SlideShare a Scribd company logo
1 of 58
By : Abhishek Shah
SAL Institute of Technology and
Engineering Research
Ahmedabad
INDIA
Content
 Slump Test
 Flow Test
 Compacting Factor Test
 Ve Be Time Test
 L-Box Test
 J-Ring Test
 V-Funnel Test
 Orimet Test
Slump Test
Principle
Apparatus
Procedure
Types
Of
Slump
Aim
Slump Test
 Aim :-
To Determine the Consistency Of Concrete
 Principle
The slump test result is a measure of the behavior of a compacted
inverted cone of concrete under the action of gravity. It measures the
consistency or the wetness of concrete.
Slump Test
 Apparatus
 Slump cone : frustum of a cone, 300 mm (12 in) of height. The
base is 200 mm (8in) in diameter and it has a smaller opening
at the top of 100 mm
 Scale for measurement,
 Temping rod(steel) 15mm diameter, 60cm length.
Slump Test
 Procedure
 The base is placed on a smooth surface and the container is
filled with concrete in three layers, whose workability is to be
tested .
 Each layer is temped 25 times with a standard 16 mm (5/8 in)
diameter steel rod, rounded at the end.
 When the mold is completely filled with concrete, the top
surface is struck off (leveled with mold top opening) by
means of screening and rolling motion of the temping rod.
 The mold must be firmly held against its base during the
entire operation so that it could not move due to the pouring
of concrete and this can be done by means of handles or foot
– rests brazed to the mold.
Slump Test
 Procedure
 Immediately after filling is completed and the concrete is
leveled, the cone is slowly and carefully lifted vertically, an
unsupported concrete will now slump.
 The decrease in the height of the center of the slumped
concrete is called slump.
 The slump is measured by placing the cone just besides the
slump concrete and the temping rod is placed over the cone
so that it should also come over the area of slumped concrete.
 The decrease in height of concrete to that of mould is noted
with scale. (usually measured to the nearest 5 mm (1/4 in).
Slump Test
 Types Of Slump
The slumped concrete takes various shapes, and
according to the profile of slumped concrete, the slump is
termed as;
 Collapse Slump
 Shear Slump
 True Slump
Slump Test
 Types Of Slump
 Collapse Slump
In a collapse slump the concrete collapses completely.
 A collapse slump will generally mean that the mix is too wet or that it
is a high workability mix, for which slump test is not appropriate.
 Shear Slump
In a shear slump the top portion of the concrete shears off and slips
sideways. OR
If one-half of the cone slides down an inclined plane, the slump is said
to be a shear slump.
 If a shear or collapse slump is achieved, a fresh sample should be
taken and the test is repeated.
 If the shear slump persists, as may the case with harsh mixes, this is
an indication of lack of cohesion of the mix.
Slump Test
 Types Of Slump
 True Slump
In a true slump the concrete simply subsides, keeping more or less to
shape
 This is the only slump which is used in various tests.
 Mixes of stiff consistence have a Zero slump, so that in the rather dry
range no variation can be detected between mixes of different
workability.
However , in a lean mix with a tendency to harshness, a true slump can
easily change to the shear slump type or even to collapse, and widely
different values of slump can be obtained in different samples from the
same mix; thus, the slump test is unreliable for lean mixes.
Slump Test
 Uses
 The slump test is used to ensure uniformity for different batches
of similar concrete under field conditions and to ascertain the
effects of plasticizers on their introduction.
 This test is very useful on site as a check on the day-to-day or
hour- to-hour variation in the materials being fed into the mixer.
An increase in slump may mean, for instance, that the moisture
content of aggregate has unexpectedly increases.
 Other cause would be a change in the grading of the aggregate,
such as a deficiency of sand.
 Too high or too low a slump gives immediate warning and
enables the mixer operator to remedy the situation.
 This application of slump test as well as its simplicity, is
responsible for its widespread use.
Slump Test
Degree of
workability
Slump (mm) Use for which concrete is suitable
Very low 0 - 25
Very dry mixes; used in road making. Roads
vibrated by power operated machines
Low 25 - 50
Low workability mixes; used for foundations
with light reinforcement. Roads vibrated by
hand operated Machines
Medium 50 - 100
Medium workability mixes; manually
compacted flat slabs using crushed
aggregates. Normal reinforced concrete
manually compacted and heavily reinforced
sections with vibrations
High 100 - 175
High workability concrete; for sections
with congested reinforcement. Not
normally suitable for vibration
>Table : Workability, Slump and Compacting Factor of concrete with 19 or 38 mm (3/4 or 11/2 in) maximum size of aggregate.
Aim
Principle
Apparatus
Procedure
Result
Flow Test
Aim :-
The flow table test or flow test is a method to determine the
consistence of fresh concrete.
 Principle
This test is giving us the ability of concrete to flow under the
gravitational force when poured and compacted within the cone
and suddenly lifted up
Flow Test
 Equipment
 Flow table with a grip and a hinge, 70 cm x 70 cm.
 Abrams cone, open at the top and at the bottom - 30 cm high, 17
cm top diameter, 25 cm base diameter
 Water bucket and broom for wetting the flow table.
 Tamping rod, 60 cm height
 Scale for measurement
Flow Test
 Conducting
 The flow table is wetted.
 The cone is placed on the flow table and filled with fresh
concrete in two layers, each layer 25 times tamp with
tamping rod.
 The cone is lifted, allowing the concrete to flow.
 The flow table is then lifted up several centimeters and
then dropped, causing the concrete flow a little bit further.
 After this the diameter of the concrete is measured in a 6
different direction and take the average.
Flow Test
Flow Test
Percent of
Flow
0 – 20 % 20 – 60 % 60 – 100 % 100 – 120 % 120 – 150 %
Consistency Dry Stiff Plastic Wet Sloppy
Aim
Principle
Apparatus
Procedure
Result
Compacting Factor Test
 Aim
 To measure the degree of compaction For the standard
amount of work and thus offer a direct and reasonably
reliable assessment of the workability Of concrete .
 Principle
 the test require measurement of the weight of the
partially and fully compacted concrete and the ratio the
partially compacted weight to the fully compacted
weight, which is always less than one, is known as
compacted factor .
 For the normal range of concrete the compacting factor
lies between 0.8 - 0.92
Compacting Factor Test
 Apparatus
 Trowels
 Hand Scoop (15.2 cm long)
 Rod of steel or other suitable material
(1.6 cm diameter, 61 cm long rounded
at one end ).
 Balance.
Compacting Factor Test
 Procedure
1) Ensure the apparatus and associated equipment are clean before test
and free from hardened concrete and superfluous water .
2) Weigh the bottom cylinder to nearest 10gm , put it back on the stand
and cover it up with a pair of floats .
3) Gently fill the upper hopper with the sampled concrete to the level of
the rim with use of a scoop .
4) Immediately open the trap door of the upper hopper and allow the
sampled concrete to fall into the middle hopper .
5) Remove the floats on top of the bottom cylinder and open the trap
door of the middle hopper allowing the sampled concrete to fall into
the bottom cylinder .
6) Remove the surplus concrete above the top of the bottom cylinder by
holding a float in each hand and move towards each other to cut off
the concrete across the top of cylinder
Compacting Factor Test
7) Wipe clean the outside of cylinder of concrete and weigh to nearest
10gm .
8) Subtract the weight of empty cylinder from the weight of cylinder plus
concrete to obtain the weight of partially compacted concrete .
9) Remove the concrete from the cylinder and refill with sampled
concrete in layers .
10) Compact each layer thoroughly with the standard Compacting Bar to
achieve full compaction .
11) Float off the surplus concrete to top of cylinder and wipe it clean .
12) Weigh the cylinder to nearest 10gm and subtract the weight of empty
cylinder from the weight of cylinder plus concrete to obtain the weight
of fully compacted concrete .
Compacting Factor Test
Workability Slump (mm) C.F Uses
Very Low 0 - 25 0.78 Roads - Pavements
Low 25 - 50 0.85 Foundations Concrete
Medium 25 - 100 0.92 Reinforced Concrete
High 100 - 175 0.95
Reinforced Concrete
(High Reinforcement)
VeBe Time Test
 Aim
 To Measure the workability of Concrete
 Principle
 It is based on measuring the time (Called VEBE time) needed to transfer the
shape of a concrete mix from a frustum cone to a cylinder (these shapes are
standardized by the apparatus of this test), by vibrating and compacting the
mix. The more VEBE time needed the less workable the mix is. This method
is very useful for stiff mixes.
VeBe Time Test
 Apparatus
 Cylindrical container with diameter = 240
mm, and height = 200 mm
 Mold: the same mold used in the slump
test.
 Disc : A transparent horizontal disc
attached to a rod which slides vertically
 Vibrating Table : 380*260 mm, supported
by four rubber shock absorbers
 Tamping Rod
 Stop watch
VeBe Time Test
 Procedure
1) Slump test as described earlier is performed, placing the slump
cone inside the sheet metal cylindrical pot of the consist meter.
2) The glass disc attached to the swivel arm is turn and place on the
top of the concrete in the pot.
3) The electrical vibrator is then switched on and simultaneously a
stop watch started.
4) The vibration is continued till such time as the conical shape of the
concrete disappears and the concrete assume a cylindrical shape.
5) This can be judge by observing the glass disc from the top
disappearance of transparency.
6) Immediately when the concrete fully assume a cylindrical shape,
the stop watch is switched off.
VeBe Time Test
7) The time required for the shape of concrete to change from slump
cone shape to cylindrical shape in second is known as Vibe Degree.
8) This method is very suitable for very dry concrete whose slump
value cannot be measure by slump test, but the vibration is too
vigorous for concrete with slump greater than about 50m.
The test fails if VeBe Time is less than 5 seconds .. And the test must be
created when no collapse or shears slump in concrete
Apparatus
L-Box Test
 Aim
 The method aims at investigating the passing ability of SCC.
 Principle
 It measures the reached height of fresh SCC after passing through the
specified gaps of steel bars and flowing within a defined flow distance.
With this reached height, the passing or blocking behavior of SCC can be
estimated
 Apparatus
 Two types of gates can be
used, one with 3 smooth bars
and one with 2 smooth bars.
The gaps are 41 and 59 mm,
respectively
 Suitable tool for ensuring
that the box is level i.e. a
spirit level
 Suitable buckets for taking
concrete sample
L Box Test
L-Box Test
L-Box Test
 Procedure
 Place the L-box in a stable and level position
 Fill the vertical part of the L-box, with the extra adapter mounted, with
12.7 liters of representative fresh SCC
 Let the concrete rest in the vertical part for one minute (± 10 seconds).
During this time the concrete will display whether it is stable or not
(segregation).
 Lift the sliding gate and let the concrete flow out of the vertical part into
the horizontal part of the L-box.
 When the concrete has stopped moving, measure the average distance,
noted as Δh, between the top edge of the box and the concrete that
reached the end of the box, at three positions, one at the centre and two at
each side
L-Box Test
 Expression Of Results
 The passing ratio PL or blocking ratio BL is calculated using equation (2) or
(2’), and expressed in dimensionless to the nearest 0.01
 Precision
 The passing ratio PL or blocking ratio BL is calculated using equation (2) or
(2’), and expressed in dimensionless to the nearest 0.01
 Based on the inter-laboratory test organised in the EU-project “Testing-
SCC” (GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 22
operators from 11 laboratories, the precision of the L-box passing or
blocking ratio can be expressed by the following equations
or
where Hmax = 91 mm and H = 150 − Δh
L-Box Test
 Precision
 r = 0.474 – 0.463PL, with R2 = 0.996, when PL ≥ 0.65; and r = 0.18 when PL < 0.65
(3)
or
 r = 0.463BL – 0.011, with R2 = 0.996, when BL ≤ 0.35; and r = 0.18 when BL > 0.35
(3’)
and
 R = 0.454 – 0.425PL, with R2 = 0.989, when PL ≥ 0.65; and R = 0.18 when PL < 0.65
(4)
or
 R = 0.425BL – 0.029, with R2 = 0.996, when BL ≤ 0.35; and R = 0.18 when BL > 0.35
(4’)
where R2 is the square correlation coefficient.
 Some values are listed in Table 2 for convenience of use
L-Box Test
Definition
ProcedureApparatus
J-Ring Test
 Definition
 The J-ring test aims at investigating both the filling ability and the passing
ability of SCC. It can also be used to investigate the resistance of SCC to
segregation by comparing test results from two different portions of sample.
The J-ring test measures three parameters: flow spread, flow time T50J
(optional) and blocking step. The J-ring flow spread indicates the restricted
deformability of SCC due to blocking effect of reinforcement bars and the
flow time T50 indicates the rate of deformation within a defined flow
distance. The blocking step quantifies the effect of blocking.
 Apparatus
 J-ring with the dimensions as shown in Figure 6, where the positions for the
measurement of height differences are also given
 Straight rod for aligning the reference line in the measurement, with a length
of about 400 mm and at least one flat side having the flexure less than 1 mm.
J-Ring Test
J-Ring Test
 Procedure
 Place the cleaned base plate in a stable and level position
 Fill the bucket with 6~7 litres of representative fresh SCC and let the sample
stand still for about 1 minute (± 10 seconds).
 Under the 1 minute waiting period pre-wet the inner surface of the cone and
the test urface of the base plate using the moist sponge or towel, and place
the cone in the centre on the 200 mm circle of the base plate and put the
weight ring on the top of the cone to keep it in place. (If a heavy cone is used,
or the cone is kept in position by hand no weight ring is needed).
 Place the J-ring on the base plate around the cone
 Fill the cone with the sample from the bucket without any external
compacting action such as rodding or vibrating. The surplus concrete above
the top of the cone should be struck off, and any concrete remaining on the
base plate should be removed
J-Ring Test
 Procedure
 Check and make sure that the test surface is neither too wet nor too dry. No
dry area on the base plate is allowed and any surplus of the water should be
removed – the moisture state of the plate shall be ‘just wet’.
 After a short rest (no more than 30 seconds for cleaning and checking the
moist state of the test surface), lift the cone perpendicular to the base plate in
a single movement, in such a manner that the concrete is allowed to flow out
freely without obstruction from the cone, and start the stopwatch the
moment the cone loose the contact with the base plate
 Stop the stopwatch when the front of the concrete first touches the circle of
diameter 500 mm. The stopwatch reading is recorded as the T50J value. The
test is completed when the concrete flow has ceased.
 lay the straight rod with the flat side on the top side of the J-ring and
measure the relative height differences between the lower edge of the
straight rod and the concrete surface at the central position (Δh0) and at
the four positions outside the J-ring, two (Δhx1, Δhx2) in the x-direction
and the other two (Δhy1, Δhy2) in the y-direction (perpendicular to x)
J-Ring Test
 Procedure
 Measure the largest diameter of the flow spread, dmax, and the one
perpendicular to it, dperp, using the ruler (reading to nearest 5 mm). Care
should be taken to prevent the ruler from bending
NOTE For non-circular concrete spreads the x-direction is that of the largest
spread diameter
 Expression Of Results
 The J-ring flow spread SJ is the average of diameters dmax and dperp, as
shown in Equation (6). SJ is expressed in mm to the nearest 5 mm
J-Ring Test
 Expression Of Results
 The J-ring flow time T50J is the period between the moment the cone leaves
the base plate and SCC first touches the circle of diameter 500 mm. T50J is
expressed in seconds to the nearest 1/10 seconds
 The J-ring blocking step BJ is calculated using equation (7) and expressed in
mm to the nearest 1 mm.
J-Ring Test
 Precisions
 Based on the inter-laboratory test organised in the EU-project “Testing-SCC”
(GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 16
operators from 8 laboratories, the values of repeatability and reproducibility
of the J-ring flow spread and flow time T50J are listed in Table 6
V-Funnel Test
 Definition
 The V-funnel flow time is the period a defined volume of SCC needs to pass a
narrow opening and gives an indication of the filling ability of SCC provided
that blocking and/or segregation do not take place; the flow time of the V-
funnel test is to some degree related to the plastic viscosity.
 Apparatus
 V-funnel, as shown in Figure 7, made of steel, with a flat, horizontal top and
placed on vertical supports, and with a momentary releasable, watertight
opening gate
 Stopwatch with the accuracy of 0.1 second
for recording the flow time
 Straightedge for levelling the concrete
 Buckets with a capacity of 12∼14 litres
for taking concrete sample
 Moist sponge or towel for wetting
the inner surface of the V-funnel
V-Funnel Test
 Procedure
 Place the cleaned V-funnel vertically on a stable and flat ground, with the top
opening horizontally positioned
 Wet the interior of the funnel with the moist sponge or towel and remove the
surplus of water, e.g. through the opening. The inner side of the funnel should
be ‘just wet’.
 Close the gate and place a bucket under it in order to retain the concrete to be
passed
 Fill the funnel completely with a representative sample of SCC without
applying any compaction or rodding
 Remove any surplus of concrete from the top of the funnel using the
straightedge.
 Open the gate after a waiting period of (10 ± 2) seconds. Start the stopwatch at
the same moment the gate opens
V-Funnel Test
 Procedure
 Look inside the funnel and stop the time at the moment when clear space is
visible through the opening of the funnel. The stopwatch reading is recorded
as the V-funnel flow time, noted as tV
 Do not touch or move the V-funnel until it is empty
 Expression Of Results
 The V-funnel flow time tV is the period from releasing the gate until first light
enters the opening, expressed to the nearest 0.1 second
V-Funnel Test
 Expression Of Results
 Based on the inter-laboratory test organised in the EU-project “Testing-SCC”
(GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 20 operators
from 10 laboratories, the precision of the V-funnel flow time can be expressed
by the following equations
 the precision of the V-funnel flow time can be expressed by the following
equations:
 r = 0.335 tV – 0.62, with R2 = 0.823, when 3 ≤ tV ≤ 15; and r = 4.4 when tV > 15 (8)
and
 R = 0.502 tV – 0.943, with R2 = 0.984, when 3 ≤ tV ≤ 15; and R = 6.6 when tV > 15 (9)
where R2 is the square correlation coefficient.
 Some values are listed in Table 5 for convenience of use.
V-Funnel Test
Procedure
Definition
Apparatus
Orimet Test
 Definition
 The Orimet flow time is the period a defined volume of SCC needs to pass a
narrow opening (a tube narrowed by an orifice). The flow time of the Orimet
test is to some degree related to the plastic viscosity
 Apparatus
 Orimet, made of steel, with the tube of a length of 600 mm and an inner
diameter of 120 mm. The orifice, which narrows the opening of the tube and
shears SCC, is interchangeable; its diameter can be chosen according to the
mixture composition and the criteria on SCC. Figure 8 shows the filling of the
Orimet with a bucket
 Stopwatch with the accuracy of 0.1 second for recording the flow time
 Straightedge for levelling the concrete
 Buckets with a capacity of 10∼12 litres for taking concrete sample
 Moist sponge or towel for wetting the inner surface of the Orimet
Orimet Test
Orimet Test
 Procedure
 Place the cleaned Orimet vertically on a stable and flat ground, with the top
opening horizontally positioned and check whether the tripod is completely
extended
 Wet the interior of the Orimet with the moist sponge or towel and remove the
surplus of water, e.g. through the opening. The inner side of the Orimet
should be ‘just wet’.
 Close the gate and place a bucket under it in order to retain the concrete to be
passed
 Fill the Orimet completely with a representative sample of SCC without
applying any compaction or rodding
 Remove any surplus of concrete from the top of the Orimet using the
straightedge
 Open the gate after a waiting period of (10 ± 2) seconds. Start the stopwatch at
the same moment the gate opens
Orimet Test
 Procedure
 Look inside the Orimet and stop the time at the moment when clear space is
visible through the opening of the Orimet. The stopwatch reading is recorded
as the Orimet flow time, noted as tO
 Expression Of Results
 The Orimet flow time tO is the period from releasing the gate until first light
enters the opening, expressed to the nearest 0.1 second
 Based on the inter-laboratory test organised in the EU-project “Testing-SCC”
(GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 20 operators
from 10 laboratories, the precision of the Orimet flow time (with the orifice 70
mm) can be expressed by the following equations
Orimet Test
 Expression Of Results
 r = 0.433 tO – 0.594, with R2 = 0.996, when 3 ≤ tO ≤ 15; and r = 6.6 when tO > 15
(10)
and
 R = 0.472 tO – 0.28, with R2 = 0.947, when 3 ≤ tO ≤ 15; and R = 6.8 when tO > 15 (11)
where R2 is the square correlation coefficient.
 Some values are listed in Table 6 for convenience of use.
Thank You

More Related Content

What's hot

Classification and testing of bricks
Classification and testing of bricksClassification and testing of bricks
Classification and testing of bricksIrish Nivitha
 
Creep and shrinkage
Creep and shrinkageCreep and shrinkage
Creep and shrinkageAsad Rehman
 
Properties of fresh and Hardened Concrete
Properties of fresh and Hardened ConcreteProperties of fresh and Hardened Concrete
Properties of fresh and Hardened ConcreteVijay RAWAT
 
Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concreteLavanya Singh
 
Shrinkage of concrete
Shrinkage of concreteShrinkage of concrete
Shrinkage of concretePramod GK
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concreteAglaia Connect
 
CONCRETE MIX DESIGN
CONCRETE MIX DESIGNCONCRETE MIX DESIGN
CONCRETE MIX DESIGNNikul Gopani
 
Compressive strength in concrete test
Compressive strength in concrete testCompressive strength in concrete test
Compressive strength in concrete testSelva Prakash
 
semi destructive tests on concrete _Imran_bk
semi destructive tests on concrete _Imran_bksemi destructive tests on concrete _Imran_bk
semi destructive tests on concrete _Imran_bkBk Imran
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration TestMuftah Aljoat
 

What's hot (20)

Classification and testing of bricks
Classification and testing of bricksClassification and testing of bricks
Classification and testing of bricks
 
Slump test
Slump test Slump test
Slump test
 
Mix design-ppt
Mix design-pptMix design-ppt
Mix design-ppt
 
Slump Test - Report
Slump Test - ReportSlump Test - Report
Slump Test - Report
 
Creep and shrinkage
Creep and shrinkageCreep and shrinkage
Creep and shrinkage
 
Properties of fresh and Hardened Concrete
Properties of fresh and Hardened ConcreteProperties of fresh and Hardened Concrete
Properties of fresh and Hardened Concrete
 
Water in concrete
Water in concreteWater in concrete
Water in concrete
 
Admixture of concrete
Admixture of concreteAdmixture of concrete
Admixture of concrete
 
Special Concretes
Special Concretes Special Concretes
Special Concretes
 
hot and cold weather concreting
hot and cold weather concretinghot and cold weather concreting
hot and cold weather concreting
 
Shrinkage of concrete
Shrinkage of concreteShrinkage of concrete
Shrinkage of concrete
 
Fresh Concrete
Fresh ConcreteFresh Concrete
Fresh Concrete
 
Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
Unit 2 aggregates
Unit 2  aggregatesUnit 2  aggregates
Unit 2 aggregates
 
Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concrete
 
Compaction of concrete
Compaction of concreteCompaction of concrete
Compaction of concrete
 
CONCRETE MIX DESIGN
CONCRETE MIX DESIGNCONCRETE MIX DESIGN
CONCRETE MIX DESIGN
 
Compressive strength in concrete test
Compressive strength in concrete testCompressive strength in concrete test
Compressive strength in concrete test
 
semi destructive tests on concrete _Imran_bk
semi destructive tests on concrete _Imran_bksemi destructive tests on concrete _Imran_bk
semi destructive tests on concrete _Imran_bk
 
Cone Penetration Test
Cone Penetration TestCone Penetration Test
Cone Penetration Test
 

Similar to Standard test on fresh concrete

Fresh concrete properties & its standard tests
Fresh concrete properties & its standard testsFresh concrete properties & its standard tests
Fresh concrete properties & its standard testsMaHmoud AliraQi
 
A presentation on Fresh Concrete Chapter 2_Fresh-Concrete.ppt
A presentation on Fresh Concrete Chapter 2_Fresh-Concrete.pptA presentation on Fresh Concrete Chapter 2_Fresh-Concrete.ppt
A presentation on Fresh Concrete Chapter 2_Fresh-Concrete.pptRudraBasugade
 
Concrete Technology
Concrete TechnologyConcrete Technology
Concrete TechnologyLove Sharma
 
Module 3 Properties of Concrete.ppt
Module 3 Properties of Concrete.pptModule 3 Properties of Concrete.ppt
Module 3 Properties of Concrete.pptVaibhavSoni742163
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixturesTarun kumar
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptxJanak82
 
Tests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TEST
Tests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TESTTests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TEST
Tests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TESTNisarg Mistry
 
Tests of cement in concrete technology
Tests of cement in concrete technologyTests of cement in concrete technology
Tests of cement in concrete technologySunny Saha
 
FRESH CONCRETE PROPERTIES.pptx
FRESH CONCRETE PROPERTIES.pptxFRESH CONCRETE PROPERTIES.pptx
FRESH CONCRETE PROPERTIES.pptxHimabindu Rudroju
 
Self compacting concrete Mix
Self compacting concrete MixSelf compacting concrete Mix
Self compacting concrete MixHafizullah Sadat
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete Sreekutty S
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Mayur Rahangdale
 

Similar to Standard test on fresh concrete (20)

Fresh concrete properties & its standard tests
Fresh concrete properties & its standard testsFresh concrete properties & its standard tests
Fresh concrete properties & its standard tests
 
Test of concrete
Test of concrete Test of concrete
Test of concrete
 
Fresh Concrete
Fresh Concrete Fresh Concrete
Fresh Concrete
 
Ct
CtCt
Ct
 
Group 4 (concrete)
Group 4 (concrete)Group 4 (concrete)
Group 4 (concrete)
 
A presentation on Fresh Concrete Chapter 2_Fresh-Concrete.ppt
A presentation on Fresh Concrete Chapter 2_Fresh-Concrete.pptA presentation on Fresh Concrete Chapter 2_Fresh-Concrete.ppt
A presentation on Fresh Concrete Chapter 2_Fresh-Concrete.ppt
 
Concrete Technology
Concrete TechnologyConcrete Technology
Concrete Technology
 
Slump
SlumpSlump
Slump
 
Module 3 Properties of Concrete.ppt
Module 3 Properties of Concrete.pptModule 3 Properties of Concrete.ppt
Module 3 Properties of Concrete.ppt
 
Cement and admixtures
Cement and admixturesCement and admixtures
Cement and admixtures
 
Fresh Concrete.pdf
Fresh Concrete.pdfFresh Concrete.pdf
Fresh Concrete.pdf
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx
 
Tests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TEST
Tests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TESTTests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TEST
Tests on fresh concrete SLUMP TEST VEE BEE TEST COMPACTION FACTOR TEST
 
Tests of cement in concrete technology
Tests of cement in concrete technologyTests of cement in concrete technology
Tests of cement in concrete technology
 
FRESH CONCRETE PROPERTIES.pptx
FRESH CONCRETE PROPERTIES.pptxFRESH CONCRETE PROPERTIES.pptx
FRESH CONCRETE PROPERTIES.pptx
 
Self compacting concrete Mix
Self compacting concrete MixSelf compacting concrete Mix
Self compacting concrete Mix
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
Concrete checking test
Concrete checking testConcrete checking test
Concrete checking test
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
Sampling of cement ,Consistency test no cement ,Initial and final setting tim...
 

More from Abhishek Shah

STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...Abhishek Shah
 
Mechanical Compaction of Concrete
Mechanical Compaction of Concrete Mechanical Compaction of Concrete
Mechanical Compaction of Concrete Abhishek Shah
 
Application & Comparison of different Formwork System used within Ind...
Application  &  Comparison  of  different  Formwork System  used  within  Ind...Application  &  Comparison  of  different  Formwork System  used  within  Ind...
Application & Comparison of different Formwork System used within Ind...Abhishek Shah
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Ready Mix Concrete: Economic and Qualitative Growth for Construction Industry
Ready Mix Concrete: Economic and Qualitative Growth for Construction IndustryReady Mix Concrete: Economic and Qualitative Growth for Construction Industry
Ready Mix Concrete: Economic and Qualitative Growth for Construction IndustryAbhishek Shah
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...Abhishek Shah
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryAbhishek Shah
 

More from Abhishek Shah (8)

STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
STUDY OF CONSTRUCTION DISPUTES & IT’s RESOLUTION THROUGH ARBITRATION FOR AHME...
 
Mechanical Compaction of Concrete
Mechanical Compaction of Concrete Mechanical Compaction of Concrete
Mechanical Compaction of Concrete
 
Ready Mix Concrete
Ready Mix ConcreteReady Mix Concrete
Ready Mix Concrete
 
Application & Comparison of different Formwork System used within Ind...
Application  &  Comparison  of  different  Formwork System  used  within  Ind...Application  &  Comparison  of  different  Formwork System  used  within  Ind...
Application & Comparison of different Formwork System used within Ind...
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Ready Mix Concrete: Economic and Qualitative Growth for Construction Industry
Ready Mix Concrete: Economic and Qualitative Growth for Construction IndustryReady Mix Concrete: Economic and Qualitative Growth for Construction Industry
Ready Mix Concrete: Economic and Qualitative Growth for Construction Industry
 
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons..."Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
"Ranking of Causes of Disputes and Use of Dispute Resolution Methods for Cons...
 
Different Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction IndustryDifferent Types of Formwork Syetem Used within Indian Construction Industry
Different Types of Formwork Syetem Used within Indian Construction Industry
 

Recently uploaded

THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...JojoEDelaCruz
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxAshokKarra1
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 

Recently uploaded (20)

THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptxYOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
YOUVE GOT EMAIL_FINALS_EL_DORADO_2024.pptx
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
ENG 5 Q4 WEEk 1 DAY 1 Restate sentences heard in one’s own words. Use appropr...
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
Karra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptxKarra SKD Conference Presentation Revised.pptx
Karra SKD Conference Presentation Revised.pptx
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 

Standard test on fresh concrete

  • 1. By : Abhishek Shah SAL Institute of Technology and Engineering Research Ahmedabad INDIA
  • 2. Content  Slump Test  Flow Test  Compacting Factor Test  Ve Be Time Test  L-Box Test  J-Ring Test  V-Funnel Test  Orimet Test
  • 4. Slump Test  Aim :- To Determine the Consistency Of Concrete  Principle The slump test result is a measure of the behavior of a compacted inverted cone of concrete under the action of gravity. It measures the consistency or the wetness of concrete.
  • 5. Slump Test  Apparatus  Slump cone : frustum of a cone, 300 mm (12 in) of height. The base is 200 mm (8in) in diameter and it has a smaller opening at the top of 100 mm  Scale for measurement,  Temping rod(steel) 15mm diameter, 60cm length.
  • 6. Slump Test  Procedure  The base is placed on a smooth surface and the container is filled with concrete in three layers, whose workability is to be tested .  Each layer is temped 25 times with a standard 16 mm (5/8 in) diameter steel rod, rounded at the end.  When the mold is completely filled with concrete, the top surface is struck off (leveled with mold top opening) by means of screening and rolling motion of the temping rod.  The mold must be firmly held against its base during the entire operation so that it could not move due to the pouring of concrete and this can be done by means of handles or foot – rests brazed to the mold.
  • 7. Slump Test  Procedure  Immediately after filling is completed and the concrete is leveled, the cone is slowly and carefully lifted vertically, an unsupported concrete will now slump.  The decrease in the height of the center of the slumped concrete is called slump.  The slump is measured by placing the cone just besides the slump concrete and the temping rod is placed over the cone so that it should also come over the area of slumped concrete.  The decrease in height of concrete to that of mould is noted with scale. (usually measured to the nearest 5 mm (1/4 in).
  • 8. Slump Test  Types Of Slump The slumped concrete takes various shapes, and according to the profile of slumped concrete, the slump is termed as;  Collapse Slump  Shear Slump  True Slump
  • 9. Slump Test  Types Of Slump  Collapse Slump In a collapse slump the concrete collapses completely.  A collapse slump will generally mean that the mix is too wet or that it is a high workability mix, for which slump test is not appropriate.  Shear Slump In a shear slump the top portion of the concrete shears off and slips sideways. OR If one-half of the cone slides down an inclined plane, the slump is said to be a shear slump.  If a shear or collapse slump is achieved, a fresh sample should be taken and the test is repeated.  If the shear slump persists, as may the case with harsh mixes, this is an indication of lack of cohesion of the mix.
  • 10. Slump Test  Types Of Slump  True Slump In a true slump the concrete simply subsides, keeping more or less to shape  This is the only slump which is used in various tests.  Mixes of stiff consistence have a Zero slump, so that in the rather dry range no variation can be detected between mixes of different workability. However , in a lean mix with a tendency to harshness, a true slump can easily change to the shear slump type or even to collapse, and widely different values of slump can be obtained in different samples from the same mix; thus, the slump test is unreliable for lean mixes.
  • 11. Slump Test  Uses  The slump test is used to ensure uniformity for different batches of similar concrete under field conditions and to ascertain the effects of plasticizers on their introduction.  This test is very useful on site as a check on the day-to-day or hour- to-hour variation in the materials being fed into the mixer. An increase in slump may mean, for instance, that the moisture content of aggregate has unexpectedly increases.  Other cause would be a change in the grading of the aggregate, such as a deficiency of sand.  Too high or too low a slump gives immediate warning and enables the mixer operator to remedy the situation.  This application of slump test as well as its simplicity, is responsible for its widespread use.
  • 12. Slump Test Degree of workability Slump (mm) Use for which concrete is suitable Very low 0 - 25 Very dry mixes; used in road making. Roads vibrated by power operated machines Low 25 - 50 Low workability mixes; used for foundations with light reinforcement. Roads vibrated by hand operated Machines Medium 50 - 100 Medium workability mixes; manually compacted flat slabs using crushed aggregates. Normal reinforced concrete manually compacted and heavily reinforced sections with vibrations High 100 - 175 High workability concrete; for sections with congested reinforcement. Not normally suitable for vibration >Table : Workability, Slump and Compacting Factor of concrete with 19 or 38 mm (3/4 or 11/2 in) maximum size of aggregate.
  • 14. Flow Test Aim :- The flow table test or flow test is a method to determine the consistence of fresh concrete.  Principle This test is giving us the ability of concrete to flow under the gravitational force when poured and compacted within the cone and suddenly lifted up
  • 15. Flow Test  Equipment  Flow table with a grip and a hinge, 70 cm x 70 cm.  Abrams cone, open at the top and at the bottom - 30 cm high, 17 cm top diameter, 25 cm base diameter  Water bucket and broom for wetting the flow table.  Tamping rod, 60 cm height  Scale for measurement
  • 16. Flow Test  Conducting  The flow table is wetted.  The cone is placed on the flow table and filled with fresh concrete in two layers, each layer 25 times tamp with tamping rod.  The cone is lifted, allowing the concrete to flow.  The flow table is then lifted up several centimeters and then dropped, causing the concrete flow a little bit further.  After this the diameter of the concrete is measured in a 6 different direction and take the average.
  • 18. Flow Test Percent of Flow 0 – 20 % 20 – 60 % 60 – 100 % 100 – 120 % 120 – 150 % Consistency Dry Stiff Plastic Wet Sloppy
  • 20. Compacting Factor Test  Aim  To measure the degree of compaction For the standard amount of work and thus offer a direct and reasonably reliable assessment of the workability Of concrete .  Principle  the test require measurement of the weight of the partially and fully compacted concrete and the ratio the partially compacted weight to the fully compacted weight, which is always less than one, is known as compacted factor .  For the normal range of concrete the compacting factor lies between 0.8 - 0.92
  • 21. Compacting Factor Test  Apparatus  Trowels  Hand Scoop (15.2 cm long)  Rod of steel or other suitable material (1.6 cm diameter, 61 cm long rounded at one end ).  Balance.
  • 22. Compacting Factor Test  Procedure 1) Ensure the apparatus and associated equipment are clean before test and free from hardened concrete and superfluous water . 2) Weigh the bottom cylinder to nearest 10gm , put it back on the stand and cover it up with a pair of floats . 3) Gently fill the upper hopper with the sampled concrete to the level of the rim with use of a scoop . 4) Immediately open the trap door of the upper hopper and allow the sampled concrete to fall into the middle hopper . 5) Remove the floats on top of the bottom cylinder and open the trap door of the middle hopper allowing the sampled concrete to fall into the bottom cylinder . 6) Remove the surplus concrete above the top of the bottom cylinder by holding a float in each hand and move towards each other to cut off the concrete across the top of cylinder
  • 23. Compacting Factor Test 7) Wipe clean the outside of cylinder of concrete and weigh to nearest 10gm . 8) Subtract the weight of empty cylinder from the weight of cylinder plus concrete to obtain the weight of partially compacted concrete . 9) Remove the concrete from the cylinder and refill with sampled concrete in layers . 10) Compact each layer thoroughly with the standard Compacting Bar to achieve full compaction . 11) Float off the surplus concrete to top of cylinder and wipe it clean . 12) Weigh the cylinder to nearest 10gm and subtract the weight of empty cylinder from the weight of cylinder plus concrete to obtain the weight of fully compacted concrete .
  • 24. Compacting Factor Test Workability Slump (mm) C.F Uses Very Low 0 - 25 0.78 Roads - Pavements Low 25 - 50 0.85 Foundations Concrete Medium 25 - 100 0.92 Reinforced Concrete High 100 - 175 0.95 Reinforced Concrete (High Reinforcement)
  • 25.
  • 26. VeBe Time Test  Aim  To Measure the workability of Concrete  Principle  It is based on measuring the time (Called VEBE time) needed to transfer the shape of a concrete mix from a frustum cone to a cylinder (these shapes are standardized by the apparatus of this test), by vibrating and compacting the mix. The more VEBE time needed the less workable the mix is. This method is very useful for stiff mixes.
  • 27. VeBe Time Test  Apparatus  Cylindrical container with diameter = 240 mm, and height = 200 mm  Mold: the same mold used in the slump test.  Disc : A transparent horizontal disc attached to a rod which slides vertically  Vibrating Table : 380*260 mm, supported by four rubber shock absorbers  Tamping Rod  Stop watch
  • 28. VeBe Time Test  Procedure 1) Slump test as described earlier is performed, placing the slump cone inside the sheet metal cylindrical pot of the consist meter. 2) The glass disc attached to the swivel arm is turn and place on the top of the concrete in the pot. 3) The electrical vibrator is then switched on and simultaneously a stop watch started. 4) The vibration is continued till such time as the conical shape of the concrete disappears and the concrete assume a cylindrical shape. 5) This can be judge by observing the glass disc from the top disappearance of transparency. 6) Immediately when the concrete fully assume a cylindrical shape, the stop watch is switched off.
  • 29. VeBe Time Test 7) The time required for the shape of concrete to change from slump cone shape to cylindrical shape in second is known as Vibe Degree. 8) This method is very suitable for very dry concrete whose slump value cannot be measure by slump test, but the vibration is too vigorous for concrete with slump greater than about 50m. The test fails if VeBe Time is less than 5 seconds .. And the test must be created when no collapse or shears slump in concrete
  • 31. L-Box Test  Aim  The method aims at investigating the passing ability of SCC.  Principle  It measures the reached height of fresh SCC after passing through the specified gaps of steel bars and flowing within a defined flow distance. With this reached height, the passing or blocking behavior of SCC can be estimated
  • 32.  Apparatus  Two types of gates can be used, one with 3 smooth bars and one with 2 smooth bars. The gaps are 41 and 59 mm, respectively  Suitable tool for ensuring that the box is level i.e. a spirit level  Suitable buckets for taking concrete sample L Box Test
  • 34. L-Box Test  Procedure  Place the L-box in a stable and level position  Fill the vertical part of the L-box, with the extra adapter mounted, with 12.7 liters of representative fresh SCC  Let the concrete rest in the vertical part for one minute (± 10 seconds). During this time the concrete will display whether it is stable or not (segregation).  Lift the sliding gate and let the concrete flow out of the vertical part into the horizontal part of the L-box.  When the concrete has stopped moving, measure the average distance, noted as Δh, between the top edge of the box and the concrete that reached the end of the box, at three positions, one at the centre and two at each side
  • 35. L-Box Test  Expression Of Results  The passing ratio PL or blocking ratio BL is calculated using equation (2) or (2’), and expressed in dimensionless to the nearest 0.01  Precision  The passing ratio PL or blocking ratio BL is calculated using equation (2) or (2’), and expressed in dimensionless to the nearest 0.01  Based on the inter-laboratory test organised in the EU-project “Testing- SCC” (GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 22 operators from 11 laboratories, the precision of the L-box passing or blocking ratio can be expressed by the following equations or where Hmax = 91 mm and H = 150 − Δh
  • 36. L-Box Test  Precision  r = 0.474 – 0.463PL, with R2 = 0.996, when PL ≥ 0.65; and r = 0.18 when PL < 0.65 (3) or  r = 0.463BL – 0.011, with R2 = 0.996, when BL ≤ 0.35; and r = 0.18 when BL > 0.35 (3’) and  R = 0.454 – 0.425PL, with R2 = 0.989, when PL ≥ 0.65; and R = 0.18 when PL < 0.65 (4) or  R = 0.425BL – 0.029, with R2 = 0.996, when BL ≤ 0.35; and R = 0.18 when BL > 0.35 (4’) where R2 is the square correlation coefficient.  Some values are listed in Table 2 for convenience of use
  • 39. J-Ring Test  Definition  The J-ring test aims at investigating both the filling ability and the passing ability of SCC. It can also be used to investigate the resistance of SCC to segregation by comparing test results from two different portions of sample. The J-ring test measures three parameters: flow spread, flow time T50J (optional) and blocking step. The J-ring flow spread indicates the restricted deformability of SCC due to blocking effect of reinforcement bars and the flow time T50 indicates the rate of deformation within a defined flow distance. The blocking step quantifies the effect of blocking.  Apparatus  J-ring with the dimensions as shown in Figure 6, where the positions for the measurement of height differences are also given  Straight rod for aligning the reference line in the measurement, with a length of about 400 mm and at least one flat side having the flexure less than 1 mm.
  • 41. J-Ring Test  Procedure  Place the cleaned base plate in a stable and level position  Fill the bucket with 6~7 litres of representative fresh SCC and let the sample stand still for about 1 minute (± 10 seconds).  Under the 1 minute waiting period pre-wet the inner surface of the cone and the test urface of the base plate using the moist sponge or towel, and place the cone in the centre on the 200 mm circle of the base plate and put the weight ring on the top of the cone to keep it in place. (If a heavy cone is used, or the cone is kept in position by hand no weight ring is needed).  Place the J-ring on the base plate around the cone  Fill the cone with the sample from the bucket without any external compacting action such as rodding or vibrating. The surplus concrete above the top of the cone should be struck off, and any concrete remaining on the base plate should be removed
  • 42. J-Ring Test  Procedure  Check and make sure that the test surface is neither too wet nor too dry. No dry area on the base plate is allowed and any surplus of the water should be removed – the moisture state of the plate shall be ‘just wet’.  After a short rest (no more than 30 seconds for cleaning and checking the moist state of the test surface), lift the cone perpendicular to the base plate in a single movement, in such a manner that the concrete is allowed to flow out freely without obstruction from the cone, and start the stopwatch the moment the cone loose the contact with the base plate  Stop the stopwatch when the front of the concrete first touches the circle of diameter 500 mm. The stopwatch reading is recorded as the T50J value. The test is completed when the concrete flow has ceased.  lay the straight rod with the flat side on the top side of the J-ring and measure the relative height differences between the lower edge of the straight rod and the concrete surface at the central position (Δh0) and at the four positions outside the J-ring, two (Δhx1, Δhx2) in the x-direction and the other two (Δhy1, Δhy2) in the y-direction (perpendicular to x)
  • 43. J-Ring Test  Procedure  Measure the largest diameter of the flow spread, dmax, and the one perpendicular to it, dperp, using the ruler (reading to nearest 5 mm). Care should be taken to prevent the ruler from bending NOTE For non-circular concrete spreads the x-direction is that of the largest spread diameter  Expression Of Results  The J-ring flow spread SJ is the average of diameters dmax and dperp, as shown in Equation (6). SJ is expressed in mm to the nearest 5 mm
  • 44. J-Ring Test  Expression Of Results  The J-ring flow time T50J is the period between the moment the cone leaves the base plate and SCC first touches the circle of diameter 500 mm. T50J is expressed in seconds to the nearest 1/10 seconds  The J-ring blocking step BJ is calculated using equation (7) and expressed in mm to the nearest 1 mm.
  • 45. J-Ring Test  Precisions  Based on the inter-laboratory test organised in the EU-project “Testing-SCC” (GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 16 operators from 8 laboratories, the values of repeatability and reproducibility of the J-ring flow spread and flow time T50J are listed in Table 6
  • 46.
  • 47. V-Funnel Test  Definition  The V-funnel flow time is the period a defined volume of SCC needs to pass a narrow opening and gives an indication of the filling ability of SCC provided that blocking and/or segregation do not take place; the flow time of the V- funnel test is to some degree related to the plastic viscosity.  Apparatus  V-funnel, as shown in Figure 7, made of steel, with a flat, horizontal top and placed on vertical supports, and with a momentary releasable, watertight opening gate  Stopwatch with the accuracy of 0.1 second for recording the flow time  Straightedge for levelling the concrete  Buckets with a capacity of 12∼14 litres for taking concrete sample  Moist sponge or towel for wetting the inner surface of the V-funnel
  • 48. V-Funnel Test  Procedure  Place the cleaned V-funnel vertically on a stable and flat ground, with the top opening horizontally positioned  Wet the interior of the funnel with the moist sponge or towel and remove the surplus of water, e.g. through the opening. The inner side of the funnel should be ‘just wet’.  Close the gate and place a bucket under it in order to retain the concrete to be passed  Fill the funnel completely with a representative sample of SCC without applying any compaction or rodding  Remove any surplus of concrete from the top of the funnel using the straightedge.  Open the gate after a waiting period of (10 ± 2) seconds. Start the stopwatch at the same moment the gate opens
  • 49. V-Funnel Test  Procedure  Look inside the funnel and stop the time at the moment when clear space is visible through the opening of the funnel. The stopwatch reading is recorded as the V-funnel flow time, noted as tV  Do not touch or move the V-funnel until it is empty  Expression Of Results  The V-funnel flow time tV is the period from releasing the gate until first light enters the opening, expressed to the nearest 0.1 second
  • 50. V-Funnel Test  Expression Of Results  Based on the inter-laboratory test organised in the EU-project “Testing-SCC” (GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 20 operators from 10 laboratories, the precision of the V-funnel flow time can be expressed by the following equations  the precision of the V-funnel flow time can be expressed by the following equations:  r = 0.335 tV – 0.62, with R2 = 0.823, when 3 ≤ tV ≤ 15; and r = 4.4 when tV > 15 (8) and  R = 0.502 tV – 0.943, with R2 = 0.984, when 3 ≤ tV ≤ 15; and R = 6.6 when tV > 15 (9) where R2 is the square correlation coefficient.  Some values are listed in Table 5 for convenience of use.
  • 53. Orimet Test  Definition  The Orimet flow time is the period a defined volume of SCC needs to pass a narrow opening (a tube narrowed by an orifice). The flow time of the Orimet test is to some degree related to the plastic viscosity  Apparatus  Orimet, made of steel, with the tube of a length of 600 mm and an inner diameter of 120 mm. The orifice, which narrows the opening of the tube and shears SCC, is interchangeable; its diameter can be chosen according to the mixture composition and the criteria on SCC. Figure 8 shows the filling of the Orimet with a bucket  Stopwatch with the accuracy of 0.1 second for recording the flow time  Straightedge for levelling the concrete  Buckets with a capacity of 10∼12 litres for taking concrete sample  Moist sponge or towel for wetting the inner surface of the Orimet
  • 55. Orimet Test  Procedure  Place the cleaned Orimet vertically on a stable and flat ground, with the top opening horizontally positioned and check whether the tripod is completely extended  Wet the interior of the Orimet with the moist sponge or towel and remove the surplus of water, e.g. through the opening. The inner side of the Orimet should be ‘just wet’.  Close the gate and place a bucket under it in order to retain the concrete to be passed  Fill the Orimet completely with a representative sample of SCC without applying any compaction or rodding  Remove any surplus of concrete from the top of the Orimet using the straightedge  Open the gate after a waiting period of (10 ± 2) seconds. Start the stopwatch at the same moment the gate opens
  • 56. Orimet Test  Procedure  Look inside the Orimet and stop the time at the moment when clear space is visible through the opening of the Orimet. The stopwatch reading is recorded as the Orimet flow time, noted as tO  Expression Of Results  The Orimet flow time tO is the period from releasing the gate until first light enters the opening, expressed to the nearest 0.1 second  Based on the inter-laboratory test organised in the EU-project “Testing-SCC” (GRD2- 2000-30024/G6RD-CT-2001-00580) with 2 replicates and 20 operators from 10 laboratories, the precision of the Orimet flow time (with the orifice 70 mm) can be expressed by the following equations
  • 57. Orimet Test  Expression Of Results  r = 0.433 tO – 0.594, with R2 = 0.996, when 3 ≤ tO ≤ 15; and r = 6.6 when tO > 15 (10) and  R = 0.472 tO – 0.28, with R2 = 0.947, when 3 ≤ tO ≤ 15; and R = 6.8 when tO > 15 (11) where R2 is the square correlation coefficient.  Some values are listed in Table 6 for convenience of use.