More Related Content More from Skillogic Solutions (20) PMP Training Project Time Management Part 33. Inputs: Develop Schedule
The major outputs of all the time management planning
processes are inputs to developing the schedule
All the planning effort for time management comes together in
this process
© 2016 Skillogic Knowledge Solutions. All Rights Reserved3
4. Tools & technique: Develop Schedule
Critical path method is about determining planned start and
finish dates for an activity. We use the duration and the logical
relationships to derive the start and finish dates
Earliest finish date is dependent on its duration and its earliest
start date
Earliest start of the second activity is dependent on the earliest
finish of the previous activity
Forward pass involves calculating the earliest start and finish
dates for the activities in a network
© 2016 Skillogic Knowledge Solutions. All Rights Reserved4
5. Tools & technique: Develop Schedule
When determining the Early start and early finish dates
(forward pass), leads and lags between activities should be
accounted for. Lag between 2 activities is indicated by a
positive symbol
A lead between two activities indicates that there is an
acceleration of the second activity to start before the
completion of first activity. Lead between 2 activities is
indicated by a negative symbol
© 2016 Skillogic Knowledge Solutions. All Rights Reserved5
6. Tools & technique: Develop Schedule
When we have larger numbers it becomes tedious to calculate
the early start and finish dates of activities
Formulae for forward pass:
ES of 1st activity = 1
EF of any activity = ES + Duration – 1
ES of next activity = EF of previous activity + 1
© 2016 Skillogic Knowledge Solutions. All Rights Reserved6
7. Tools & technique: Develop Schedule
Backward pass is used to calculate the Late start and Late
finish dates of activities in a network
The amount of flexibility available can be known by
calculating the earliest and latest dates of an activity
Scenario 1: If the Latest finish date of the last activity is not
known then Latest finish date of the last activity is the same as
the Earliest finish date of that activity
Scenario 2: Latest finish date of the last activity is known and
is different than Earliest finish data of that activity
Latest start date of an activity is based on the Latest finish date
and the duration of the activity
© 2016 Skillogic Knowledge Solutions. All Rights Reserved7
8. Tools & technique: Develop Schedule
The time that the start of an activity can be delayed without
delaying the project end date is called Total Float Total float of
an activity = LS-ES OR LF-EF
The total float is applied to all the activities in a path. If one
activity consumes the complete float then the other activities on
the path will not have any more float
Free float is the flexibility between two activities
Free float = ES (successor ) – ES - Duration
© 2016 Skillogic Knowledge Solutions. All Rights Reserved8
9. Tools & technique: Develop Schedule
Characteristics of critical path:
1. Duration of the total project can be obtained by adding the
duration of the activities on critical path
2. Activities with longest duration
3. Usually Zero total float
4. There can be multiple critical paths
5. When there are any changes, a new critical path may arise
6. Any delay in critical path will delay the overall
project
7. Free float cannot be more than total float
8. Does not consider resources
© 2016 Skillogic Knowledge Solutions. All Rights Reserved9
10. Tools & technique: Develop Schedule
Critical path method applies resources to the critical path
Critical path gets altered when resources are applied and is
called Critical Chain
Critical chain method is done after the critical path method
Buffers (additional time to manage uncertainties) in the project
are considered in critical chain method
Buffers for individual activities are taken and placed in buffer
pool
Buffer pool is applied either at the end of the project (project
buffer) or at a place where non critical activities converge the
critical path(feeder buffer)
PM can use this buffer to deal with uncertainties
© 2016 Skillogic Knowledge Solutions. All Rights Reserved10
11. Tools & technique: Develop Schedule
Schedule compressing is shortening the project schedule due
to constraints
Schedule compression is obtained using crashing and fast
tracking. Compression should always be performed on critical
path
Crashing is done by doing a what-if /trade-off between cost and
schedule. Best solution is one which gives greatest
compression with minimum cost
© 2016 Skillogic Knowledge Solutions. All Rights Reserved11
12. Tools & technique: Develop Schedule
What-if analysis includes evaluating multiple scenarios to
impact the schedule
We use simulation methodology to evaluated different
scenarios. Monte Carlo simulation is most widely used
All resource may not be available at all times of project. Hence
we perform resources leveling to address the issues of having
too many resources or less resources during various times of
project
© 2016 Skillogic Knowledge Solutions. All Rights Reserved12
13. Outputs: Develop Schedule
Project schedule includes the planned start and end date for
each activity
Project schedule can be represented as Gant chart, schedule
network diagram, bar chart etc.
Approved version of project schedule is called Schedule
baseline
© 2016 Skillogic Knowledge Solutions. All Rights Reserved13
14. Introduction: Control Schedule
This process is about monitoring and controlling the project
schedule by monitoring various factors related to schedule
This process also handles the changes
© 2016 Skillogic Knowledge Solutions. All Rights Reserved14
15. Control ScheduleInputs
• Project
management
plan
• Project schedule
• Work
performance
data
• Project
calendars
• Schedule data
• Organizational
process assets
Tools&Techniques
• Performance
reviews
• Project
management
software
• Resource
optimization
techniques
• Modeling
techniques
• Leads and lags
• Schedule
compression
• Scheduling tool
Outputs
• Work
performance
information
• Schedule
forecasts
• Change requests
• Project
management
plan updates
• Project
documents
updates
• Organizational
process assets
updates
© 2016 Skillogic Knowledge Solutions. All Rights Reserved15
16. Tools: Control Schedule
Performance reviews is reporting to stakeholders on the actual
start and finish dates and the percentage completion of various
activities
Variance analysis compares the estimated start and finish dates
with the actual start and finish dates. This helps in identifying
the variance and investigating reasons for variation
© 2016 Skillogic Knowledge Solutions. All Rights Reserved16
17. Outputs: Control Schedule
PMP updates include changes to the schedule baseline to
accommodate the approved change requests
When a change related to schedule is approved, the PMP
should be updated
© 2016 Skillogic Knowledge Solutions. All Rights Reserved17
18. © 2015 Skillogic Knowledge Solutions. All Rights Reserved18
Skillogic Knowledge Solutions
Call Us
@ 901-989-9000
If you are looking for PMP Certification Training in Chennai visit:
http://in.skillogic.com/pmp-training/pmp-certification-chennai