Sample Final Test with-KEY

Multiple Choice
Identify the letter of the choice that best completes the statement or answers the question.

____    1. Outputs of organizational planning are:
           a. Project organization chart
           b. Staffing management plan
           c. Project template
           d. All of the above
____    2. A(n) ____ event is a specific, uncertain event that may occur to the detriment or enhancement of the project.
           a. chance                                          c. unplanned
           b. risk                                            d. hidden
____    3. The final output of the seller selection process is a ____.
           a. bid                                             c. charter
           b. contract                                        d. proposal
____    4. Key outputs in project human resource management include ____ updates and team performance assessment.
           a. project                                         c. program
           b. staffing                                        d. portfolio
____    5. Scope verification:
           a. Is the formal acceptance of the project scope by the stakeholders
           b. Refers to the final project report describing the project at completion
           c. Is not necessary if the project competes on time and on budget
           d. Occurs only when revisions or change orders are made to the project
____    6. Slack or ____ is the amount of time an activity may be delayed without delaying a succeeding activity or the
           project finish date.
           a. leeway                                          c. redundancy
           b. float                                           d. space
____    7. The goal of ____ control is to know the status of the schedule, influence the factors that cause schedule
           changes, determine whether the schedule has changed, and manage changes when they occur.
           a. time                                            c. cost
           b. schedule                                        d. scope
____    8. Which of the following portfolio management tasks should occur first?
           a. prioritize projects on a list                   c. divide projects into investment categories
           b. put all projects into one list                  d. put all projects in one list
____    9. Two tools to assist in contract closure are ____ audits and a records management system.
           a. dispatch                                        c. procurement
           b. supply                                          d. acquisition
____   10. Which of the following is not a true statement about control charts?
           a. Control charts can be used to establish as well as maintain process control
           b. Control charts are used to determine acceptance limits when no limits are stipulated by the
               product specification; otherwise, one should use the limits dictated by the specification
           c. All data points outside the control chart limits are variations explained by assignable
               causes
           d. b and c
____   11. Under which risk register heading would you list cost overruns on early activities, which might be
           symptomatic of a poor cost estimate?
           a. The impact to the project if the risk event occurs
b. Triggers for each risk event
           c. The probability of the risk event occurring
           d. The status of the risk event
____ 12.   Cost of quality is:
           a. The expense of nonconformance to requirements and specifications
           b. The direct responsibility of the project team members
           c. The expense of conformance to requirements and specifications
           d. a and c
____ 13.   The term ―____‖ is used to describe each level of work in the WBS.
           a. activity                                      c. task
           b. module                                        d. node
____ 14.   A stakeholder ____ provides information on key stakeholders to help manage relationships with them.
           a. study                                         c. analysis
           b. charter                                       d. guide
____ 15.   A parametric cost estimate:
           a. Is a bottom up estimating technique
           b. Is a top down estimating technique
           c. Is a statistical estimating technique
           d. b and c
____ 16.   Some projects have a senior manager called a(n) ____ who acts as a key proponent for a project.
           a. champion                                      c. sponsor
           b. coach                                         d. advocate
____ 17.   ____ contracts reduce the risk of incurring higher costs than expected.
           a. Variable-price                                c. Oral
           b. Bid                                           d. Fixed-price
____ 18.   Cost ____ involves allocating the overall cost estimate to individual tasks over time to establish a baseline for
           measuring performance.
           a. estimating                                    c. allowance
           b. account                                       d. budgeting
____ 19.   An organization should consider only projects with a ____ NPV if financial value is a key criterion for project
           selection.
           a. positive                                      c. zero
           b. negative                                      d. well-defined
____ 20.   Because many projects fail due to unclear requirements and expectations, starting with a project ____ makes
           sense.
           a. charter                                       c. vision statement
           b. contract                                      d. compact
____ 21.   What is the PERT weighted average based on an optimistic estimate of 6 days, a most likely estimate of 8
           days, and a pessimistic time of 12 days?
           a. 6                                             c. 11
           b. 8                                             d. 12
____ 22.   Project ____ management includes acquiring or procuring goods and services for a project from outside the
           organization.
           a. logistics                                     c. acquisition
           b. procurement                                   d. supply
____ 23.   The main monitoring and controlling task performed as part of project cost management is ____ control.
           a. time                                          c. scope
           b. schedule                                      d. cost
____ 24. Projects should first and foremost address business ____.
         a. portfolios                                   c. needs
         b. ventures                                     d. practices
____ 25. ____ are the results of applying capabilities.
         a. Outcomes                                     c. Effects
         b. Events                                       d. Impressions
____ 26. Poor scope definition may cause all but:
         a. Higher project costs
         b. Rework
         c. Increased productivity
         d. Low morale
____ 27. Contract updates are often made by having both parties—the buyer and the seller—sign a(n) ____ to the
         contract.
         a. addendum                                     c. alteration
         b. revision                                     d. appendix
____ 28. The main outputs of the quality control process are:
         a. Pareto diagram, acceptance decisions, and process adjustments
         b. Bar charts, network diagrams, and rework
         c. Acceptance decisions, rework, and process adjustments
         d. Acceptance decisions, performance indicators, and rework
____ 29. Quality management deals with the following except:
         a. Conformance to requirements and specifications
         b. Satisfying the needs of the customer
         c. Making the product more desirable and luxurious
         d. a and c
____ 30. Which type of contract provides the highest rank to the owner (buyer)?
         a. Cost plus percentage of cost
         b. Cost plus fixed fee
         c. Firm fixed price
         d. Fixed price incentive
____ 31. Project management ____ facilitate communication among stakeholders and provide a baseline for progress
         measurement and project control.
         a. charters                                     c. contracts
         b. plans                                        d. compacts
____ 32. A(n) ____ cause is the real or underlying reason a problem occurs.
         a. secondary                                    c. envisioned
         b. indirect                                     d. root
____ 33. ____ estimates involve estimating individual activities and summing them to get a project total.
         a. Bottom-up                                    c. Ad hoc
         b. Provisional                                  d. Temporary
____ 34. After a project is approved, senior managers should meet to determine the ____, time, and cost constraints for
         the project.
         a. range                                        c. vision
         b. scope                                        d. boundary
____ 35. Which of the following is a category under portfolio best practices?
         a. Project initiation process standardization
         b. Project plan development process measurement
         c. Portfolio risk management planning process improvement.
         d. Project scope definition process improvement
____ 36. Project management software uses the ____ format to represent the WBS.
         a. tabular                                        c. flexible
         b. binary                                         d. chart
____ 37. The overall duration of the project schedule is not influenced by:
         a. Using mandatory dependencies as constraints
         b. Using discretionary dependencies as constraints
         c. The capabilities of the resources which are assigned to perform the work
         d. Using the arrow diagramming method instead of the precedence diagramming method
             (PDM) of scheduling
____ 38. In an AOA network diagram, a(n) ____ occurs when two or more nodes precede a single node.
         a. merge                                          c. union
         b. join                                           d. intersection
____ 39. The main output of scope planning is a ____ management plan, which is a document that includes
         descriptions of how the team will prepare the scope statement, create the WBS, verify completion of the
         project deliverables, and control requests for changes to the project scope.
         a. scope                                          c. program
         b. project                                        d. portfolio
____ 40. If you want to praise a project team member for doing a good job, a(n) ____ would most likely want everyone
         to hear about her good work.
         a. introvert                                      c. recluse
         b. extrovert                                      d. loner
____ 41. According to Douglas McGregor, people who believe in Theory ____ assume that workers dislike and avoid
         work if possible, so managers must use coercion, threats, and various control schemes to get workers to make
         adequate efforts to meet objectives.
         a. W                                              c. Y
         b. X                                              d. Z
____ 42. In a(n) ____, each bar represents an attribute or a characteristic of a problem or situation, and the height of the
         bar represents its frequency.
         a. run chart                                      c. histogram
         b. control chart                                  d. scatter diagram
____ 43. The main monitoring and controlling task performed as part of project time management is ____ control.
         a. document                                       c. schedule
         b. employee                                       d. scope
____ 44. Which of the following are considered to be milestones?
         a. Project completion date
         b. Contract date
         c. Key event completion date
         d. All of the above
____ 45. Project ____ management involves coordinating all the project management knowledge areas throughout a
         project’s life span.
         a. union                                          c. unification
         b. synthesis                                      d. integration
____ 46. The main procurement management task performed to monitor and control projects is administering the ____.
         a. vision plan                                    c. charter
         b. contract                                       d. project platform
____ 47. A(n) ____ histogram is a column chart that shows the number of resources required for or assigned to a
         project over time.
         a. resource                                       c. allocation
         b. requirements                                   d. assignment
____ 48. Quality assurance:
         a. Refers to the prevention of product defects
         b. Is an auditing function that provides feedback to the project team and client about the
             quality of the output being produced
         c. Is the technical process that includes the construction of control charts, which specify the
             acceptability limits for conforming output
         d. a and b
____ 49. Blake and Mouton (1964) delineated ____ basic modes for handling conflicts.
         a. four                                           c. six
         b. five                                           d. seven
____ 50. Project time management involves the following main processes:
         a. Activity definition, duration estimating, and schedule development
         b. Activity definition, sequencing, duration estimating, schedule development, and control
         c. Activity identification, sequencing, duration estimating, schedule development, and
             control
         d. Activity definition, sequencing, and schedule control
____ 51. ____ includes the actual amount of time spent working on an activity plus elapsed time.
         a. Extension                                      c. Period
         b. Duration                                       d. Length
____ 52. What method is used to communicate staffing requirements to the organization?
         a. Gantt chart
         b. Staffing plan
         c. Responsibility matrix
         d. Project objective statement
____ 53. The main purpose of project planning is to guide project ____.
         a. initiation                                     c. review
         b. execution                                      d. evaluation
____ 54. Two key outputs of performance reporting are performance reports and ____.
         a. forecasts                                      c. retrospectives
         b. cost-benefit analyses                          d. performance reviews
____ 55. Weights may be established by assigning percentages or ____.
         a. results                                        c. scores
         b. values                                         d. points
____ 56. Many maturity models have five levels, with level one describing characteristics of the least organized or least
         mature organizations, and level ____ describing the characteristics of the most organized and most mature
         organizations.
         a. two                                            c. four
         b. three                                          d. five
____ 57. Which of the following is not a characteristic of a ―work package‖?
         a. It is a task at the lowest level of any branch of the WBS
         b. It is a summary task at the top level of the WBS
         c. It consists of manageable units of work that can be planned, budgeted, scheduled, and
             controlled
         d. It usually contains no more than 80 work hours (effort) to complete
____ 58. Contract ____ includes the contract itself along with requested unapproved contract changes and approved
         change requests.
         a. authorization                                  c. documentation
         b. review                                         d. negotiation
____ 59. Network diagrams are good for depicting:
a. Slack time
           b. Schedule start and finish dates
           c. Plan versus actual schedule
           d. Task dependencies
____ 60.   Project teams sometimes use ____—unplanned responses to risk events—when they do not have contingency
           plans in place.
           a. work charts                                     c. work processes
           b. work flows                                      d. workarounds
____ 61.   Suppose that the purchase price for a piece of equipment is $10,000, and incurs operational costs of $300 per
           day. If the same equipment can be leased for $500 per day and you need the equipment for ____ days, it
           would be more economical to lease the equipment.
           a. 30                                              c. 80
           b. 60                                              d. 100
____ 62.   The project manager should work with his or her team and ____ to determine the level of detail needed in the
           WBS dictionary.
           a. client                                          c. auditor
           b. customer                                        d. sponsor
____ 63.   Under which risk register heading would you list a defective product, poor survey results, reduced consulting
           costs, or good publicity?
           a. An identification number for each risk event
           b. A rank for each risk event
           c. The name of the risk event
           d. A description of the risk event
____ 64.   In the context of earned value management, ____ are calculated by subtracting the actual cost or planned
           value from EV, and indexes are calculated by dividing EV by the actual cost or planned value.
           a. fluctuations                                    c. variances
           b. valuations                                      d. deviations
____ 65.   A(n) ____ scoring model is a tool that provides a systematic process for selecting projects based on many
           criteria.
           a. weighted                                        c. variable
           b. biased                                          d. opportunity
____ 66.   Earned value management involves calculating ____ values for each activity or summary activity from a
           project’s WBS.
           a. three                                           c. five
           b. four                                            d. six
____ 67.   The main planning tasks performed as part of project scope management include scope planning, scope
           definition, and ____.
           a. scope evaluation                                c. creating the WBS
           b. scope reduction                                 d. scope expansion
____ 68.    ―Earned value‖ can best be defined as:
           a. The value of the equipment that has been installed as of the data date
           b. The sum of the labor costs that have been incurred on the project to date
           c. A method of measuring the amount of money that has been spent to date
           d. The actual cost of work performed (ACWP) minus the budgeted cost of work performed
                (BCWP)
____ 69.   If a project’s stakeholders are not satisfied with the quality of the project management or the resulting
           products, the project team will need to adjust ____, time, and cost to satisfy stakeholder needs and
           expectations.
           a. range                                           c. vision
b. breadth                                         d. scope
____ 70.   Which technique shows external dependencies best?
           a. Activity on arrow diagramming
           b. Activity on node diagramming
           c. PERT diagramming
           d. None of the above
____ 71.   After deciding which projects to pursue, organizations need to decide if it is advantageous to manage several
           projects together as part of a(n) ____.
           a. aggregate                                       c. cluster
           b. program                                         d. group
____ 72.   Which of the following actions will most likely improve team productivity?
           a. Ensure that social events are mandatory and include a business-related goal.
           b. Expand the size of work teams to over seven members.
           c. Reduce the amount of attention paid to virtual team members.
           d. Acknowledge individual and group accomplishments.
____ 73.   There are ____ important dimensions of risk events.
           a. two                                             c. four
           b. three                                           d. five
____ 74.   Project Communication management is divided into:
           a. Communication requirements, information distribution, performance reporting, and
               administrative procedure
           b. Communications planning, information distribution, performance reporting, and
               administrative closure
           c. Communications planning, response planning, progress reporting, and information
               distribution
           d. Communications planning, information distribution, schedule reporting, and stakeholder
               analysis
____ 75.   By adding all of the ____ for all project activities, you can determine how the project as a whole is
           performing and forecast both when it will be completed and how much it will cost at completion.
           a. earned values                                   c. planned values`
           b. actual costs                                    d. cost variances
____ 76.   Tools included in overall change control are:
           a. Configuration management
           b. Performance measurement
           c. Project management information system
           d. All of the above
____ 77.   The PMBOK® Guide lists at least ____ documents that project teams can produce as part of project planning.
           a. 50                                              c. 100
           b. 75                                              d. 125
____ 78.   A project portfolio ____ map compares relative value to project risk.
           a. venture                                         c. risk
           b. viability                                       d. value
____ 79.   A change control board is:
           a. An informal or formal group of team members responsible for changes to a project
           b. A formal group of people responsible for approving or rejecting changes to the project
               baselines
           c. The project manager and several key team members working to ensure cost and schedule
               control during the life of the project
           d. An informal group that has oversight of project implementations
____ 80. A three-point estimate is an estimate that includes a(n) ____, most likely, and pessimistic estimate, such as
         three weeks, four weeks, and five weeks, respectively.
         a. optimistic                                     c. remote
         b. unusual                                        d. conditional
____ 81. In a software project, the planned value (PV) was 80,000, the earned value (EV) was 75,000 and the actual
         cost (AC) was 71,000, what is the cost performance index?
         a. –0.947
         b. 0.947
         c. 0.937
         d. 1.056
____ 82. Risk reassessment, risk audits, variance and trend analysis, technical performance measurements, reserve
         analysis, and status meetings or periodic risk reviews are all tools and techniques for performing ____
         monitoring and control.
         a. scope                                          c. cost
         b. risk                                           d. quality
____ 83. Performance in meeting project scope goals is based on the scope ____.
         a. definition                                     c. baseline
         b. revision                                       d. statement
____ 84. The major processes of project risk management are:
         a. Plan response, identify, document, and assess
         b. Identify, mitigate, and plan response
         c. Respond, evaluate, and document
         d. Identify, quantify, develop response, and control
____ 85. Project integration management includes ____ processes.
         a. two                                            c. seven
         b. four                                           d. nine
____ 86. A risk management plan should cover:
         a. Who is responsible for managing various areas of risk
         b. How contingency plans will be implemented
         c. How reserves will be allocated
         d. All of the above
____ 87. To ____ a project, you must finalize all activities and transfer the completed or canceled work to the
         appropriate people.
         a. close                                          c. audit
         b. initiate                                       d. assess
____ 88. After assigning weights for the criteria and scores for each project, you calculate a weighted score for each
         project by multiplying the weight for each criterion by its score and ____ the resulting values.
         a. multiplying                                    c. dividing
         b. adding                                         d. subtracting
____ 89. According to David McClelland, people with a high need for ____ desire harmonious relationships with other
         people and need to feel accepted by others.
         a. isolation                                      c. affiliation
         b. assurance                                      d. solitude
____ 90. ____ estimates, also called top-down estimates, use the actual cost of a previous, similar project as the basis
         for estimating the cost of the current project.
         a. Homologous                                     c. Sequential
         b. Analogous                                      d. Parallel
____ 91. A project manager must be sure to check with his organization to find out its guidelines for when discounting
         starts, what discount rate to use, and what ____ the organization prefers.
a. charts                                          c. format
            b. technique                                       d. results
____ 92.    Scope statements should include, at a minimum, a description of the project, including its overall objectives
            and justification; detailed descriptions of all project ____; characteristics and requirements of products and
            services produced as part of the project; and project success criteria.
            a. stakeholders                                    c. meetings
            b. volunteers                                      d. deliverables
____ 93.    A common way to summarize work performance information is by using a(n) ____ report.
            a. performance                                     c. projection
            b. milestone                                       d. evaluation
____ 94.    ____ risk events might include the performance failure of a product produced as part of a project, delays in
            completing work as scheduled, increases in estimated costs, supply shortages, litigation against the company,
            and strikes.
            a. Negative                                        c. Calculated
            b. Hidden                                          d. Countervailing
____ 95.    How many communication channels do 12 people require?
            a. 12                                              c. 36
            b. 24                                              d. 66
____ 96.    ____ dependencies involve relationships between project and nonproject activities.
            a. Internal                                        c. Ancillary
            b. External                                        d. Miscellaneous
____ 97.    Project integration management includes the following processes:
            a. Scope planning
            b. Scope definition
            c. Scope verification
            d. Integrated change control
____ 98.    The cost of providing a work space for project workers, office furniture, electricity, and a cafeteria are ____
            costs.
            a. direct                                          c. indirect
            b. explicit                                        d. incidental
____ 99.    A process for handling changes should be defined during project ____ as part of the project management plan.
            a. deployment                                      c. execution
            b. initiation                                      d. planning
____ 100.   The main executing tasks performed as part of project ____ include requesting seller responses and selecting
            sellers.
            a. procurement                                     c. initiation
            b. planning                                        d. monitoring
____ 101.   The PMBOK Guide® is a ____ that describes best practices for what should be done to manage a project.
            a. rule book                                       c. protocol
            b. standard                                        d. secondary authority
____ 102.   A cost baseline is a(n) ____ budget that project managers use to measure and monitor cost performance.
            a. incidental                                      c. time-phased
            b. basic                                           d. incremental
____ 103.   Suppose that after one week of work, the earned value is $4000 and the planned value is $5000. What is the
            value of the schedule performance index (SPI)?
            a. 75%                                             c. 120%
            b. 80%                                             d. 125%
____ 104.   A request for quote (RFQ) differs from a request for proposal (RFP) in that:
a. RFQs generally ask for innovative processes
            b. RFPs generally ask for guaranteed maximum prices
            c. RFQs generally ask for a lump sum price
            d. RFPs generally ask for technical skills and implementation approach
____ 105.   Projects that address competitive ____ are much more likely to be successful because they will be important
            to the organization’s competitive position.
            a. value                                           c. tactics
            b. products                                        d. strategy
____ 106.   Which of the following is a common problem encountered during project execution?
            a. Communications are good.
            b. The project sponsor and/or other senior managers are very supportive of the project.
            c. The project objectives/scope are clear.
            d. People working on the project are incompetent or unmotivated.
____ 107.   Which of the following methods best helps a project manager identify and learn about key project
            stakeholders?
            a. questioning acquaintances                       c. consulting biographies
            b. reviewing organizational charts                 d. performing Internet searches
____ 108.   After defining project activities, the next step in project time management is activity ____.
            a. organization                                    c. segmenting
            b. sequencing                                      d. ordering
____ 109.   A quality ____ is a structured review of specific quality management activities that helps identify lessons
            learned, which could improve performance on current or future projects.
            a. survey                                          c. audit
            b. overview                                        d. assessment
____ 110.   The scope statement should not include:
            a. Project justification
            b. Project deliverables
            c. Project objectives
            d. Project budget
____ 111.   Three primary methods for determining the projected financial value of projects include net present value
            analysis, return on investment, and ____ analysis.
            a. growth                                          c. environmental impact
            b. payback                                         d. efficiency
____ 112.   The main human resource management task performed as part of monitoring and controlling a project is
            managing the project ____, which, of course, is no small task.
            a. sponsors                                        c. team
            b. clients                                         d. supplies
____ 113.   Under which risk register heading would you list identification of a defective hard drive as the source of a
            computer defect?
            a. The category under which the risk event falls
            b. The risk owner, or person who will own or take responsibility for the risk event
            c. Potential responses to each risk event
            d. The root cause of the risk event
____ 114.   Duration estimates are provided as a ____ number, such as four weeks; as a range, such as three to five
            weeks; or as a three-point estimate.
            a. continuous                                      c. fractional
            b. random                                          d. discrete
____ 115.   Examples of common ____ used by organizations include failure rates of products produced, availability of
            goods and services, and customer satisfaction ratings.
a. metrics                                        c. requirements
            b. analytics                                      d. guidelines
____ 116.   According to the research of Fast Company, which of the following is one of the three top reasons that people
            voluntarily leave their job?
            a. They are learning too many new things.         c. They do not feel they make a difference.
            b. They are growing into their position.          d. They get proper recognition.
____ 117.   A best practice is ―a(n) ____ way recognized by industry to achieve a stated goal or objective.‖
            a. optimal                                        c. targeted
            b. suboptimal                                     d. inefficient
____ 118.   Which of the following topics could you expect to find in a procurement management plan?
            a. methodology for risk management
            b. guidelines on types of contracts to be used in different situations
            c. budget and schedule estimates for risk-related activities
            d. risk categories
____ 119.   A(n) ____ log is a tool used to document and monitor the resolution of project issues.
            a. event                                          c. problem
            b. issue                                          d. running
____ 120.   Based on the implementation of quality-control measurements, ____ adjustments often result in updates to the
            quality baseline, organizational process assets, and the project management plan.
            a. contract                                       c. process
            b. quality                                        d. project
____ 121.   The main disadvantage of ____ is that it can end up lengthening the project schedule, because starting some
            tasks too soon often increases project risk and results in rework.
            a. reviewing                                      c. extending
            b. crashing                                       d. fast tracking
____ 122.   A ____ contract has the least amount of risk for the buyer.
            a. firm -fixed price                              c. soft-fixed-price
            b. fixed-price incentive                          d. contingent-fixed
____ 123.   A(n) ____ is a document in which sellers describe what they will do to meet the requirements of a buyer.
            a. proposal                                       c. schedule
            b. charter                                        d. draft
____ 124.   PMI defines a project ____ as an uncertainty that can have a negative or positive effect on meeting project
            objectives.
            a. hazard                                         c. risk
            b. danger                                         d. challenge
____ 125.   In the context of monitoring and controlling tasks for project quality management, ____ decisions determine
            if the products or services produced as part of the project will be accepted or rejected.
            a. acceptance                                     c. rework
            b. rejection                                      d. redesign
____ 126.   In general, the majority of a project’s time and budget is spent on project ____.
            a. planning                                       c. review
            b. execution                                      d. duplication
____ 127.   Activity ____ provide schedule-related information about each activity, such as predecessors, successors,
            logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions
            related to the activity.
            a. features                                       c. properties
            b. characteristics                                d. attributes
____ 128.   In an AOA network diagram, ____ occur when two or more activities follow a single node.
a. drives                                         c. bursts
            b. flares                                         d. runs
____ 129.   What method(s) is(are) available to the project manager for short listing contractor proposals?
            a. Comparing proposals against independent estimates
            b. Weighing systems
            c. Subjective screening systems
            d. All of the above
____ 130.   In a software project, the planned value (PV) was 80,000, the earned value (EV) was 75,000 and the actual
            cost (AC) was 71,000, what is the cost variance (CV)?
            a. –4,000
            b. +4,000
            c. +9,000
            d. –9,000
____ 131.   According to Frederick Herzberg, a(n) ____ factor is a basic necessity, such as air-conditioning during hot
            weather.
            a. motivational                                   c. environmental
            b. hygiene                                        d. incidental
____ 132.   ____ should be formed and continuously updated to help the organization as a whole make better strategic
            decisions.
            a. Monitors                                       c. Projects
            b. Portfolios                                     d. Programs
____ 133.   In the context of earned value management, the ____ cost is the total direct and indirect costs incurred in
            accomplishing work on an activity during a given period.
            a. real                                           c. actual
            b. estimated                                      d. projected
____ 134.   ____ motivation causes people to do something for a reward or to avoid a penalty.
            a. Derived                                        c. Extrinsic
            b. Intrinsic                                      d. Primary
____ 135.   When using the ____ mode to resolve conflicts, the project manager de-emphasizes or avoids areas of
            differences and emphasizes areas of agreement.
            a. adversarial                                    c. antagonistic
            b. dialectic                                      d. smoothing
____ 136.   Which of the following is not a selection criteria for choosing a new project?
            a. Risk
            b. Rate of return
            c. In-house personnel available
            d. Competition’s out-sourcing method
____ 137.   The cost performance index (CPI) is:
            a. Earned value divided by actual cost
            b. Actual cost divided by earned value
            c. Earned value divided by planned value
            d. Planned value to date times percent complete
____ 138.   The project is considered on schedule if:
            a. Schedule variance (SV) is negative
            b. Cost variance (CV) is positive
            c. Schedule performance index (SPI) is one or 100 percent
            d. Earned value (EV) is positive
____ 139.   Project ____ management ensures that the project will satisfy the stated or implied needs for which it was
            undertaken.
a. integration                                       c. portfolio
            b. quality                                           d. performance
____ 140.   ____ development uses the results of all the preceding project time management processes to determine the
            start and end dates of project activities and of the entire project.
            a. Task                                              c. Work Package
            b. Schedule                                          d. Activity
____ 141.   A ____ is a product or service produced or provided as part of a project.
            a. process                                           c. deliverable
            b. result                                            d. requirement
____ 142.   The approved time estimate for a project can be divided by the ____ performance index to calculate when the
            project will be completed.
            a. cost                                              c. price
            b. schedule                                          d. itinerary
____ 143.   The ____ mode can be viewed as the win-lose approach to conflict resolution.
            a. forcing                                           c. negotiating
            b. compromising                                      d. bargaining
____ 144.   Which of the following is a key output of project procurement management?
            a. quality metrics                                   c. contract statements of work
            b. quality checklists                                d. project Web site
____ 145.   ____ risk events include completing work sooner than planned or at an unexpectedly reduced cost,
            collaborating with suppliers to produce better products, and obtaining good publicity from the project.
            a. Collaborative                                     c. Anticipated
            b. Positive                                          d. Probable
____ 146.   You calculate cash ____ by subtracting costs from benefits, or expenses from income.
            a. flow                                              c. budgets
            b. statements                                        d. structure
____ 147.   The main monitoring and controlling tasks performed as part of project ____ management are scope
            verification and scope control.
            a. integration                                       c. cost
            b. scope                                             d. time
____ 148.   It is helpful to create a ____, or initial, scope statement during project initiation so that the entire project team
            can start important discussions and work related to the project scope.
            a. tentative                                         c. preliminary
            b. provisional                                       d. categorical
____ 149.   ____ change orders are oral or written acts or omissions by someone with actual or apparent authority that can
            be construed to have the same effect as a written change order.
            a. Virtual                                           c. Apparent
            b. Non-binding                                       d. Constructive
____ 150.   The project team develops a preliminary scope statement during project ____.
            a. review                                            c. orientation
            b. initiation                                        d. development
____
Sample Final Test Key
Answer Section

MULTIPLE CHOICE

      1.   ANS:   D
      2.   ANS:   B
      3.   ANS:   B
      4.   ANS:   B
      5.   ANS:   A
      6.   ANS:   B
      7.   ANS:   B
      8.   ANS:   D
      9.   ANS:   C
     10.   ANS:   D
     11.   ANS:   B
     12.   ANS:   D
     13.   ANS:   C
     14.   ANS:   C
     15.   ANS:   D
     16.   ANS:   A
     17.   ANS:   D
     18.   ANS:   D
     19.   ANS:   A
     20.   ANS:   A
     21.   ANS:   B
     22.   ANS:   B
     23.   ANS:   D
     24.   ANS:   C
     25.   ANS:   A
     26.   ANS:   C
     27.   ANS:   A
     28.   ANS:   C
     29.   ANS:   C
     30.   ANS:   A
     31.   ANS:   B
     32.   ANS:   D
     33.   ANS:   A
     34.   ANS:   B
     35.   ANS:   C
     36.   ANS:   A
     37.   ANS:   D
     38.   ANS:   A
     39.   ANS:   A
     40.   ANS:   B
41.   ANS:   B
42.   ANS:   C
43.   ANS:   C
44.   ANS:   D
45.   ANS:   D
46.   ANS:   B
47.   ANS:   A
48.   ANS:   B
49.   ANS:   B
50.   ANS:   B
51.   ANS:   B
52.   ANS:   B
53.   ANS:   B
54.   ANS:   A
55.   ANS:   D
56.   ANS:   D
57.   ANS:   B
58.   ANS:   C
59.   ANS:   D
60.   ANS:   D
61.   ANS:   A
62.   ANS:   D
63.   ANS:   C
64.   ANS:   C
65.   ANS:   A
66.   ANS:   A
67.   ANS:   C
68.   ANS:   D
69.   ANS:   D
70.   ANS:   D
71.   ANS:   B
72.   ANS:   D
73.   ANS:   A
74.   ANS:   B
75.   ANS:   A
76.   ANS:   D
77.   ANS:   A
78.   ANS:   C
79.   ANS:   B
80.   ANS:   A
81.   ANS:   D
82.   ANS:   B
83.   ANS:   C
84.   ANS:   D
85.   ANS:   C
86.   ANS:   D
87.   ANS:   A
 88.   ANS:   B
 89.   ANS:   C
 90.   ANS:   B
 91.   ANS:   C
 92.   ANS:   D
 93.   ANS:   B
 94.   ANS:   A
 95.   ANS:   D
 96.   ANS:   B
 97.   ANS:   D
 98.   ANS:   C
 99.   ANS:   D
100.   ANS:   A
101.   ANS:   B
102.   ANS:   C
103.   ANS:   B
104.   ANS:   D
105.   ANS:   D
106.   ANS:   D
107.   ANS:   A
108.   ANS:   B
109.   ANS:   C
110.   ANS:   D
111.   ANS:   B
112.   ANS:   C
113.   ANS:   D
114.   ANS:   D
115.   ANS:   A
116.   ANS:   C
117.   ANS:   A
118.   ANS:   B
119.   ANS:   B
120.   ANS:   C
121.   ANS:   D
122.   ANS:   A
123.   ANS:   A
124.   ANS:   C
125.   ANS:   A
126.   ANS:   B
127.   ANS:   D
128.   ANS:   C
129.   ANS:   D
130.   ANS:   B
131.   ANS:   B
132.   ANS:   B
133.   ANS:   C
134.   ANS:   C
135.   ANS:   D
136.   ANS:   D
137.   ANS:   A
138.   ANS:   C
139.   ANS:   B
140.   ANS:   B
141.   ANS:   C
142.   ANS:   B
143.   ANS:   A
144.   ANS:   C
145.   ANS:   B
146.   ANS:   A
147.   ANS:   B
148.   ANS:   C
149.   ANS:   D
150.   ANS:   B

More Related Content

What's hot

Se réapproprier la gestion BIM avec annexes
Se réapproprier la gestion BIM avec annexesSe réapproprier la gestion BIM avec annexes
Se réapproprier la gestion BIM avec annexesPMI-Montréal
 
Bim and project management
Bim and project managementBim and project management
Bim and project managementOmar Selim
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answersMohamed Saeed
 
MTECH BIM project case study
MTECH BIM project case studyMTECH BIM project case study
MTECH BIM project case studyStephen Au
 
Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quize2e4
 
Sample project-charter-template
Sample project-charter-templateSample project-charter-template
Sample project-charter-templatewebtech46
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management examJamil Faraj , PMP
 
10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management examJamil Faraj , PMP
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Introduction to BIM and business case of BIM
Introduction to BIM and business case of BIMIntroduction to BIM and business case of BIM
Introduction to BIM and business case of BIMreem-yousef
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionReshma Philip
 

What's hot (20)

Se réapproprier la gestion BIM avec annexes
Se réapproprier la gestion BIM avec annexesSe réapproprier la gestion BIM avec annexes
Se réapproprier la gestion BIM avec annexes
 
Pmp5
Pmp5Pmp5
Pmp5
 
Pmp4
Pmp4Pmp4
Pmp4
 
1
11
1
 
Bim and project management
Bim and project managementBim and project management
Bim and project management
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
MTECH BIM project case study
MTECH BIM project case studyMTECH BIM project case study
MTECH BIM project case study
 
BIM Execution plan
BIM  Execution  planBIM  Execution  plan
BIM Execution plan
 
Exam1
Exam1Exam1
Exam1
 
Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quiz
 
Pmp6
Pmp6Pmp6
Pmp6
 
Sample project-charter-template
Sample project-charter-templateSample project-charter-template
Sample project-charter-template
 
BIM for Project Managers
BIM for Project ManagersBIM for Project Managers
BIM for Project Managers
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Introduction to BIM and business case of BIM
Introduction to BIM and business case of BIMIntroduction to BIM and business case of BIM
Introduction to BIM and business case of BIM
 
BEP
BEPBEP
BEP
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuction
 

Similar to Sample Final Test KEY

1. Which of the following is more reflective of managerial taska..docx
1. Which of the following is more reflective of managerial taska..docx1. Which of the following is more reflective of managerial taska..docx
1. Which of the following is more reflective of managerial taska..docxelliotkimberlee
 
Qhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docxQhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docxamrit47
 
Final Examination925 North Spurg.docx
Final Examination925 North Spurg.docxFinal Examination925 North Spurg.docx
Final Examination925 North Spurg.docxmydrynan
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdfsuhshbhosale
 
ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...smumbahelp
 
Acc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_withAcc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_withsupportonlineexam11
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
Mb0033 mb0049
Mb0033 mb0049Mb0033 mb0049
Mb0033 mb0049amitpr
 
Acc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_withAcc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_withenersivard
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC QuestionsMonica Waters
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperThanh Nguyen
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersThanh Nguyen
 
EVM Assessment Student Name Instruction
EVM Assessment Student Name         InstructionEVM Assessment Student Name         Instruction
EVM Assessment Student Name InstructionBetseyCalderon89
 
Ops 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answersOps 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answersGliven
 
OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%johnMilit
 
OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%7593retzeth
 

Similar to Sample Final Test KEY (20)

UNIT1.docx
UNIT1.docxUNIT1.docx
UNIT1.docx
 
1. Which of the following is more reflective of managerial taska..docx
1. Which of the following is more reflective of managerial taska..docx1. Which of the following is more reflective of managerial taska..docx
1. Which of the following is more reflective of managerial taska..docx
 
Qhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docxQhe degree of risk associated with a project is typically at its .docx
Qhe degree of risk associated with a project is typically at its .docx
 
Final Examination925 North Spurg.docx
Final Examination925 North Spurg.docxFinal Examination925 North Spurg.docx
Final Examination925 North Spurg.docx
 
1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf1.            This Project Management concept ensures the various e.pdf
1.            This Project Management concept ensures the various e.pdf
 
ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...ICFAI Projects and Operations Management - Solved assignments and case study ...
ICFAI Projects and Operations Management - Solved assignments and case study ...
 
Acc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_withAcc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_with
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
Mb0033 mb0049
Mb0033 mb0049Mb0033 mb0049
Mb0033 mb0049
 
Acc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_withAcc 561 final_exam_3rd_set_52_questions_with
Acc 561 final_exam_3rd_set_52_questions_with
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC Questions
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
PMI ACP Classroom Question Paper
PMI ACP Classroom Question PaperPMI ACP Classroom Question Paper
PMI ACP Classroom Question Paper
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
PMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with AnswersPMI ACP Classroom Question Paper with Answers
PMI ACP Classroom Question Paper with Answers
 
EVM Assessment Student Name Instruction
EVM Assessment Student Name         InstructionEVM Assessment Student Name         Instruction
EVM Assessment Student Name Instruction
 
Ops 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answersOps 571 ops/571 final exam 100% correct answers
Ops 571 ops/571 final exam 100% correct answers
 
OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS571 Final EXAM MCQ`s Correct Answers 100%
 
OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%
OPS 571 OPS/571 Final EXAM MCQ`s Correct Answers 100%
 

More from University High School - Fresno (14)

Dah time mgmt matching exercise answers
Dah time mgmt matching exercise answersDah time mgmt matching exercise answers
Dah time mgmt matching exercise answers
 
Capm time mgmt fas track as
Capm time mgmt fas track asCapm time mgmt fas track as
Capm time mgmt fas track as
 
Capm ccvc capm time 4th edition pmbok review
Capm ccvc capm time   4th edition pmbok reviewCapm ccvc capm time   4th edition pmbok review
Capm ccvc capm time 4th edition pmbok review
 
Capm test taking preparation hints
Capm test taking preparation hintsCapm test taking preparation hints
Capm test taking preparation hints
 
Capm process cheat sheet
Capm process cheat sheetCapm process cheat sheet
Capm process cheat sheet
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Capm time mgmt matching exercise
Capm time mgmt matching exerciseCapm time mgmt matching exercise
Capm time mgmt matching exercise
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Zoskctr hints tips 20090723doc
Zoskctr hints tips 20090723docZoskctr hints tips 20090723doc
Zoskctr hints tips 20090723doc
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Source code examples
Source code examplesSource code examples
Source code examples
 
Business computing survey
Business computing surveyBusiness computing survey
Business computing survey
 
Watson
WatsonWatson
Watson
 

Sample Final Test KEY

  • 1. Sample Final Test with-KEY Multiple Choice Identify the letter of the choice that best completes the statement or answers the question. ____ 1. Outputs of organizational planning are: a. Project organization chart b. Staffing management plan c. Project template d. All of the above ____ 2. A(n) ____ event is a specific, uncertain event that may occur to the detriment or enhancement of the project. a. chance c. unplanned b. risk d. hidden ____ 3. The final output of the seller selection process is a ____. a. bid c. charter b. contract d. proposal ____ 4. Key outputs in project human resource management include ____ updates and team performance assessment. a. project c. program b. staffing d. portfolio ____ 5. Scope verification: a. Is the formal acceptance of the project scope by the stakeholders b. Refers to the final project report describing the project at completion c. Is not necessary if the project competes on time and on budget d. Occurs only when revisions or change orders are made to the project ____ 6. Slack or ____ is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date. a. leeway c. redundancy b. float d. space ____ 7. The goal of ____ control is to know the status of the schedule, influence the factors that cause schedule changes, determine whether the schedule has changed, and manage changes when they occur. a. time c. cost b. schedule d. scope ____ 8. Which of the following portfolio management tasks should occur first? a. prioritize projects on a list c. divide projects into investment categories b. put all projects into one list d. put all projects in one list ____ 9. Two tools to assist in contract closure are ____ audits and a records management system. a. dispatch c. procurement b. supply d. acquisition ____ 10. Which of the following is not a true statement about control charts? a. Control charts can be used to establish as well as maintain process control b. Control charts are used to determine acceptance limits when no limits are stipulated by the product specification; otherwise, one should use the limits dictated by the specification c. All data points outside the control chart limits are variations explained by assignable causes d. b and c ____ 11. Under which risk register heading would you list cost overruns on early activities, which might be symptomatic of a poor cost estimate? a. The impact to the project if the risk event occurs
  • 2. b. Triggers for each risk event c. The probability of the risk event occurring d. The status of the risk event ____ 12. Cost of quality is: a. The expense of nonconformance to requirements and specifications b. The direct responsibility of the project team members c. The expense of conformance to requirements and specifications d. a and c ____ 13. The term ―____‖ is used to describe each level of work in the WBS. a. activity c. task b. module d. node ____ 14. A stakeholder ____ provides information on key stakeholders to help manage relationships with them. a. study c. analysis b. charter d. guide ____ 15. A parametric cost estimate: a. Is a bottom up estimating technique b. Is a top down estimating technique c. Is a statistical estimating technique d. b and c ____ 16. Some projects have a senior manager called a(n) ____ who acts as a key proponent for a project. a. champion c. sponsor b. coach d. advocate ____ 17. ____ contracts reduce the risk of incurring higher costs than expected. a. Variable-price c. Oral b. Bid d. Fixed-price ____ 18. Cost ____ involves allocating the overall cost estimate to individual tasks over time to establish a baseline for measuring performance. a. estimating c. allowance b. account d. budgeting ____ 19. An organization should consider only projects with a ____ NPV if financial value is a key criterion for project selection. a. positive c. zero b. negative d. well-defined ____ 20. Because many projects fail due to unclear requirements and expectations, starting with a project ____ makes sense. a. charter c. vision statement b. contract d. compact ____ 21. What is the PERT weighted average based on an optimistic estimate of 6 days, a most likely estimate of 8 days, and a pessimistic time of 12 days? a. 6 c. 11 b. 8 d. 12 ____ 22. Project ____ management includes acquiring or procuring goods and services for a project from outside the organization. a. logistics c. acquisition b. procurement d. supply ____ 23. The main monitoring and controlling task performed as part of project cost management is ____ control. a. time c. scope b. schedule d. cost
  • 3. ____ 24. Projects should first and foremost address business ____. a. portfolios c. needs b. ventures d. practices ____ 25. ____ are the results of applying capabilities. a. Outcomes c. Effects b. Events d. Impressions ____ 26. Poor scope definition may cause all but: a. Higher project costs b. Rework c. Increased productivity d. Low morale ____ 27. Contract updates are often made by having both parties—the buyer and the seller—sign a(n) ____ to the contract. a. addendum c. alteration b. revision d. appendix ____ 28. The main outputs of the quality control process are: a. Pareto diagram, acceptance decisions, and process adjustments b. Bar charts, network diagrams, and rework c. Acceptance decisions, rework, and process adjustments d. Acceptance decisions, performance indicators, and rework ____ 29. Quality management deals with the following except: a. Conformance to requirements and specifications b. Satisfying the needs of the customer c. Making the product more desirable and luxurious d. a and c ____ 30. Which type of contract provides the highest rank to the owner (buyer)? a. Cost plus percentage of cost b. Cost plus fixed fee c. Firm fixed price d. Fixed price incentive ____ 31. Project management ____ facilitate communication among stakeholders and provide a baseline for progress measurement and project control. a. charters c. contracts b. plans d. compacts ____ 32. A(n) ____ cause is the real or underlying reason a problem occurs. a. secondary c. envisioned b. indirect d. root ____ 33. ____ estimates involve estimating individual activities and summing them to get a project total. a. Bottom-up c. Ad hoc b. Provisional d. Temporary ____ 34. After a project is approved, senior managers should meet to determine the ____, time, and cost constraints for the project. a. range c. vision b. scope d. boundary ____ 35. Which of the following is a category under portfolio best practices? a. Project initiation process standardization b. Project plan development process measurement c. Portfolio risk management planning process improvement. d. Project scope definition process improvement
  • 4. ____ 36. Project management software uses the ____ format to represent the WBS. a. tabular c. flexible b. binary d. chart ____ 37. The overall duration of the project schedule is not influenced by: a. Using mandatory dependencies as constraints b. Using discretionary dependencies as constraints c. The capabilities of the resources which are assigned to perform the work d. Using the arrow diagramming method instead of the precedence diagramming method (PDM) of scheduling ____ 38. In an AOA network diagram, a(n) ____ occurs when two or more nodes precede a single node. a. merge c. union b. join d. intersection ____ 39. The main output of scope planning is a ____ management plan, which is a document that includes descriptions of how the team will prepare the scope statement, create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope. a. scope c. program b. project d. portfolio ____ 40. If you want to praise a project team member for doing a good job, a(n) ____ would most likely want everyone to hear about her good work. a. introvert c. recluse b. extrovert d. loner ____ 41. According to Douglas McGregor, people who believe in Theory ____ assume that workers dislike and avoid work if possible, so managers must use coercion, threats, and various control schemes to get workers to make adequate efforts to meet objectives. a. W c. Y b. X d. Z ____ 42. In a(n) ____, each bar represents an attribute or a characteristic of a problem or situation, and the height of the bar represents its frequency. a. run chart c. histogram b. control chart d. scatter diagram ____ 43. The main monitoring and controlling task performed as part of project time management is ____ control. a. document c. schedule b. employee d. scope ____ 44. Which of the following are considered to be milestones? a. Project completion date b. Contract date c. Key event completion date d. All of the above ____ 45. Project ____ management involves coordinating all the project management knowledge areas throughout a project’s life span. a. union c. unification b. synthesis d. integration ____ 46. The main procurement management task performed to monitor and control projects is administering the ____. a. vision plan c. charter b. contract d. project platform ____ 47. A(n) ____ histogram is a column chart that shows the number of resources required for or assigned to a project over time. a. resource c. allocation b. requirements d. assignment
  • 5. ____ 48. Quality assurance: a. Refers to the prevention of product defects b. Is an auditing function that provides feedback to the project team and client about the quality of the output being produced c. Is the technical process that includes the construction of control charts, which specify the acceptability limits for conforming output d. a and b ____ 49. Blake and Mouton (1964) delineated ____ basic modes for handling conflicts. a. four c. six b. five d. seven ____ 50. Project time management involves the following main processes: a. Activity definition, duration estimating, and schedule development b. Activity definition, sequencing, duration estimating, schedule development, and control c. Activity identification, sequencing, duration estimating, schedule development, and control d. Activity definition, sequencing, and schedule control ____ 51. ____ includes the actual amount of time spent working on an activity plus elapsed time. a. Extension c. Period b. Duration d. Length ____ 52. What method is used to communicate staffing requirements to the organization? a. Gantt chart b. Staffing plan c. Responsibility matrix d. Project objective statement ____ 53. The main purpose of project planning is to guide project ____. a. initiation c. review b. execution d. evaluation ____ 54. Two key outputs of performance reporting are performance reports and ____. a. forecasts c. retrospectives b. cost-benefit analyses d. performance reviews ____ 55. Weights may be established by assigning percentages or ____. a. results c. scores b. values d. points ____ 56. Many maturity models have five levels, with level one describing characteristics of the least organized or least mature organizations, and level ____ describing the characteristics of the most organized and most mature organizations. a. two c. four b. three d. five ____ 57. Which of the following is not a characteristic of a ―work package‖? a. It is a task at the lowest level of any branch of the WBS b. It is a summary task at the top level of the WBS c. It consists of manageable units of work that can be planned, budgeted, scheduled, and controlled d. It usually contains no more than 80 work hours (effort) to complete ____ 58. Contract ____ includes the contract itself along with requested unapproved contract changes and approved change requests. a. authorization c. documentation b. review d. negotiation ____ 59. Network diagrams are good for depicting:
  • 6. a. Slack time b. Schedule start and finish dates c. Plan versus actual schedule d. Task dependencies ____ 60. Project teams sometimes use ____—unplanned responses to risk events—when they do not have contingency plans in place. a. work charts c. work processes b. work flows d. workarounds ____ 61. Suppose that the purchase price for a piece of equipment is $10,000, and incurs operational costs of $300 per day. If the same equipment can be leased for $500 per day and you need the equipment for ____ days, it would be more economical to lease the equipment. a. 30 c. 80 b. 60 d. 100 ____ 62. The project manager should work with his or her team and ____ to determine the level of detail needed in the WBS dictionary. a. client c. auditor b. customer d. sponsor ____ 63. Under which risk register heading would you list a defective product, poor survey results, reduced consulting costs, or good publicity? a. An identification number for each risk event b. A rank for each risk event c. The name of the risk event d. A description of the risk event ____ 64. In the context of earned value management, ____ are calculated by subtracting the actual cost or planned value from EV, and indexes are calculated by dividing EV by the actual cost or planned value. a. fluctuations c. variances b. valuations d. deviations ____ 65. A(n) ____ scoring model is a tool that provides a systematic process for selecting projects based on many criteria. a. weighted c. variable b. biased d. opportunity ____ 66. Earned value management involves calculating ____ values for each activity or summary activity from a project’s WBS. a. three c. five b. four d. six ____ 67. The main planning tasks performed as part of project scope management include scope planning, scope definition, and ____. a. scope evaluation c. creating the WBS b. scope reduction d. scope expansion ____ 68. ―Earned value‖ can best be defined as: a. The value of the equipment that has been installed as of the data date b. The sum of the labor costs that have been incurred on the project to date c. A method of measuring the amount of money that has been spent to date d. The actual cost of work performed (ACWP) minus the budgeted cost of work performed (BCWP) ____ 69. If a project’s stakeholders are not satisfied with the quality of the project management or the resulting products, the project team will need to adjust ____, time, and cost to satisfy stakeholder needs and expectations. a. range c. vision
  • 7. b. breadth d. scope ____ 70. Which technique shows external dependencies best? a. Activity on arrow diagramming b. Activity on node diagramming c. PERT diagramming d. None of the above ____ 71. After deciding which projects to pursue, organizations need to decide if it is advantageous to manage several projects together as part of a(n) ____. a. aggregate c. cluster b. program d. group ____ 72. Which of the following actions will most likely improve team productivity? a. Ensure that social events are mandatory and include a business-related goal. b. Expand the size of work teams to over seven members. c. Reduce the amount of attention paid to virtual team members. d. Acknowledge individual and group accomplishments. ____ 73. There are ____ important dimensions of risk events. a. two c. four b. three d. five ____ 74. Project Communication management is divided into: a. Communication requirements, information distribution, performance reporting, and administrative procedure b. Communications planning, information distribution, performance reporting, and administrative closure c. Communications planning, response planning, progress reporting, and information distribution d. Communications planning, information distribution, schedule reporting, and stakeholder analysis ____ 75. By adding all of the ____ for all project activities, you can determine how the project as a whole is performing and forecast both when it will be completed and how much it will cost at completion. a. earned values c. planned values` b. actual costs d. cost variances ____ 76. Tools included in overall change control are: a. Configuration management b. Performance measurement c. Project management information system d. All of the above ____ 77. The PMBOK® Guide lists at least ____ documents that project teams can produce as part of project planning. a. 50 c. 100 b. 75 d. 125 ____ 78. A project portfolio ____ map compares relative value to project risk. a. venture c. risk b. viability d. value ____ 79. A change control board is: a. An informal or formal group of team members responsible for changes to a project b. A formal group of people responsible for approving or rejecting changes to the project baselines c. The project manager and several key team members working to ensure cost and schedule control during the life of the project d. An informal group that has oversight of project implementations
  • 8. ____ 80. A three-point estimate is an estimate that includes a(n) ____, most likely, and pessimistic estimate, such as three weeks, four weeks, and five weeks, respectively. a. optimistic c. remote b. unusual d. conditional ____ 81. In a software project, the planned value (PV) was 80,000, the earned value (EV) was 75,000 and the actual cost (AC) was 71,000, what is the cost performance index? a. –0.947 b. 0.947 c. 0.937 d. 1.056 ____ 82. Risk reassessment, risk audits, variance and trend analysis, technical performance measurements, reserve analysis, and status meetings or periodic risk reviews are all tools and techniques for performing ____ monitoring and control. a. scope c. cost b. risk d. quality ____ 83. Performance in meeting project scope goals is based on the scope ____. a. definition c. baseline b. revision d. statement ____ 84. The major processes of project risk management are: a. Plan response, identify, document, and assess b. Identify, mitigate, and plan response c. Respond, evaluate, and document d. Identify, quantify, develop response, and control ____ 85. Project integration management includes ____ processes. a. two c. seven b. four d. nine ____ 86. A risk management plan should cover: a. Who is responsible for managing various areas of risk b. How contingency plans will be implemented c. How reserves will be allocated d. All of the above ____ 87. To ____ a project, you must finalize all activities and transfer the completed or canceled work to the appropriate people. a. close c. audit b. initiate d. assess ____ 88. After assigning weights for the criteria and scores for each project, you calculate a weighted score for each project by multiplying the weight for each criterion by its score and ____ the resulting values. a. multiplying c. dividing b. adding d. subtracting ____ 89. According to David McClelland, people with a high need for ____ desire harmonious relationships with other people and need to feel accepted by others. a. isolation c. affiliation b. assurance d. solitude ____ 90. ____ estimates, also called top-down estimates, use the actual cost of a previous, similar project as the basis for estimating the cost of the current project. a. Homologous c. Sequential b. Analogous d. Parallel ____ 91. A project manager must be sure to check with his organization to find out its guidelines for when discounting starts, what discount rate to use, and what ____ the organization prefers.
  • 9. a. charts c. format b. technique d. results ____ 92. Scope statements should include, at a minimum, a description of the project, including its overall objectives and justification; detailed descriptions of all project ____; characteristics and requirements of products and services produced as part of the project; and project success criteria. a. stakeholders c. meetings b. volunteers d. deliverables ____ 93. A common way to summarize work performance information is by using a(n) ____ report. a. performance c. projection b. milestone d. evaluation ____ 94. ____ risk events might include the performance failure of a product produced as part of a project, delays in completing work as scheduled, increases in estimated costs, supply shortages, litigation against the company, and strikes. a. Negative c. Calculated b. Hidden d. Countervailing ____ 95. How many communication channels do 12 people require? a. 12 c. 36 b. 24 d. 66 ____ 96. ____ dependencies involve relationships between project and nonproject activities. a. Internal c. Ancillary b. External d. Miscellaneous ____ 97. Project integration management includes the following processes: a. Scope planning b. Scope definition c. Scope verification d. Integrated change control ____ 98. The cost of providing a work space for project workers, office furniture, electricity, and a cafeteria are ____ costs. a. direct c. indirect b. explicit d. incidental ____ 99. A process for handling changes should be defined during project ____ as part of the project management plan. a. deployment c. execution b. initiation d. planning ____ 100. The main executing tasks performed as part of project ____ include requesting seller responses and selecting sellers. a. procurement c. initiation b. planning d. monitoring ____ 101. The PMBOK Guide® is a ____ that describes best practices for what should be done to manage a project. a. rule book c. protocol b. standard d. secondary authority ____ 102. A cost baseline is a(n) ____ budget that project managers use to measure and monitor cost performance. a. incidental c. time-phased b. basic d. incremental ____ 103. Suppose that after one week of work, the earned value is $4000 and the planned value is $5000. What is the value of the schedule performance index (SPI)? a. 75% c. 120% b. 80% d. 125% ____ 104. A request for quote (RFQ) differs from a request for proposal (RFP) in that:
  • 10. a. RFQs generally ask for innovative processes b. RFPs generally ask for guaranteed maximum prices c. RFQs generally ask for a lump sum price d. RFPs generally ask for technical skills and implementation approach ____ 105. Projects that address competitive ____ are much more likely to be successful because they will be important to the organization’s competitive position. a. value c. tactics b. products d. strategy ____ 106. Which of the following is a common problem encountered during project execution? a. Communications are good. b. The project sponsor and/or other senior managers are very supportive of the project. c. The project objectives/scope are clear. d. People working on the project are incompetent or unmotivated. ____ 107. Which of the following methods best helps a project manager identify and learn about key project stakeholders? a. questioning acquaintances c. consulting biographies b. reviewing organizational charts d. performing Internet searches ____ 108. After defining project activities, the next step in project time management is activity ____. a. organization c. segmenting b. sequencing d. ordering ____ 109. A quality ____ is a structured review of specific quality management activities that helps identify lessons learned, which could improve performance on current or future projects. a. survey c. audit b. overview d. assessment ____ 110. The scope statement should not include: a. Project justification b. Project deliverables c. Project objectives d. Project budget ____ 111. Three primary methods for determining the projected financial value of projects include net present value analysis, return on investment, and ____ analysis. a. growth c. environmental impact b. payback d. efficiency ____ 112. The main human resource management task performed as part of monitoring and controlling a project is managing the project ____, which, of course, is no small task. a. sponsors c. team b. clients d. supplies ____ 113. Under which risk register heading would you list identification of a defective hard drive as the source of a computer defect? a. The category under which the risk event falls b. The risk owner, or person who will own or take responsibility for the risk event c. Potential responses to each risk event d. The root cause of the risk event ____ 114. Duration estimates are provided as a ____ number, such as four weeks; as a range, such as three to five weeks; or as a three-point estimate. a. continuous c. fractional b. random d. discrete ____ 115. Examples of common ____ used by organizations include failure rates of products produced, availability of goods and services, and customer satisfaction ratings.
  • 11. a. metrics c. requirements b. analytics d. guidelines ____ 116. According to the research of Fast Company, which of the following is one of the three top reasons that people voluntarily leave their job? a. They are learning too many new things. c. They do not feel they make a difference. b. They are growing into their position. d. They get proper recognition. ____ 117. A best practice is ―a(n) ____ way recognized by industry to achieve a stated goal or objective.‖ a. optimal c. targeted b. suboptimal d. inefficient ____ 118. Which of the following topics could you expect to find in a procurement management plan? a. methodology for risk management b. guidelines on types of contracts to be used in different situations c. budget and schedule estimates for risk-related activities d. risk categories ____ 119. A(n) ____ log is a tool used to document and monitor the resolution of project issues. a. event c. problem b. issue d. running ____ 120. Based on the implementation of quality-control measurements, ____ adjustments often result in updates to the quality baseline, organizational process assets, and the project management plan. a. contract c. process b. quality d. project ____ 121. The main disadvantage of ____ is that it can end up lengthening the project schedule, because starting some tasks too soon often increases project risk and results in rework. a. reviewing c. extending b. crashing d. fast tracking ____ 122. A ____ contract has the least amount of risk for the buyer. a. firm -fixed price c. soft-fixed-price b. fixed-price incentive d. contingent-fixed ____ 123. A(n) ____ is a document in which sellers describe what they will do to meet the requirements of a buyer. a. proposal c. schedule b. charter d. draft ____ 124. PMI defines a project ____ as an uncertainty that can have a negative or positive effect on meeting project objectives. a. hazard c. risk b. danger d. challenge ____ 125. In the context of monitoring and controlling tasks for project quality management, ____ decisions determine if the products or services produced as part of the project will be accepted or rejected. a. acceptance c. rework b. rejection d. redesign ____ 126. In general, the majority of a project’s time and budget is spent on project ____. a. planning c. review b. execution d. duplication ____ 127. Activity ____ provide schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity. a. features c. properties b. characteristics d. attributes ____ 128. In an AOA network diagram, ____ occur when two or more activities follow a single node.
  • 12. a. drives c. bursts b. flares d. runs ____ 129. What method(s) is(are) available to the project manager for short listing contractor proposals? a. Comparing proposals against independent estimates b. Weighing systems c. Subjective screening systems d. All of the above ____ 130. In a software project, the planned value (PV) was 80,000, the earned value (EV) was 75,000 and the actual cost (AC) was 71,000, what is the cost variance (CV)? a. –4,000 b. +4,000 c. +9,000 d. –9,000 ____ 131. According to Frederick Herzberg, a(n) ____ factor is a basic necessity, such as air-conditioning during hot weather. a. motivational c. environmental b. hygiene d. incidental ____ 132. ____ should be formed and continuously updated to help the organization as a whole make better strategic decisions. a. Monitors c. Projects b. Portfolios d. Programs ____ 133. In the context of earned value management, the ____ cost is the total direct and indirect costs incurred in accomplishing work on an activity during a given period. a. real c. actual b. estimated d. projected ____ 134. ____ motivation causes people to do something for a reward or to avoid a penalty. a. Derived c. Extrinsic b. Intrinsic d. Primary ____ 135. When using the ____ mode to resolve conflicts, the project manager de-emphasizes or avoids areas of differences and emphasizes areas of agreement. a. adversarial c. antagonistic b. dialectic d. smoothing ____ 136. Which of the following is not a selection criteria for choosing a new project? a. Risk b. Rate of return c. In-house personnel available d. Competition’s out-sourcing method ____ 137. The cost performance index (CPI) is: a. Earned value divided by actual cost b. Actual cost divided by earned value c. Earned value divided by planned value d. Planned value to date times percent complete ____ 138. The project is considered on schedule if: a. Schedule variance (SV) is negative b. Cost variance (CV) is positive c. Schedule performance index (SPI) is one or 100 percent d. Earned value (EV) is positive ____ 139. Project ____ management ensures that the project will satisfy the stated or implied needs for which it was undertaken.
  • 13. a. integration c. portfolio b. quality d. performance ____ 140. ____ development uses the results of all the preceding project time management processes to determine the start and end dates of project activities and of the entire project. a. Task c. Work Package b. Schedule d. Activity ____ 141. A ____ is a product or service produced or provided as part of a project. a. process c. deliverable b. result d. requirement ____ 142. The approved time estimate for a project can be divided by the ____ performance index to calculate when the project will be completed. a. cost c. price b. schedule d. itinerary ____ 143. The ____ mode can be viewed as the win-lose approach to conflict resolution. a. forcing c. negotiating b. compromising d. bargaining ____ 144. Which of the following is a key output of project procurement management? a. quality metrics c. contract statements of work b. quality checklists d. project Web site ____ 145. ____ risk events include completing work sooner than planned or at an unexpectedly reduced cost, collaborating with suppliers to produce better products, and obtaining good publicity from the project. a. Collaborative c. Anticipated b. Positive d. Probable ____ 146. You calculate cash ____ by subtracting costs from benefits, or expenses from income. a. flow c. budgets b. statements d. structure ____ 147. The main monitoring and controlling tasks performed as part of project ____ management are scope verification and scope control. a. integration c. cost b. scope d. time ____ 148. It is helpful to create a ____, or initial, scope statement during project initiation so that the entire project team can start important discussions and work related to the project scope. a. tentative c. preliminary b. provisional d. categorical ____ 149. ____ change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order. a. Virtual c. Apparent b. Non-binding d. Constructive ____ 150. The project team develops a preliminary scope statement during project ____. a. review c. orientation b. initiation d. development ____
  • 14. Sample Final Test Key Answer Section MULTIPLE CHOICE 1. ANS: D 2. ANS: B 3. ANS: B 4. ANS: B 5. ANS: A 6. ANS: B 7. ANS: B 8. ANS: D 9. ANS: C 10. ANS: D 11. ANS: B 12. ANS: D 13. ANS: C 14. ANS: C 15. ANS: D 16. ANS: A 17. ANS: D 18. ANS: D 19. ANS: A 20. ANS: A 21. ANS: B 22. ANS: B 23. ANS: D 24. ANS: C 25. ANS: A 26. ANS: C 27. ANS: A 28. ANS: C 29. ANS: C 30. ANS: A 31. ANS: B 32. ANS: D 33. ANS: A 34. ANS: B 35. ANS: C 36. ANS: A 37. ANS: D 38. ANS: A 39. ANS: A 40. ANS: B
  • 15. 41. ANS: B 42. ANS: C 43. ANS: C 44. ANS: D 45. ANS: D 46. ANS: B 47. ANS: A 48. ANS: B 49. ANS: B 50. ANS: B 51. ANS: B 52. ANS: B 53. ANS: B 54. ANS: A 55. ANS: D 56. ANS: D 57. ANS: B 58. ANS: C 59. ANS: D 60. ANS: D 61. ANS: A 62. ANS: D 63. ANS: C 64. ANS: C 65. ANS: A 66. ANS: A 67. ANS: C 68. ANS: D 69. ANS: D 70. ANS: D 71. ANS: B 72. ANS: D 73. ANS: A 74. ANS: B 75. ANS: A 76. ANS: D 77. ANS: A 78. ANS: C 79. ANS: B 80. ANS: A 81. ANS: D 82. ANS: B 83. ANS: C 84. ANS: D 85. ANS: C 86. ANS: D
  • 16. 87. ANS: A 88. ANS: B 89. ANS: C 90. ANS: B 91. ANS: C 92. ANS: D 93. ANS: B 94. ANS: A 95. ANS: D 96. ANS: B 97. ANS: D 98. ANS: C 99. ANS: D 100. ANS: A 101. ANS: B 102. ANS: C 103. ANS: B 104. ANS: D 105. ANS: D 106. ANS: D 107. ANS: A 108. ANS: B 109. ANS: C 110. ANS: D 111. ANS: B 112. ANS: C 113. ANS: D 114. ANS: D 115. ANS: A 116. ANS: C 117. ANS: A 118. ANS: B 119. ANS: B 120. ANS: C 121. ANS: D 122. ANS: A 123. ANS: A 124. ANS: C 125. ANS: A 126. ANS: B 127. ANS: D 128. ANS: C 129. ANS: D 130. ANS: B 131. ANS: B 132. ANS: B
  • 17. 133. ANS: C 134. ANS: C 135. ANS: D 136. ANS: D 137. ANS: A 138. ANS: C 139. ANS: B 140. ANS: B 141. ANS: C 142. ANS: B 143. ANS: A 144. ANS: C 145. ANS: B 146. ANS: A 147. ANS: B 148. ANS: C 149. ANS: D 150. ANS: B