Cocomo model
Software engineering
organic, semidetached,
and embedded systems
Boehm’s [1981] definition of organic,
semidetached, and embedded systems are
elaborated below
• Organic:
A development project can be considered of organic
type, if the project deals with developing a well
understood application program, the size of the
development team is reasonably small, and the
team members are experienced in developing
similar types of projects.
Semidetached
• A development project can be considered of
semidetached type, if the development
consists of a mixture of experienced and
inexperienced staff.
• Team members may have limited experience
on related systems but may be unfamiliar with
some aspects of the system being developed.
Embedded
• A development project is considered to be of
embedded type, if the software being
developed is strongly coupled to complex
hardware, or if the stringent regulations on
the operational procedures exist
COCOMO
• COCOMO (Constructive Cost Estimation
Model) was proposed by Boehm [1981].
According to Boehm, software cost estimation
should be done through three stages: Basic
COCOMO, Intermediate COCOMO, and
Complete COCOMO.
Basic COCOMO Model
• The basic COCOMO model gives an
approximate estimate of the project
parameters. The basic COCOMO estimation
model is given by the following expressions:
• Effort = a1 х (KLOC)a2 PM
• Tdev = b1 x (Effort)b2 Months
Continued..
Where
• KLOC is the estimated size of the software product
expressed in Kilo Lines of Code,
• a1, a2, b1, b2 are constants for each category of software
products,
• Tdev is the estimated time to develop the software,
expressed in months,
• Effort is the total effort required to develop the software
product, expressed in person months (PMs).
Continued..
• The effort estimation is expressed in units of
person-months (PM). It is the area under the
person-month plot (as shown in fig.).
• It should be carefully noted that an effort of
100 PM does not imply that 100 persons
should work for 1 month nor does it imply
that 1 person should be employed for 100
months, but it denotes the area under the
person-month curve.
Continued..
Estimation of
development effort
• For the three classes of software products,
the formulas for estimating the effort based
on the code size are shown below:
• Organic : Effort = 2.4(KLOC)1.05 PM
• Semi-detached : Effort = 3.0(KLOC)1.12 PM
• Embedded : Effort = 3.6(KLOC)1.20 PM
Estimation of
development time
• For the three classes of software products,
the formulas for estimating the development
time based on the effort are given below:
• Organic : Tdev = 2.5(Effort)0.38 Months
• Semi-detached : Tdev = 2.5(Effort)0.35 Months
• Embedded : Tdev = 2.5(Effort)0.32 Months
Example
• Assume that the size of an organic type
software product has been estimated to be
32,000 lines of source code. Assume that the
average salary of software engineers be Rs.
15,000/- per month. Determine the effort
required to develop the software product and
the nominal development time.
Solution
• From the basic COCOMO estimation formula
for organic software:
• Effort = 2.4 х (32)1.05 = 91 PM
• Nominal development time = 2.5 х (91)0.38 =
14 months
• Cost required to develop the product = 14 х
15,000
• = Rs. 210,000/-
ITFT -  Cocomo model

More Related Content

What's hot

Cocomo model (muskan soni)
Cocomo model (muskan soni)Cocomo model (muskan soni)
Cocomo model (muskan soni)MuskanSony
 
Software estimation models ii lec .05
Software estimation models ii lec .05Software estimation models ii lec .05
Software estimation models ii lec .05Noor Ul Hudda Memon
 
COCOMO Model in software project management
COCOMO Model in software project managementCOCOMO Model in software project management
COCOMO Model in software project managementSyed Hassan Ali
 
COCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of ProjectCOCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of ProjectNavjyotsinh Jadeja
 
software project management Cocomo model
software project management Cocomo modelsoftware project management Cocomo model
software project management Cocomo modelREHMAT ULLAH
 
Software Estimation Part I
Software Estimation Part ISoftware Estimation Part I
Software Estimation Part Isslovepk
 
New microsoft office power point presentation
New microsoft office power point presentationNew microsoft office power point presentation
New microsoft office power point presentationMiha Tisca
 
Software estimation
Software estimationSoftware estimation
Software estimationMd Shakir
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelPrakash Poudel
 
Software Estimation Techniques
Software Estimation TechniquesSoftware Estimation Techniques
Software Estimation Techniqueskamal
 

What's hot (20)

Cocomo model (muskan soni)
Cocomo model (muskan soni)Cocomo model (muskan soni)
Cocomo model (muskan soni)
 
Cocomo models
Cocomo modelsCocomo models
Cocomo models
 
Software estimation models ii lec .05
Software estimation models ii lec .05Software estimation models ii lec .05
Software estimation models ii lec .05
 
COCOMO Model in software project management
COCOMO Model in software project managementCOCOMO Model in software project management
COCOMO Model in software project management
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
COCOMO MODEL 1 And 2
COCOMO MODEL 1 And 2COCOMO MODEL 1 And 2
COCOMO MODEL 1 And 2
 
Cocom ii
Cocom iiCocom ii
Cocom ii
 
COCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of ProjectCOCOMO model | How to calculate effort, staffing and Duration of Project
COCOMO model | How to calculate effort, staffing and Duration of Project
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Cocomo
CocomoCocomo
Cocomo
 
software project management Cocomo model
software project management Cocomo modelsoftware project management Cocomo model
software project management Cocomo model
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Software Estimation Part I
Software Estimation Part ISoftware Estimation Part I
Software Estimation Part I
 
COCOMO MODEL
COCOMO MODELCOCOMO MODEL
COCOMO MODEL
 
New microsoft office power point presentation
New microsoft office power point presentationNew microsoft office power point presentation
New microsoft office power point presentation
 
COCOMO model
COCOMO modelCOCOMO model
COCOMO model
 
Software estimation
Software estimationSoftware estimation
Software estimation
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Cocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity modelCocomo ( cot constrictive model) and capability maturity model
Cocomo ( cot constrictive model) and capability maturity model
 
Software Estimation Techniques
Software Estimation TechniquesSoftware Estimation Techniques
Software Estimation Techniques
 

Viewers also liked

Chapter 4 software project planning
Chapter 4 software project planningChapter 4 software project planning
Chapter 4 software project planningPiyush Gogia
 
TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?Emerson Schenatto
 
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MGOtimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MGSamyr Abdo
 
Information technology
Information technologyInformation technology
Information technologyHaitham Farouk
 
Cocomo
CocomoCocomo
Cocomogmjuan
 
Estimativa de Esforço
Estimativa de EsforçoEstimativa de Esforço
Estimativa de Esforçoelliando dias
 
COCOMO E COCOMO II
COCOMO E COCOMO IICOCOMO E COCOMO II
COCOMO E COCOMO IIIsraelCunha
 
Eng.Software-Métricas
Eng.Software-MétricasEng.Software-Métricas
Eng.Software-Métricaselliando dias
 
Medida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de FunçãoMedida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de FunçãoÁlvaro Farias Pinheiro
 
Estimativa de software usando pontos de função
Estimativa de software usando pontos de funçãoEstimativa de software usando pontos de função
Estimativa de software usando pontos de funçãoClaudio Martins
 
Cocomo II
Cocomo IICocomo II
Cocomo IIActimel
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9Ian Sommerville
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimationHaitham Ahmed
 

Viewers also liked (19)

Chapter 4 software project planning
Chapter 4 software project planningChapter 4 software project planning
Chapter 4 software project planning
 
USC COCOMO II
USC COCOMO IIUSC COCOMO II
USC COCOMO II
 
TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?TDC 2015 Porto Alegre - Preciso estimar mesmo?
TDC 2015 Porto Alegre - Preciso estimar mesmo?
 
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MGOtimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
Otimização do Desempenho de Times Ágeis - UaiJUG techdays - Uberlândia - MG
 
Fi ti- aula 10
Fi ti- aula 10Fi ti- aula 10
Fi ti- aula 10
 
COCOMO II
COCOMO IICOCOMO II
COCOMO II
 
Information technology
Information technologyInformation technology
Information technology
 
Cocomo
CocomoCocomo
Cocomo
 
Estimativa de Esforço
Estimativa de EsforçoEstimativa de Esforço
Estimativa de Esforço
 
COCOMO E COCOMO II
COCOMO E COCOMO IICOCOMO E COCOMO II
COCOMO E COCOMO II
 
Eng.Software-Métricas
Eng.Software-MétricasEng.Software-Métricas
Eng.Software-Métricas
 
Medida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de FunçãoMedida de Esforço de Software com Análise de Ponto de Função
Medida de Esforço de Software com Análise de Ponto de Função
 
Estimativas em projetos de software
Estimativas em projetos de softwareEstimativas em projetos de software
Estimativas em projetos de software
 
Fundamentos APF
Fundamentos APFFundamentos APF
Fundamentos APF
 
Estimativa de software usando pontos de função
Estimativa de software usando pontos de funçãoEstimativa de software usando pontos de função
Estimativa de software usando pontos de função
 
Cocomo II
Cocomo IICocomo II
Cocomo II
 
Ch23-Software Engineering 9
Ch23-Software Engineering 9Ch23-Software Engineering 9
Ch23-Software Engineering 9
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 

Similar to ITFT - Cocomo model

Exp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptxExp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptxYagnaGummadi
 
Putnam Resource allocation model.ppt
Putnam Resource allocation model.pptPutnam Resource allocation model.ppt
Putnam Resource allocation model.pptAnupamaSharma80
 
Effort estimation( software Engineering)
Effort estimation( software Engineering)Effort estimation( software Engineering)
Effort estimation( software Engineering)kiran Patel
 
cocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdfcocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdfssuser2d043c
 
Software engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomoSoftware engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomoVaibhav Khanna
 
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsSe 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsbabak danyal
 
COCOMO methods for software size estimation
COCOMO methods for software size estimationCOCOMO methods for software size estimation
COCOMO methods for software size estimationPramod Parajuli
 
COCOMO 1 Model ppt AR-1.pdf
COCOMO 1 Model  ppt AR-1.pdfCOCOMO 1 Model  ppt AR-1.pdf
COCOMO 1 Model ppt AR-1.pdf23017156038
 
COCOMO Model.pptx
COCOMO Model.pptxCOCOMO Model.pptx
COCOMO Model.pptxsuchi70
 
software project management
software project managementsoftware project management
software project managementJassir4
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICSneha Padhiar
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICSneha Padhiar
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptx3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptxAbhishekKumar66407
 

Similar to ITFT - Cocomo model (20)

5. COCOMO.pdf
5. COCOMO.pdf5. COCOMO.pdf
5. COCOMO.pdf
 
Exp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptxExp 02-COCOMO (1).pptx
Exp 02-COCOMO (1).pptx
 
Putnam Resource allocation model.ppt
Putnam Resource allocation model.pptPutnam Resource allocation model.ppt
Putnam Resource allocation model.ppt
 
Effort estimation( software Engineering)
Effort estimation( software Engineering)Effort estimation( software Engineering)
Effort estimation( software Engineering)
 
cocomo.pptx
cocomo.pptxcocomo.pptx
cocomo.pptx
 
COCOMO (Software Engineering)
COCOMO (Software Engineering)COCOMO (Software Engineering)
COCOMO (Software Engineering)
 
cocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdfcocomo-220726173706-141e0dsdsd8f0 (1).pdf
cocomo-220726173706-141e0dsdsd8f0 (1).pdf
 
Software engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomoSoftware engineering 10 software cost estimation cocomo
Software engineering 10 software cost estimation cocomo
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
Cocomomodel
CocomomodelCocomomodel
Cocomomodel
 
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation modelsSe 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
Se 381 - lec 25 - 32 - 12 may29 - program size and cost estimation models
 
COCOMO methods for software size estimation
COCOMO methods for software size estimationCOCOMO methods for software size estimation
COCOMO methods for software size estimation
 
COCOMO 1 Model ppt AR-1.pdf
COCOMO 1 Model  ppt AR-1.pdfCOCOMO 1 Model  ppt AR-1.pdf
COCOMO 1 Model ppt AR-1.pdf
 
COCOMO Model.pptx
COCOMO Model.pptxCOCOMO Model.pptx
COCOMO Model.pptx
 
software project management
software project managementsoftware project management
software project management
 
LECT9.ppt
LECT9.pptLECT9.ppt
LECT9.ppt
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
 
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERICCOCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
COCOMO FP COST ESTIMATION TECHNIQUES:NUMERIC
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptx3. Lect 29_ 30_ 32 Project Planning.pptx
3. Lect 29_ 30_ 32 Project Planning.pptx
 

More from Shruti Kunwar

ITFT - Software prototyping
ITFT -  Software prototypingITFT -  Software prototyping
ITFT - Software prototypingShruti Kunwar
 
ITFT - Software development life cycle
ITFT  -   Software development life cycleITFT  -   Software development life cycle
ITFT - Software development life cycleShruti Kunwar
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planningShruti Kunwar
 
ITFT - Henderson clark model
ITFT  -  Henderson clark modelITFT  -  Henderson clark model
ITFT - Henderson clark modelShruti Kunwar
 
ITFT - Fourth generation techniques
ITFT  -  Fourth generation techniquesITFT  -  Fourth generation techniques
ITFT - Fourth generation techniquesShruti Kunwar
 

More from Shruti Kunwar (9)

ITFT - Spiral model
ITFT -    Spiral modelITFT -    Spiral model
ITFT - Spiral model
 
ITFT - Software
ITFT -  SoftwareITFT -  Software
ITFT - Software
 
ITFT - Software prototyping
ITFT -  Software prototypingITFT -  Software prototyping
ITFT - Software prototyping
 
ITFT - Software development life cycle
ITFT  -   Software development life cycleITFT  -   Software development life cycle
ITFT - Software development life cycle
 
ITFT - Project planning
ITFT  -    Project planningITFT  -    Project planning
ITFT - Project planning
 
ITFT - Innovation
ITFT -     InnovationITFT -     Innovation
ITFT - Innovation
 
ITFT - Henderson clark model
ITFT  -  Henderson clark modelITFT  -  Henderson clark model
ITFT - Henderson clark model
 
ITFT - Fourth generation techniques
ITFT  -  Fourth generation techniquesITFT  -  Fourth generation techniques
ITFT - Fourth generation techniques
 
ITFT - Design
ITFT -   DesignITFT -   Design
ITFT - Design
 

Recently uploaded

An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfSanaAli374401
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhikauryashika82
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Disha Kariya
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...KokoStevan
 

Recently uploaded (20)

An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
SECOND SEMESTER TOPIC COVERAGE SY 2023-2024 Trends, Networks, and Critical Th...
 

ITFT - Cocomo model

  • 2. organic, semidetached, and embedded systems Boehm’s [1981] definition of organic, semidetached, and embedded systems are elaborated below • Organic: A development project can be considered of organic type, if the project deals with developing a well understood application program, the size of the development team is reasonably small, and the team members are experienced in developing similar types of projects.
  • 3. Semidetached • A development project can be considered of semidetached type, if the development consists of a mixture of experienced and inexperienced staff. • Team members may have limited experience on related systems but may be unfamiliar with some aspects of the system being developed.
  • 4. Embedded • A development project is considered to be of embedded type, if the software being developed is strongly coupled to complex hardware, or if the stringent regulations on the operational procedures exist
  • 5. COCOMO • COCOMO (Constructive Cost Estimation Model) was proposed by Boehm [1981]. According to Boehm, software cost estimation should be done through three stages: Basic COCOMO, Intermediate COCOMO, and Complete COCOMO.
  • 6. Basic COCOMO Model • The basic COCOMO model gives an approximate estimate of the project parameters. The basic COCOMO estimation model is given by the following expressions: • Effort = a1 х (KLOC)a2 PM • Tdev = b1 x (Effort)b2 Months
  • 7. Continued.. Where • KLOC is the estimated size of the software product expressed in Kilo Lines of Code, • a1, a2, b1, b2 are constants for each category of software products, • Tdev is the estimated time to develop the software, expressed in months, • Effort is the total effort required to develop the software product, expressed in person months (PMs).
  • 8. Continued.. • The effort estimation is expressed in units of person-months (PM). It is the area under the person-month plot (as shown in fig.). • It should be carefully noted that an effort of 100 PM does not imply that 100 persons should work for 1 month nor does it imply that 1 person should be employed for 100 months, but it denotes the area under the person-month curve.
  • 10. Estimation of development effort • For the three classes of software products, the formulas for estimating the effort based on the code size are shown below: • Organic : Effort = 2.4(KLOC)1.05 PM • Semi-detached : Effort = 3.0(KLOC)1.12 PM • Embedded : Effort = 3.6(KLOC)1.20 PM
  • 11. Estimation of development time • For the three classes of software products, the formulas for estimating the development time based on the effort are given below: • Organic : Tdev = 2.5(Effort)0.38 Months • Semi-detached : Tdev = 2.5(Effort)0.35 Months • Embedded : Tdev = 2.5(Effort)0.32 Months
  • 12. Example • Assume that the size of an organic type software product has been estimated to be 32,000 lines of source code. Assume that the average salary of software engineers be Rs. 15,000/- per month. Determine the effort required to develop the software product and the nominal development time.
  • 13. Solution • From the basic COCOMO estimation formula for organic software: • Effort = 2.4 х (32)1.05 = 91 PM • Nominal development time = 2.5 х (91)0.38 = 14 months • Cost required to develop the product = 14 х 15,000 • = Rs. 210,000/-