Chapter-5
Contract Management
5.1 Method of Work execution
5.2 Types of Contract
5.3 Tendering Process-Preparation
before Tendering; Tender
Notice; Tender Document;
Conditions of Contract;
Prequalification; Tender;
Evaluation; Selection and
Award
5.1 Method of Work execution
Broadly any construction work can be executed through two methods:
1.Through amanat
2.Through contract
1.Through amanat: When the works are executed by the owner itself,
by hiring workers and supplying materials and equipment, it is
known as execution of work through Amanat.
The record of labor employed each day and the part on which
materials and equipment if any employed is maintained in book
keeping. The record will also indicate the progress of work also.
It is useful when the work is small and necessary to do
immediately, and the expertise are available within the
organization. It saves the cost required for making profit by the
contractor and VAT also. It also keeps the staff busy in the work.
2.Through contract: Contract is an agreement between two or
more parties to do or not to do any work. It is legal and time
bound. Offer and acceptance must be there.
Work Execution through Contract
a)sealed competitive bidding
i)International competitive bidding(ICB)
ii)National/local competitive bidding(NCB/LCB)
b)sealed Quotation
c)Direct procurement
d)users’ committee
e)procurement under special circumstances
a)sealed competitive bidding
i) International competitive bidding(ICB):
An international competitive bidding shall be invited
on any of the following conditions :
• Where the goods or construction works as
requisitioned by a public entity are not available
under competitive price from more than one
construction entrepreneur or supplier within
country.
• In making invitation to national tender for the
procurement of goods, construction works or other
services, no tender is submitted and same has to be
procured aboard.
• Where foreign goods or construction works have
to be procured from foreign assistance under an
agreement enter into with a donor party.
• Where the public entity certifies the goods or
construction works, being of complex and special
type, have to be procured by means of an
international tender.
• Notice on invitation to tender shall be published
in English language an all tender or
prequalification documents shall be published in
English.
• In publishing a notice a period of at least 45
days shall be given
• Notice shall be published in daily newspaper
of national circulation and it may also be
published in any international communication
media.
• Notice shall be placed in website of concerned
entity or that of the Public procurement
Monitoring Office (PPMO)
ii)National/local competitive bidding(NCB/LCB):
Contractors are invited from within the nation or local.
 For any procurement having cost estimate more than
10 Lakh for goods and other services, and more than
20 Lakh for works for which ICB is not required, NCB
shall be preferred.
• In publishing a notice a period of at least 30 days shall
be given
• Notice shall be published in daily newspaper of
national circulation and it may also be published in any
international communication media.
• Notice shall be placed in website of concerned entity
or that of the Public procurement Monitoring Office
(PPMO)
b)sealed Quotation: Procurement of works up to
20 lakh and Procurement of goods and other
services up to 10 lakh can be carried out
adopting sealed quotation.
c)Direct procurement:Goods or Consultancy
Services or Other services or construction work
may be procured by means of direct
procurement in the following circumstances:
• The value of miscellaneous procurement does
not exceed the prescribed threshold.
 Goods or consultancy service or other
service : Up to 3 Lakh
 Construction work : Up to 5 Lakh
d)users’ committee:
This method is used for executing small labor
intensive works where the objective is to:
• Provide employment and income directly to persons
living in the project area.
• Increase the utilization of local know how,
appropriate technologies and materials
• Hand over the completed works for operation and
maintenance directly by persons living in the project
area.
• When objective of project is to create employment
which enhances the economy, quality or
substantiality of beneficiary community then this
method is used.
Works up to 60 lakh may be carried out by
community participation.
e)procurement under special circumstances:
• Emergency/ special circumstances.
• Depends on contract amount
5.2 Types of Contract
Types of Construction Contracts
Two broad categories:
• Price based - lump sum or unite rate contracts -
price or rates are submitted by the contractor in
his tender
• Cost based - cost-reimbursable and target cost
contract - actual cost incurred by the contractors
is reimbursed(To compensate with payment ;
especially, to repay money spent on one’s behalf),
together with a fee for overheads and profit.
Types of Contracts
1. Lump sum contract
• A lump sum contract may be entered into for
procuring a construction work such as ground
water pipeline installation, the quantities of
which are difficult to measure or a construction
work such as superstructure of a bridge, the
quantities of which can be measured.
• Such contract shall specify that the
construction entrepreneur shall be responsible
for all types of risks and liabilities associated
with the construction work
• Provided that if the financial liabilities of the
construction entrepreneur increases as a
consequence of an order issued by the public
entity that involves any change in the
construction work after the commencement
of work upon making the contract, the public
entity shall bear the liabilities.
• Sometimes called Drawings and Specifications
Contract
Advantages of Lump Sum Contract
• The final price is known, by the owner, before
the work commences.
• The contractor has more incentive to reduce
his cost to increase the profit.
• The contractor hopes to complete the job
as quickly as possible, to minimize
overhead, to maximize profit and to move to
the next Job.
Disadvantages of Lump Sum Contract
• Changes in drawings and specifications can
be very expensive and source of trouble. In
other words the contract has very limited
flexibility for design changes.
• The contractor carries much of the risks. The
tendered price may include high risk
contingency.
• Competent contractors may decide not to
bid to avoid a high-risk lump sum contract.
2. Unit Price (BOQ) contract
• Unit price contract may be entered into where the
quantity of a construction work is difficult to be
ascertained or where construction work is to be
procured on the basis of unit price set forth in the
bill of quantity.
• The bidder has to include in such unit price the
materials, labor and the other matters required to
complete the proposed construction work.
• In making payment for work done under this
contract, the public entity shall make such
payment on the basis of the unit of work actually
done and measured in the field.
Advantages of unit price contract
• Fair basis for competition.
• In comparing with lump-sum contract,
 Changes in contract documents can be made easily by
the owner.
 Lower risk for contractor.
Disadvantages of Unit Price Contract
• The exact final price of the project is not known
to the owner until the completion of the project.
• Upto date account and record keeping is
necessary
• Possibility of submitting unbalanced bid
3.Cost Reimbursable Contract
• A cost reimbursable contract may be entered
into for procuring a construction work involving
high risk and unpredictable conditions, when it
is likely that a construction entrepreneur would
refuse to, or be unable to, perform the work
under a unit price contract.
• While making payment to construction
entrepreneur for the construction work
procured under this contract, such payment may
include the costs actually incurred by that
entrepreneur, overheads of that work plus profit
set forth in the approved cost estimate.
Advantages of Cost Reimbursement Contract
• Start construction without waiting for the whole
set of drawings and specifications.
• More flexibility for the owner to make changes
as work progresses.
• Draw the contractor expertise during design.
Disadvantages of Cost Reimbursement
Contract
• It is difficult to predict the final cost and the
distribution of it, which may cause financial
problems to the owner.
• Contractor pays less attention to cost control.
4.Design and build contract(turn key contract):
• A design and build contract may be entered for
procuring the design and build of any construction from
the same entrepreneur.
• The work set forth in this contract shall commence only
after the public entity has through its technician or
group of technicians examined and approved the design
of construction work.
• In a design/build contract, the owner enters into a
single agreement by which the design and build
contractor agrees to perform both the design and
construction of the project.
• As well as being responsible for faulty workmanship in
construction, the contractor is also liable for any
deficiencies in design under this arrangement.
• A Design build contract is usually the preferred
contracting method under tight schedule
circumstances, and it is intended to save time.
– Advantages
• In conventional type of contract, incase of
damage/failure of structure, it is often difficult to
determine whether such damage/failure is due to
design fault or construction (quality) fault; which
arises disputes between owner and contractor Such
situation is reduced in design/build contract as both
responsibility is of contract.
• Because the owner warrants the sufficiency of the
plans in a conventional construction contract, he is
liable for any increased costs because of defective or
inadequate plans. But in a design/build contract, the
contractor is then unable to look to the owner for
additional compensation.
• In design/build contract the project can often be
completed within a shorter period of time than with
the traditional three-party arrangement.
• Since a design/build project can be designed and
constructed in phases, the contractor is able to
order necessary materials for subsequent phases
ahead of time perhaps at a reduced cost.
• Contractor’s control over design details allows the
contractor to use familiar construction methods and
processes in building the structure, with the result
of much more efficient construction. These savings
ultimately benefit the owner.
– Disadvantages
• For owner it is often difficult to effectively compare the various
preliminary design proposals submitted by design/build
contractors. The designs will probably not be uniform because
there are usually many different methods of satisfying the owner’s
general needs and performance specifications.
• The owner’s input on the detailed design of the structure will be
limited because the contractor, rather than the owner, is
responsible for furnishing the design work. As a result, the
finished structure may not be exactly as the owner envisioned.
This can lead to later disputes.
• The owner may not obtain the lowest cost for the project since
the design/build contract is usually entered into by negotiation
rather than competitive bidding.
• There is only limited scope for the client to make changes to his
requirements once the client's requirements (i.e. Inflexibility) and
contractor's proposals have been agreed otherwise the cost
consequences may be prohibitive.
• The client has less control and influence over design matters due
to which quality may be impaired.
BOOT, BOT Contract
• BOOT (build, own, operate, transfer) is a public-
private partnership (PPP) project model in which a
private organization conducts a large development
project under contract to a public-sector partner, such
as a government agency. A BOOT project is often seen
as a way to develop a large public infrastructure
project with private funding.
BOOT model
• The public-sector partner contracts with a private
developer - typically a large corporation or
consortium of businesses with specific expertise - to
design and implement a large project.
• The public-sector partner may provide limited
funding or some other benefit (such as tax
exempt status) but the private-sector partner
assumes the risks associated with planning,
constructing, operating and maintaining the
project for a specified time period.
• The private partner builds a facility to the
specification agreed by the public agency.
• Government retains strategic control over the
project.
• During the specified period called concession
period, the developer charges customers who
use the infrastructure that's been built to realize
a profit.
• At the end of concession period, the private-
sector partner transfers ownership to the
funding organization, either freely or for an
amount stipulated in the original contract
(generally to fulfill viability gap). Such contracts
are typically long-term; usually 20-30 years.
• BOOT is sometimes known as BOT (build, own,
transfer).
• Variations on the BOOT model include BOO
(build, own, operate), BLT (build, lease, transfer)
and BLOT (build, lease, operate, transfer), BTO
(Build, transfer, operate), LOT (Lease, operate,
transfer), DOT (develop, operate, transfer) etc.
Advantages
• The majority of construction and long-term
operating risk can be transferred onto the BOOT
provider.
• The scheme is not constrained through a lack of
funding, a lack or expertise or project
management capability. Also, there are strong
financial incentives for the BOOT operator to
complete the construction and get the scheme
operational as soon as possible.
• Project completes on time.
• BOOT operators are experienced with
management and operation of infrastructure
assets and bring these skills to the scheme.
• Accountability for the asset design,
construction and service delivery is very high
given that if the performance targets are not
met, the operator stands to lose a portion of
capital expenditure, capital profit, operating
expenditure and operating profit.
• Corporate structuring issues and costs are
minimal within a BOOT model, as project
funding, ownership and operation are the
responsibility of the BOOT operator. These
costs will however be built into the BOOT
project pricing.
Disadvantages
• BOOT is likely to result in a higher cost to end users.
Because the private investor is interested to profit.
• Not useful for projects which has low economic
return.
• Community users may have a negative reaction to
private sector involvement in the scheme, particularly
if the private sector is an overseas owned company.
• Management and monitoring of the service level can
be time consuming and resource hungry. Procedures
need to be in place to allow users to assess service
performance and penalize the BOOT operator where
necessary.
5.3 Tendering Process-Preparation
before Tendering; Tender
Notice; Tender Document;
Conditions of Contract;
Prequalification; Tender;
Evaluation; Selection and
Award
What is Tender?
-Tender is a written offer/proposal by the
tenderer (the person who offer the tender) to
perform the work or to supply some specified
goods at a certain rate/amount within a fixed
time frame under certain agreement.
-It is the first step in the formulation of
contract
What is tender notice?
-Tender notice is the information inviting bids
from competent contractors.
-It should be widely published in important daily
newspaper
Preparation before Tendering
-Desk study
-Survey
-Design, Drawing , and Specification
-Rate analysis and cost estimation
-Approval of budget
-Tender document/Bid document preparation
-Tender notice publication
Tender notice
• Tender notice is the information inviting bids from
competent contractors.
Essentials of Tender notice
Implementing Agency
Project Name
Notice No
First date of publication
Contract No
Description of work and location of work
Bid security/Earnest money deposit
Fee for Bid document
Office for buying bidding document and submit tender
Last date of submission of bid
Continue…………..
Bid opening date
Cost estimate of the project
Maximum no of partner in joint venture(JV)
Pre bid meeting
Date place and time for opening of the tender
Tender Document
Tender document/Bidding document is a
document prepared by the owner for
submission by bidders by filling up the price or
rate. tender document includes instruction to
bidders, specifications, drawing, design, terms
of reference, schedule of works, evaluation
criteria, bill of quantities, condition of contract
and similar other document.
Matters to be stated in bidding
documents:
Instruction to bidders(ITB)
Tender notice
Bid data sheet
Plan, Drawing of the proposed work
Bill of quantities(BOQ)
Quantity of goods
Work to be done by the bidder
Time of supplying goods, completing construction
work
Provision regarding warrantee and repair and
maintenance
Type and quantity of necessary Training and
supervision to be provided by the bidder
Provision that the goods or spare parts to be
supplied must be new and original
Source of financing required for proposed
procurement
Conditions of Contract
-Terms and conditions agreed by client and
contractor
-2 types
• General- Internationally accepted
• Special –specific to country/project
Prequalification
• Prequalification is carried out in advance of bidding to
establish a list of capable firms to be invited to tender while
ensuring that a proper level of competition is safeguard.
• In order to procure such construction work as determined
to be large and complex by the PPMO from time to time or
procure goods of high value such as industrial plants or
identify qualified bidders, a public entity shall, prior to
making invitation to tender, prepare prequalification
documents and public invite to proposals for determination
of prequalification.
• According to PPMO Prequalification is done for the
construction works greater than 2 crore.
Evaluation of bid
Substantially Responsive Bid: If all the relevant
Documents are present in the proposal/bid,
that is called Substantially responsive bid
-Clause 25 0f PPA 2063
A. Cost based selection: Lowest evaluated
substantially responsive bid is awarded the
contract in CBS
B. Quality and cost based selection
-Quality upto 90% and cost upto 10%
THANK YOU

More Related Content

What's hot

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
Muneesh Methwani
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
Pundlik Rathod
 

What's hot (20)

Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Epc contracts.
Epc contracts.Epc contracts.
Epc contracts.
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Contracts
ContractsContracts
Contracts
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Procurement system
Procurement systemProcurement system
Procurement system
 

Similar to Types of contracts

Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
jairam131
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
Timun Loh
 

Similar to Types of contracts (20)

contract procedure
contract procedurecontract procedure
contract procedure
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION05 Contract Management.pptx . DEFINITION
05 Contract Management.pptx . DEFINITION
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Unit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & ByelawsUnit 1-Contract Documents & Byelaws
Unit 1-Contract Documents & Byelaws
 
types-170309142854.pptx
types-170309142854.pptxtypes-170309142854.pptx
types-170309142854.pptx
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 
PROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptxPROJECT CONTRACTS.pptx
PROJECT CONTRACTS.pptx
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Project procuremenet contract in ethiopia
Project procuremenet contract in ethiopiaProject procuremenet contract in ethiopia
Project procuremenet contract in ethiopia
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Construction practices
Construction practicesConstruction practices
Construction practices
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
eeec ppt001.pptx
eeec ppt001.pptxeeec ppt001.pptx
eeec ppt001.pptx
 
3. Contract Pricing.pdf
3. Contract Pricing.pdf3. Contract Pricing.pdf
3. Contract Pricing.pdf
 

Recently uploaded

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Recently uploaded (20)

HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 

Types of contracts

  • 1. Chapter-5 Contract Management 5.1 Method of Work execution 5.2 Types of Contract 5.3 Tendering Process-Preparation before Tendering; Tender Notice; Tender Document; Conditions of Contract; Prequalification; Tender; Evaluation; Selection and Award
  • 2. 5.1 Method of Work execution Broadly any construction work can be executed through two methods: 1.Through amanat 2.Through contract 1.Through amanat: When the works are executed by the owner itself, by hiring workers and supplying materials and equipment, it is known as execution of work through Amanat. The record of labor employed each day and the part on which materials and equipment if any employed is maintained in book keeping. The record will also indicate the progress of work also. It is useful when the work is small and necessary to do immediately, and the expertise are available within the organization. It saves the cost required for making profit by the contractor and VAT also. It also keeps the staff busy in the work.
  • 3. 2.Through contract: Contract is an agreement between two or more parties to do or not to do any work. It is legal and time bound. Offer and acceptance must be there. Work Execution through Contract a)sealed competitive bidding i)International competitive bidding(ICB) ii)National/local competitive bidding(NCB/LCB) b)sealed Quotation c)Direct procurement d)users’ committee e)procurement under special circumstances
  • 4. a)sealed competitive bidding i) International competitive bidding(ICB): An international competitive bidding shall be invited on any of the following conditions : • Where the goods or construction works as requisitioned by a public entity are not available under competitive price from more than one construction entrepreneur or supplier within country. • In making invitation to national tender for the procurement of goods, construction works or other services, no tender is submitted and same has to be procured aboard.
  • 5. • Where foreign goods or construction works have to be procured from foreign assistance under an agreement enter into with a donor party. • Where the public entity certifies the goods or construction works, being of complex and special type, have to be procured by means of an international tender. • Notice on invitation to tender shall be published in English language an all tender or prequalification documents shall be published in English.
  • 6. • In publishing a notice a period of at least 45 days shall be given • Notice shall be published in daily newspaper of national circulation and it may also be published in any international communication media. • Notice shall be placed in website of concerned entity or that of the Public procurement Monitoring Office (PPMO)
  • 7. ii)National/local competitive bidding(NCB/LCB): Contractors are invited from within the nation or local.  For any procurement having cost estimate more than 10 Lakh for goods and other services, and more than 20 Lakh for works for which ICB is not required, NCB shall be preferred. • In publishing a notice a period of at least 30 days shall be given • Notice shall be published in daily newspaper of national circulation and it may also be published in any international communication media. • Notice shall be placed in website of concerned entity or that of the Public procurement Monitoring Office (PPMO)
  • 8. b)sealed Quotation: Procurement of works up to 20 lakh and Procurement of goods and other services up to 10 lakh can be carried out adopting sealed quotation. c)Direct procurement:Goods or Consultancy Services or Other services or construction work may be procured by means of direct procurement in the following circumstances: • The value of miscellaneous procurement does not exceed the prescribed threshold.  Goods or consultancy service or other service : Up to 3 Lakh  Construction work : Up to 5 Lakh
  • 9. d)users’ committee: This method is used for executing small labor intensive works where the objective is to: • Provide employment and income directly to persons living in the project area. • Increase the utilization of local know how, appropriate technologies and materials • Hand over the completed works for operation and maintenance directly by persons living in the project area. • When objective of project is to create employment which enhances the economy, quality or substantiality of beneficiary community then this method is used. Works up to 60 lakh may be carried out by community participation.
  • 10. e)procurement under special circumstances: • Emergency/ special circumstances. • Depends on contract amount
  • 11. 5.2 Types of Contract Types of Construction Contracts Two broad categories: • Price based - lump sum or unite rate contracts - price or rates are submitted by the contractor in his tender • Cost based - cost-reimbursable and target cost contract - actual cost incurred by the contractors is reimbursed(To compensate with payment ; especially, to repay money spent on one’s behalf), together with a fee for overheads and profit.
  • 12. Types of Contracts 1. Lump sum contract • A lump sum contract may be entered into for procuring a construction work such as ground water pipeline installation, the quantities of which are difficult to measure or a construction work such as superstructure of a bridge, the quantities of which can be measured. • Such contract shall specify that the construction entrepreneur shall be responsible for all types of risks and liabilities associated with the construction work
  • 13. • Provided that if the financial liabilities of the construction entrepreneur increases as a consequence of an order issued by the public entity that involves any change in the construction work after the commencement of work upon making the contract, the public entity shall bear the liabilities. • Sometimes called Drawings and Specifications Contract
  • 14. Advantages of Lump Sum Contract • The final price is known, by the owner, before the work commences. • The contractor has more incentive to reduce his cost to increase the profit. • The contractor hopes to complete the job as quickly as possible, to minimize overhead, to maximize profit and to move to the next Job.
  • 15. Disadvantages of Lump Sum Contract • Changes in drawings and specifications can be very expensive and source of trouble. In other words the contract has very limited flexibility for design changes. • The contractor carries much of the risks. The tendered price may include high risk contingency. • Competent contractors may decide not to bid to avoid a high-risk lump sum contract.
  • 16. 2. Unit Price (BOQ) contract • Unit price contract may be entered into where the quantity of a construction work is difficult to be ascertained or where construction work is to be procured on the basis of unit price set forth in the bill of quantity. • The bidder has to include in such unit price the materials, labor and the other matters required to complete the proposed construction work. • In making payment for work done under this contract, the public entity shall make such payment on the basis of the unit of work actually done and measured in the field.
  • 17. Advantages of unit price contract • Fair basis for competition. • In comparing with lump-sum contract,  Changes in contract documents can be made easily by the owner.  Lower risk for contractor. Disadvantages of Unit Price Contract • The exact final price of the project is not known to the owner until the completion of the project. • Upto date account and record keeping is necessary • Possibility of submitting unbalanced bid
  • 18. 3.Cost Reimbursable Contract • A cost reimbursable contract may be entered into for procuring a construction work involving high risk and unpredictable conditions, when it is likely that a construction entrepreneur would refuse to, or be unable to, perform the work under a unit price contract. • While making payment to construction entrepreneur for the construction work procured under this contract, such payment may include the costs actually incurred by that entrepreneur, overheads of that work plus profit set forth in the approved cost estimate.
  • 19. Advantages of Cost Reimbursement Contract • Start construction without waiting for the whole set of drawings and specifications. • More flexibility for the owner to make changes as work progresses. • Draw the contractor expertise during design. Disadvantages of Cost Reimbursement Contract • It is difficult to predict the final cost and the distribution of it, which may cause financial problems to the owner. • Contractor pays less attention to cost control.
  • 20. 4.Design and build contract(turn key contract): • A design and build contract may be entered for procuring the design and build of any construction from the same entrepreneur. • The work set forth in this contract shall commence only after the public entity has through its technician or group of technicians examined and approved the design of construction work. • In a design/build contract, the owner enters into a single agreement by which the design and build contractor agrees to perform both the design and construction of the project. • As well as being responsible for faulty workmanship in construction, the contractor is also liable for any deficiencies in design under this arrangement. • A Design build contract is usually the preferred contracting method under tight schedule circumstances, and it is intended to save time.
  • 21. – Advantages • In conventional type of contract, incase of damage/failure of structure, it is often difficult to determine whether such damage/failure is due to design fault or construction (quality) fault; which arises disputes between owner and contractor Such situation is reduced in design/build contract as both responsibility is of contract. • Because the owner warrants the sufficiency of the plans in a conventional construction contract, he is liable for any increased costs because of defective or inadequate plans. But in a design/build contract, the contractor is then unable to look to the owner for additional compensation.
  • 22. • In design/build contract the project can often be completed within a shorter period of time than with the traditional three-party arrangement. • Since a design/build project can be designed and constructed in phases, the contractor is able to order necessary materials for subsequent phases ahead of time perhaps at a reduced cost. • Contractor’s control over design details allows the contractor to use familiar construction methods and processes in building the structure, with the result of much more efficient construction. These savings ultimately benefit the owner.
  • 23. – Disadvantages • For owner it is often difficult to effectively compare the various preliminary design proposals submitted by design/build contractors. The designs will probably not be uniform because there are usually many different methods of satisfying the owner’s general needs and performance specifications. • The owner’s input on the detailed design of the structure will be limited because the contractor, rather than the owner, is responsible for furnishing the design work. As a result, the finished structure may not be exactly as the owner envisioned. This can lead to later disputes. • The owner may not obtain the lowest cost for the project since the design/build contract is usually entered into by negotiation rather than competitive bidding. • There is only limited scope for the client to make changes to his requirements once the client's requirements (i.e. Inflexibility) and contractor's proposals have been agreed otherwise the cost consequences may be prohibitive. • The client has less control and influence over design matters due to which quality may be impaired.
  • 24. BOOT, BOT Contract • BOOT (build, own, operate, transfer) is a public- private partnership (PPP) project model in which a private organization conducts a large development project under contract to a public-sector partner, such as a government agency. A BOOT project is often seen as a way to develop a large public infrastructure project with private funding. BOOT model • The public-sector partner contracts with a private developer - typically a large corporation or consortium of businesses with specific expertise - to design and implement a large project.
  • 25. • The public-sector partner may provide limited funding or some other benefit (such as tax exempt status) but the private-sector partner assumes the risks associated with planning, constructing, operating and maintaining the project for a specified time period. • The private partner builds a facility to the specification agreed by the public agency. • Government retains strategic control over the project. • During the specified period called concession period, the developer charges customers who use the infrastructure that's been built to realize a profit.
  • 26. • At the end of concession period, the private- sector partner transfers ownership to the funding organization, either freely or for an amount stipulated in the original contract (generally to fulfill viability gap). Such contracts are typically long-term; usually 20-30 years. • BOOT is sometimes known as BOT (build, own, transfer). • Variations on the BOOT model include BOO (build, own, operate), BLT (build, lease, transfer) and BLOT (build, lease, operate, transfer), BTO (Build, transfer, operate), LOT (Lease, operate, transfer), DOT (develop, operate, transfer) etc.
  • 27. Advantages • The majority of construction and long-term operating risk can be transferred onto the BOOT provider. • The scheme is not constrained through a lack of funding, a lack or expertise or project management capability. Also, there are strong financial incentives for the BOOT operator to complete the construction and get the scheme operational as soon as possible. • Project completes on time. • BOOT operators are experienced with management and operation of infrastructure assets and bring these skills to the scheme.
  • 28. • Accountability for the asset design, construction and service delivery is very high given that if the performance targets are not met, the operator stands to lose a portion of capital expenditure, capital profit, operating expenditure and operating profit. • Corporate structuring issues and costs are minimal within a BOOT model, as project funding, ownership and operation are the responsibility of the BOOT operator. These costs will however be built into the BOOT project pricing.
  • 29. Disadvantages • BOOT is likely to result in a higher cost to end users. Because the private investor is interested to profit. • Not useful for projects which has low economic return. • Community users may have a negative reaction to private sector involvement in the scheme, particularly if the private sector is an overseas owned company. • Management and monitoring of the service level can be time consuming and resource hungry. Procedures need to be in place to allow users to assess service performance and penalize the BOOT operator where necessary.
  • 30. 5.3 Tendering Process-Preparation before Tendering; Tender Notice; Tender Document; Conditions of Contract; Prequalification; Tender; Evaluation; Selection and Award
  • 31. What is Tender? -Tender is a written offer/proposal by the tenderer (the person who offer the tender) to perform the work or to supply some specified goods at a certain rate/amount within a fixed time frame under certain agreement. -It is the first step in the formulation of contract
  • 32. What is tender notice? -Tender notice is the information inviting bids from competent contractors. -It should be widely published in important daily newspaper
  • 33.
  • 34. Preparation before Tendering -Desk study -Survey -Design, Drawing , and Specification -Rate analysis and cost estimation -Approval of budget -Tender document/Bid document preparation -Tender notice publication
  • 35. Tender notice • Tender notice is the information inviting bids from competent contractors. Essentials of Tender notice Implementing Agency Project Name Notice No First date of publication Contract No Description of work and location of work Bid security/Earnest money deposit Fee for Bid document Office for buying bidding document and submit tender Last date of submission of bid
  • 36. Continue………….. Bid opening date Cost estimate of the project Maximum no of partner in joint venture(JV) Pre bid meeting Date place and time for opening of the tender
  • 37. Tender Document Tender document/Bidding document is a document prepared by the owner for submission by bidders by filling up the price or rate. tender document includes instruction to bidders, specifications, drawing, design, terms of reference, schedule of works, evaluation criteria, bill of quantities, condition of contract and similar other document.
  • 38. Matters to be stated in bidding documents: Instruction to bidders(ITB) Tender notice Bid data sheet Plan, Drawing of the proposed work Bill of quantities(BOQ) Quantity of goods Work to be done by the bidder Time of supplying goods, completing construction work Provision regarding warrantee and repair and maintenance
  • 39. Type and quantity of necessary Training and supervision to be provided by the bidder Provision that the goods or spare parts to be supplied must be new and original Source of financing required for proposed procurement
  • 40. Conditions of Contract -Terms and conditions agreed by client and contractor -2 types • General- Internationally accepted • Special –specific to country/project
  • 41. Prequalification • Prequalification is carried out in advance of bidding to establish a list of capable firms to be invited to tender while ensuring that a proper level of competition is safeguard. • In order to procure such construction work as determined to be large and complex by the PPMO from time to time or procure goods of high value such as industrial plants or identify qualified bidders, a public entity shall, prior to making invitation to tender, prepare prequalification documents and public invite to proposals for determination of prequalification. • According to PPMO Prequalification is done for the construction works greater than 2 crore.
  • 42. Evaluation of bid Substantially Responsive Bid: If all the relevant Documents are present in the proposal/bid, that is called Substantially responsive bid -Clause 25 0f PPA 2063 A. Cost based selection: Lowest evaluated substantially responsive bid is awarded the contract in CBS B. Quality and cost based selection -Quality upto 90% and cost upto 10%