SlideShare a Scribd company logo
1 of 18
PMI Project Management
Professional (PMP)® Workshop
Project Time Management
Part 3
© 2016 Skillogic Knowledge Solutions. All Rights Reserved2
Inputs: Develop Schedule
 The major outputs of all the time management planning
processes are inputs to developing the schedule
 All the planning effort for time management comes together in
this process
© 2016 Skillogic Knowledge Solutions. All Rights Reserved3
Tools & technique: Develop Schedule
 Critical path method is about determining planned start and
finish dates for an activity. We use the duration and the logical
relationships to derive the start and finish dates
 Earliest finish date is dependent on its duration and its earliest
start date
 Earliest start of the second activity is dependent on the earliest
finish of the previous activity
 Forward pass involves calculating the earliest start and finish
dates for the activities in a network
© 2016 Skillogic Knowledge Solutions. All Rights Reserved4
Tools & technique: Develop Schedule
 When determining the Early start and early finish dates
(forward pass), leads and lags between activities should be
accounted for. Lag between 2 activities is indicated by a
positive symbol
 A lead between two activities indicates that there is an
acceleration of the second activity to start before the
completion of first activity. Lead between 2 activities is
indicated by a negative symbol
© 2016 Skillogic Knowledge Solutions. All Rights Reserved5
Tools & technique: Develop Schedule
 When we have larger numbers it becomes tedious to calculate
the early start and finish dates of activities
 Formulae for forward pass:
ES of 1st activity = 1
EF of any activity = ES + Duration – 1
ES of next activity = EF of previous activity + 1
© 2016 Skillogic Knowledge Solutions. All Rights Reserved6
Tools & technique: Develop Schedule
 Backward pass is used to calculate the Late start and Late
finish dates of activities in a network
 The amount of flexibility available can be known by
calculating the earliest and latest dates of an activity
 Scenario 1: If the Latest finish date of the last activity is not
known then Latest finish date of the last activity is the same as
the Earliest finish date of that activity
 Scenario 2: Latest finish date of the last activity is known and
is different than Earliest finish data of that activity
 Latest start date of an activity is based on the Latest finish date
and the duration of the activity
© 2016 Skillogic Knowledge Solutions. All Rights Reserved7
Tools & technique: Develop Schedule
 The time that the start of an activity can be delayed without
delaying the project end date is called Total Float Total float of
an activity = LS-ES OR LF-EF
 The total float is applied to all the activities in a path. If one
activity consumes the complete float then the other activities on
the path will not have any more float
 Free float is the flexibility between two activities
Free float = ES (successor ) – ES - Duration
© 2016 Skillogic Knowledge Solutions. All Rights Reserved8
Tools & technique: Develop Schedule
Characteristics of critical path:
1. Duration of the total project can be obtained by adding the
duration of the activities on critical path
2. Activities with longest duration
3. Usually Zero total float
4. There can be multiple critical paths
5. When there are any changes, a new critical path may arise
6. Any delay in critical path will delay the overall
project
7. Free float cannot be more than total float
8. Does not consider resources
© 2016 Skillogic Knowledge Solutions. All Rights Reserved9
Tools & technique: Develop Schedule
 Critical path method applies resources to the critical path
 Critical path gets altered when resources are applied and is
called Critical Chain
 Critical chain method is done after the critical path method
 Buffers (additional time to manage uncertainties) in the project
are considered in critical chain method
 Buffers for individual activities are taken and placed in buffer
pool
 Buffer pool is applied either at the end of the project (project
buffer) or at a place where non critical activities converge the
critical path(feeder buffer)
 PM can use this buffer to deal with uncertainties
© 2016 Skillogic Knowledge Solutions. All Rights Reserved10
Tools & technique: Develop Schedule
 Schedule compressing is shortening the project schedule due
to constraints
 Schedule compression is obtained using crashing and fast
tracking. Compression should always be performed on critical
path
 Crashing is done by doing a what-if /trade-off between cost and
schedule. Best solution is one which gives greatest
compression with minimum cost
© 2016 Skillogic Knowledge Solutions. All Rights Reserved11
Tools & technique: Develop Schedule
 What-if analysis includes evaluating multiple scenarios to
impact the schedule
 We use simulation methodology to evaluated different
scenarios. Monte Carlo simulation is most widely used
 All resource may not be available at all times of project. Hence
we perform resources leveling to address the issues of having
too many resources or less resources during various times of
project
© 2016 Skillogic Knowledge Solutions. All Rights Reserved12
Outputs: Develop Schedule
 Project schedule includes the planned start and end date for
each activity
 Project schedule can be represented as Gant chart, schedule
network diagram, bar chart etc.
 Approved version of project schedule is called Schedule
baseline
© 2016 Skillogic Knowledge Solutions. All Rights Reserved13
Introduction: Control Schedule
 This process is about monitoring and controlling the project
schedule by monitoring various factors related to schedule
 This process also handles the changes
© 2016 Skillogic Knowledge Solutions. All Rights Reserved14
Control ScheduleInputs
• Project
management
plan
• Project schedule
• Work
performance
data
• Project
calendars
• Schedule data
• Organizational
process assets
Tools&Techniques
• Performance
reviews
• Project
management
software
• Resource
optimization
techniques
• Modeling
techniques
• Leads and lags
• Schedule
compression
• Scheduling tool
Outputs
• Work
performance
information
• Schedule
forecasts
• Change requests
• Project
management
plan updates
• Project
documents
updates
• Organizational
process assets
updates
© 2016 Skillogic Knowledge Solutions. All Rights Reserved15
Tools: Control Schedule
 Performance reviews is reporting to stakeholders on the actual
start and finish dates and the percentage completion of various
activities
 Variance analysis compares the estimated start and finish dates
with the actual start and finish dates. This helps in identifying
the variance and investigating reasons for variation
© 2016 Skillogic Knowledge Solutions. All Rights Reserved16
Outputs: Control Schedule
 PMP updates include changes to the schedule baseline to
accommodate the approved change requests
 When a change related to schedule is approved, the PMP
should be updated
© 2016 Skillogic Knowledge Solutions. All Rights Reserved17
© 2015 Skillogic Knowledge Solutions. All Rights Reserved18
Skillogic Knowledge Solutions
Call Us
@ 901-989-9000
If you are looking for PMP Certification Training in Chennai visit:
http://in.skillogic.com/pmp-training/pmp-certification-chennai

More Related Content

Viewers also liked

Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1
Nam Trung
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6
Nam Trung
 

Viewers also liked (18)

Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1
 
PMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk ManagementPMP PMBOK 5th Ch 11 Project Risk Management
PMP PMBOK 5th Ch 11 Project Risk Management
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6
 
PMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time managementPMP PMBOK 5TH Ch 6 time management
PMP PMBOK 5TH Ch 6 time management
 
PMP_Professional and Social Responsibility
PMP_Professional and Social ResponsibilityPMP_Professional and Social Responsibility
PMP_Professional and Social Responsibility
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
 
PMP_Project Human Resources Management
PMP_Project Human Resources ManagementPMP_Project Human Resources Management
PMP_Project Human Resources Management
 
PMP_Project Quality Management
PMP_Project Quality ManagementPMP_Project Quality Management
PMP_Project Quality Management
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Project time management
Project time managementProject time management
Project time management
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
PMP_Project Risk Management
PMP_Project Risk ManagementPMP_Project Risk Management
PMP_Project Risk Management
 
Pmp slide share
Pmp slide sharePmp slide share
Pmp slide share
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
 
Project Management Professional (PMP)
Project Management Professional (PMP) Project Management Professional (PMP)
Project Management Professional (PMP)
 
PMP_Project Stakeholder Management
PMP_Project Stakeholder ManagementPMP_Project Stakeholder Management
PMP_Project Stakeholder Management
 

More from Skillogic Solutions

More from Skillogic Solutions (20)

Ethical Hacking Course in Hyderabad April 2024.pptx
Ethical Hacking Course in Hyderabad April 2024.pptxEthical Hacking Course in Hyderabad April 2024.pptx
Ethical Hacking Course in Hyderabad April 2024.pptx
 
Cyber Security Course in Hyderabad April 2024
Cyber Security Course in Hyderabad April 2024Cyber Security Course in Hyderabad April 2024
Cyber Security Course in Hyderabad April 2024
 
Ethical Hacking Course in Chennai April 2024
Ethical Hacking Course in Chennai April 2024Ethical Hacking Course in Chennai April 2024
Ethical Hacking Course in Chennai April 2024
 
Cyber Security Course in Chennai April 2024
Cyber Security Course in Chennai April 2024Cyber Security Course in Chennai April 2024
Cyber Security Course in Chennai April 2024
 
Ethical Hacking Course in Bangalore April 2024
Ethical Hacking Course in Bangalore April 2024Ethical Hacking Course in Bangalore April 2024
Ethical Hacking Course in Bangalore April 2024
 
Cyber Security Course in Bangalore April 2024
Cyber Security Course in Bangalore April 2024Cyber Security Course in Bangalore April 2024
Cyber Security Course in Bangalore April 2024
 
Cyber Security Course in Pune March 2024.pptx
Cyber Security Course in Pune March 2024.pptxCyber Security Course in Pune March 2024.pptx
Cyber Security Course in Pune March 2024.pptx
 
Ethical Hacking Course in Chennai April 2024
Ethical Hacking Course in Chennai April 2024Ethical Hacking Course in Chennai April 2024
Ethical Hacking Course in Chennai April 2024
 
Cyber Security Course in Chennai March 2024
Cyber Security Course in Chennai March 2024Cyber Security Course in Chennai March 2024
Cyber Security Course in Chennai March 2024
 
Ethical Hacking Course in Bangalore March 2024.pptx
Ethical Hacking Course in Bangalore March 2024.pptxEthical Hacking Course in Bangalore March 2024.pptx
Ethical Hacking Course in Bangalore March 2024.pptx
 
Cyber Security Course in Bangalore March 2024
Cyber Security Course in Bangalore March 2024Cyber Security Course in Bangalore March 2024
Cyber Security Course in Bangalore March 2024
 
Ethical Hacking Course in Hyderabad March 2024
Ethical Hacking Course in Hyderabad March 2024Ethical Hacking Course in Hyderabad March 2024
Ethical Hacking Course in Hyderabad March 2024
 
Cyber Security Course in Hyderabad March 2024
Cyber Security Course in Hyderabad March 2024Cyber Security Course in Hyderabad March 2024
Cyber Security Course in Hyderabad March 2024
 
Ethical Hacking Course in Pune March 2024
Ethical Hacking Course in Pune March 2024Ethical Hacking Course in Pune March 2024
Ethical Hacking Course in Pune March 2024
 
Cyber Security Course in Pune March 2024
Cyber Security Course in Pune March 2024Cyber Security Course in Pune March 2024
Cyber Security Course in Pune March 2024
 
Ethical Hacking Course in Chennai March 2024
Ethical Hacking Course in Chennai March 2024Ethical Hacking Course in Chennai March 2024
Ethical Hacking Course in Chennai March 2024
 
Cyber Security Course in Chennai March.pptx
Cyber Security Course in Chennai March.pptxCyber Security Course in Chennai March.pptx
Cyber Security Course in Chennai March.pptx
 
Ethical Hacking Course in Bangalore March
Ethical Hacking Course in Bangalore MarchEthical Hacking Course in Bangalore March
Ethical Hacking Course in Bangalore March
 
Cyber Security Course in Bangalore March 2024
Cyber Security Course in Bangalore March 2024Cyber Security Course in Bangalore March 2024
Cyber Security Course in Bangalore March 2024
 
Ethical Hacking Course in Hyderabad March.pptx
Ethical Hacking Course in Hyderabad March.pptxEthical Hacking Course in Hyderabad March.pptx
Ethical Hacking Course in Hyderabad March.pptx
 

Recently uploaded

Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
fonyou31
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
SoniaTolstoy
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Krashi Coaching
 

Recently uploaded (20)

BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 

PMP Training Project Time Management Part 3

  • 2. Project Time Management Part 3 © 2016 Skillogic Knowledge Solutions. All Rights Reserved2
  • 3. Inputs: Develop Schedule  The major outputs of all the time management planning processes are inputs to developing the schedule  All the planning effort for time management comes together in this process © 2016 Skillogic Knowledge Solutions. All Rights Reserved3
  • 4. Tools & technique: Develop Schedule  Critical path method is about determining planned start and finish dates for an activity. We use the duration and the logical relationships to derive the start and finish dates  Earliest finish date is dependent on its duration and its earliest start date  Earliest start of the second activity is dependent on the earliest finish of the previous activity  Forward pass involves calculating the earliest start and finish dates for the activities in a network © 2016 Skillogic Knowledge Solutions. All Rights Reserved4
  • 5. Tools & technique: Develop Schedule  When determining the Early start and early finish dates (forward pass), leads and lags between activities should be accounted for. Lag between 2 activities is indicated by a positive symbol  A lead between two activities indicates that there is an acceleration of the second activity to start before the completion of first activity. Lead between 2 activities is indicated by a negative symbol © 2016 Skillogic Knowledge Solutions. All Rights Reserved5
  • 6. Tools & technique: Develop Schedule  When we have larger numbers it becomes tedious to calculate the early start and finish dates of activities  Formulae for forward pass: ES of 1st activity = 1 EF of any activity = ES + Duration – 1 ES of next activity = EF of previous activity + 1 © 2016 Skillogic Knowledge Solutions. All Rights Reserved6
  • 7. Tools & technique: Develop Schedule  Backward pass is used to calculate the Late start and Late finish dates of activities in a network  The amount of flexibility available can be known by calculating the earliest and latest dates of an activity  Scenario 1: If the Latest finish date of the last activity is not known then Latest finish date of the last activity is the same as the Earliest finish date of that activity  Scenario 2: Latest finish date of the last activity is known and is different than Earliest finish data of that activity  Latest start date of an activity is based on the Latest finish date and the duration of the activity © 2016 Skillogic Knowledge Solutions. All Rights Reserved7
  • 8. Tools & technique: Develop Schedule  The time that the start of an activity can be delayed without delaying the project end date is called Total Float Total float of an activity = LS-ES OR LF-EF  The total float is applied to all the activities in a path. If one activity consumes the complete float then the other activities on the path will not have any more float  Free float is the flexibility between two activities Free float = ES (successor ) – ES - Duration © 2016 Skillogic Knowledge Solutions. All Rights Reserved8
  • 9. Tools & technique: Develop Schedule Characteristics of critical path: 1. Duration of the total project can be obtained by adding the duration of the activities on critical path 2. Activities with longest duration 3. Usually Zero total float 4. There can be multiple critical paths 5. When there are any changes, a new critical path may arise 6. Any delay in critical path will delay the overall project 7. Free float cannot be more than total float 8. Does not consider resources © 2016 Skillogic Knowledge Solutions. All Rights Reserved9
  • 10. Tools & technique: Develop Schedule  Critical path method applies resources to the critical path  Critical path gets altered when resources are applied and is called Critical Chain  Critical chain method is done after the critical path method  Buffers (additional time to manage uncertainties) in the project are considered in critical chain method  Buffers for individual activities are taken and placed in buffer pool  Buffer pool is applied either at the end of the project (project buffer) or at a place where non critical activities converge the critical path(feeder buffer)  PM can use this buffer to deal with uncertainties © 2016 Skillogic Knowledge Solutions. All Rights Reserved10
  • 11. Tools & technique: Develop Schedule  Schedule compressing is shortening the project schedule due to constraints  Schedule compression is obtained using crashing and fast tracking. Compression should always be performed on critical path  Crashing is done by doing a what-if /trade-off between cost and schedule. Best solution is one which gives greatest compression with minimum cost © 2016 Skillogic Knowledge Solutions. All Rights Reserved11
  • 12. Tools & technique: Develop Schedule  What-if analysis includes evaluating multiple scenarios to impact the schedule  We use simulation methodology to evaluated different scenarios. Monte Carlo simulation is most widely used  All resource may not be available at all times of project. Hence we perform resources leveling to address the issues of having too many resources or less resources during various times of project © 2016 Skillogic Knowledge Solutions. All Rights Reserved12
  • 13. Outputs: Develop Schedule  Project schedule includes the planned start and end date for each activity  Project schedule can be represented as Gant chart, schedule network diagram, bar chart etc.  Approved version of project schedule is called Schedule baseline © 2016 Skillogic Knowledge Solutions. All Rights Reserved13
  • 14. Introduction: Control Schedule  This process is about monitoring and controlling the project schedule by monitoring various factors related to schedule  This process also handles the changes © 2016 Skillogic Knowledge Solutions. All Rights Reserved14
  • 15. Control ScheduleInputs • Project management plan • Project schedule • Work performance data • Project calendars • Schedule data • Organizational process assets Tools&Techniques • Performance reviews • Project management software • Resource optimization techniques • Modeling techniques • Leads and lags • Schedule compression • Scheduling tool Outputs • Work performance information • Schedule forecasts • Change requests • Project management plan updates • Project documents updates • Organizational process assets updates © 2016 Skillogic Knowledge Solutions. All Rights Reserved15
  • 16. Tools: Control Schedule  Performance reviews is reporting to stakeholders on the actual start and finish dates and the percentage completion of various activities  Variance analysis compares the estimated start and finish dates with the actual start and finish dates. This helps in identifying the variance and investigating reasons for variation © 2016 Skillogic Knowledge Solutions. All Rights Reserved16
  • 17. Outputs: Control Schedule  PMP updates include changes to the schedule baseline to accommodate the approved change requests  When a change related to schedule is approved, the PMP should be updated © 2016 Skillogic Knowledge Solutions. All Rights Reserved17
  • 18. © 2015 Skillogic Knowledge Solutions. All Rights Reserved18 Skillogic Knowledge Solutions Call Us @ 901-989-9000 If you are looking for PMP Certification Training in Chennai visit: http://in.skillogic.com/pmp-training/pmp-certification-chennai