserved. 15 Impact on engineers, contractors, inspectors: Installations intending to utilize a porch or deck receptacle outlet to meet the outdoor receptacle requirements of this section must ensure that the placement of the receptacle permits ready access from grade and is within the specified height limitation. A deck can preclude such accessibility and drive the need for another outdoor receptacle outlet beneath the deck accessible at grade level. • Outdoor receptacle outlets must be readily accessible from grade level • Installed no higher than 6-1/2 ft above grade level • At least one receptacle outlet at the front and rear of dwelling Outdoor Outlets (Dwellings) Section 210.52(E)(1)/(E)(2) NEC 210 — Branch Circuits
  • 16. New ©2014 Schneider Electric. All Rights Reserved. TM 16 • A receptacle outlet is required to be installed for each car space in an attached or detached garage with electric power • The branch circuit supplying the receptacle(s) can only serve outlets in the garage Impact on engineers, contractors, inspectors: The single garage receptacle permitted in existing requirements creates a safety issue by fostering the permanent use of extension cords where the receptacle was not conveniently located or in multi-car garages where distance to the receptacle was too far. The new requirements address this concern by specifying the intended area the receptacle serves and including one for each space. The garage branch circuit must only serve garage outlets. Flood lights and other luminaires mounted on the exterior of the garage will need to be supplied from a separate branch circuit. Garages (one family dwellings) Section 210.52(G)(1) NEC 210 — Branch Circuits
  • 17. New ©2014 Schneider Electric. All Rights Reserved. TM 17 Impact on engineers, contractors, inspectors: Aside from one- and two-family dwellings, the new requirements for a receptacle outlet for maintenance and servicing of electrical service areas apply to all service equipment regardless of the application. Small services for signs, community irrigation, and 240 V loads are examples where this requirement will impact the installation to supply the required 125 V receptacle. • New section requires at least one 125 V, single-phase, 15 or 20 A rated receptacle outlet within 15 m (50 ft) of the electrical service equipment • Exception for one- and two- family dwellings Section 210.64 Electrical Service Areas NEC 210 — Branch Circuits
  • 18. New ©2014 Schneider Electric. All Rights Reserved. TM 18 Impact on engineers, contractors, inspectors: Grounding electrode conductors and grounding electrode bonding jumpers are required to be installed with protection where exposed to physical damage. This revision clarifies that the portions of these conductors which are direct buried are considered protected and the burial depth requirements normally associated with underground wiring do not apply. • Table 300.5 sets the minimum cover requirements • Grounding electrode conductors and bonding jumpers do not have to meet the burial depth requirements for direct-buried conductors Grounding Electrode Installation — Securing and Protection Against Physical Damage Section 250.64(B)NEC 250 — Grounding and Bonding Grounding electrode conductor Bonding jumper
  • 19. New ©2014 Schneider Electric. All Rights Reserved. TM 19 Impact on engineers, contractors, inspectors: The connection to a concrete-encased electrode can be disruptive to the normal construction schedule since concrete is usually installed early in the building process. The allowance to use an extension provides a convenient method of connection and inspection during the normal electrical installation and verification phases of construction. • Allows extension of the electrode to area above the concrete • Must be accessible to allow for inspection of the connection • Applies to conductor, reinforcing rod, and bar types Grounding Electrode Connections — Concrete-encased Electrode Extension Section 250.68(C)(3)NEC 250 — Grounding and Bonding
  • 20. New ©2014 Schneider Electric. All Rights Reserved. TM 20 • Allows extension of a grounding electrode conductor from another branch circuit • Branch circuits must originate in the same panelboard Impact on engineers, contractors, inspectors: Replacing non-grounding receptacles or extending a branch circuit without an equipment grounding conductor (EGC) can be a challenge in many existing installations. This allowance provides relief from installing a separate EGC from the panelboard while addressing the safety aspects of the installation. Equipment Grounding Connections — Non-grounding Receptacle Replacement or Branch Circuit Extensions Section 250.130(C)(4)NEC 250 — Grounding and Bonding Extension from another branch circuit
  • 21. Revision TM ©2014 Schneider Electric. All Rights Reserved. 21 Section 310.15(B)(7) Impact on engineers, contractors, inspectors: The existing service conductor size table has been replaced with an 0.83 adjustment factor which results in the same base conductor size as the original table value. Conductor correction or adjustment factors may now apply to the installation. • Table 310.15(B)(7) removed • Service or Feeder ratings 100 A through 400 A, an adjustment factor of 0.83 of the service or feeder ampere rating can be used to determine the size of the ungrounded conductors where supplying the entire load • Other correction or adjustment factors applicable to the conductor installation apply 120/240 V, Single-phase, Services and Main Power Feeders (Dwellings) NEC 310 — Conductors for General Wiring
  • 22. Revision TM ©2014 Schneider Electric. All Rights Reserved. 22 • Standard ceiling outlet boxes for luminaire or lampholder use must support 50 lbs • Luminaires exceeding 50 lbs and supported from the ceiling box must use a box which is marked with the maximum weight allowed Impact on engineers, contractors, inspectors: Large luminaires can exceed the rated weight support of standard ceiling outlet boxes. Many installations utilize independent support for such luminaires, but this code revision recognizes that special boxes marked with the support rating are suitable for this application. Boxes at Luminaire or Lampholder Outlets — Ceiling Outlets Section 314.27(A)(2) NEC 314 — Outlet, Device, Pull and Junction Boxes; Conduit Bodies; Fittings; and Handhole Enclosures
  • 23. Revision TM ©2014 Schneider Electric. All Rights Reserved. 23 Impact on engineers, contractors, inspectors: Modifying or repairing an existing wiring installation can be a difficult installation and code compliance challenge. The devices added to this section provide a permanent installation method for exposed and concealed modifications to the wiring system. The listing requirement ensures evaluation for the intended use and safety aspects of installing without a box. • Removes the requirement for a box when installing self- contained switches, self-contained receptacles, or NM interconnectors • Applies to exposed cable wiring and concealed repair wiring • Devices must be listed Devices of Insulating Material Section 334.40(B)NEC 334 — NM Cable: Types NM, NMC, and NMS
  • 24. New ©2014 Schneider Electric. All Rights Reserved. TM 24 Impact on engineers, contractors, inspectors: Surface raceways must be installed as a complete system with the appropriate components as intended by the product manufacturer. The marking requirement added in this section will assist in verifying that the system is installed as intended. • New marking requirement for each length of raceway • Manufacturer’s name or unique identification • Similar revision for non-metallic surface raceways in 388.120 Surface Metal Raceway Marking Section 386.120NEC 386 — Surface Metal Raceway
  • 25. New ©2014 Schneider Electric. All Rights Reserved. TM 25 Impact on engineers, contractors, inspectors: Flexible cords and cables are not permitted to be concealed or as a substitute for the fixed wiring of a structure. This presents a challenge when wall mounting a television, monitor, or device where the existing wiring system did not place a receptacle in the desired location. In utilizing a listed assembly, this revision provides a compliant method for addressing common applications where the use of flexible cords and cables is desired. • Permits flexible cord connection between a receptacle outlet and an inlet • Inlet is permanently wired using a standard wiring method to a single receptacle outlet • Wall mounting of flat screen televisions or monitors is a common application Section 400.7(A)(11) Flexible Cords and Cables NEC 400 — Flexible Cords and Cables Photo courtesy of DataComm Electronics
  • 26. Revision TM ©2014 Schneider Electric. All Rights Reserved. 26 A grounded circuit conductor must be provided at the switch location unless one of the follow apply: • Raceway sized to accommodate a grounded conductor • Box enclosing the switch is accessible without removing finish materials • Snap switches with integral enclosures • Switch does not serve a habitable room or bathroom • Multiple switch locations control the same lighting load and the entire floor area is visible from one or more switches • Area lighting is automatically controlled • Switch controls a receptacle load Impact on engineers, contractors, inspectors: The requirement to provide a grounded circuit conductor at each switch location has been revised to provide needed relief. Where multiple switches are installed in the same area, the addition of a grounded conductor is no longer required at all locations. Permission to install the grounded conductor at a future date is allowed where access is available to the switch. Switches Controlling Lighting Loads Section 404.2(C) NEC 404 — Switches Habitable Room Lighting outlet Power source Visible from most areas and all room entry points Grounded circuit conductor Provided Not required
  • 27. Revision TM ©2014 Schneider Electric. All Rights Reserved. 27 Impact on engineers, contractors, inspectors: Revisions to this section recognize the added safety benefit for “extra duty” covers for wet location receptacles. Extra duty covers provide enhanced mechanical strength and “in-use” protection for outdoor and other wet location receptacles. • Expands the “extra duty” cover requirement to all wet location receptacle locations, not just those supported from grade • Similar revision to 590.4(D)(2) – clarifies the “extra duty” requirements apply to all wet location temporary installations, including dwellings Section 406.9(B)(1) 15 and 20 A Receptacles in a Wet Location NEC406—Receptacles,Cord Connectors, and Attachment Plugs (Caps)
  • 28. Revision TM ©2014 Schneider Electric. All Rights Reserved. 28 Impact on engineers, contractors, inspectors: Improving the energy efficiency of installed lighting systems can be a challenge when the existing luminaires require field conversion to support the efficiency upgrade. Listed retrofit kits ensure that the safety aspects of the conversion have been considered and are in compliance with the product safety standard. • Expands the listing requirements to retrofit kits for lampholders and luminaires • Retrofit kit definition added to Article 100 which provides clarity and distinguishes retrofit kits from re-lamping activities (no field conversion of the utilization equipment) Luminaires, Lampholders, and Lamps — Listing Required Section 410.6NEC 410 — Luminaires, Lampholders, and Lamps
  • 29. Revision TM ©2014 Schneider Electric. All Rights Reserved. 29 Section 445.11 Impact on contractors, inspectors: Generators will now include a marking indicating if it is bonded. If the generator is not bonded, markings such as “floating” or “ungrounded” may be included. This marking is important when generators are used in home standby applications and must be coordinated with the system transfer equipment. Marking NEC 445 — Generators Revision requires marking when the neutral of a generator is bonded to the generator frame.
  • 30. New ©2014 Schneider Electric. All Rights Reserved. TM 30 GFCI Protection for Receptacles on Portable Generators (< 15 kW) Section 445.20 NEC 445 — Generators Impact on engineers, contractors, inspectors: Portable generator installations which utilize a 125/250 V locking-type receptacle in home back-up applications will be impacted by this change. Such use requires connection as a separately derived system and transfer equipment which switches the neutral unless the generator configuration prevents use of the 125 V, 15 and 20 A receptacle outlets. • All 125 V, single-phase, 15 and 20 A receptacle outlets shall..… »» Have GFCI integral to the generator or receptacle or »» Be arranged so that these receptacles are not be available for use when the 125/250 V locking receptacle is in use • Generators without a 125/250 V locking-type receptacle are exempt • Listed cord sets or devices incorporating listed GFCI protection are permitted for installations of generators manufactured or re-manufactured prior to January 1, 2015
  • 31. New ©2014 Schneider Electric. All Rights Reserved. TM 31 Impact on engineers, contractors, inspectors: EV supply equipment installations must comply with the appropriate ratings to demonstrate suitability for the environment where it is located, intended use and access, and exposure to physical damage. The EV charging station branch circuit breaker and wire must also be sized at 125 percent of its rated load, unless an energy management feature is associated with the EV charging infrastructure. A system of components that provides an AC output that is supplied to the vehicle for the purpose of providing input power to an on-board charger. • 625.17 cords and cables added to cover the power supply cords and output cable to the EV • 625.41 permits an energy management system to establish calculated load • 625.44 sets requirements for cord and plug connected EV supply equipment Electric Vehicle (EV) Supply Equipment System Section 625NEC 625 — Electric Vehicle Charging System
  • 32. New ©2014 Schneider Electric. All Rights Reserved. TM 32 • Supplied from 125 V receptacle outlets where rated 15 or 20 A, non-locking, 2-pole, 3-wire, grounding type or • Supplied at less than 50 V DC Impact on engineers, contractors, inspectors: Cord and plug connection requirements of EV supply equipment are divided into separate sections based on the rated voltage of the supply. The 125 V receptacle outlets must be non-locking to provide physical protection should the vehicle move while connected. Section 210.17 requires a dedicated branch circuit for outlets intended for this use. Electric Vehicle (EV) Supply Equipment Connections to 125 V, Single-phase, 15 A, and 20 A Receptable Outlets Section 625.44(A)NEC 625 — Electric Vehicle Charging System
  • 33. New ©2014 Schneider Electric. All Rights Reserved. TM 33 Impact on engineers, contractors, inspectors: EVSE rated 250 V or greater must be fastened in place and located based on the rated environmental conditions. The supply cord to the EVSE presents a challenge in ensuring physical damage exposure does not create a hazard. This is especially difficult when the EVSE is intended for public use. The installer may consider using a hard-wired connection for the EVSE to eliminate any concerns with damage to the supply cord of the EVSE. Receptacle outlets must comply with all of the following: • Rated 250 V maximum • 50 A or less • Non-locking, 2-pole, 3-wire, and 3-pole, 4-wire, grounding type • EVSE fastened in place • Supply cord limited to 6 ft length • Located to avoid physical damage to the supply cord All other EVSE (over 250 V) must be permanently wired and fastened in place Electric Vehicle Supply Equipment (EVSE) — Connections to Other Receptacle Outlets Section 625.44(B)NEC 625 — Electric Vehicle Charging System
  • 34. Revision TM ©2014 Schneider Electric. All Rights Reserved. 34 Impact on engineers, contractors, inspectors: Small portable generators used in optional standby systems are frequently connected using cord- and plug-type connections. This revision allows this connection to serve as the building disconnect for the generator supply. The cord and plug and associated flanged inlet must be rated for the conditions of use and outdoor installation location. structure disconnect • Power inlet installations must include the 702.7(C) sign requirements indicating if the system is separately derived or non-separately derived • Flanged inlet or other cord- and plug-type connections of small portable generators can serve as the building or Outdoor Generator Sets — Portable Generators (< 15 kW) Section 702.12(B)NEC 702 — Optional Standby Systems