Welingkar’s Distance Learning Division

CHAPTER-8

Operation Research Techniques in
Transportation

We Learn – A Continuous Learning Forum
North West Corner Rule
• Model to determine the optimum solution to a
problem of separate demand points being supplied
from separate points
• Let us take a situation where there are 3 supply
sources S1,S2,S3 and S4 and demand sinks
D1,D2,D3,D4
• The costs associate with 12 combinations as well as
the supplies ex each supply point and demands at
each demand center are depicted in the figure on
next slide
Ch-08 - 0peration Research Techniques in Transportation
North West Corner Rule fig-1
Destinations
/origins

D1

D2

D3

D4

D5

D6

S1

3

7

12

10

9

9

S2

14

20

13

6

12

4

S3

12

15

13

9

6

8

Demand

3

5

4

6

3

21

Ch-08 - 0peration Research Techniques in Transportation
North West Corner Rule fig-1
• The three supply points S1,S2 and S3 can supply 9
units, 4 units, and 8 units respectively, whereas the
three demand points D1, D2, D3, and D4 require
3,5,4,6 and 3 units respectively
• The cost at the point of calculation will be treated as
negative figures, because they are basically items
whose negative impact the exercise is trying to
minimize, in this case the total demand is 21units
and the supply available is also 21 units

Ch-08 - 0peration Research Techniques in Transportation
North West Corner Rule
• Where the supply may be more than demand, an
additional dummy demand column has to be put
with the residual supply being shown as units
required by this demand center, and in the boxes for
costs zero should be put
• Similarly, in case demand exceeds shown there
against, and again in the cost zero should be put in
the respective additional squares.

Ch-08 - 0peration Research Techniques in Transportation
North West Corner Rule Figure-2
Destinations/
origins

D1

D2

D3

D4

D5

Supply

S1

11

12

13

14

15

9

S2

21

22

23

24

25

4

S3

31

32

33

34

35

8

Demand

3

5

4

6

3

21

Ch-08 - 0peration Research Techniques in Transportation
North West Corner Rule Figure-2
• In fig2 we shall give the 15 squares individual
numbers for easier identification
• The five squares across supply point 1 will
have no. 11 to 15, against supply point 2 the
numbers will be 21 to 25, and for the 3rd one
the no. will be 31 to 35.

Ch-08 - 0peration Research Techniques in Transportation
North West Corner Rule Figure-2
• Allocate supplies fro the supply sources to the demand sinks
• The process starts form the north west corner i.e. square
11, and hence the name north west corner rule
• Demand sink 1 has requirement for 3 units, and supply source
1 can supply 9 units, the total requirement of D1 from
S1, when the situation is such that after meeting the demand
of D1 from S1 , units remain, then the next allotment should
be made horizontally, i.e. the next supply from S1 should go to
D2

Ch-08 - 0peration Research Techniques in Transportation
Deploying vehicles-Listing Method

C

D

A

G

E

B

F

Ch-08 - 0peration Research Techniques in Transportation
Deploying vehicles-Listing Method
• A is the starting point from where materials are sent
out for delivery to various points B,C, D,E,F and G.
• The distance between
• A and B is 9 km, A and C is 11 km
• B & C is 9 km, C & D is 14 km
• C & E is 11 km, D & E is 7 km
• E & F is 10 km, D & F is 10 km
• D & G is 15 km, F & G is 11 km

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
A

B

C

D

E

F

G

AB=9

BA=9

CA=11

DC=14

EB=14

FD=10

GD=15

AC=11

BC=9

CB=9

DE=7

EC=11

FE=10

GF=11

BE=14

CD=14

DF=10

ED=7

FG=11

CE=11

DG=15

EF=10

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
• To initiate the solution procedure , a value of zero is
assigned to the starting point, in this case A.
• Thereafter select the shortest distance from origin A
which in this case is AB as AC is longer at 11. In case
both the distances are the same then selecting either
will do
• The value of B will be the total of value for A Zero
plus the value AB which is 9 i.e.9

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
A=0

B=9

C

D

E

F

G

CA=11

DC=14

EB=14

FD=10

GD=15

BC=9

CB=9

DE=7

EC=11

FE=10

GF=11

BE=14

CD=14

DF=10

ED=7

FG=11

CE=11

DG=15

EF=10

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
• Thereafter from B we again choose the
shortest of the alternate routes
• You would have noted that under B, the route
BA has been removed because that is no
longer an option

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
A=0

B=9

D

E

F

G

DC=14

EB=14

FD=10

GD=15

DE=7

BE=14

C=18

EC=11

FE=10

GF=11

CD=14

DF=10

ED=7

FG=11

CE=11

DG=15

EF=10

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
A=0

B=9

D

E

F

G

DC=14

EB=14

FD=10

GD=15

DE=7

BE=14

C=18

EC=11

FE=10

GF=11

CD=14

DF=10

ED=7

FG=11

CE=11

DG=15

EF=10

Ch-08 - 0peration Research Techniques in Transportation
Next we observe that from C E is a shorter
route hence
A=0

B=9

C=18

D

E=29

BE=14

CD=14

ED=7

DG=15

GD=15

FE=10

DF=10

G

FD=10

DE=7

F

GF=11

FG=11

EF=10

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
• The route becomes A-B-C-E=29 km.
proceeding this way you will finally find that
the shortest route is
• A-B-C-E-D-F-G=9+9+11+7+10+11=57

Ch-08 - 0peration Research Techniques in Transportation
Listing Method
• The importance of this model is listing
• Unless they are plotted systematically and
eliminated sequentially the above apparently
simple exercise may be difficult in real life

Ch-08 - 0peration Research Techniques in Transportation
PERT & CPM
• In order to realize valid results within time and
budget expectations, one has to schedule jobs
and tasks
• Through scheduling one not only plans tasks,
but also checks that resources are utilized
optimally
• Above two techniques are very commonly
used

Ch-08 - 0peration Research Techniques in Transportation
Critical Path Method
• In CPM the entire project work plan is graphically
portrayed. This graph or network displays the
interdependencies between activities that will lead
to successful completion of the project. It must
satisfy the following objectives
– Evaluate progress towards attainment of project
completion
– Focus attention on potential and actual problems during
work

Ch-08 - 0peration Research Techniques in Transportation
Critical Path Method
– Provide frequent, accurate status reports at
critical check points
– Provide a regular and updated prediction of when
the project will be completed
– Provide at any time during the project
determination of the shortest completion time if
priorities and resources are shifted

Ch-08 - 0peration Research Techniques in Transportation
Preparing a flow chart
• The project events joined by lines (activities)
• The activities are depicted by lines illustrate
project relationships and inter dependences

Ch-08 - 0peration Research Techniques in Transportation
Preparing a flow chart
• The events depict significant occurrences or
milestones in the completion of the project
• Activities may be real or dummy, when it signifies an
actual task that has be done, which means resources
to be needed whereas dummy activities depicted in
the flow chart just to show that the dummy activity
needs to be completed before another activity can
be taken up, which means in terms of resource the
dummy will not extent any

Ch-08 - 0peration Research Techniques in Transportation
PERT network

7

3

1

2

5

4
Real Activites
Dummy Activites

6

8

9

10

Ch-08 - 0peration Research Techniques in Transportation
PERT
• Circles with numbers are events
• The dark continues lines depict real activities and
the hyphenated lines depict dummy activities
• The next step is to assign time to the activities as
well as resources and costs.
• This is where CPM comes in,
• While in PERT probabilistic time estimates are put
in while preparing the flow chart, CPM will use
exact deterministic times with cost benefit trade
offs
Ch-08 - 0peration Research Techniques in Transportation
Example of putting up a new systems set up at a
manufacturing location
1. Studying the existing system in details and
documenting all the current procedures
2. Customizing the system to suit the organizational
requirement
3. Configuring the hardware requirement
4. Making application to exercise authorities
5. Training staff for new system
6. Preparing new master data
7. Setting date for change over
8. Uploading old data on new server
Ch-08 - 0peration Research Techniques in Transportation
This brings up the issue of
• Optimistic time
– The time estimate if activity proceeds perfectly (a)

• Pessimistic time
– The time estimate if extreme difficulties are experienced
(b)

• Most Likely Time
– The expected time (c) the expected time as a mean can be
calculated by apportioning weights to the 3 times, for
instance giving weights of 1 each to (a) and (b) and 3 to (c)
one can calculate the mean time

Ch-08 - 0peration Research Techniques in Transportation
Activity

(a)

(b)

(c)

Expected
mean time

1.Studying the existing system in
details and documenting all the current
procedures

1

3

1.5

1.7

2.Customizing the system to suit the
organizational requirement

2

4

3

3

.25

.1

.5

.75

4. Making application to exercise
authorities

1

4

1.5

1.9

5. Training staff for new system

1

2

1

1.2

1.5

3

2

2.1

3.Configuring the hardware
requirement

6. Preparing new master data
7. Setting date for change over
8.Uploading old data on new server

Ch-08 - 0peration Research Techniques in Transportation
Network Representation
4
2
5

1

3

6
Real Activites
Dummy Activites

8

7
Ch-08 - 0peration Research Techniques in Transportation
Interpretation
• Linkage between (2) and (4) and (8) does not require
allotment of a resources from the organization, save
may be follow ups but non completion of event (4)
will not bring about event (8) and finally (7) now on
the basis of the expected mean time if we track the
path from (1) to (7) via the three routes we shall get
three sets of time. The one with longest time is the
critical path, while the others are the slack paths

Ch-08 - 0peration Research Techniques in Transportation
Summary
• To determine optimum solution to a
distribution problem, we need to employ
suitable operation research technique
• North-west corner rule, listing method are
suitable for planning and assigning vehicles for
different routes
• PERT and CPM are useful for timely
completion of a project

Ch-08 - 0peration Research Techniques in Transportation

More Related Content

What's hot

Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation pptDeepika Bansal
 
Transportation Assignment
Transportation AssignmentTransportation Assignment
Transportation AssignmentNilam Kabra
 
Transportation problem ppt
Transportation problem pptTransportation problem ppt
Transportation problem pptDr T.Sivakami
 
Continuous Review Inventory System
Continuous Review Inventory SystemContinuous Review Inventory System
Continuous Review Inventory System3abooodi
 
Transportation model and assignment model
Transportation model and assignment modelTransportation model and assignment model
Transportation model and assignment modelpriyanka yadav
 
3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Pooling3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Poolingpirama2000
 
Drivers of supply chain performance group 2
Drivers of supply chain performance group 2Drivers of supply chain performance group 2
Drivers of supply chain performance group 2Bhupesh Bindal
 
Inventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAInventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAAJ Raina
 
Transportation in supply chain
Transportation in supply chain Transportation in supply chain
Transportation in supply chain RakshaSharma26
 
Supply Chain Management chap 3
Supply Chain Management chap 3Supply Chain Management chap 3
Supply Chain Management chap 3Umair Arain
 
Supply Chain Management chap 10
Supply Chain Management chap 10Supply Chain Management chap 10
Supply Chain Management chap 10Umair Arain
 
Purchasing and vendor management
Purchasing and vendor managementPurchasing and vendor management
Purchasing and vendor managementNarendra Chaudhary
 

What's hot (20)

Deepika(14 mba5012) transportation ppt
Deepika(14 mba5012)  transportation pptDeepika(14 mba5012)  transportation ppt
Deepika(14 mba5012) transportation ppt
 
Transportation Assignment
Transportation AssignmentTransportation Assignment
Transportation Assignment
 
Least cost
Least costLeast cost
Least cost
 
Transportation problem ppt
Transportation problem pptTransportation problem ppt
Transportation problem ppt
 
Continuous Review Inventory System
Continuous Review Inventory SystemContinuous Review Inventory System
Continuous Review Inventory System
 
Operations
OperationsOperations
Operations
 
01a Bullwhip Effect
01a Bullwhip Effect01a Bullwhip Effect
01a Bullwhip Effect
 
LEAST COST METHOD
LEAST COST METHOD LEAST COST METHOD
LEAST COST METHOD
 
Transportation model and assignment model
Transportation model and assignment modelTransportation model and assignment model
Transportation model and assignment model
 
3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Pooling3 Inventory Management And Risk Pooling
3 Inventory Management And Risk Pooling
 
Drivers of supply chain performance group 2
Drivers of supply chain performance group 2Drivers of supply chain performance group 2
Drivers of supply chain performance group 2
 
Inventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBAInventory Management - a ppt for PGDM/MBA
Inventory Management - a ppt for PGDM/MBA
 
Transportation in supply chain
Transportation in supply chain Transportation in supply chain
Transportation in supply chain
 
5. transportation problems
5. transportation problems5. transportation problems
5. transportation problems
 
Supply Chain Management chap 3
Supply Chain Management chap 3Supply Chain Management chap 3
Supply Chain Management chap 3
 
Warehouse Racking
Warehouse RackingWarehouse Racking
Warehouse Racking
 
SUPPLY CHAIN STRATEGIES
SUPPLY CHAIN STRATEGIESSUPPLY CHAIN STRATEGIES
SUPPLY CHAIN STRATEGIES
 
Supply Chain Management chap 10
Supply Chain Management chap 10Supply Chain Management chap 10
Supply Chain Management chap 10
 
FUNDAMENTAL OF WAREHOUSING
FUNDAMENTAL OF WAREHOUSINGFUNDAMENTAL OF WAREHOUSING
FUNDAMENTAL OF WAREHOUSING
 
Purchasing and vendor management
Purchasing and vendor managementPurchasing and vendor management
Purchasing and vendor management
 

Viewers also liked

Basic operation research
Basic operation researchBasic operation research
Basic operation researchVivekanandam BE
 
Solving Transportation Problem in Operations Research
Solving Transportation Problem in Operations ResearchSolving Transportation Problem in Operations Research
Solving Transportation Problem in Operations ResearchChandan Pahelwani
 
Operation research history and overview application limitation
Operation research history and overview application limitationOperation research history and overview application limitation
Operation research history and overview application limitationBalaji P
 
Transportation Problem in Operational Research
Transportation Problem in Operational ResearchTransportation Problem in Operational Research
Transportation Problem in Operational ResearchNeha Sharma
 
Advanced operation research
Advanced operation researchAdvanced operation research
Advanced operation researchSajid Ali
 
transporation problem - stepping stone method
transporation problem - stepping stone methodtransporation problem - stepping stone method
transporation problem - stepping stone methodoragon291764
 
Transportation and Assignment
Transportation and AssignmentTransportation and Assignment
Transportation and AssignmentLokesh Payasi
 
Transportation Problem
Transportation ProblemTransportation Problem
Transportation ProblemAlvin Niere
 
applications of operation research in business
applications of operation research in businessapplications of operation research in business
applications of operation research in businessraaz kumar
 
The profit maximizing firm
The profit maximizing firmThe profit maximizing firm
The profit maximizing firmJassen Jiary
 
Industrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture NotesIndustrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture NotesFellowBuddy.com
 

Viewers also liked (20)

Basic operation research
Basic operation researchBasic operation research
Basic operation research
 
Solving Transportation Problem in Operations Research
Solving Transportation Problem in Operations ResearchSolving Transportation Problem in Operations Research
Solving Transportation Problem in Operations Research
 
Operation research history and overview application limitation
Operation research history and overview application limitationOperation research history and overview application limitation
Operation research history and overview application limitation
 
unbalanced transportation problem
unbalanced transportation problemunbalanced transportation problem
unbalanced transportation problem
 
Transportation Problem in Operational Research
Transportation Problem in Operational ResearchTransportation Problem in Operational Research
Transportation Problem in Operational Research
 
Advanced operation research
Advanced operation researchAdvanced operation research
Advanced operation research
 
Assignment model
Assignment modelAssignment model
Assignment model
 
Span of a Management - Management Principles
Span of a Management - Management PrinciplesSpan of a Management - Management Principles
Span of a Management - Management Principles
 
transporation problem - stepping stone method
transporation problem - stepping stone methodtransporation problem - stepping stone method
transporation problem - stepping stone method
 
Inventory Control & Management
Inventory Control & ManagementInventory Control & Management
Inventory Control & Management
 
Transportation and Assignment
Transportation and AssignmentTransportation and Assignment
Transportation and Assignment
 
Transportation Problem
Transportation ProblemTransportation Problem
Transportation Problem
 
applications of operation research in business
applications of operation research in businessapplications of operation research in business
applications of operation research in business
 
Operational reseach ppt
Operational reseach pptOperational reseach ppt
Operational reseach ppt
 
B2B eCommerce
B2B eCommerceB2B eCommerce
B2B eCommerce
 
Liason and Public Relations
Liason and Public RelationsLiason and Public Relations
Liason and Public Relations
 
The profit maximizing firm
The profit maximizing firmThe profit maximizing firm
The profit maximizing firm
 
Managing Travel and Ticket Booking
Managing Travel and Ticket BookingManaging Travel and Ticket Booking
Managing Travel and Ticket Booking
 
Networking / Internet and Web Technologies
Networking / Internet and Web TechnologiesNetworking / Internet and Web Technologies
Networking / Internet and Web Technologies
 
Industrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture NotesIndustrial Engineering & Operation Research Lecture Notes
Industrial Engineering & Operation Research Lecture Notes
 

Similar to Operation Research Techniques in Transportation

Case Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysisCase Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysisSarang Bhutada
 
final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.pptxicohos114
 
Project management
Project managementProject management
Project managementsmumbahelp
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project managementAhmad Basim Hamza
 
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhdGL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhdnithinnick66
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chaintanishkagupta907
 
How to determine demand Centers-of-Gravity
How to determine demand Centers-of-Gravity How to determine demand Centers-of-Gravity
How to determine demand Centers-of-Gravity StellingConsulting
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateAdina Levin
 
A Dynamic Logistic Dispatching System With Set-Based Particle Swarm Optimization
A Dynamic Logistic Dispatching System With Set-Based Particle Swarm OptimizationA Dynamic Logistic Dispatching System With Set-Based Particle Swarm Optimization
A Dynamic Logistic Dispatching System With Set-Based Particle Swarm OptimizationRajib Roy
 
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docxCASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docxtroutmanboris
 
arithmaticpipline-170310085040.pptx
arithmaticpipline-170310085040.pptxarithmaticpipline-170310085040.pptx
arithmaticpipline-170310085040.pptxAshokRachapalli1
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path MethodParth Desani
 
Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...IEA-ETSAP
 
Final Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP OrdersFinal Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP OrdersBrian Kaiser, PE
 

Similar to Operation Research Techniques in Transportation (20)

Cpmprt
CpmprtCpmprt
Cpmprt
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Case Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysisCase Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysis
 
Ballou13
Ballou13Ballou13
Ballou13
 
final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
 
Project management
Project managementProject management
Project management
 
13 lecture project management
13 lecture project management13 lecture project management
13 lecture project management
 
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhdGL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
GL3eChap13-new.pptqpotieuwbsjsjsushshshdhd
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Unit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chainUnit 3 PERT.pptx in related to supply chain
Unit 3 PERT.pptx in related to supply chain
 
How to determine demand Centers-of-Gravity
How to determine demand Centers-of-Gravity How to determine demand Centers-of-Gravity
How to determine demand Centers-of-Gravity
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule Update
 
A Dynamic Logistic Dispatching System With Set-Based Particle Swarm Optimization
A Dynamic Logistic Dispatching System With Set-Based Particle Swarm OptimizationA Dynamic Logistic Dispatching System With Set-Based Particle Swarm Optimization
A Dynamic Logistic Dispatching System With Set-Based Particle Swarm Optimization
 
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docxCASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
 
arithmaticpipline-170310085040.pptx
arithmaticpipline-170310085040.pptxarithmaticpipline-170310085040.pptx
arithmaticpipline-170310085040.pptx
 
CPM - Critical Path Method
CPM - Critical Path MethodCPM - Critical Path Method
CPM - Critical Path Method
 
ch13.ppt
ch13.pptch13.ppt
ch13.ppt
 
Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...
 
Final Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP OrdersFinal Report - Optimizing Work Distribution for NP Orders
Final Report - Optimizing Work Distribution for NP Orders
 

More from We Learn - A Continuous Learning Forum from Welingkar's Distance Learning Program.

More from We Learn - A Continuous Learning Forum from Welingkar's Distance Learning Program. (20)

PGDM in Supply Chain Management
PGDM in Supply Chain ManagementPGDM in Supply Chain Management
PGDM in Supply Chain Management
 
PGDM in Rural & Agribusiness Management
PGDM in Rural & Agribusiness ManagementPGDM in Rural & Agribusiness Management
PGDM in Rural & Agribusiness Management
 
PGDM in E-Commerce Management
PGDM in E-Commerce ManagementPGDM in E-Commerce Management
PGDM in E-Commerce Management
 
PGDM in Service Excellence
PGDM in Service ExcellencePGDM in Service Excellence
PGDM in Service Excellence
 
PGDM in International Management
PGDM in International ManagementPGDM in International Management
PGDM in International Management
 
PGDM in IT Project Management
PGDM in IT Project ManagementPGDM in IT Project Management
PGDM in IT Project Management
 
Distance Learning PGDM in E-Business Management
Distance Learning PGDM in E-Business ManagementDistance Learning PGDM in E-Business Management
Distance Learning PGDM in E-Business Management
 
Distance Learning PGDM in Business Administration
Distance Learning PGDM in Business AdministrationDistance Learning PGDM in Business Administration
Distance Learning PGDM in Business Administration
 
PGDM in Finance Management
PGDM in Finance ManagementPGDM in Finance Management
PGDM in Finance Management
 
PGDM in Marketing Management
PGDM in Marketing ManagementPGDM in Marketing Management
PGDM in Marketing Management
 
PGDM in Operation Management
PGDM in Operation ManagementPGDM in Operation Management
PGDM in Operation Management
 
Marketing Management
Marketing ManagementMarketing Management
Marketing Management
 
PGDM in Media & Advertising
PGDM in Media & AdvertisingPGDM in Media & Advertising
PGDM in Media & Advertising
 
We School HR Management
We School HR ManagementWe School HR Management
We School HR Management
 
WE SCHOOL TRAVEL & TOURISM MANAGEMENT
WE SCHOOL TRAVEL & TOURISM MANAGEMENTWE SCHOOL TRAVEL & TOURISM MANAGEMENT
WE SCHOOL TRAVEL & TOURISM MANAGEMENT
 
Personal budgeting
Personal budgetingPersonal budgeting
Personal budgeting
 
Maintaining the financial health of businesses through financial accounting
Maintaining the financial health of businesses through financial accountingMaintaining the financial health of businesses through financial accounting
Maintaining the financial health of businesses through financial accounting
 
Asset Management Case Sstudy
Asset Management  Case SstudyAsset Management  Case Sstudy
Asset Management Case Sstudy
 
Team management’ scored on the football
Team management’ scored on the footballTeam management’ scored on the football
Team management’ scored on the football
 
Mc donalds Recruitment Case Study
Mc donalds Recruitment Case StudyMc donalds Recruitment Case Study
Mc donalds Recruitment Case Study
 

Recently uploaded

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 

Recently uploaded (20)

Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 

Operation Research Techniques in Transportation

  • 1. Welingkar’s Distance Learning Division CHAPTER-8 Operation Research Techniques in Transportation We Learn – A Continuous Learning Forum
  • 2. North West Corner Rule • Model to determine the optimum solution to a problem of separate demand points being supplied from separate points • Let us take a situation where there are 3 supply sources S1,S2,S3 and S4 and demand sinks D1,D2,D3,D4 • The costs associate with 12 combinations as well as the supplies ex each supply point and demands at each demand center are depicted in the figure on next slide Ch-08 - 0peration Research Techniques in Transportation
  • 3. North West Corner Rule fig-1 Destinations /origins D1 D2 D3 D4 D5 D6 S1 3 7 12 10 9 9 S2 14 20 13 6 12 4 S3 12 15 13 9 6 8 Demand 3 5 4 6 3 21 Ch-08 - 0peration Research Techniques in Transportation
  • 4. North West Corner Rule fig-1 • The three supply points S1,S2 and S3 can supply 9 units, 4 units, and 8 units respectively, whereas the three demand points D1, D2, D3, and D4 require 3,5,4,6 and 3 units respectively • The cost at the point of calculation will be treated as negative figures, because they are basically items whose negative impact the exercise is trying to minimize, in this case the total demand is 21units and the supply available is also 21 units Ch-08 - 0peration Research Techniques in Transportation
  • 5. North West Corner Rule • Where the supply may be more than demand, an additional dummy demand column has to be put with the residual supply being shown as units required by this demand center, and in the boxes for costs zero should be put • Similarly, in case demand exceeds shown there against, and again in the cost zero should be put in the respective additional squares. Ch-08 - 0peration Research Techniques in Transportation
  • 6. North West Corner Rule Figure-2 Destinations/ origins D1 D2 D3 D4 D5 Supply S1 11 12 13 14 15 9 S2 21 22 23 24 25 4 S3 31 32 33 34 35 8 Demand 3 5 4 6 3 21 Ch-08 - 0peration Research Techniques in Transportation
  • 7. North West Corner Rule Figure-2 • In fig2 we shall give the 15 squares individual numbers for easier identification • The five squares across supply point 1 will have no. 11 to 15, against supply point 2 the numbers will be 21 to 25, and for the 3rd one the no. will be 31 to 35. Ch-08 - 0peration Research Techniques in Transportation
  • 8. North West Corner Rule Figure-2 • Allocate supplies fro the supply sources to the demand sinks • The process starts form the north west corner i.e. square 11, and hence the name north west corner rule • Demand sink 1 has requirement for 3 units, and supply source 1 can supply 9 units, the total requirement of D1 from S1, when the situation is such that after meeting the demand of D1 from S1 , units remain, then the next allotment should be made horizontally, i.e. the next supply from S1 should go to D2 Ch-08 - 0peration Research Techniques in Transportation
  • 9. Deploying vehicles-Listing Method C D A G E B F Ch-08 - 0peration Research Techniques in Transportation
  • 10. Deploying vehicles-Listing Method • A is the starting point from where materials are sent out for delivery to various points B,C, D,E,F and G. • The distance between • A and B is 9 km, A and C is 11 km • B & C is 9 km, C & D is 14 km • C & E is 11 km, D & E is 7 km • E & F is 10 km, D & F is 10 km • D & G is 15 km, F & G is 11 km Ch-08 - 0peration Research Techniques in Transportation
  • 12. Listing Method • To initiate the solution procedure , a value of zero is assigned to the starting point, in this case A. • Thereafter select the shortest distance from origin A which in this case is AB as AC is longer at 11. In case both the distances are the same then selecting either will do • The value of B will be the total of value for A Zero plus the value AB which is 9 i.e.9 Ch-08 - 0peration Research Techniques in Transportation
  • 14. Listing Method • Thereafter from B we again choose the shortest of the alternate routes • You would have noted that under B, the route BA has been removed because that is no longer an option Ch-08 - 0peration Research Techniques in Transportation
  • 17. Next we observe that from C E is a shorter route hence A=0 B=9 C=18 D E=29 BE=14 CD=14 ED=7 DG=15 GD=15 FE=10 DF=10 G FD=10 DE=7 F GF=11 FG=11 EF=10 Ch-08 - 0peration Research Techniques in Transportation
  • 18. Listing Method • The route becomes A-B-C-E=29 km. proceeding this way you will finally find that the shortest route is • A-B-C-E-D-F-G=9+9+11+7+10+11=57 Ch-08 - 0peration Research Techniques in Transportation
  • 19. Listing Method • The importance of this model is listing • Unless they are plotted systematically and eliminated sequentially the above apparently simple exercise may be difficult in real life Ch-08 - 0peration Research Techniques in Transportation
  • 20. PERT & CPM • In order to realize valid results within time and budget expectations, one has to schedule jobs and tasks • Through scheduling one not only plans tasks, but also checks that resources are utilized optimally • Above two techniques are very commonly used Ch-08 - 0peration Research Techniques in Transportation
  • 21. Critical Path Method • In CPM the entire project work plan is graphically portrayed. This graph or network displays the interdependencies between activities that will lead to successful completion of the project. It must satisfy the following objectives – Evaluate progress towards attainment of project completion – Focus attention on potential and actual problems during work Ch-08 - 0peration Research Techniques in Transportation
  • 22. Critical Path Method – Provide frequent, accurate status reports at critical check points – Provide a regular and updated prediction of when the project will be completed – Provide at any time during the project determination of the shortest completion time if priorities and resources are shifted Ch-08 - 0peration Research Techniques in Transportation
  • 23. Preparing a flow chart • The project events joined by lines (activities) • The activities are depicted by lines illustrate project relationships and inter dependences Ch-08 - 0peration Research Techniques in Transportation
  • 24. Preparing a flow chart • The events depict significant occurrences or milestones in the completion of the project • Activities may be real or dummy, when it signifies an actual task that has be done, which means resources to be needed whereas dummy activities depicted in the flow chart just to show that the dummy activity needs to be completed before another activity can be taken up, which means in terms of resource the dummy will not extent any Ch-08 - 0peration Research Techniques in Transportation
  • 25. PERT network 7 3 1 2 5 4 Real Activites Dummy Activites 6 8 9 10 Ch-08 - 0peration Research Techniques in Transportation
  • 26. PERT • Circles with numbers are events • The dark continues lines depict real activities and the hyphenated lines depict dummy activities • The next step is to assign time to the activities as well as resources and costs. • This is where CPM comes in, • While in PERT probabilistic time estimates are put in while preparing the flow chart, CPM will use exact deterministic times with cost benefit trade offs Ch-08 - 0peration Research Techniques in Transportation
  • 27. Example of putting up a new systems set up at a manufacturing location 1. Studying the existing system in details and documenting all the current procedures 2. Customizing the system to suit the organizational requirement 3. Configuring the hardware requirement 4. Making application to exercise authorities 5. Training staff for new system 6. Preparing new master data 7. Setting date for change over 8. Uploading old data on new server Ch-08 - 0peration Research Techniques in Transportation
  • 28. This brings up the issue of • Optimistic time – The time estimate if activity proceeds perfectly (a) • Pessimistic time – The time estimate if extreme difficulties are experienced (b) • Most Likely Time – The expected time (c) the expected time as a mean can be calculated by apportioning weights to the 3 times, for instance giving weights of 1 each to (a) and (b) and 3 to (c) one can calculate the mean time Ch-08 - 0peration Research Techniques in Transportation
  • 29. Activity (a) (b) (c) Expected mean time 1.Studying the existing system in details and documenting all the current procedures 1 3 1.5 1.7 2.Customizing the system to suit the organizational requirement 2 4 3 3 .25 .1 .5 .75 4. Making application to exercise authorities 1 4 1.5 1.9 5. Training staff for new system 1 2 1 1.2 1.5 3 2 2.1 3.Configuring the hardware requirement 6. Preparing new master data 7. Setting date for change over 8.Uploading old data on new server Ch-08 - 0peration Research Techniques in Transportation
  • 30. Network Representation 4 2 5 1 3 6 Real Activites Dummy Activites 8 7 Ch-08 - 0peration Research Techniques in Transportation
  • 31. Interpretation • Linkage between (2) and (4) and (8) does not require allotment of a resources from the organization, save may be follow ups but non completion of event (4) will not bring about event (8) and finally (7) now on the basis of the expected mean time if we track the path from (1) to (7) via the three routes we shall get three sets of time. The one with longest time is the critical path, while the others are the slack paths Ch-08 - 0peration Research Techniques in Transportation
  • 32. Summary • To determine optimum solution to a distribution problem, we need to employ suitable operation research technique • North-west corner rule, listing method are suitable for planning and assigning vehicles for different routes • PERT and CPM are useful for timely completion of a project Ch-08 - 0peration Research Techniques in Transportation