SlideShare a Scribd company logo
1 of 56
Name Enrollment No.
Desai Keval J. 131100106005
Desai Divy J. 131100106008
Naik Kunj N. 131100106016
Patel Kinjal M. 131100106032
Patel Yash 131100106042
Guided by – Prof. Sunil Jaganiya
Prof. Pritesh Rathod
1
 Deduction for opening in masonry
 Length of steel bars
 Number of bars
 Examples
1. Rectangular Openings
2. Segmental Arch Openings
3. Semi-circular Arch Opening
4. Masonry of Arch
5. Lintel over Opening
 For rectangular opening full deduction is made
 Deduction = L x H x Thickness of wall
• When there is a segmental arch opening over the
rectangular opening, deduction in masonry is made
for both the rectangular opening and the segmental
arch opening .
• Area of rectangular part = L x H
• Area of segmental part = 2/3L x R + R3
/2L
• Therefore, the Total deduction :
[L x H + 2/3L x R ] x thickness of wall
 Area of the semi-circular portion = ∏ R2
/2
 But the approximate area of the semi circular
portion
= ¾ L x R
 Therefore, The Total Deduction
= [L x H + ¾ L x R] x thickness of wall
 The quantity of masonry in arch is measured in
cubic metre as a separate item.
 The quantity of arch masonry is deducted from the
total masonry.
 Masonry of arch
= Centre length of arch X breadth of the arch
;X thickness of arch
Therefore deduction for arch in masonry
= Lm x b x t
 An R.C.C lintel is provided over the door/ window
opening.
 The quantity of R.C.C of lintel is deducted from the
masonry work.
 A bearing of 10 to 15cm from the edge of opening is
provided to the lintel on either end of the opening.
Therefore,
Length of lintel (L) = Span of opening +2 x bearing
Deduction for lintel = L x Width of wall x
thickness of lintel
1. 90◦ Bend
2. 180◦ Bend
3. Overlap
4. For bent up bars
5. Lateral ties or vertical stirrups
6. Bent-up and hook
 Extra length for one bend = 4D
 Therefore, length of bar = L + 4D
B = Cover
D = Dia. Of bar
 Extra length for one hook = 9D
 If hook is at one end,
Total length of bar = L + 9D
 If hook is at both ends,
Total length of the bar = L + 9D + 9D
 For bars in tension,
Extra length = 40D + 9D + 9D
= 58D (For mild steel bars)
= 68.5D (For deformed steel bars)
 For bars in compression,
Extra length= 45D (For mild steel bars)
 CD = x/sinθ – x/tan θ
=x[ 1/sinθ – 1/tan θ ]
 If the bar is bent up at 45◦ ,
θ = 45◦
Therefore, CD = x [ 1.414-1.0 ]
=0.414x
=0.45x
Therefore, for bar bent up at 45◦,
Extra Length = 0.45x
 Let, X and Y are the outer dimensions of a
beam/column.
 A = X – 2 x cover – 2 x dia. of ring bar
 B = Y – 2 x cover – 2 x dia. of ring bar
 Length of 2 hooks = 2 x 12D or 0.15m
Therefore,
length of ring bar = 2 (A+B) + 24D
 Length of two hooks = 9D + 9D
 Extra length for one bent = 0.45X
Therefore,
Total length of bar = L + 9D + 9D + 0.45X
 Space = distance within which bars are to be laid
= L – 2 x cover
Therefore,
Number of bars =
(L – 2 x cove 𝑅)
c/c spacing of bars
 No. of stirrups in a beam
=
Length of beam − 2 x cover
c/c spacing of stirrups
+ 1
 Weight of reinforcement bar for 1m length
= d2/162 kg
where, d = diameter of bar in mm
Dia. Of Bar (mm)
Wt. of 1m length of Bar
(kg)
6 0.22
8 0.39
9 0.50
10 0.62
12 0.89
16 1.58
18 2.00
20 2.46
22 2.98
25 3.85
 A room has a clear dimension 3.0m × 7.0m . It has an
R.C.C slab as shown in fig.
 Top and Bottom cover is 20mm and end cover 50mm.
Calculate the following,
1) cement concrete for slab (1:1.5:3)
2) centering and shuttering for slab
3) Weight of 12mm Φ bars
4) Weight of 6 mm Φ distribution steel bars
5) Abstract for approximate estimate
6) Cement, sand, Aggregate for slab
7) Percentage steel in slab
8) Cost of slab per m.
9) Prepare bar bending schedule
weight of steel bars 12mm Φ @ 0.9 kg/m
6mm Φ @ 0.22 kg/m
Item
no
Item Description No. Length
(m)
Breadth
(m)
Height
(m)
Quantity
1
Cement concrete for
slab : (1:1.5:3)
L=7.0+0.23
+0.23
=7.46 m
B=3+0.23
+0.23
=3.46 m
1 7.46 3.46 0.12 3.09 cu.m
2
Centering and
shuttering for Slab
Bottom
Sides
1 7.0 3.0 21.0
2 7.46 0.15 2.24
2 3.46 0.15
1.04
24.28
sq. m.
3. 12 MM MAIN STEEL BARS @ 150 MM C/C
ALTERNATE BENT UP.
 L = 3+ 0.23 + 0.23 +[2 × 9 × 0.012] (two hooks) – [2 × 0.05] (cover)
= 3.58 m (straight length of bar)
 Span = 7 + 0.23+ 0.23 – [2 × 0.05] (cover)
= 7.36 m
 No. of bars =
7.36
0.15
+ 1
= 50 nos.
 Extra length of bent up bars
 Length = 0.45x
Where x = 0.12 - 2 × 0.02 (cover) - 0.012 (bar)
= 0.068 m
Item
no
Item Description No
Length
(m)
Breadth
(m)
Unit
Weight
(m)
Quantity
3.
12 mm main steel bars @
150 mm c/c alternate bent
up.
L =3.58+0.45x
=3.58+0.45×0.068
=3.61m
50 3.61 0.9 kg/m 162.45 kg
4. 6 MM DIA. DISTRIBUTION STEEL @ 180 MM
C/C BARS AT BOTTOM:
 Hook length = 9d
= 9 × 0.006
= 0.054 < 0.075 (mini. Hook length)
 L = 7 + 0.23 + 0.23 + [2 × 0.075] (hook) -
[2 × 0.05] (cover)
= 7.51m
 Width of slab = 3 + 0.23 + 0 23 – [2 × 0.05]
= 3.36m
 No. of bars =
3.36
0.18
+ 1
= 19.66
≈ 20 nos.
 Bars at top :
 Width of slab at one end for Bent up bar at top
= 0.23 + 0.45 - 0.068 - 0.05 (cover)
= 0.562 m
 No. of bars at one end
=
0.562
0.18
+ 1
=4.12
say 5 nos.
 No. of bars at both ends
= 2 × 5
= 10 nos.
 Total no. of bars = 20 + 10
= 30 nos.
Item
no
Item Description No
Length
(m)
Breadth
(m)
Unit
Weight
(m)
Quantity
4.
6 mm dia. Distribution steel.
@ 180 mm c/c
L = 7 + 0.23 + 0.23 +
2 × 0.075 (hook) -
2 × 0.05 (cover)
= 7.51 m
Total no. of bars = 20 + 10
= 30 nos
30 7.51
0.22
Kg/m
49.56
kg
No Item Qty. Per Rate
Amount
Rs.
1. Cement concrete for slab (1:1.5:3) 3.09 Cu. m 8800.00 27192.00
2 Centering and shuttering for slab 24.28 Sq. m 100.00 2428.00
3 12 mm Φ bars (HYSD bars) 162.45 Kg 45 7310
4 6 mm Φ bars (mild steel) 49.56 Kg 45 2230
5
Labour for cutting,bending and
placing steel
= 162.45 + 49.56
= 212.01 kg
212.01 Kg 5 1060
Total Rs.
Add 5% contingencies Rs.
Grand total Rs.
Say Rs.
40,220/-
2011/-
42,231/-
42,300/-
6. Cement, Sand, Aggregate for slab :
 Volume of dry concrete = 1.52 × 3.09
= 4.70 m3
 Cement =
1
5.5
× 4.70 = 0.855 m3
Now,
0.855
0.035
= 24.43 bags
 Sand =
1.5
5.5
× 4.70
= 1.28 m3
 Aggregate =
3
5.5
× 4.70 = 2.56 m3
7. Percentage of steel in slab :
 Volume of steel =
mass
density
=
212.01
7850
= 0.027 m3
 Volume of concrete = 3.09 m3
 Percentage of steel =
volume of steel
volume of concrete
× 100
=
0.027
3.09
× 100
= 0.873 %
8. Cost of slab per m2
 L = 7 + 0.23 + 0.23
= 7.46 m
 B = 3 + 0.23 + 0.23
= 3.46 m
Total area = 7.46 × 3.46 = 25.81 m2
 Cost of slab per m2 =
42300
25.81
= 1638.89 Rs.
Say 1640.00 Rs.
9. BAR BENDING SCHEDULE
Dia of
bar
Shape and length of bar
(cm)
Length
(m)
No Total
length
(m)
Unit
weight
(Kg/m)
Total
weight
(kg)
12 mm
Φ main
steel
3.61 50 180.5 0.9 162.45
6 mm
Φ
distribu
tion
steel
7.51 30 225.3 0.22 49.56
Total = 212.01
kg
 Calculated the quantities of the following items for a beam shown in
figure.
(a) reinforced concrete (1:2:4) for beam
or
(a) form work for beam
(b) weight of steel in kg
(c) prepare bar bending schedule.
(d) percentage steel w.r.t. reinforced concrete
References:-
A= 20mm Ø STRAIGHT BAR 3NOS. @ 2.5 kg/mt.
B= 16mm Ø BENT UP BAR 2NOS. @1.6 kg/mt.
C= 16mm Ø BENT UP BAR 2NOS. @1.6 kg/mt.
D= 12mm Ø ANCHOR BAR 2NOS. @0.89 kg/mt.
E= 10mm Ø STIRRUPS 10cm c/c @ 0.62 kg/mt.
F= 8mm Ø STIRRUPS @ 15cm c/c @ 0.40 kg/mt.
G= 6mm Ø STIRRUPS @ 21cm c/c @ 0.22 kg/mt.
H= 20mm Ø PINS @ 21cm c/c @ 0.25 kg/mt.
Item
no
Item Description No
Length
(m)
Breadth
(m)
Unit
Weight
(kg/m)
Quantity
(a)
(a)
Reinforced concrete (1:2:4)
for beam
L = 7 + 0.3 + 0.3 = 7.6 m
B = 0.30 m
H = 0.50 m
Or
Formwork for beam :
1 7.6 0.30 0.50 1.14 m3
Bottom 1 7 0.3 - 2.10 m2
Sides 2 7.6 - 0.5 7.60 m2
Ends 2 - 0.3 0.5
0.30 m2
10.0 m2
Item
no.
Item Description No.
Length
(m)
Unit
weight
(Kg/m)
Total
weight
(kg)
(b)
Weight of steel in kg :
A = 20 mm Φ straight bars
L = 7 + 0.3 + 0.3 +
[2×9×0.02](two hooks) –
[2× 0.05] (cover)
= 7.86 m
No. of bars = 3
3 7.86 @2.5
58.95
kg
H = 20 mm Φ pins :
L = 0.3 – [2× 0.025] (side cover)
= 0.25 m
No. of pins = span/spacing+1
Span = 7.6 – [2× 0.05] – [2×1.8]
+ [2×0.9]
= 2.10 m
Nos. = 2.10/0.21 +1 = 11 nos.
11 0.25
@2.5 6.88
kg
Item
no.
Item Description No.
Length
(m)
Unit
weight
(Kg/m)
Total
weight
(kg)
B = 16 mm Φ bent up bar
L = straight length of bar + [2×0.45x]
Straight length = 7.6 +
[2×9×0.016](hook)
- [2×0.05]
= 7.79 m
X = 0.5 – [2×0.025] (cover)
- [2×0.010] (stirrups) – 0.016
= 0.41 m
L = 7.79 + [2×0.45×0.41]
= 8.16 m
No. of bars = 2 nos.
2 8.16 @1.6
26.11
kg
D = 12 mm Φ anchor bar
L = 7.6 + [2×9×0.012] (two hook)
- [2×0.05] (cover)
= 7.72 m
2 7.72 @0.89
13.74
kg
Item
no.
Item Description No.
Length
(m)
Unit
weight
(Kg/m)
Total
weight
(kg)
E = 10 mm Φ stirrups :
A = 0.5 – [2×0.025] – [2×0.010]
= 0.43 m
B = 0.3 – [2×0.025] – [2×0.010]
= 0.23 m
L = 2(A+B) + 24D
(minimum hook length)
= 2(0.43+0.23) + 24×0.010
= 1.56m
Nos. = 2(1.8/0.1+1) = 38 nos.
38 1.56 @0.62 36.75 kg
F = 8 mm Φ stirrups :
A = 0.5 – [2×0.025] – [2×0.008]
= 0.434 m
B = 0.3 – [2×0.025] – [2×0.008]
= 0.234 m
Item
no.
Item Description No.
Length
(m)
Unit
weight
(Kg/m)
Total
weight
(kg)
L = 2 (A+B) + 24 D (hook)
= 2 (0.434 + 0.234) + 24×0.008
= 1.53 m
Nos. = 2(0.9/0.15) = 12 nos.
No stirrup is shown at the end.
Therefore 1 is not added.
12 1.53 @0.40 7.34 kg
G = 6 mm Φ stirrups:
A = 0.5 – [2×0.025] – [2×0.006]
= 0.438 m
B = 0.3 – [2×0.025] – [2×0.006]
= 0.238 m
L = 2 (A+B) + 0.15
(minimum hook length)
= 2 (0.438 + 0.238) + 0.15
= 1.502 m
Nos. = (7.6 – [2×1.8] – [2×0.9]) /
0.21
= 10.47 nos. =11 nos.
11 1.502 @0.22 3.36 kg
Dia
mm
Shape size cm
Length
(m)
No.
Total
length
(m)
Unite
weight
(kg/m)
Total
weight
(kg)
A type
20 mm
7.86 3 23.58 2.5 58.95
B type
16 mm Straight = 760 – [2×5] –
2 × 180
= 390
Top straight = 180 - 41
= 139
8.16 2 16.32 1.6 26.11
C type
16 mm
Straight = 760 – [2×5] –
[2×180] –
[2×90
= 210
Top straight = 180
8.13 2 16.26 1.6
26.0
Dia
mm
Shape size cm
Length
(m)
No.
Total
length
(m)
Unite
weight
(kg/m)
Total
weight
(kg)
D type
12 mm
7.72 2 15.44 0.89 13.74
E type
10 mm
Hook = 12d = 12×1.0
=12 cm
1.56 38 59.28 0.62 36.75
F type
8 mm
Hook=12d=12×8=9.6cm
Minimum hook length is
larger of 12 Φ or 7.5 cm.
1.53 12 18.36 0.40 7.34
Dia
mm
Shape size cm
Lengt
h
(m)
No.
Total
length
(m)
Unite
weight
(kg/m)
Total
weight
(kg)
G type 1.502 11 16.52 0.22 3.63
H type
20 mm
0.25 11 2.75 2.5 6.88
(d) Percentage steel w.r.t. reinforced concrete
 volume of steel =
mass
density
= 179.40/7850
= 0.0228 m3
 volume of concrete = 1.14 m3
 % steel =
volume of steel
volume of concrete
× 100
= 0.0228/1.14 × 100
= 2%.
 A reinforced cement concrete column is shown in figure.
Calculate the quantities of the following items.
1) 1 : 2 : 4 cement concrete for column and footing.
or
formwork for column and footing.
2) Steel for column and footing in kg.
3) Bar bending schedule
4) Number of cement bags for 1 : 2 : 4 R.C.C
or
4) Sand and aggregate for 1:2:4 concrete.
Item
no
Item Description No.
Length
(m)
Breadth
(m)
Height
(m)
Quantity
1. 1 : 2 : 4 cement concrete
for column and footing
For column :
Footing without slope
Area at bottom of footing
A1 =1 × 1 = 1 m2
Area at top of footing
A2 = 0.3 × 0.3 = 0.09 m2
Volume of sloping portion
=
ℎ
3
(A1 + A2 + A1 A2 )
=
0.5
3
(11+ 0.09+ 1 × 0.09)
=0.23 m3
1
1
3.5
1
0.3
1
0.3
0.3
0.32 m3
0.30 m3
0.23 m3
0.85 m3
Item
no
Item Description No.
Length
(m)
Breadth
(m)
Height
(m)
Quantity
Or
1.
Formwork for column and
footing
For column
For footing
A = 4 × (0.3+1) × 0.61 / 2
= 1.59 m2
At the edge of footing
4
4
-
1.0
0.3
-
3.5
0.3
4.2 m2
1.59 m2
1.20 m2
6.99 m2
Item
no.
Item Description No.
Length
(m)
Unit
weight
(Kg/m)
Total
weight
(kg)
2. Steel for column and footing :
Column bars :
16 Φ - 4 nos.
L = 3.5 + 0.5 + 0.3 + 0.3 +
[2 × 9 × 0.016] (two hook) -
[2 × 0.05] (cover) –
[2 × 0.012] (bars)
= 4.76 m
4 4.76 1.60 30.46 kg
Lateral tie :
8 mm Φ @ 15 cm c/c
A = 0.25 - 2 × 0.008
= 0.234 m
B = 0.234 m
L = 2 (A+B) +24 Φ
= 2 (0.234 + 0.234) + 24 × 0.008
= 1.13 m
Item
no.
Item Description No.
Length
(m)
Unit
weight
(Kg/m)
Total
weight
(kg)
No.of lateral ties
=
[3.5 +0.5+0.3 − 2×0.05 − 2×0.012 ]
0.15
+ 1
= 28.84
=29 nos.
29 1.13 @0.4
13.11
kg
Footing bars 12 Φ bars @ 100 mm c/c
both ways
L= 0.9 + 2 × 9 × 0.012
= 1.12 m
No. of bars = 0.9/0.10 + 1
= 10 nos.
2×10 1.12 @0.9 20.26
kg
Total = 63.73
kg
3. BAR BENDING SCHEDULE
Dia mm Shape size cm
Length
(m)
No.
Total
length
(m)
Unite
weight
(kg/m)
Total
weight
(kg)
16 Φ
Column
Bars
4.76 4 19.04 1.6
30.46
Kg
8 Φ
lateral
Ties
1.13 29 32.77 0.4
13.11
Kg
12 Φ
footing
Bars
1.12 20 22.4 0.9
20.16
Kg
Total wt.
63.73
Kg
4. Number of cement bags for 1 : 2 : 4 R.C.C
 total concrete = 0.85 m3
 volume of dry concrete = 0.85 × 1.52 = 1.292 m3
 1 : 2 : 4 = 7
 cement = 1 / 7 × 1.292 = 0.184 m3 = 0.184 / 0.035 = 5.26 bags
or
4. Sand and aggregate for 1:2:4 concrete :
 1 : 2 : 4 = 7
 volume of dry concrete = 1.292 m3
 sand = 2 / 7 × 1.292 = 0.37 m3
 aggregate = 4 / 7 × 1.292 = 0.74 m3
 Atul Prakashan by Dr. R.P. Rethaliya
 https://images.google.com/
Deduction of opening , Number of bars and Bar Bending Scheduling

More Related Content

What's hot

Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...Sayed Sajid H.Zidani
 
LECTURE 5 safety and stability analysis- modified-2
LECTURE 5 safety and stability analysis- modified-2LECTURE 5 safety and stability analysis- modified-2
LECTURE 5 safety and stability analysis- modified-2Bakenaz A. Zeidan
 
Breakwaters and types
Breakwaters and types Breakwaters and types
Breakwaters and types M Aamer Raza
 
Case study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityCase study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityAbhishek Mangukiya
 
Topic 3 mass haul diagram
Topic 3   mass haul diagramTopic 3   mass haul diagram
Topic 3 mass haul diagramkmasz kamal
 
Testing of hardened concrete
Testing of hardened concreteTesting of hardened concrete
Testing of hardened concreteJ C
 
Design of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tankDesign of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tankShoaib Wani
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Make Mannan
 
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSAsaru Champ
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test pptsayan sarkar
 
Unit 1 anchorage systems
Unit 1   anchorage systemsUnit 1   anchorage systems
Unit 1 anchorage systemsHaripriya Kumar
 
Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress methodJYOTIRANJAN43
 

What's hot (20)

Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 03 Determination of the flakiness and the elongation index for ...
 
LECTURE 5 safety and stability analysis- modified-2
LECTURE 5 safety and stability analysis- modified-2LECTURE 5 safety and stability analysis- modified-2
LECTURE 5 safety and stability analysis- modified-2
 
Hydraulic jump
Hydraulic jumpHydraulic jump
Hydraulic jump
 
bridge design
 bridge design bridge design
bridge design
 
Breakwaters and types
Breakwaters and types Breakwaters and types
Breakwaters and types
 
Case study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacityCase study on effect of water table on bearing capacity
Case study on effect of water table on bearing capacity
 
Topic 3 mass haul diagram
Topic 3   mass haul diagramTopic 3   mass haul diagram
Topic 3 mass haul diagram
 
Testing of hardened concrete
Testing of hardened concreteTesting of hardened concrete
Testing of hardened concrete
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Design of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tankDesign of overhead RCC rectangular water tank
Design of overhead RCC rectangular water tank
 
Flat bottom Overhead Water tank
Flat bottom Overhead Water tankFlat bottom Overhead Water tank
Flat bottom Overhead Water tank
 
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
Numerical problem and solution on pile capacity (usefulsearch.org) ( usefuls...
 
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITSDIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
 
Staircase design
Staircase designStaircase design
Staircase design
 
RCC beam Detail estimate
RCC beam Detail estimate RCC beam Detail estimate
RCC beam Detail estimate
 
Specific Energy (Lecture notes 05)
Specific Energy (Lecture notes 05)Specific Energy (Lecture notes 05)
Specific Energy (Lecture notes 05)
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test ppt
 
Water tank design ppt
Water tank design pptWater tank design ppt
Water tank design ppt
 
Unit 1 anchorage systems
Unit 1   anchorage systemsUnit 1   anchorage systems
Unit 1 anchorage systems
 
Rcc design by working stress method
Rcc design by working stress methodRcc design by working stress method
Rcc design by working stress method
 

Viewers also liked

Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Lamdade Akhil
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailingAli Ishaqi
 
Sp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailingSp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailingjemmabarsby
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)mbrsalman
 
Engineering formula sheet
Engineering formula sheetEngineering formula sheet
Engineering formula sheetsankalptiwari
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Columnমু সা
 
Development Length Hook Splice Of Reinforcements
Development Length Hook Splice Of ReinforcementsDevelopment Length Hook Splice Of Reinforcements
Development Length Hook Splice Of ReinforcementsSHERAZ HAMEED
 
lintel and arches for building construction
lintel and arches for building constructionlintel and arches for building construction
lintel and arches for building constructionNagma Modi
 
Bbs d2 deck segment ea06 496 r3
Bbs d2 deck segment ea06 496 r3Bbs d2 deck segment ea06 496 r3
Bbs d2 deck segment ea06 496 r3Duc Tran Xuan
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction FormworkAnkit Singhai
 
Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...
Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...
Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...India Water Portal
 
Numericals curved bar
Numericals curved barNumericals curved bar
Numericals curved barYatin Singh
 
International project appraisal
International project appraisalInternational project appraisal
International project appraisal17somya
 
Project Appraisal chapter 2
Project Appraisal chapter 2Project Appraisal chapter 2
Project Appraisal chapter 2Mazhar Poohlah
 
Synopsis on SMS Based Appliances Control
Synopsis on SMS Based Appliances ControlSynopsis on SMS Based Appliances Control
Synopsis on SMS Based Appliances ControlTarun Sharma
 

Viewers also liked (20)

Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Sp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailingSp 34-1987 handbook on reinforcement and detailing
Sp 34-1987 handbook on reinforcement and detailing
 
Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)Civil Engineering (Beams,Columns)
Civil Engineering (Beams,Columns)
 
Engineering formula sheet
Engineering formula sheetEngineering formula sheet
Engineering formula sheet
 
Presentation on Slab, Beam & Column
Presentation on Slab, Beam & ColumnPresentation on Slab, Beam & Column
Presentation on Slab, Beam & Column
 
Development Length Hook Splice Of Reinforcements
Development Length Hook Splice Of ReinforcementsDevelopment Length Hook Splice Of Reinforcements
Development Length Hook Splice Of Reinforcements
 
lintel and arches for building construction
lintel and arches for building constructionlintel and arches for building construction
lintel and arches for building construction
 
ONE WAY SLAB DESIGN
ONE WAY SLAB DESIGNONE WAY SLAB DESIGN
ONE WAY SLAB DESIGN
 
Bbs d2 deck segment ea06 496 r3
Bbs d2 deck segment ea06 496 r3Bbs d2 deck segment ea06 496 r3
Bbs d2 deck segment ea06 496 r3
 
Oilseed crops in rice-based farming systems in southern Bangladesh
Oilseed crops in rice-based farming systems in southern BangladeshOilseed crops in rice-based farming systems in southern Bangladesh
Oilseed crops in rice-based farming systems in southern Bangladesh
 
All you need to know about Construction Formwork
All you need to know about Construction FormworkAll you need to know about Construction Formwork
All you need to know about Construction Formwork
 
Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...
Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...
Water conservation & management in rural Punjab_S.R. Aggarwal_Deptt. of Water...
 
Numericals curved bar
Numericals curved barNumericals curved bar
Numericals curved bar
 
International project appraisal
International project appraisalInternational project appraisal
International project appraisal
 
Project Appraisal chapter 2
Project Appraisal chapter 2Project Appraisal chapter 2
Project Appraisal chapter 2
 
Solution guide
Solution guideSolution guide
Solution guide
 
Gopi frc
Gopi frcGopi frc
Gopi frc
 
Synopsis on SMS Based Appliances Control
Synopsis on SMS Based Appliances ControlSynopsis on SMS Based Appliances Control
Synopsis on SMS Based Appliances Control
 
Al bahr
Al bahrAl bahr
Al bahr
 

Similar to Deduction of opening , Number of bars and Bar Bending Scheduling

Diethyl Ether (DEE): Equipments Design
Diethyl Ether (DEE): Equipments DesignDiethyl Ether (DEE): Equipments Design
Diethyl Ether (DEE): Equipments DesignPratik Patel
 
materi kuliah it pln perhitungan plat balok
materi kuliah it pln perhitungan plat balokmateri kuliah it pln perhitungan plat balok
materi kuliah it pln perhitungan plat balokIlhamPutera2
 
Design and Manufacturing of Press Tools for Compressor Shell
Design and Manufacturing of Press Tools for Compressor ShellDesign and Manufacturing of Press Tools for Compressor Shell
Design and Manufacturing of Press Tools for Compressor ShellINFOGAIN PUBLICATION
 
Sums on Rigid Pavement Design
Sums on Rigid Pavement DesignSums on Rigid Pavement Design
Sums on Rigid Pavement DesignArnabKarmakar18
 
BAR BENDING SCHEDULE.pptx
BAR BENDING SCHEDULE.pptxBAR BENDING SCHEDULE.pptx
BAR BENDING SCHEDULE.pptxAMALKRISHNA31
 
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNCONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNAkshika Mahanama
 
Diseño y calculo de un puente de placa y vigas
Diseño y calculo de un puente de placa y vigasDiseño y calculo de un puente de placa y vigas
Diseño y calculo de un puente de placa y vigasDavid Chavez Huerto
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET Journal
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxDP NITHIN
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfAberaMamoJaleta
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumIRJET Journal
 
Cylindrical liner
Cylindrical linerCylindrical liner
Cylindrical linerHridoy Saha
 
Planing,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALLPlaning,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALLArshana Anu
 
estimation of structure
estimation of structureestimation of structure
estimation of structurekamariya keyur
 
Design of Football Stadium - Design Project for Civil Engineers
Design of Football Stadium - Design Project for Civil EngineersDesign of Football Stadium - Design Project for Civil Engineers
Design of Football Stadium - Design Project for Civil EngineersIndhumathi1134
 

Similar to Deduction of opening , Number of bars and Bar Bending Scheduling (20)

Diethyl Ether (DEE): Equipments Design
Diethyl Ether (DEE): Equipments DesignDiethyl Ether (DEE): Equipments Design
Diethyl Ether (DEE): Equipments Design
 
Columns.pdf
Columns.pdfColumns.pdf
Columns.pdf
 
materi kuliah it pln perhitungan plat balok
materi kuliah it pln perhitungan plat balokmateri kuliah it pln perhitungan plat balok
materi kuliah it pln perhitungan plat balok
 
Design and Manufacturing of Press Tools for Compressor Shell
Design and Manufacturing of Press Tools for Compressor ShellDesign and Manufacturing of Press Tools for Compressor Shell
Design and Manufacturing of Press Tools for Compressor Shell
 
Isolated Footing
Isolated FootingIsolated Footing
Isolated Footing
 
Sums on Rigid Pavement Design
Sums on Rigid Pavement DesignSums on Rigid Pavement Design
Sums on Rigid Pavement Design
 
BAR BENDING SCHEDULE.pptx
BAR BENDING SCHEDULE.pptxBAR BENDING SCHEDULE.pptx
BAR BENDING SCHEDULE.pptx
 
2 compression
2  compression2  compression
2 compression
 
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMNCONSTRUCTION TECHNOLOGY COSTING OF COLUMN
CONSTRUCTION TECHNOLOGY COSTING OF COLUMN
 
Diseño y calculo de un puente de placa y vigas
Diseño y calculo de un puente de placa y vigasDiseño y calculo de un puente de placa y vigas
Diseño y calculo de un puente de placa y vigas
 
Puentes
PuentesPuentes
Puentes
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line System
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptx
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
 
Cylindrical liner
Cylindrical linerCylindrical liner
Cylindrical liner
 
Planing,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALLPlaning,designing and analysis of HI TECH SHOPPING MALL
Planing,designing and analysis of HI TECH SHOPPING MALL
 
estimation of structure
estimation of structureestimation of structure
estimation of structure
 
Design of Football Stadium - Design Project for Civil Engineers
Design of Football Stadium - Design Project for Civil EngineersDesign of Football Stadium - Design Project for Civil Engineers
Design of Football Stadium - Design Project for Civil Engineers
 
Doubly reinforced beam design
Doubly reinforced beam   designDoubly reinforced beam   design
Doubly reinforced beam design
 

More from Yash Patel

statue of unity
statue of unitystatue of unity
statue of unityYash Patel
 
RETAINING WALL
RETAINING WALLRETAINING WALL
RETAINING WALLYash Patel
 
Famous places in India
Famous places in IndiaFamous places in India
Famous places in IndiaYash Patel
 
Canal Regulation Work
Canal Regulation WorkCanal Regulation Work
Canal Regulation WorkYash Patel
 
Street lighting
Street lightingStreet lighting
Street lightingYash Patel
 
Axially loaded columns
Axially loaded columnsAxially loaded columns
Axially loaded columnsYash Patel
 
Formwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of ArchFormwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of ArchYash Patel
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam Yash Patel
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its typeYash Patel
 
Lacing, battening
Lacing, battening Lacing, battening
Lacing, battening Yash Patel
 
Separation of boundary layer
Separation of boundary layerSeparation of boundary layer
Separation of boundary layerYash Patel
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, EqualizationYash Patel
 
Drought management and water harvesting
Drought management and water harvesting Drought management and water harvesting
Drought management and water harvesting Yash Patel
 
Environment Engineering
Environment EngineeringEnvironment Engineering
Environment EngineeringYash Patel
 

More from Yash Patel (15)

statue of unity
statue of unitystatue of unity
statue of unity
 
RETAINING WALL
RETAINING WALLRETAINING WALL
RETAINING WALL
 
Famous places in India
Famous places in IndiaFamous places in India
Famous places in India
 
Canal Regulation Work
Canal Regulation WorkCanal Regulation Work
Canal Regulation Work
 
Street lighting
Street lightingStreet lighting
Street lighting
 
Axially loaded columns
Axially loaded columnsAxially loaded columns
Axially loaded columns
 
Formwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of ArchFormwork for Bridge and Centering Of Arch
Formwork for Bridge and Centering Of Arch
 
Ventilation
VentilationVentilation
Ventilation
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
 
railway failure and its type
railway failure and its typerailway failure and its type
railway failure and its type
 
Lacing, battening
Lacing, battening Lacing, battening
Lacing, battening
 
Separation of boundary layer
Separation of boundary layerSeparation of boundary layer
Separation of boundary layer
 
Physical Unit Operation- Screening, Grit Removal, Equalization
Physical Unit Operation-Screening, Grit Removal,EqualizationPhysical Unit Operation-Screening, Grit Removal,Equalization
Physical Unit Operation- Screening, Grit Removal, Equalization
 
Drought management and water harvesting
Drought management and water harvesting Drought management and water harvesting
Drought management and water harvesting
 
Environment Engineering
Environment EngineeringEnvironment Engineering
Environment Engineering
 

Recently uploaded

Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate productionChinnuNinan
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 

Recently uploaded (20)

Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate production
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 

Deduction of opening , Number of bars and Bar Bending Scheduling

  • 1. Name Enrollment No. Desai Keval J. 131100106005 Desai Divy J. 131100106008 Naik Kunj N. 131100106016 Patel Kinjal M. 131100106032 Patel Yash 131100106042 Guided by – Prof. Sunil Jaganiya Prof. Pritesh Rathod 1
  • 2.
  • 3.  Deduction for opening in masonry  Length of steel bars  Number of bars  Examples
  • 4. 1. Rectangular Openings 2. Segmental Arch Openings 3. Semi-circular Arch Opening 4. Masonry of Arch 5. Lintel over Opening
  • 5.  For rectangular opening full deduction is made  Deduction = L x H x Thickness of wall
  • 6. • When there is a segmental arch opening over the rectangular opening, deduction in masonry is made for both the rectangular opening and the segmental arch opening . • Area of rectangular part = L x H • Area of segmental part = 2/3L x R + R3 /2L • Therefore, the Total deduction : [L x H + 2/3L x R ] x thickness of wall
  • 7.  Area of the semi-circular portion = ∏ R2 /2  But the approximate area of the semi circular portion = ¾ L x R  Therefore, The Total Deduction = [L x H + ¾ L x R] x thickness of wall
  • 8.  The quantity of masonry in arch is measured in cubic metre as a separate item.  The quantity of arch masonry is deducted from the total masonry.  Masonry of arch = Centre length of arch X breadth of the arch ;X thickness of arch Therefore deduction for arch in masonry = Lm x b x t
  • 9.  An R.C.C lintel is provided over the door/ window opening.  The quantity of R.C.C of lintel is deducted from the masonry work.  A bearing of 10 to 15cm from the edge of opening is provided to the lintel on either end of the opening.
  • 10. Therefore, Length of lintel (L) = Span of opening +2 x bearing Deduction for lintel = L x Width of wall x thickness of lintel
  • 11. 1. 90◦ Bend 2. 180◦ Bend 3. Overlap 4. For bent up bars 5. Lateral ties or vertical stirrups 6. Bent-up and hook
  • 12.  Extra length for one bend = 4D  Therefore, length of bar = L + 4D
  • 13. B = Cover D = Dia. Of bar  Extra length for one hook = 9D  If hook is at one end, Total length of bar = L + 9D  If hook is at both ends, Total length of the bar = L + 9D + 9D
  • 14.  For bars in tension, Extra length = 40D + 9D + 9D = 58D (For mild steel bars) = 68.5D (For deformed steel bars)  For bars in compression, Extra length= 45D (For mild steel bars)
  • 15.  CD = x/sinθ – x/tan θ =x[ 1/sinθ – 1/tan θ ]  If the bar is bent up at 45◦ , θ = 45◦ Therefore, CD = x [ 1.414-1.0 ] =0.414x =0.45x Therefore, for bar bent up at 45◦, Extra Length = 0.45x
  • 16.  Let, X and Y are the outer dimensions of a beam/column.  A = X – 2 x cover – 2 x dia. of ring bar  B = Y – 2 x cover – 2 x dia. of ring bar  Length of 2 hooks = 2 x 12D or 0.15m Therefore, length of ring bar = 2 (A+B) + 24D
  • 17.  Length of two hooks = 9D + 9D  Extra length for one bent = 0.45X Therefore, Total length of bar = L + 9D + 9D + 0.45X
  • 18.  Space = distance within which bars are to be laid = L – 2 x cover Therefore, Number of bars = (L – 2 x cove 𝑅) c/c spacing of bars  No. of stirrups in a beam = Length of beam − 2 x cover c/c spacing of stirrups + 1
  • 19.  Weight of reinforcement bar for 1m length = d2/162 kg where, d = diameter of bar in mm
  • 20. Dia. Of Bar (mm) Wt. of 1m length of Bar (kg) 6 0.22 8 0.39 9 0.50 10 0.62 12 0.89 16 1.58 18 2.00 20 2.46 22 2.98 25 3.85
  • 21.
  • 22.  A room has a clear dimension 3.0m × 7.0m . It has an R.C.C slab as shown in fig.  Top and Bottom cover is 20mm and end cover 50mm.
  • 23. Calculate the following, 1) cement concrete for slab (1:1.5:3) 2) centering and shuttering for slab 3) Weight of 12mm Φ bars 4) Weight of 6 mm Φ distribution steel bars 5) Abstract for approximate estimate 6) Cement, sand, Aggregate for slab 7) Percentage steel in slab 8) Cost of slab per m. 9) Prepare bar bending schedule weight of steel bars 12mm Φ @ 0.9 kg/m 6mm Φ @ 0.22 kg/m
  • 24. Item no Item Description No. Length (m) Breadth (m) Height (m) Quantity 1 Cement concrete for slab : (1:1.5:3) L=7.0+0.23 +0.23 =7.46 m B=3+0.23 +0.23 =3.46 m 1 7.46 3.46 0.12 3.09 cu.m 2 Centering and shuttering for Slab Bottom Sides 1 7.0 3.0 21.0 2 7.46 0.15 2.24 2 3.46 0.15 1.04 24.28 sq. m.
  • 25. 3. 12 MM MAIN STEEL BARS @ 150 MM C/C ALTERNATE BENT UP.  L = 3+ 0.23 + 0.23 +[2 × 9 × 0.012] (two hooks) – [2 × 0.05] (cover) = 3.58 m (straight length of bar)  Span = 7 + 0.23+ 0.23 – [2 × 0.05] (cover) = 7.36 m  No. of bars = 7.36 0.15 + 1 = 50 nos.  Extra length of bent up bars  Length = 0.45x Where x = 0.12 - 2 × 0.02 (cover) - 0.012 (bar) = 0.068 m
  • 26. Item no Item Description No Length (m) Breadth (m) Unit Weight (m) Quantity 3. 12 mm main steel bars @ 150 mm c/c alternate bent up. L =3.58+0.45x =3.58+0.45×0.068 =3.61m 50 3.61 0.9 kg/m 162.45 kg
  • 27. 4. 6 MM DIA. DISTRIBUTION STEEL @ 180 MM C/C BARS AT BOTTOM:  Hook length = 9d = 9 × 0.006 = 0.054 < 0.075 (mini. Hook length)  L = 7 + 0.23 + 0.23 + [2 × 0.075] (hook) - [2 × 0.05] (cover) = 7.51m  Width of slab = 3 + 0.23 + 0 23 – [2 × 0.05] = 3.36m  No. of bars = 3.36 0.18 + 1 = 19.66 ≈ 20 nos.
  • 28.  Bars at top :  Width of slab at one end for Bent up bar at top = 0.23 + 0.45 - 0.068 - 0.05 (cover) = 0.562 m  No. of bars at one end = 0.562 0.18 + 1 =4.12 say 5 nos.  No. of bars at both ends = 2 × 5 = 10 nos.  Total no. of bars = 20 + 10 = 30 nos.
  • 29. Item no Item Description No Length (m) Breadth (m) Unit Weight (m) Quantity 4. 6 mm dia. Distribution steel. @ 180 mm c/c L = 7 + 0.23 + 0.23 + 2 × 0.075 (hook) - 2 × 0.05 (cover) = 7.51 m Total no. of bars = 20 + 10 = 30 nos 30 7.51 0.22 Kg/m 49.56 kg
  • 30. No Item Qty. Per Rate Amount Rs. 1. Cement concrete for slab (1:1.5:3) 3.09 Cu. m 8800.00 27192.00 2 Centering and shuttering for slab 24.28 Sq. m 100.00 2428.00 3 12 mm Φ bars (HYSD bars) 162.45 Kg 45 7310 4 6 mm Φ bars (mild steel) 49.56 Kg 45 2230 5 Labour for cutting,bending and placing steel = 162.45 + 49.56 = 212.01 kg 212.01 Kg 5 1060 Total Rs. Add 5% contingencies Rs. Grand total Rs. Say Rs. 40,220/- 2011/- 42,231/- 42,300/-
  • 31. 6. Cement, Sand, Aggregate for slab :  Volume of dry concrete = 1.52 × 3.09 = 4.70 m3  Cement = 1 5.5 × 4.70 = 0.855 m3 Now, 0.855 0.035 = 24.43 bags  Sand = 1.5 5.5 × 4.70 = 1.28 m3  Aggregate = 3 5.5 × 4.70 = 2.56 m3
  • 32. 7. Percentage of steel in slab :  Volume of steel = mass density = 212.01 7850 = 0.027 m3  Volume of concrete = 3.09 m3  Percentage of steel = volume of steel volume of concrete × 100 = 0.027 3.09 × 100 = 0.873 %
  • 33. 8. Cost of slab per m2  L = 7 + 0.23 + 0.23 = 7.46 m  B = 3 + 0.23 + 0.23 = 3.46 m Total area = 7.46 × 3.46 = 25.81 m2  Cost of slab per m2 = 42300 25.81 = 1638.89 Rs. Say 1640.00 Rs.
  • 34. 9. BAR BENDING SCHEDULE Dia of bar Shape and length of bar (cm) Length (m) No Total length (m) Unit weight (Kg/m) Total weight (kg) 12 mm Φ main steel 3.61 50 180.5 0.9 162.45 6 mm Φ distribu tion steel 7.51 30 225.3 0.22 49.56 Total = 212.01 kg
  • 35.  Calculated the quantities of the following items for a beam shown in figure. (a) reinforced concrete (1:2:4) for beam or (a) form work for beam (b) weight of steel in kg (c) prepare bar bending schedule. (d) percentage steel w.r.t. reinforced concrete
  • 36.
  • 37. References:- A= 20mm Ø STRAIGHT BAR 3NOS. @ 2.5 kg/mt. B= 16mm Ø BENT UP BAR 2NOS. @1.6 kg/mt. C= 16mm Ø BENT UP BAR 2NOS. @1.6 kg/mt. D= 12mm Ø ANCHOR BAR 2NOS. @0.89 kg/mt. E= 10mm Ø STIRRUPS 10cm c/c @ 0.62 kg/mt. F= 8mm Ø STIRRUPS @ 15cm c/c @ 0.40 kg/mt. G= 6mm Ø STIRRUPS @ 21cm c/c @ 0.22 kg/mt. H= 20mm Ø PINS @ 21cm c/c @ 0.25 kg/mt.
  • 38. Item no Item Description No Length (m) Breadth (m) Unit Weight (kg/m) Quantity (a) (a) Reinforced concrete (1:2:4) for beam L = 7 + 0.3 + 0.3 = 7.6 m B = 0.30 m H = 0.50 m Or Formwork for beam : 1 7.6 0.30 0.50 1.14 m3 Bottom 1 7 0.3 - 2.10 m2 Sides 2 7.6 - 0.5 7.60 m2 Ends 2 - 0.3 0.5 0.30 m2 10.0 m2
  • 39. Item no. Item Description No. Length (m) Unit weight (Kg/m) Total weight (kg) (b) Weight of steel in kg : A = 20 mm Φ straight bars L = 7 + 0.3 + 0.3 + [2×9×0.02](two hooks) – [2× 0.05] (cover) = 7.86 m No. of bars = 3 3 7.86 @2.5 58.95 kg H = 20 mm Φ pins : L = 0.3 – [2× 0.025] (side cover) = 0.25 m No. of pins = span/spacing+1 Span = 7.6 – [2× 0.05] – [2×1.8] + [2×0.9] = 2.10 m Nos. = 2.10/0.21 +1 = 11 nos. 11 0.25 @2.5 6.88 kg
  • 40. Item no. Item Description No. Length (m) Unit weight (Kg/m) Total weight (kg) B = 16 mm Φ bent up bar L = straight length of bar + [2×0.45x] Straight length = 7.6 + [2×9×0.016](hook) - [2×0.05] = 7.79 m X = 0.5 – [2×0.025] (cover) - [2×0.010] (stirrups) – 0.016 = 0.41 m L = 7.79 + [2×0.45×0.41] = 8.16 m No. of bars = 2 nos. 2 8.16 @1.6 26.11 kg D = 12 mm Φ anchor bar L = 7.6 + [2×9×0.012] (two hook) - [2×0.05] (cover) = 7.72 m 2 7.72 @0.89 13.74 kg
  • 41. Item no. Item Description No. Length (m) Unit weight (Kg/m) Total weight (kg) E = 10 mm Φ stirrups : A = 0.5 – [2×0.025] – [2×0.010] = 0.43 m B = 0.3 – [2×0.025] – [2×0.010] = 0.23 m L = 2(A+B) + 24D (minimum hook length) = 2(0.43+0.23) + 24×0.010 = 1.56m Nos. = 2(1.8/0.1+1) = 38 nos. 38 1.56 @0.62 36.75 kg F = 8 mm Φ stirrups : A = 0.5 – [2×0.025] – [2×0.008] = 0.434 m B = 0.3 – [2×0.025] – [2×0.008] = 0.234 m
  • 42. Item no. Item Description No. Length (m) Unit weight (Kg/m) Total weight (kg) L = 2 (A+B) + 24 D (hook) = 2 (0.434 + 0.234) + 24×0.008 = 1.53 m Nos. = 2(0.9/0.15) = 12 nos. No stirrup is shown at the end. Therefore 1 is not added. 12 1.53 @0.40 7.34 kg G = 6 mm Φ stirrups: A = 0.5 – [2×0.025] – [2×0.006] = 0.438 m B = 0.3 – [2×0.025] – [2×0.006] = 0.238 m L = 2 (A+B) + 0.15 (minimum hook length) = 2 (0.438 + 0.238) + 0.15 = 1.502 m Nos. = (7.6 – [2×1.8] – [2×0.9]) / 0.21 = 10.47 nos. =11 nos. 11 1.502 @0.22 3.36 kg
  • 43. Dia mm Shape size cm Length (m) No. Total length (m) Unite weight (kg/m) Total weight (kg) A type 20 mm 7.86 3 23.58 2.5 58.95 B type 16 mm Straight = 760 – [2×5] – 2 × 180 = 390 Top straight = 180 - 41 = 139 8.16 2 16.32 1.6 26.11 C type 16 mm Straight = 760 – [2×5] – [2×180] – [2×90 = 210 Top straight = 180 8.13 2 16.26 1.6 26.0
  • 44. Dia mm Shape size cm Length (m) No. Total length (m) Unite weight (kg/m) Total weight (kg) D type 12 mm 7.72 2 15.44 0.89 13.74 E type 10 mm Hook = 12d = 12×1.0 =12 cm 1.56 38 59.28 0.62 36.75 F type 8 mm Hook=12d=12×8=9.6cm Minimum hook length is larger of 12 Φ or 7.5 cm. 1.53 12 18.36 0.40 7.34
  • 45. Dia mm Shape size cm Lengt h (m) No. Total length (m) Unite weight (kg/m) Total weight (kg) G type 1.502 11 16.52 0.22 3.63 H type 20 mm 0.25 11 2.75 2.5 6.88
  • 46. (d) Percentage steel w.r.t. reinforced concrete  volume of steel = mass density = 179.40/7850 = 0.0228 m3  volume of concrete = 1.14 m3  % steel = volume of steel volume of concrete × 100 = 0.0228/1.14 × 100 = 2%.
  • 47.  A reinforced cement concrete column is shown in figure. Calculate the quantities of the following items. 1) 1 : 2 : 4 cement concrete for column and footing. or formwork for column and footing. 2) Steel for column and footing in kg. 3) Bar bending schedule 4) Number of cement bags for 1 : 2 : 4 R.C.C or 4) Sand and aggregate for 1:2:4 concrete.
  • 48.
  • 49. Item no Item Description No. Length (m) Breadth (m) Height (m) Quantity 1. 1 : 2 : 4 cement concrete for column and footing For column : Footing without slope Area at bottom of footing A1 =1 × 1 = 1 m2 Area at top of footing A2 = 0.3 × 0.3 = 0.09 m2 Volume of sloping portion = ℎ 3 (A1 + A2 + A1 A2 ) = 0.5 3 (11+ 0.09+ 1 × 0.09) =0.23 m3 1 1 3.5 1 0.3 1 0.3 0.3 0.32 m3 0.30 m3 0.23 m3 0.85 m3
  • 50. Item no Item Description No. Length (m) Breadth (m) Height (m) Quantity Or 1. Formwork for column and footing For column For footing A = 4 × (0.3+1) × 0.61 / 2 = 1.59 m2 At the edge of footing 4 4 - 1.0 0.3 - 3.5 0.3 4.2 m2 1.59 m2 1.20 m2 6.99 m2
  • 51. Item no. Item Description No. Length (m) Unit weight (Kg/m) Total weight (kg) 2. Steel for column and footing : Column bars : 16 Φ - 4 nos. L = 3.5 + 0.5 + 0.3 + 0.3 + [2 × 9 × 0.016] (two hook) - [2 × 0.05] (cover) – [2 × 0.012] (bars) = 4.76 m 4 4.76 1.60 30.46 kg Lateral tie : 8 mm Φ @ 15 cm c/c A = 0.25 - 2 × 0.008 = 0.234 m B = 0.234 m L = 2 (A+B) +24 Φ = 2 (0.234 + 0.234) + 24 × 0.008 = 1.13 m
  • 52. Item no. Item Description No. Length (m) Unit weight (Kg/m) Total weight (kg) No.of lateral ties = [3.5 +0.5+0.3 − 2×0.05 − 2×0.012 ] 0.15 + 1 = 28.84 =29 nos. 29 1.13 @0.4 13.11 kg Footing bars 12 Φ bars @ 100 mm c/c both ways L= 0.9 + 2 × 9 × 0.012 = 1.12 m No. of bars = 0.9/0.10 + 1 = 10 nos. 2×10 1.12 @0.9 20.26 kg Total = 63.73 kg
  • 53. 3. BAR BENDING SCHEDULE Dia mm Shape size cm Length (m) No. Total length (m) Unite weight (kg/m) Total weight (kg) 16 Φ Column Bars 4.76 4 19.04 1.6 30.46 Kg 8 Φ lateral Ties 1.13 29 32.77 0.4 13.11 Kg 12 Φ footing Bars 1.12 20 22.4 0.9 20.16 Kg Total wt. 63.73 Kg
  • 54. 4. Number of cement bags for 1 : 2 : 4 R.C.C  total concrete = 0.85 m3  volume of dry concrete = 0.85 × 1.52 = 1.292 m3  1 : 2 : 4 = 7  cement = 1 / 7 × 1.292 = 0.184 m3 = 0.184 / 0.035 = 5.26 bags or 4. Sand and aggregate for 1:2:4 concrete :  1 : 2 : 4 = 7  volume of dry concrete = 1.292 m3  sand = 2 / 7 × 1.292 = 0.37 m3  aggregate = 4 / 7 × 1.292 = 0.74 m3
  • 55.  Atul Prakashan by Dr. R.P. Rethaliya  https://images.google.com/